WO2015088439A1 - Système de récupération de sol pour des travaux de dynamitage - Google Patents

Système de récupération de sol pour des travaux de dynamitage Download PDF

Info

Publication number
WO2015088439A1
WO2015088439A1 PCT/SG2013/000523 SG2013000523W WO2015088439A1 WO 2015088439 A1 WO2015088439 A1 WO 2015088439A1 SG 2013000523 W SG2013000523 W SG 2013000523W WO 2015088439 A1 WO2015088439 A1 WO 2015088439A1
Authority
WO
WIPO (PCT)
Prior art keywords
cable
floor
winch drum
recovery system
rack assembly
Prior art date
Application number
PCT/SG2013/000523
Other languages
English (en)
Inventor
Christopher Mark CHARLTON
Original Assignee
Blastechnik Pte Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Blastechnik Pte Ltd filed Critical Blastechnik Pte Ltd
Priority to PCT/SG2013/000523 priority Critical patent/WO2015088439A1/fr
Publication of WO2015088439A1 publication Critical patent/WO2015088439A1/fr

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B24GRINDING; POLISHING
    • B24CABRASIVE OR RELATED BLASTING WITH PARTICULATE MATERIAL
    • B24C9/00Appurtenances of abrasive blasting machines or devices, e.g. working chambers, arrangements for handling used abrasive material
    • B24C9/003Removing abrasive powder out of the blasting machine

Definitions

  • This invention relates generally to a floor recovery system for use with abrasive blasting works.
  • abrasive blasting works have been conventionally used to remove large amounts of spent abrasives from the abrasive blasting process.
  • Some applications of abrasive blasting works are the removal of millscale, paint and other coatings from a surface, removing rust, cutting substrates and the like.
  • abrasives such as metals, sand or synthetic materials are carried in a stream of air, at high velocities for impingement against an object to be treated.
  • a result of this process is that large amounts of spent abrasives accumulate on the floor of the work area.
  • Floor recovery systems are frequently used in conjunction with abrasive blasting works so that these spent abrasives can be recovered, recycled and reused.
  • floor recovery systems typically include a perforated floor above a solid floor having at least a channel therein.
  • the blasting process is performed above the perforated floor and the spent abrasives are collected on the solid floor when it falls through the perforated floor.
  • Scraper assemblies, screw conveyors, belt conveyors or pneumatic ducts are typically mounted above the solid floor, below the perforated floor, within the channel to transport recovered abrasive and debris.
  • scraper assemblies When scraper assemblies are used, they are fitted with pivoting blades which contact with the floor to convey the abrasives in a forward stroke toward a central collection channel on the floor. Once the scraper assemblies have traversed the length of the channel, they are pivoted away from the floor and conveyed in a backward stroke.
  • floor recovery systems used with abrasive blasting works.
  • An example of a floor recovery system is that described in the preceding paragraph.
  • These floor recovery systems may utilize a wire rope powered by drive motor and gearbox, pneumatic cylinders, or chain assemblies or combination of one another to move the scraper assemblies to and fro across the length of the channel.
  • the floor recovery system is powered by a chain assembly
  • the ends of the wire rope are attached to the chain and fed through a drive mounted sprocket.
  • a disadvantage of this configuration is that as only the ends of the wire rope are attached to the chain, the length of the stroke is limited. This translates to an extremely long scraper assembly fixed with multiple blades within to counter the short stroke length.
  • Some of the scraper assemblies used in such systems can comprise more than half the length of the channel which leads to increased wear, servicing and maintenance issues, more efforts in installation and significantly more material for construction leading to increases costs. For example, longer and bigger scraper assemblies are difficult to service due to removal of a large proportion of the floor grids to reach the scraper assemblies. Increased wear of the scraper assemblies is attributed to a larger proportion of the surface area of the scraper assemblies being subjected to rebounding abrasives during the blasting works. The same disadvantages apply to scraper floors fitted with an oscilating pneumatic cylinder located at one end of the recovery channel.
  • Another type of floor recovery system includes the use of belt conveyors or screw conveyors. Multiple hoppers are installed in the longitudinal channels below the perforated floor. The belt or screw conveyor lies below the multiple hoppers so that spent abrasives that fall through the perforated floor and the hoppers will land on the belt or screw conveyor to be conveyed to a central collection bucket.
  • the first is that they make use of pneumatic cylinders and chain assemblies which requires extensive costs and maintenance to operate. Pneumatic cylinders are not designed to be used in a harsh environment like the blasting room. The limited stroke length afforded by pneumatic cylinders lead to long scraper assemblies which lead to other problems such as that mentioned above.
  • the second is that the former floor recovery system uses very long racks fitted with multiple blades that are moved for short distances and transfers the spent abrasives from one blade to the next, which makes collection of the spent abrasives inefficient.
  • Another type of recovery system is a pneumatic conveying system.
  • This system utilises a series of negative pressure fans.
  • the recovery floor consists of a series of pneumatic conveying ducts into which the blasted abrasive falls. The abrasive and waste is then recovered by pneumatic conveying.
  • the disadvantages associated with this type of recovery floor are that heavy abrasive particles are not easy to pneumatically convey. In order to do so high amounts of fan static pressure and airflow are required. To generate this high static power and airflow very large electric motors are required. Subsequent power consumption is extremely high for this style of recovery floor.
  • a floor recovery system for abrasive blasting works comprising at least one rack assembly movable along each of a plurality of longitudinal channels for conveying spent abrasives from the floor of the longitudinal channel to a collector, a continuous length of cable configured for moving in a first direction to effect movement of the at least one rack assembly in the first direction along the longitudinal channel, and movable in a second direction to effect movement of the at least one rack assembly in the second direction along the longitudinal channel, and a winch drum configured for engagement with the ends of the cable, the winch drum rotatable to effect movement of the cable in the first direction and the second direction.
  • the rack assemblies are attached to the continuous length of cable.
  • the continuous length of cable is routed across the length of each channel alternately.
  • the winch drum is a double-sided winch drum further including a first side and a second side.
  • the winch drum is rotatable in a first direction such that the first side of the winch drum draws the cable onto the drum while the second side of the winch drum releases an equivalent amount of cable off the drum simultaneously.
  • the winch drum is rotatable in a second direction such that the first side of the winch drum releases the continuous cable off the winch drum while the second side of the winch drum draws the equivalent length of continuous cable onto the winch drum simultaneously.
  • the rack assembly further comprises a pivoting blade pivotably mounted on the rack assembly, the pivoting blade pivotable between a first position and a second position, wherein in the first position, the pivoting blade engages the floor of the channel so as to convey the abrasives, and in the second position, the pivoting blade is raised above the floor of the channel.
  • the pivoting blade further comprises a yoke positioned at a proximal end of the blade, and a clamping member for securing the yoke to the cable.
  • the winch drum when the winch drum is rotated to effect movement of the cable in a first direction, the cable engages the yoke of the pivoting blade such that the pivoting blade moves to the first position.
  • the winch drum when the winch drum is rotated to effect movement of the cable in a second direction, the cable engages the yoke of the pivoting blade such that the pivoting blade moves to the second position.
  • the rack assembly further includes support members on each side of the rack assembly, wherein the support members are slidably mounted on the rail guides of the channel.
  • FIG. 1 is a plan view of a floor recovery system for abrasive blasting works, with the perforated floor grids shown;
  • FIG. 2 is a plan view of the floor recovery system for abrasive blasting works shown with only a portion of the perforated floor grids;
  • FIG. 3 is a side view of the floor recovery system; [0023] FIG. 4 is a side view of a rack assembly; [0024] FIG. 5 is an elevation view of a rack assembly; [0025] FIG. 6 is plan view of a rack assembly. DETAILED DESCRIPTION
  • FIGs 1 and 2 illustrate a floor recovery system 10, as shown from above, for abrasive blasting works.
  • the floor recovery system 10 is utilised in an enclosed environment or an abrasive blasting room for the purpose of recovering recyclable abrasives and contaminants from the floor after blasting.
  • a perforated floor grating 14, as shown in Figure 1 is supported above a solid floor and allows abrasive and contaminants to drop through the floor grating 14 and onto the solid floor during the abrasive blasting works.
  • the abrasive blasting works occur above the perforated floor grating 14.
  • the floor recovery system 10 includes a number of longitudinal channels 18 spanning the solid floor.
  • Each longitudinal channel 18 is fitted with a rack assembly 20 that traverses the entire length of the channel 18, which typically covers one end of the blast room to the other end of the blast room.
  • the spent abrasives and contaminants are dropped off on a belt or screw conveyor 15.
  • Figure 2 shows a floor recovery system 10 with a small portion of the solid floor with the perforated floor grating 14, with identical elements as shown in Figure 1.
  • the rack assemblies 20 are removably detachable from a continuous cable 16 that is movable in a first direction and a second direction when in use.
  • the continuous cable 16 travels around the longitudinal channels 18 having each end of the cable 16 attached to a rotating winch drum 13 powered by a power source (not shown).
  • the power source can be a motor or the like.
  • the cable 16 is arranged in a manner around the longitudinal channels 18 such that rotation of the winch drum 13 in a first direction effects movement of the rack assemblies 20 from approximately one end of the longitudinal channel 18 to the other end of the longitudinal channel 18 and rotation of the winch drum 13 in a second direction effects movement of the rack assemblies 20 in an opposed direction.
  • the cable arrangement can be effected by a pulley arrangement which allows the cable 16 to traverse continuously around all the longitudinal channels.
  • the length of cable 16 is configured such that the cable is routed longitudinally on each longitudinal channel 18 alternately. As only one single length of cable 16 is used for the floor recovery system, all the rack assemblies 20 are affixed to the single length of cable 16.
  • the winch drum 13 is a double-sided drum. One end of the cable 16 is wound round a first side of the winch drum 13 and the other end of the cable is wound round the second side of the winch drum 13.
  • the winch drum 13 rotates in a first direction
  • the cable is drawn onto the drum to effect movement of the rack assemblies 20 along the longitudinal channel 18 in the first direction.
  • the second side of the winch drum 13 rotates in an opposed direction to the first direction.
  • an equivalent length of cable 16 is released from the second side of the winch drum 13.
  • the rack assemblies 20 reach the ends of the longitudinal channel 18, the first side of the winch drum 13 rotates in the opposed direction or second direction.
  • the second side of the winch drum 13 releases a length of cable 16 to effect movement of the rack assembly 20 in the second direction and at the same time draws in an equivalent length of cable 16 on the first side of the winch drum 13.
  • the cable drawn onto the first side of the winch drum is creating the pulling force to move the rack assembly.
  • the cable is made of wire rope, although it is envisaged that other types of cables capable of performing the same function can be used.
  • a continuous length of cable 16 together with the winch drum 13 enables a longer stroke length which allows the rack assemblies 20 to be made shorter and thereby allows them to traverse the entire length of the longitudinal channel 18. This also allows the rack assemblies 20 to be easily removable from the floor recovery system 10 for servicing and maintenance. Large portions of the perforated floor grating need not be removed to reach the compact rack assembly.
  • a compact rack assembly means less wear and tear as it is subjected to less impact from rebounding abrasives and therefore longer life-span.
  • a compact rack assembly means less material to manufacture and therefore less costs are incurred.
  • FIG. 3 shows a side view of the floor recovery system 10.
  • the cable 16 in motion effects the movement of the rack assembly 20 from one end of the longitudinal channel to the other end where a collector 15 is located to receive the abrasives.
  • the collector 15 can be a belt conveyor or a cross screw conveyor which transports the abrasives to a bucket elevator for further processing.
  • the collector 15 is shown at one end of the floor recovery system, it is envisaged that the location of the collector 15 can be placed in any suitable location along the floor recovery system 10.
  • the belt conveyor or screw conveyor transports the abrasives along the width of the floor of the recovery system.
  • Figure 4 is a side view of a rack assembly 20 affixed to the cable 16 on the longitudinal channel 18.
  • the rack assembly 20 is approximately 600mm long. It is also approximately 100mm narrower in width than the longitudinal channel 18.
  • the rack assembly 20 includes a pivoting blade 21 spanning the approximately the width of the longitudinal channel 18 (See Figure 6).
  • the pivoting blade 21 is pivotally mounted on the rack assembly and is movable between a first position and a second position. The first position of the pivoting blade allows the pivoting blade to contact the floor or approximately 10mm above the floor.
  • the pivoting blade is set approximately 10mm above the floor of the longitudinal channel because this allows a layer of 10mm thick abrasive to build up on the floor and become a self replacing protective wear plate so as to push the abrasives along the length of the longitudinal channel in a direction towards the collector 15.
  • the first position of the pivoting blade 21 occurs when the rack assembly is in a forward motion.
  • the second position of the pivoting blade allows the pivoting blade to pivot away or to be raised from the floor of the longitudinal channel such that it is no longer in contact with the abrasives on the floor of the longitudinal channel. When this occurs, the movement of the rack assembly is in a backwards motion and the direction of travel of the rack assembly is reversed from when the pivoting blade is in the first position.
  • the pivoting blade 21 is raised above the abrasives by approximately 10-20mm.
  • FIG. 5 is an elevation view of the rack assembly 20 on one of the channels 18.
  • Each channel 18 includes rail guides 22 running on each side of the channel 18.
  • the rack assembly 20 includes support members 23 that can be slidably mounted on the rail guides. Two support members on each side of the rack assembly are configured for mounting on the rail guides.
  • the support members 23 enable the rack assembly 20 to be suspended above the floor of the channel 18 and to allow the pivoting blade 21 to pivot between the first and second positions.
  • the support member 23 is made of polyurethane and includes VEE slide blocks which allows it to be slidably mounted on the rail guides.
  • the pivoting blade 21 is pivotally mounted to the rack assembly by a pivot bearing (not shown) on each side of the blade to allow the blade to pivot freely.
  • Figure 6 is a plan view of the rack assembly when mounted on the rail guides of one of the channels 18.
  • the rack assembly 20 is affixed to the cable 16 at approximately midway of the rack assembly.
  • the support members 23 are located on each side of the rack assembly 20 and configured such that the rack assembly is slidably mounted on the rail guides in a secure position.
  • the pivoting blade 21 includes a yoke 24 for affixing to the cable 16.
  • a clamping member 25 clamps the yoke securely onto the cable 16.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Finish Polishing, Edge Sharpening, And Grinding By Specific Grinding Devices (AREA)

Abstract

L'invention concerne un système de récupération de sol pour des travaux de dynamitage abrasifs. Le système comprend au moins un bâti mobile le long de chacun d'une pluralité de canaux longitudinaux pour transporter des produits abrasifs après usage à partir du sol du canal longitudinal vers un collecteur. Il comprend en outre une longueur de câble continue configurée pour se déplacer dans une première direction pour effectuer un mouvement dudit au moins un bâti dans la première direction le long du canal longitudinal, et mobile dans une seconde direction pour effectuer un mouvement dudit au moins un bâti dans la seconde direction le long du canal longitudinal. En outre, une poupée de treuil configurée pour venir en prise avec les extrémités du câble est fournie, la poupée de treuil pouvant tourner pour effectuer le mouvement du câble dans la première direction et la seconde direction.
PCT/SG2013/000523 2013-12-10 2013-12-10 Système de récupération de sol pour des travaux de dynamitage WO2015088439A1 (fr)

Priority Applications (1)

Application Number Priority Date Filing Date Title
PCT/SG2013/000523 WO2015088439A1 (fr) 2013-12-10 2013-12-10 Système de récupération de sol pour des travaux de dynamitage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/SG2013/000523 WO2015088439A1 (fr) 2013-12-10 2013-12-10 Système de récupération de sol pour des travaux de dynamitage

Publications (1)

Publication Number Publication Date
WO2015088439A1 true WO2015088439A1 (fr) 2015-06-18

Family

ID=53371578

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/SG2013/000523 WO2015088439A1 (fr) 2013-12-10 2013-12-10 Système de récupération de sol pour des travaux de dynamitage

Country Status (1)

Country Link
WO (1) WO2015088439A1 (fr)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112744243A (zh) * 2019-10-31 2021-05-04 比亚迪股份有限公司 轨道车辆

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3530832A (en) * 1968-04-03 1970-09-29 Mag Eng Inc De Apparatus for use in removing manure from buildings having manure collecting channels
US3790007A (en) * 1971-11-09 1974-02-05 B Sprague Abrasive recovery system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3530832A (en) * 1968-04-03 1970-09-29 Mag Eng Inc De Apparatus for use in removing manure from buildings having manure collecting channels
US3790007A (en) * 1971-11-09 1974-02-05 B Sprague Abrasive recovery system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112744243A (zh) * 2019-10-31 2021-05-04 比亚迪股份有限公司 轨道车辆

Similar Documents

Publication Publication Date Title
KR101658829B1 (ko) 스크류 컨베이어 스케일 제거 장치
US3900968A (en) Mobile cleaning and polishing device
JP2008260628A (ja) ベルトクリーニング装置
CN205366966U (zh) 一种自动旋转的皮带清扫器
US3790007A (en) Abrasive recovery system
WO2015088439A1 (fr) Système de récupération de sol pour des travaux de dynamitage
CN214651784U (zh) 一种钢材生产用的钢材推送装置
CN105500101B (zh) 切割机
CN202377900U (zh) 钢丝盘条除锈机
CA3033894C (fr) Crible a rouleaux auto-nettoyant
CN107257705B (zh) 用于从气流中分离颗粒的装置和方法
KR20090110396A (ko) 대차운반용 셔틀레일의 이물질 제거장치
CN104670804A (zh) 活动式刮板输送机
CN107399586A (zh) 一种输送带的清理装置
CN109772511B (zh) 用于对废钢回收处理的设备
KR100905110B1 (ko) 벨트컨베이어의 진행방향에 따라 자동탈착이 가능한클리너장치
CN112777239A (zh) 一种多用途的传送带用变速箱
CN210171762U (zh) 一种可行走带旋转的自动喷漆系统
KR20170055947A (ko) 스트립 방향전환 롤 표면의 이물질 제거장치
CN209720892U (zh) 重型板式给矿机粉矿清理装置
JP2015000782A (ja) コンベヤベルトの付着物除去装置及び付着物除去方法
CN219747581U (zh) 一种轨道抛丸清理机
CN104495235B (zh) 一种挡煤刮板机
CN110900014A (zh) 一种全自动上料激光切管机
CN214526449U (zh) 输送机尾轮部

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 13899172

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 13899172

Country of ref document: EP

Kind code of ref document: A1