WO2014033155A1 - Controlling a modular converter in two stages - Google Patents

Controlling a modular converter in two stages Download PDF

Info

Publication number
WO2014033155A1
WO2014033155A1 PCT/EP2013/067791 EP2013067791W WO2014033155A1 WO 2014033155 A1 WO2014033155 A1 WO 2014033155A1 EP 2013067791 W EP2013067791 W EP 2013067791W WO 2014033155 A1 WO2014033155 A1 WO 2014033155A1
Authority
WO
WIPO (PCT)
Prior art keywords
converter
vector
modular converter
reference vector
control
Prior art date
Application number
PCT/EP2013/067791
Other languages
French (fr)
Inventor
Tobias Geyer
Original Assignee
Abb Technology Ag
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Abb Technology Ag filed Critical Abb Technology Ag
Priority to EP13758794.5A priority Critical patent/EP2891240A1/en
Priority to CN201380045206.XA priority patent/CN104584414B/en
Priority to BR112015004285A priority patent/BR112015004285A2/en
Publication of WO2014033155A1 publication Critical patent/WO2014033155A1/en
Priority to US14/629,674 priority patent/US9590530B2/en

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02MAPPARATUS FOR CONVERSION BETWEEN AC AND AC, BETWEEN AC AND DC, OR BETWEEN DC AND DC, AND FOR USE WITH MAINS OR SIMILAR POWER SUPPLY SYSTEMS; CONVERSION OF DC OR AC INPUT POWER INTO SURGE OUTPUT POWER; CONTROL OR REGULATION THEREOF
    • H02M7/00Conversion of ac power input into dc power output; Conversion of dc power input into ac power output
    • H02M7/42Conversion of dc power input into ac power output without possibility of reversal
    • H02M7/44Conversion of dc power input into ac power output without possibility of reversal by static converters
    • H02M7/48Conversion of dc power input into ac power output without possibility of reversal by static converters using discharge tubes with control electrode or semiconductor devices with control electrode
    • H02M7/483Converters with outputs that each can have more than two voltages levels
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02HEMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
    • H02H7/00Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions
    • H02H7/10Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions for converters; for rectifiers
    • H02H7/12Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions for converters; for rectifiers for static converters or rectifiers
    • H02H7/122Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions for converters; for rectifiers for static converters or rectifiers for inverters, i.e. dc/ac converters
    • H02H7/1227Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions for converters; for rectifiers for static converters or rectifiers for inverters, i.e. dc/ac converters responsive to abnormalities in the output circuit, e.g. short circuit
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02MAPPARATUS FOR CONVERSION BETWEEN AC AND AC, BETWEEN AC AND DC, OR BETWEEN DC AND DC, AND FOR USE WITH MAINS OR SIMILAR POWER SUPPLY SYSTEMS; CONVERSION OF DC OR AC INPUT POWER INTO SURGE OUTPUT POWER; CONTROL OR REGULATION THEREOF
    • H02M7/00Conversion of ac power input into dc power output; Conversion of dc power input into ac power output
    • H02M7/42Conversion of dc power input into ac power output without possibility of reversal
    • H02M7/44Conversion of dc power input into ac power output without possibility of reversal by static converters
    • H02M7/48Conversion of dc power input into ac power output without possibility of reversal by static converters using discharge tubes with control electrode or semiconductor devices with control electrode
    • H02M7/483Converters with outputs that each can have more than two voltages levels
    • H02M7/4835Converters with outputs that each can have more than two voltages levels comprising two or more cells, each including a switchable capacitor, the capacitors having a nominal charge voltage which corresponds to a given fraction of the input voltage, and the capacitors being selectively connected in series to determine the instantaneous output voltage
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02MAPPARATUS FOR CONVERSION BETWEEN AC AND AC, BETWEEN AC AND DC, OR BETWEEN DC AND DC, AND FOR USE WITH MAINS OR SIMILAR POWER SUPPLY SYSTEMS; CONVERSION OF DC OR AC INPUT POWER INTO SURGE OUTPUT POWER; CONTROL OR REGULATION THEREOF
    • H02M7/00Conversion of ac power input into dc power output; Conversion of dc power input into ac power output
    • H02M7/42Conversion of dc power input into ac power output without possibility of reversal
    • H02M7/44Conversion of dc power input into ac power output without possibility of reversal by static converters
    • H02M7/48Conversion of dc power input into ac power output without possibility of reversal by static converters using discharge tubes with control electrode or semiconductor devices with control electrode
    • H02M7/53Conversion of dc power input into ac power output without possibility of reversal by static converters using discharge tubes with control electrode or semiconductor devices with control electrode using devices of a triode or transistor type requiring continuous application of a control signal
    • H02M7/537Conversion of dc power input into ac power output without possibility of reversal by static converters using discharge tubes with control electrode or semiconductor devices with control electrode using devices of a triode or transistor type requiring continuous application of a control signal using semiconductor devices only, e.g. single switched pulse inverters
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02MAPPARATUS FOR CONVERSION BETWEEN AC AND AC, BETWEEN AC AND DC, OR BETWEEN DC AND DC, AND FOR USE WITH MAINS OR SIMILAR POWER SUPPLY SYSTEMS; CONVERSION OF DC OR AC INPUT POWER INTO SURGE OUTPUT POWER; CONTROL OR REGULATION THEREOF
    • H02M1/00Details of apparatus for conversion
    • H02M1/0003Details of control, feedback or regulation circuits

Definitions

  • the invention relates to a method for controlling a modular converter, a controller for controlling a modular converter and a modular converter with such a controller.
  • Modular converters and in particular modular multi-level converters are used for synthesizing voltages to be supplied to a load, for example an electrical motor or an electrical grid.
  • the modular structure of modular converters offers a number of advantages such as modularity, scalability, high output voltage and low output current distortions.
  • a standard approach to achieve closed-loop control of a modular converter is to divide the control problem into two hierarchical upper and lower stages or layers.
  • the upper, first stage may be based on vector control with a modulator.
  • the vector control scheme may operate in a dq reference frame.
  • closed- loop control of load currents may be achieved.
  • PWM pulse width modulation
  • SVM space vector modulation
  • Circulating currents and/or an energy balance within converter branches may be addressed by adding additional control loops.
  • the lower control stage utilizes the redundancy in the converter states (i.e. groups of switching states that produce the same line to line voltage) in order to balance the capacitor voltages.
  • the capacitor voltages may be sorted in an ascending/descending order of their voltage values. For a charging current the capacitors with the lowest voltages may be selected first, and conversely, the capacitors with the highest voltages may be prioritized for discharging currents.
  • An aspect of the invention relates to a method for controlling a modular converter.
  • the modular converter comprises a plurality of converter modules that may comprise semiconductor switches and at least one capacitor.
  • the modular converter is adapted for converting at least one input voltage into at least one output voltage to be supplied to a load.
  • the modular converter may connect a grid with an electrical rotating machine like a motor or a generator or may interconnect two electrical grids.
  • the modular converter may be a modular multi-level converter.
  • the modular converter may be an AC-to-DC converter, a DC-to-AC converter, or an AC-to-AC converter.
  • the method for controlling the converter comprises the steps of: receiving a control input reference vector, a control input vector and a control input parameter vector; determining a control output reference vector from the control input reference vector, the control input vector and the control input parameter vector in a first control stage (or layer); and controlling the converter modules by generating switching signals from the control output vector in a further control stage or control layer.
  • the different control stages or control layers may be implemented in different controllers.
  • the control method may supersede the vector control scheme as described above.
  • the control input reference vector i. e. a reference vector input to the first control stage
  • the control input vector may be an actual current vector that may have been estimated or measured from actual currents and/or voltages in the modular converter.
  • a vector may contain only one entry, i.e. that a vector comprises only a value. However, usually, a vector may contain at least two entries.
  • the control output reference vector (i.e. a reference vector output from the first control stage) may be a voltage reference vector that is input to the next control stage, which may be a modulator.
  • the variable manipulated by the first control stage may be a real-valued (voltage) reference for a modulator.
  • control output reference vector is determined by: predicting at least one future state of the modular converter with a prediction model of the converter; optimizing the at least one future state with respect to an objective function; and determining the control output reference vector from the future state.
  • the first control stage is adapted for predicting the evolution of an internal state vector of the modular converter (and optionally the load) and of the control output reference vector and for optimizing the control output reference vector such that the future state, or a subset of it, approaches the control input reference vector and that further control objectives like, for example, minimal switching efforts or keeping some variables within some constraints, are achieved.
  • a next control output reference vector may be determined from which the next switching state can be derived.
  • the prediction model may be a mathematical model of the modular converter and optionally the load that is implemented in the first control stage.
  • the prediction model may be adapted for calculating the future state of the converter based on an actual state of the converter.
  • An (actual and/or future) state of the modular converter may comprise current values and/or voltage values of the modular converter.
  • the actual state may comprise the control input vector and the control input parameter vector.
  • the future state may comprise an evolution of the control input vector and the control input parameter vector.
  • the prediction horizon of the prediction model needs not be one time step but may have any length.
  • the prediction model may allow the first stage to predict the system response of control actions, using a prediction horizon of any length.
  • the model may be given in state-space form.
  • a state of the modular converter may be any vector of quantities related to the evolution of currents and/or voltages in the modular converter (and optionally the load).
  • a state or state vector of the converter may comprise at least one of an upper and lower branch current and/or voltage and a DC link current and/or voltage, an output current and/or voltage and a circulating current. All these voltages and/or currents for an actual time step may be measured in the modular converter or may be estimated from other quantities. These voltages and/or currents may be used for determining, estimating and/or calculating the future state of the modular converter.
  • the objective function may be a real- valued, scalar function implemented in the first control stage.
  • the objective function may penalize differences between the control input reference vector at a time step and the predicted evolution of the control input vector at this time step.
  • the objective function may be based on a cost value associated with switching costs of the converter modules. In such a way, a scalar cost value or performance index is associated with the predicted control actions and the corresponding predicted system response. For example, a penalty on manipulating a commanded branch voltage may be used, as well as a penalty on a predicted current error (for example a difference between the input current reference vector and the predicted evolution of the input current vector).
  • the first stage may minimize the objective function with respect to constraints and the dynamical evolution in time of the prediction model
  • the dynamics of the modular converter may be predicted, which may result in an optimal sequence of control actions.
  • All the control stages of the method may be implemented in a controller of the modular converter.
  • This controller may be adapted for manipulating the branch voltages of the modular converter such that the following control objectives may be achieved:
  • Currents associated with the control input vector may be regulated along their given references (associated with the control input reference vector). For example, there may be five currents to be regulated, assuming a three-phase modular converter with a load, whose star point is not connected to ground. These five currents may be either five branch currents (the sixth branch current depends on the other five currents) or two load currents plus three circulating currents.
  • Constraints on the currents may be imposed and met, such as upper constraints and rate constraints on the branch, load, circulating and DC-link currents. Moreover, per phase leg, the sum of the upper and lower commanded branch voltages may be less than the DC-link voltage. Additional constraints on voltages and currents may be imposed, for example regarding the load.
  • control input reference vector is a current reference vector and the control input vector is an actual current vector.
  • the control input parameter vector may be an actual voltage vector, i.e. a vector of actual determined and/or measured voltages values.
  • the control output reference vector may be a voltage reference vector.
  • the control method may be a method controlling currents by manipulating (branch) voltages.
  • a sequence of future states or future state vectors is predicted for a plurality of time steps in the future, i.e. over a prediction horizon with a length of more than one time step.
  • the control output reference vector may be determined from the next future state associated with the next time step, for example by solving the underlying mathematical optimization problem, which may be a quadratic program (QP).
  • QP quadratic program
  • a receding horizon policy may be used for determining the next control action for the next time step. This may mean that only the first element of the optimal sequence of control actions is implemented, i.e. used for driving the switches of the converter modules.
  • new measurements may be obtained and the optimization problem may be solved again over a shifted prediction horizon.
  • the prediction model is based on linear equations relating voltages and/or currents at a time step with voltages and/or currents at a next time step.
  • the equations may be derived from the topology of the modular converter and Kirchhoff s laws.
  • the prediction model comprises a model of the converter modules and/or a model of the load.
  • the prediction model may model capacitors of the converter modules and may be adapted to predict an evolution of the capacitor voltages.
  • the prediction model may comprise a model of the load and may be adapted to predict an evolution of a load (grid) voltage.
  • Models of higher order load systems including AC machines, loads with filters, loads with long cables, loads with transformers, etc. may be included in the prediction model.
  • the method further comprises the step of: compensating a time delay caused by the determination of the control output reference vector by predicting currents and/or voltages, for example the control input reference vector and the control input vector, at the next time step with the use of actual currents and/or , for example the actual control output vector, the actual control input reference vector and the actual control input vector.
  • the computation of the next control action usually takes most of the time of one time step.
  • the control output reference vector may be calculated such that the control action (i.e. the switching commands) are applied at the time, the prediction has started from.
  • the objective function minimizes a change in an evolution of the control output reference vector over time.
  • the control output reference vector comprises voltages
  • the objective function minimizes voltage changes in the evolution of these voltages over time.
  • the objective function may comprise a term in which a norm is applied to the difference between two consecutive control output reference vectors.
  • the objective function is based on a quadratic norm.
  • components of the current/and or voltage vectors may be weighting differently.
  • the control input vector may comprise branch currents, and circulating currents, which may be weighted with different weights.
  • solving the prediction model may result in a quadratic programming problem.
  • the objective function is based on a linear norm.
  • solving the prediction model may result in a linear programming problem, which may be fast to solve.
  • the method further comprises the step of: determining a voltage vector from the control output reference vector in a second control stage with a modulator; and controlling the converter modules by generating switching signals from the voltage vector in a third control stage.
  • the control method may be applied in a modular AC-DC, DC-AC and AC-AC converter with a modulator.
  • the method further comprises the step of: controlling the converter modules by generating switching signals from a rounded control output reference vector.
  • the voltage reference vector input to the third control stage may be generated by only rounding the output reference vector (for example a voltage reference vector). In such a way, the switching signals may be generated directly from the output reference vector without a modulator.
  • each converter modules of the modular multilevel converter comprises two power connectors, at least two power semiconductors and a capacitor, wherein the power connectors are short-circuited in a first switching state of the power semiconductors and are connected to the capacitor in a second switching state of the power semiconductors.
  • the converter modules are serially connected by their power connectors.
  • the method further comprises the step of: detecting a converter module with a fault; short-circuiting the detected converter module; and removing the short-circuited converter model from the prediction model.
  • the control method may use an automatic reconfiguration of the prediction model, when the topology of the modular converter changes.
  • the converter modules of the modular converter and/or the load may be monitored in real-time. If a converter module fails and its terminals are shorted to bypass it, the number of converter modules available may be automatically updated and the internal prediction model of the controller may be adjusted accordingly. As a result, the control method may take the fact that some modules might be shortened into account and may use switching actions that, within the physical limitations of the converter, compensate for these shortened modules. Similarly, if a fault, disturbance and/or imbalance etc. occurs at the load, the prediction model is updated accordingly, too, and the controller compensates for this.
  • a further aspect of the invention relates to a controller for controlling a modular converter, which is adapted to perform the first stage of the control method.
  • control method may be implemented on any computational hardware including DSPs, FPGAs, CPUs and processor cores.
  • other stage of the control method may be implemented in a separate controller.
  • the controller is adapted to perform the following steps: predicting at least one future state of the modular converter with a prediction model of the modular converter, wherein the prediction model is adapted for calculating the future state of the modular converter based on an actual state of the converter, a state of the modular converter comprising current values and/or voltage values of the modular converter and/or load; optimizing the at least one future state with respect to an objective function, in particular subject to constraints and the dynamical evolution of the prediction model, wherein the objective function is based a cost value associated with switching costs or an switching effort of converter modules of the modular converter; and determining a control output reference vector from the future state.
  • a further aspect of the invention relates to a computer program that, when being executed by a processor, is adapted to perform the steps of the method the controller is adapted to perform and/or the steps of the method as described in the above and in the following.
  • a further aspect of the invention relates to a computer-readable medium on which such a computer program is stored.
  • a computer-readable medium may be a floppy disk, a hard disk, an USB (Universal Serial Bus) storage device, a RAM (Random Access Memory), a ROM (Read Only memory) and an EPROM (Erasable Programmable Read Only Memory).
  • a computer- readable medium may also be a data communication network, e.g. the Internet, which allows downloading a program code.
  • a further aspect of the invention relates to a modular converter for supplying a load with electrical voltages and/or currents.
  • the converter comprises a plurality of converter modules comprising semiconductor switches and a capacitor; a first controller as for performing the first stage of the control method as described in the above and in the following, the first controller generating a control output reference vector; and a further controller for generating switching signals for the converter modules based on the control output reference vector.
  • the modular converter is a modular multilevel converter. It has to be understood that features of the method as described in the above and in the following may be features of the controller and/or the modular converter as described in the above and in the following.
  • the controller may be seen as a model predictive current controller (MPCC), which may be adapted for regulating the branch, phase and/or circulating currents around their given references, by manipulating the total (continuous-valued) branch voltages.
  • MPCC model predictive current controller
  • Upper current constraints as well as rate constraints may be addressed by the MPC method.
  • the current references may be provided by an outer loop.
  • a modulator may be used to translate the branch voltage commands to integer numbers, which refer to the number of modules per branch being turned on.
  • a subsequent balancing method may be used to maintain the capacitor voltages around their references and to decide on the individual modules being turned on and off.
  • the proposed MPC method may be used to address a current control problem of modular multi-level converters with a large number of converter modules per converter branch.
  • the controller may achieve very short response times during transients and may require only a modest computational power.
  • the MPC method may be used to provide fast torque control for a modular mult i- level converter driving an AC rotating machine.
  • the method may be used for all applications of a modular multi-level converter, including variable speed drives, high- voltage direct current transmission, flexible AC transmission systems, static synchronous compensators, grid-interfaces for battery energy storage systems or photovoltaic modules, traction applications, etc.
  • the control method is highly flexible allowing one to incorporate and address different control objectives and operation requirements.
  • Fig. 1 schematically shows a modular converter according to an embodiment of the invention.
  • Fig. 2 schematically shows a converter module for a modular converter according to an embodiment of the invention.
  • Fig. 3 schematically shows a controller for a modular converter according to an embodiment of the invention.
  • Fig. 4 shows a flow diagram for a method for controlling a modular converter according to an embodiment of the invention.
  • Fig. 5 schematically shows a prediction model according to an embodiment of the invention.
  • Fig. 6 shows a diagram with sequences of control actions and predicted output sequences according to an embodiment of the invention.
  • Fig. 1 schematically shows a modular converter 10 with three converter phase legs 12 that interconnect a DC link 14 with an active three-phase resistive-inductive (RL) load 16.
  • Each of the phase legs 12 comprises an upper and a lower branch 20 interconnecting the positive and negative sides of the DC link 14 with one phase of the load 16.
  • the modular converter 10 may comprise converter modules 22, M pq , with p e ⁇ a, b,c ⁇ and q e ⁇ 1,2, ...n ⁇ , where n is the number of converter modules 22 per phase leg 12.
  • the modular converter 10 may comprise any number of converter modules 22 per phase leg 12.
  • Each branch 20 comprises n/2 modules 22, a resistor /?, that models conduction losses and a branch inductor L.
  • the DC link 14 is shown with a DC supply inductor L dc and a resistor R dc that model the parasitic inductance and resistance, respectively.
  • the modular converter 10 may provide n+1 voltage levels at each of its output terminals 24, V p , p E ⁇ a, b, c ⁇ , with respect to the supply ground 26, N.
  • the output terminals 24 are connected to the load 16, which comprises load inductor L l in series with a load resistor and the grid voltage V g p .
  • Fig. 2 shows a converter module 22 or converter cell 22 of the modular converter 10.
  • the converter module comprises two semiconductor switches 28 connected in series, which are connected in parallel to two free-wheeling diodes 30 and to a capacitor 32. It is also possible to incorporate the functionality of the free-wheeling diode into the semiconductor switch.
  • Each converter module 22 acts as a chopper cell with the capacitor 32, C pq .
  • Each converter module 22 has two switching states, u pq E ⁇ 0,1 ⁇ , where 1 means that the capacitor is connected to the branch 20, i.e. the upper switch 28, S pq T is turned on. The operation of the two switches 28 is complementary to one another.
  • a resistor R cap is shown in parallel to the capacitor 32 to model the leakage current of the capacitor 32.
  • each converter module 22 comprises two power connectors, at least two power semiconductors 28 and the capacitor 32, wherein the power connectors are short-circuited in a first switching state of the semiconductors and are connected to the capacitor in a second switching state of the semiconductors 28.
  • Fig. 3 schematically shows a controller 40 for the modular converter 10.
  • the controller 40 comprises three controller stages 42, 44, 46, i.e. an upper (current) controller 42, a modulator 44 and a lower (balancing) controller 46.
  • Fig. 4 shows a flow diagram for controlling the modular converter 10.
  • the controller 42 receives a controller input reference vector 48 in the form of a current reference vector 48, i , a controller input vector 50 in the form of a current vector 50, / and a controller input parameter vector 51 in the form of a parameter vector 51, v p .
  • the current vector 50 comprises one or more actual currents measured in the circuit of the modular converter 10 or estimated from other quantities measured in the circuit of the converter 10.
  • the controller 42 determines a control output reference vector 52 in the form of a voltage reference vector 52 from the control input reference vector 48, the control input vector 50 and the control input parameter vector 51. Steps 60, 62, 64 will be explained in the following in more detail.
  • a voltage vector 54 is derived from the control output vector 52.
  • an optional modulator 44 may perform a pulse-width modulation method or a space vector modulation method for generating a voltage vector 54 from the voltage reference vector 52.
  • the voltage vector 54 may be determined based on a rounding of the control output vector 52.
  • the modulator 44 may be replaced by a simple rounding scheme.
  • Such a rounding scheme may round a real- valued branch voltage to an integer number, corresponding to the number of converter modules 22 per branch 20 being turned on.
  • the balancing controller 46 directly controls the converter modules 22 by generating switching or gating signals 56 for the switches 28 from the voltage vector 54.
  • Fig. 5 shows a prediction model 80 for the modular converter 10, which is used in step 62 to predict future states of the modular converter 10.
  • the prediction model 80 may model a part of the circuitry of the modular converter 10 and the load 16. For example, with Kirchhof s laws, equations may be derived from the circuitry of the converter 10 that present a part of the prediction model 80.
  • the converter modules 22 of one branch 20 may be treated as a voltage source 82 that has to be regulated by the controller 40.
  • i a (t) i a p (t) - iaN (t)
  • ib (t) ibp (t) - ibN (t)
  • i c (t) - i a p (t) + i aN (t) - ibp (t) + i bN (t)
  • the model state vector x [ i aP i aN i bP i bN i dc ] T of the prediction model 80 includes the upper branch currents i aP , i aN and the lower branch currents i bP , i bN of phase legs a and b, as well as the DC link current i dc .
  • the model input vector u [v aP v aN v bP v bN v cP v cN ] T E R 6 of the prediction model 80 comprises the six branch voltages v aP , v aN , v bP , v bN , v cP , v cN , which are assumed to be real-valued.
  • the model output vector y has five elements. One choice is to use two load currents, either i a and i b , or i a and ⁇ , i.e. the load currents represented in the stationary orthogonal coordinate system, along with the three circulating currents i ci a , idr.b, ir.c- An alternative choice for the model output vector y is to use the five branch currents of the model state vector x.
  • the state of the modular converter 10 may be modeled with the branch currents the branch voltages v aP , v aN , v bP , v bN , v cP , v cN , the DC link current i dc , the DC link voltage v dc , the output currents i a , i b , i c , and the grid voltages v ga , v gb , V gC of the load 16.
  • these quantities are not independent from each other.
  • Fig. 6 shows the evolution of the state of the modular converter 10 over the time t, which is depicted to the right.
  • Fig. 6 shows the past 90 to the left of the y-axis, and a prediction horizon 92 to the right of the y-axis.
  • a prediction model 80 may use a discrete time state-space representation with discrete time steps k. Then from an actual state 94 at time step k, a sequence of future states 96 is predicted for the time steps k+1 to k+N, where N is the length of the prediction horizon 92.
  • Fig. 6 schematically shows the predicted sequence 98 of model output vectors y and the predicted sequence 100 of model input vectors u for the time steps k to k+N-1.
  • a prediction model 80 of the following form can be derived. Note that the ⁇ -matrix is time-varying, since it includes the voltages of the capacitor 32 of the branch modules 22.
  • the evolution of the grid voltages may be included in the prediction model 80, by adding the two states v ga and ⁇ 9 ⁇ to the model state vector x and by modeling the rotation of the grid voltage vector, whose rotational speed is proportional to the grid frequency.
  • the prediction model 80 is adapted for calculating future states 96 of the modular converter 10 based on an actual state 94 of the modular converter.
  • the prediction model 80 may be formulated in different coordinate systems, including abc, ⁇ or dq, or a combination thereof.
  • step 64 the predicted future states 96 are optimized with respect to an objective function. It has to be noted, that the steps 62 and 64 may be performed in one operation by numerically solving a mathematical programming problem defined by matrix equations, further constraints and the objective function.
  • the objective function associates a scalar performance index with different predicted scenarios, i.e. the objective function is a real-valued function of the states and control actions of the modular converter 10.
  • the objective function includes penalties on the predicted evolution tracking error and the (change in the) control effort over the prediction horizon N.
  • y * denotes the time-varying current reference vector.
  • the matrices Q and R constitute penalty matrices on the current error and the change in the manipulated variable.
  • the objective function is based on differences between the control input reference vector 48 at time step / and the evolution of the control input vector 50 at time step /. Additionally, the objective function optimizes a cost value associated with switching costs of the converter modules 10 by minimizing the differences between the model input vectors u at time step / and time step I- 1.
  • the objective function is minimized subject to the evolution of the prediction model 80 from time-step k until k+N-1.
  • constraints on the currents which are included in x and y, may be included, as well as constraints on u.
  • Upper and lower constraints as well as rate constraints can be considered.
  • the state-space model is linear
  • the cost function is quadratic and the constraints are linear
  • the resulting optimization problem is a so-called quadratic program (QP).
  • the QP can be formulated and solved efficiently, e.g. by using an active set method or a fast gradient search method.
  • step 66 the controller 42 determines the control output reference vector 52 from the sequence 100 of future control actions by taking the first element u(k) of the first model input vector u at time step k.
  • the first element u(k) is the output reference vector 52.
  • a time delay caused by the computation of the control output reference vector 52 may be compensated for. This time delay typically amounts to the length of one sampling interval.
  • the model state vector x(k+l) at time step k+1 may be predicted, for which the prediction model 80 is solved.
  • a (piecewise) linear (instead of a quadratic) cost function may be used, for example based on absolute values and/or maximal values, leading to a linear program (LP) instead of a QP.
  • LP linear program
  • step 62 additional control loops may be added.
  • step 62 the occurrence of faults, loss of modules, voltage dips, load imbalances, disturbances and/or grid (or load) asymmetries, etc. may be monitored. If a fault or asymmetry is detected, the controller 42 adjusts its control actions so as to accommodate for this event within the physical limits, providing automatic controller reconfiguration.
  • the prediction model 80 is updated to a new topology taking into account the fault or asymmetry.
  • a higher order load system 16 may be considered, including AC machines, grids with transformers and loads with filters.
  • the prediction model 80, the model state vector x, the parameter vector v p and the output vector y may be augmented accordingly. While the invention has been illustrated and described in detail in the drawings and foregoing description, such illustration and description are to be considered illustrative or exemplary and not restrictive; the invention is not limited to the disclosed embodiments. Other variations to the disclosed embodiments can be understood and effected by those skilled in the art and practising the claimed invention, from a study of the drawings, the disclosure, and the appended claims. In the claims, the word “comprising” does not exclude other elements or steps, and the indefinite article “a” or “an” does not exclude a plurality.

Abstract

A modular converter comprises a plurality of converter modules (22) adapted for converting an input voltage into an output voltage to be supplied to a load (16). A method for controlling the modular converter (10) comprises the steps of: receiving a control input reference vector (48), a control input vector (50) and a control input parameter vector (51); determining a control output reference vector (52) from the control input reference vector (48), the control input vector (50) and the control input parameter vector (51) in a first control stage (42); and controlling the converter modules (22) by generating switching signals (56) based on the control output reference vector (52) in a further control stage (46). The control output reference vector (52) is determined by: predicting at least one future state (96) of the modular converter (10) with a prediction model (80) of the modular converter (10), wherein the prediction model (80) is adapted for calculating the future state of the modular converter (10) based on an actual state (94) of the converter, a state of the modular converter (10) comprising current values and/or voltage values of the modular converter (10); optimizing the at least one future state (96) with respect to an objective function, wherein the objective function is based on a cost value associated with switching costs of the converter modules (22); and determining the control output reference vector (52) from the future state (96).

Description

DESCRIPTION
Controlling a modular converter in two stages
FIELD OF THE INVENTION
The invention relates to a method for controlling a modular converter, a controller for controlling a modular converter and a modular converter with such a controller.
BACKGROUND OF THE INVENTION
Modular converters and in particular modular multi-level converters (M2LC) are used for synthesizing voltages to be supplied to a load, for example an electrical motor or an electrical grid. The modular structure of modular converters offers a number of advantages such as modularity, scalability, high output voltage and low output current distortions.
A standard approach to achieve closed-loop control of a modular converter is to divide the control problem into two hierarchical upper and lower stages or layers. The upper, first stage may be based on vector control with a modulator. The vector control scheme may operate in a dq reference frame. By manipulating the voltage reference, which is input to the modulator, closed- loop control of load currents may be achieved. For example, carrier-based pulse width modulation (PWM) or space vector modulation (SVM) may be used in a modulator. Circulating currents and/or an energy balance within converter branches may be addressed by adding additional control loops.
The lower control stage utilizes the redundancy in the converter states (i.e. groups of switching states that produce the same line to line voltage) in order to balance the capacitor voltages. The capacitor voltages may be sorted in an ascending/descending order of their voltage values. For a charging current the capacitors with the lowest voltages may be selected first, and conversely, the capacitors with the highest voltages may be prioritized for discharging currents.
DESCRIPTION OF THE INVENTION
It may be objects of the invention to simplify the development of controllers of modular converters, to provide more flexibility in the control objective of a modular converter, to minimize switching losses of a modular converter and/or to minimize the response time of a controller of a modular converter.
These objects are achieved by the subject-matter of the independent claims. Further exemplary embodiments are evident from the dependent claims and the following description.
An aspect of the invention relates to a method for controlling a modular converter.
The modular converter comprises a plurality of converter modules that may comprise semiconductor switches and at least one capacitor. The modular converter is adapted for converting at least one input voltage into at least one output voltage to be supplied to a load. For example, the modular converter may connect a grid with an electrical rotating machine like a motor or a generator or may interconnect two electrical grids. The modular converter may be a modular multi-level converter. The modular converter may be an AC-to-DC converter, a DC-to-AC converter, or an AC-to-AC converter.
According to an embodiment of the invention, the method for controlling the converter comprises the steps of: receiving a control input reference vector, a control input vector and a control input parameter vector; determining a control output reference vector from the control input reference vector, the control input vector and the control input parameter vector in a first control stage (or layer); and controlling the converter modules by generating switching signals from the control output vector in a further control stage or control layer. The different control stages or control layers may be implemented in different controllers. The control method may supersede the vector control scheme as described above. The control input reference vector (i. e. a reference vector input to the first control stage) may be a current reference vector and the control input vector may be an actual current vector that may have been estimated or measured from actual currents and/or voltages in the modular converter.
It has to be noted that a vector may contain only one entry, i.e. that a vector comprises only a value. However, usually, a vector may contain at least two entries.
The control output reference vector (i.e. a reference vector output from the first control stage) may be a voltage reference vector that is input to the next control stage, which may be a modulator. In other words, the variable manipulated by the first control stage may be a real-valued (voltage) reference for a modulator.
According to an embodiment of the invention, the control output reference vector is determined by: predicting at least one future state of the modular converter with a prediction model of the converter; optimizing the at least one future state with respect to an objective function; and determining the control output reference vector from the future state.
Summarized, the first control stage is adapted for predicting the evolution of an internal state vector of the modular converter (and optionally the load) and of the control output reference vector and for optimizing the control output reference vector such that the future state, or a subset of it, approaches the control input reference vector and that further control objectives like, for example, minimal switching efforts or keeping some variables within some constraints, are achieved. In such a way, a next control output reference vector may be determined from which the next switching state can be derived.
The prediction model may be a mathematical model of the modular converter and optionally the load that is implemented in the first control stage. The prediction model may be adapted for calculating the future state of the converter based on an actual state of the converter. An (actual and/or future) state of the modular converter may comprise current values and/or voltage values of the modular converter. The actual state may comprise the control input vector and the control input parameter vector. The future state may comprise an evolution of the control input vector and the control input parameter vector.
It has to be noted that the prediction horizon of the prediction model needs not be one time step but may have any length. The prediction model may allow the first stage to predict the system response of control actions, using a prediction horizon of any length. The model may be given in state-space form.
A state of the modular converter may be any vector of quantities related to the evolution of currents and/or voltages in the modular converter (and optionally the load). A state or state vector of the converter may comprise at least one of an upper and lower branch current and/or voltage and a DC link current and/or voltage, an output current and/or voltage and a circulating current. All these voltages and/or currents for an actual time step may be measured in the modular converter or may be estimated from other quantities. These voltages and/or currents may be used for determining, estimating and/or calculating the future state of the modular converter.
The objective function may be a real- valued, scalar function implemented in the first control stage. The objective function may penalize differences between the control input reference vector at a time step and the predicted evolution of the control input vector at this time step. The objective function may be based on a cost value associated with switching costs of the converter modules. In such a way, a scalar cost value or performance index is associated with the predicted control actions and the corresponding predicted system response. For example, a penalty on manipulating a commanded branch voltage may be used, as well as a penalty on a predicted current error (for example a difference between the input current reference vector and the predicted evolution of the input current vector).
The first stage may minimize the objective function with respect to constraints and the dynamical evolution in time of the prediction model
Summarized, in the first stage, the dynamics of the modular converter may be predicted, which may result in an optimal sequence of control actions. All the control stages of the method may be implemented in a controller of the modular converter. This controller may be adapted for manipulating the branch voltages of the modular converter such that the following control objectives may be achieved: Currents associated with the control input vector may be regulated along their given references (associated with the control input reference vector). For example, there may be five currents to be regulated, assuming a three-phase modular converter with a load, whose star point is not connected to ground. These five currents may be either five branch currents (the sixth branch current depends on the other five currents) or two load currents plus three circulating currents.
During transient operating conditions, including step changes in the load current references and in the presence of external disturbances, very short current response times may be achieved.
Constraints on the currents may be imposed and met, such as upper constraints and rate constraints on the branch, load, circulating and DC-link currents. Moreover, per phase leg, the sum of the upper and lower commanded branch voltages may be less than the DC-link voltage. Additional constraints on voltages and currents may be imposed, for example regarding the load.
According to an embodiment of the invention, the control input reference vector is a current reference vector and the control input vector is an actual current vector. The control input parameter vector may be an actual voltage vector, i.e. a vector of actual determined and/or measured voltages values. The control output reference vector may be a voltage reference vector. The control method may be a method controlling currents by manipulating (branch) voltages.
According to an embodiment of the invention, a sequence of future states or future state vectors is predicted for a plurality of time steps in the future, i.e. over a prediction horizon with a length of more than one time step. The control output reference vector may be determined from the next future state associated with the next time step, for example by solving the underlying mathematical optimization problem, which may be a quadratic program (QP). Moreover, a receding horizon policy may be used for determining the next control action for the next time step. This may mean that only the first element of the optimal sequence of control actions is implemented, i.e. used for driving the switches of the converter modules. At the next time step, new measurements may be obtained and the optimization problem may be solved again over a shifted prediction horizon.
According to an embodiment of the invention, the prediction model is based on linear equations relating voltages and/or currents at a time step with voltages and/or currents at a next time step. For example, the equations may be derived from the topology of the modular converter and Kirchhoff s laws.
According to an embodiment of the invention, the prediction model comprises a model of the converter modules and/or a model of the load. For example, the prediction model may model capacitors of the converter modules and may be adapted to predict an evolution of the capacitor voltages. The prediction model may comprise a model of the load and may be adapted to predict an evolution of a load (grid) voltage. Models of higher order load systems, including AC machines, loads with filters, loads with long cables, loads with transformers, etc. may be included in the prediction model.
According to an embodiment of the invention, the method further comprises the step of: compensating a time delay caused by the determination of the control output reference vector by predicting currents and/or voltages, for example the control input reference vector and the control input vector, at the next time step with the use of actual currents and/or , for example the actual control output vector, the actual control input reference vector and the actual control input vector. The computation of the next control action usually takes most of the time of one time step. By starting the prediction with voltages and/or currents predicted for the next time step, the control output reference vector may be calculated such that the control action (i.e. the switching commands) are applied at the time, the prediction has started from.
According to an embodiment of the invention, the objective function minimizes a change in an evolution of the control output reference vector over time. For example, in the case the control output reference vector comprises voltages, the objective function minimizes voltage changes in the evolution of these voltages over time. For example, the objective function may comprise a term in which a norm is applied to the difference between two consecutive control output reference vectors.
According to an embodiment of the invention, the objective function is based on a quadratic norm. In such a way, components of the current/and or voltage vectors may be weighting differently. For example, the control input vector may comprise branch currents, and circulating currents, which may be weighted with different weights. In this case, solving the prediction model may result in a quadratic programming problem.
According to an embodiment of the invention, the objective function is based on a linear norm. In this case, solving the prediction model may result in a linear programming problem, which may be fast to solve.
According to an embodiment of the invention, the method further comprises the step of: determining a voltage vector from the control output reference vector in a second control stage with a modulator; and controlling the converter modules by generating switching signals from the voltage vector in a third control stage. The control method may be applied in a modular AC-DC, DC-AC and AC-AC converter with a modulator.
According to an embodiment of the invention, the method further comprises the step of: controlling the converter modules by generating switching signals from a rounded control output reference vector. The voltage reference vector input to the third control stage may be generated by only rounding the output reference vector (for example a voltage reference vector). In such a way, the switching signals may be generated directly from the output reference vector without a modulator.
For modular multi-level converters, the number of converter modules per branch may be very high. A total branch voltage, which may be defined as the sum of the capacitor voltages of module capacitors connected to the branch, may then be approximated to be real-valued, rather than discrete. In such a modular mult i- level converter each converter modules of the modular multilevel converter comprises two power connectors, at least two power semiconductors and a capacitor, wherein the power connectors are short-circuited in a first switching state of the power semiconductors and are connected to the capacitor in a second switching state of the power semiconductors.
Within a branch of the modular multi-level converter the converter modules are serially connected by their power connectors.
According to an embodiment of the invention, the method further comprises the step of: detecting a converter module with a fault; short-circuiting the detected converter module; and removing the short-circuited converter model from the prediction model. The control method may use an automatic reconfiguration of the prediction model, when the topology of the modular converter changes.
For example, the converter modules of the modular converter and/or the load may be monitored in real-time. If a converter module fails and its terminals are shorted to bypass it, the number of converter modules available may be automatically updated and the internal prediction model of the controller may be adjusted accordingly. As a result, the control method may take the fact that some modules might be shortened into account and may use switching actions that, within the physical limitations of the converter, compensate for these shortened modules. Similarly, if a fault, disturbance and/or imbalance etc. occurs at the load, the prediction model is updated accordingly, too, and the controller compensates for this.
A further aspect of the invention relates to a controller for controlling a modular converter, which is adapted to perform the first stage of the control method.
For example, the control method may be implemented on any computational hardware including DSPs, FPGAs, CPUs and processor cores. Also the other stage of the control method may be implemented in a separate controller.
According to an embodiment of the invention, the controller is adapted to perform the following steps: predicting at least one future state of the modular converter with a prediction model of the modular converter, wherein the prediction model is adapted for calculating the future state of the modular converter based on an actual state of the converter, a state of the modular converter comprising current values and/or voltage values of the modular converter and/or load; optimizing the at least one future state with respect to an objective function, in particular subject to constraints and the dynamical evolution of the prediction model, wherein the objective function is based a cost value associated with switching costs or an switching effort of converter modules of the modular converter; and determining a control output reference vector from the future state.
A further aspect of the invention relates to a computer program that, when being executed by a processor, is adapted to perform the steps of the method the controller is adapted to perform and/or the steps of the method as described in the above and in the following. A further aspect of the invention relates to a computer-readable medium on which such a computer program is stored.
A computer-readable medium may be a floppy disk, a hard disk, an USB (Universal Serial Bus) storage device, a RAM (Random Access Memory), a ROM (Read Only memory) and an EPROM (Erasable Programmable Read Only Memory). A computer- readable medium may also be a data communication network, e.g. the Internet, which allows downloading a program code.
A further aspect of the invention relates to a modular converter for supplying a load with electrical voltages and/or currents.
According to an embodiment of the invention, the converter comprises a plurality of converter modules comprising semiconductor switches and a capacitor; a first controller as for performing the first stage of the control method as described in the above and in the following, the first controller generating a control output reference vector; and a further controller for generating switching signals for the converter modules based on the control output reference vector.
According to an embodiment of the invention, the modular converter is a modular multilevel converter. It has to be understood that features of the method as described in the above and in the following may be features of the controller and/or the modular converter as described in the above and in the following.
Summarized, a method and a controller for controlling a modular converter are described, which may use the concepts of model predictive control (MPC). The controller may be seen as a model predictive current controller (MPCC), which may be adapted for regulating the branch, phase and/or circulating currents around their given references, by manipulating the total (continuous-valued) branch voltages. Upper current constraints as well as rate constraints may be addressed by the MPC method. The current references may be provided by an outer loop. A modulator may be used to translate the branch voltage commands to integer numbers, which refer to the number of modules per branch being turned on. A subsequent balancing method may be used to maintain the capacitor voltages around their references and to decide on the individual modules being turned on and off.
The proposed MPC method may be used to address a current control problem of modular multi-level converters with a large number of converter modules per converter branch. The controller may achieve very short response times during transients and may require only a modest computational power. The MPC method may be used to provide fast torque control for a modular mult i- level converter driving an AC rotating machine.
The method may be used for all applications of a modular multi-level converter, including variable speed drives, high- voltage direct current transmission, flexible AC transmission systems, static synchronous compensators, grid-interfaces for battery energy storage systems or photovoltaic modules, traction applications, etc. The control method is highly flexible allowing one to incorporate and address different control objectives and operation requirements. These and other aspects of the invention will be apparent from and elucidated with reference to the embodiments described hereinafter. BRIEF DESCRIPTION OF THE DRAWINGS
The subject-matter of the invention will be explained in more detail in the following text with reference to exemplary embodiments which are illustrated in the attached drawings.
Fig. 1 schematically shows a modular converter according to an embodiment of the invention.
Fig. 2 schematically shows a converter module for a modular converter according to an embodiment of the invention.
Fig. 3 schematically shows a controller for a modular converter according to an embodiment of the invention.
Fig. 4 shows a flow diagram for a method for controlling a modular converter according to an embodiment of the invention.
Fig. 5 schematically shows a prediction model according to an embodiment of the invention.
Fig. 6 shows a diagram with sequences of control actions and predicted output sequences according to an embodiment of the invention.
In principle, identical parts are provided with the same reference symbols in the figures.
DETAILED DESCRIPTION OF EXEMPLARY EMBODIMENTS
Fig. 1 schematically shows a modular converter 10 with three converter phase legs 12 that interconnect a DC link 14 with an active three-phase resistive-inductive (RL) load 16. Each of the phase legs 12 comprises an upper and a lower branch 20 interconnecting the positive and negative sides of the DC link 14 with one phase of the load 16. The modular converter 10 is a modular multi-level converter with n=2 series-connected converter modules 22 per branch 20.
In general, the modular converter 10 may comprise converter modules 22, Mpq, with p e {a, b,c} and q e {1,2, ...n\ , where n is the number of converter modules 22 per phase leg 12. The modular converter 10 may comprise any number of converter modules 22 per phase leg 12. Each branch 20 comprises n/2 modules 22, a resistor /?, that models conduction losses and a branch inductor L. The DC link 14 is shown with a DC supply inductor Ldc and a resistor Rdc that model the parasitic inductance and resistance, respectively. The modular converter 10 may provide n+1 voltage levels at each of its output terminals 24, Vp, p E {a, b, c}, with respect to the supply ground 26, N. The output terminals 24 are connected to the load 16, which comprises load inductor Ll in series with a load resistor and the grid voltage Vg p.
Fig. 2 shows a converter module 22 or converter cell 22 of the modular converter 10. The converter module comprises two semiconductor switches 28 connected in series, which are connected in parallel to two free-wheeling diodes 30 and to a capacitor 32. It is also possible to incorporate the functionality of the free-wheeling diode into the semiconductor switch.
Each converter module 22 acts as a chopper cell with the capacitor 32, Cpq . Each converter module 22 has two switching states, upq E {0,1}, where 1 means that the capacitor is connected to the branch 20, i.e. the upper switch 28, Spq T is turned on. The operation of the two switches 28 is complementary to one another. A resistor Rcap is shown in parallel to the capacitor 32 to model the leakage current of the capacitor 32.
Thus each converter module 22 comprises two power connectors, at least two power semiconductors 28 and the capacitor 32, wherein the power connectors are short-circuited in a first switching state of the semiconductors and are connected to the capacitor in a second switching state of the semiconductors 28. Fig. 3 schematically shows a controller 40 for the modular converter 10. The controller 40 comprises three controller stages 42, 44, 46, i.e. an upper (current) controller 42, a modulator 44 and a lower (balancing) controller 46.
The operation of the controller 40 will be explained with reference to Fig. 4, which shows a flow diagram for controlling the modular converter 10.
In step 60, the controller 42 receives a controller input reference vector 48 in the form of a current reference vector 48, i ,a controller input vector 50 in the form of a current vector 50, / and a controller input parameter vector 51 in the form of a parameter vector 51, vp. For example, the current vector 50 comprises one or more actual currents measured in the circuit of the modular converter 10 or estimated from other quantities measured in the circuit of the converter 10. In steps 62, 64, 66, the controller 42 determines a control output reference vector 52 in the form of a voltage reference vector 52 from the control input reference vector 48, the control input vector 50 and the control input parameter vector 51. Steps 60, 62, 64 will be explained in the following in more detail. In step 68, a voltage vector 54 is derived from the control output vector 52. For example, an optional modulator 44 may perform a pulse-width modulation method or a space vector modulation method for generating a voltage vector 54 from the voltage reference vector 52.
Alternatively, the voltage vector 54 may be determined based on a rounding of the control output vector 52. For example, for a sufficiently large number of converter modules 22 per branch 20, the modulator 44 may be replaced by a simple rounding scheme. Such a rounding scheme may round a real- valued branch voltage to an integer number, corresponding to the number of converter modules 22 per branch 20 being turned on. In step 70, the balancing controller 46 directly controls the converter modules 22 by generating switching or gating signals 56 for the switches 28 from the voltage vector 54. Fig. 5 shows a prediction model 80 for the modular converter 10, which is used in step 62 to predict future states of the modular converter 10.
In general, the prediction model 80 may model a part of the circuitry of the modular converter 10 and the load 16. For example, with Kirchhof s laws, equations may be derived from the circuitry of the converter 10 that present a part of the prediction model 80.
Furthermore, the converter modules 22 of one branch 20 may be treated as a voltage source 82 that has to be regulated by the controller 40.
For example, for the topology shown in Fig. 1, the output equations for the load current in phases a, b and c are as follows:
ia(t) = iap (t) - iaN (t)
ib (t) = ibp (t) - ibN (t)
ic(t) = - iap (t) + iaN (t) - ibp (t) + ibN (t)
The equation which defines the circulating currents in phases a, b and c is as follows: iCir,p (t) = — - + — ^ 3" ' p e ta' b' c}
These state equations may be derived by applying Kirchhoffs voltage law around the five circuit meshes of the circuit shown in Fig. 1. Note that these equations are independent from the number of converter modules 22 in one branch 20.
The model state vector x = [ iaP iaN ibP ibN idc]T of the prediction model 80 includes the upper branch currents iaP, iaN and the lower branch currents ibP, ibN of phase legs a and b, as well as the DC link current idc .
The model input vector u = [vaP vaN vbP vbN vcP vcN]T E R6 of the prediction model 80 comprises the six branch voltages vaP, vaN, vbP, vbN, vcP, vcN, which are assumed to be real-valued.
The three-phase grid voltage vga, vgb, vgc of the load 16 and the DC link voltage vdc constitute the parameter vector vp = [vga vgb vgc vdc]T of the prediction model 80. The model output vector y has five elements. One choice is to use two load currents, either ia and ib , or ia and ίβ , i.e. the load currents represented in the stationary orthogonal coordinate system, along with the three circulating currents ici a, idr.b, ir.c- An alternative choice for the model output vector y is to use the five branch currents of the model state vector x.
In general, the state of the modular converter 10 may be modeled with the branch currents
Figure imgf000016_0001
the branch voltages vaP, vaN, vbP, vbN, vcP, vcN, the DC link current idc, the DC link voltage vdc, the output currents ia, ib, ic, and the grid voltages vga, vgb, VgC of the load 16. However, these quantities are not independent from each other.
Fig. 6 shows the evolution of the state of the modular converter 10 over the time t, which is depicted to the right. Fig. 6 shows the past 90 to the left of the y-axis, and a prediction horizon 92 to the right of the y-axis.
For example, a prediction model 80 may use a discrete time state-space representation with discrete time steps k. Then from an actual state 94 at time step k, a sequence of future states 96 is predicted for the time steps k+1 to k+N, where N is the length of the prediction horizon 92.
In particular, Fig. 6 schematically shows the predicted sequence 98 of model output vectors y and the predicted sequence 100 of model input vectors u for the time steps k to k+N-1.
For the topology shown in Fig. 1 and Fig. 5, a prediction model 80 of the following form can be derived. Note that the ^-matrix is time-varying, since it includes the voltages of the capacitor 32 of the branch modules 22.
x k + 1) = Ax k) +
Figure imgf000016_0002
+ B2vp{k)
y(k + 1) = Cx(k + 1) This model assumes that the voltages of the capacitors 32 exhibit minor variations within the time-frame of the prediction horizon 92. However, if the prediction horizon 92 is long and/or the capacitors 32 are relatively small, it may be beneficial to explicitly model the voltage variations of the capacitors 32. This may be done by extending the model state vector x by adding the sum of the capacitor voltages of the branches 20. The resulting prediction model 80 is of first order.
The evolution of the grid voltages may be included in the prediction model 80, by adding the two states vga and ν to the model state vector x and by modeling the rotation of the grid voltage vector, whose rotational speed is proportional to the grid frequency.
In general, the prediction model 80 is adapted for calculating future states 96 of the modular converter 10 based on an actual state 94 of the modular converter.
It has to be noted that the prediction model 80 may be formulated in different coordinate systems, including abc, αβ or dq, or a combination thereof.
In step 64, the predicted future states 96 are optimized with respect to an objective function. It has to be noted, that the steps 62 and 64 may be performed in one operation by numerically solving a mathematical programming problem defined by matrix equations, further constraints and the objective function.
The objective function associates a scalar performance index with different predicted scenarios, i.e. the objective function is a real-valued function of the states and control actions of the modular converter 10.
Typically, the objective function includes penalties on the predicted evolution tracking error and the (change in the) control effort over the prediction horizon N.
Figure imgf000017_0001
Note that in the above defined model, y* denotes the time-varying current reference vector. The matrices Q and R constitute penalty matrices on the current error and the change in the manipulated variable. In particular, the objective function is based on differences between the control input reference vector 48 at time step / and the evolution of the control input vector 50 at time step /. Additionally, the objective function optimizes a cost value associated with switching costs of the converter modules 10 by minimizing the differences between the model input vectors u at time step / and time step I- 1.
The objective function is minimized subject to the evolution of the prediction model 80 from time-step k until k+N-1. Moreover, constraints on the currents, which are included in x and y, may be included, as well as constraints on u. Upper and lower constraints as well as rate constraints can be considered. Since the state-space model is linear, the cost function is quadratic and the constraints are linear, the resulting optimization problem is a so-called quadratic program (QP). The QP can be formulated and solved efficiently, e.g. by using an active set method or a fast gradient search method.
The result of the optimization step 64 is the sequence 100 of optimal model control inputs U = [uT(k) uT(k + 1) ... uT{k + N - 1)]T at time-step k.
In step 66, the controller 42 determines the control output reference vector 52 from the sequence 100 of future control actions by taking the first element u(k) of the first model input vector u at time step k. The first element u(k) is the output reference vector 52.
Only the first element u(k) of the sequence 100 of optimal control inputs is implemented at time-step k and sent to the controller 44. At the next time-step k+1, new measurements (or estimates) are obtained and the optimization problem is solved again over a shifted prediction horizon 92. This so-called receding horizon policy provides feedback and ensures that the controller 42 is robust to parameter uncertainties.
Further embodiments of the control method are explained in the following:
A time delay caused by the computation of the control output reference vector 52 may be compensated for. This time delay typically amounts to the length of one sampling interval. By using the last control input and the model state vector x(k) at time step k, the model state vector x(k+l) at time step k+1 may be predicted, for which the prediction model 80 is solved.
In step 64, a (piecewise) linear (instead of a quadratic) cost function may be used, for example based on absolute values and/or maximal values, leading to a linear program (LP) instead of a QP.
In step 62, additional control loops may be added. For example, in step 62 the occurrence of faults, loss of modules, voltage dips, load imbalances, disturbances and/or grid (or load) asymmetries, etc. may be monitored. If a fault or asymmetry is detected, the controller 42 adjusts its control actions so as to accommodate for this event within the physical limits, providing automatic controller reconfiguration. For example, the prediction model 80 is updated to a new topology taking into account the fault or asymmetry. When modeling the prediction model 80, a higher order load system 16 may be considered, including AC machines, grids with transformers and loads with filters. To address such higher order systems, the prediction model 80, the model state vector x, the parameter vector vp and the output vector y may be augmented accordingly. While the invention has been illustrated and described in detail in the drawings and foregoing description, such illustration and description are to be considered illustrative or exemplary and not restrictive; the invention is not limited to the disclosed embodiments. Other variations to the disclosed embodiments can be understood and effected by those skilled in the art and practising the claimed invention, from a study of the drawings, the disclosure, and the appended claims. In the claims, the word "comprising" does not exclude other elements or steps, and the indefinite article "a" or "an" does not exclude a plurality. A single processor or controller or other unit may fulfil the functions of several items recited in the claims. The mere fact that certain measures are recited in mutually different dependent claims does not indicate that a combination of these measures cannot be used to advantage. Any reference signs in the claims should not be construed as limiting the scope.

Claims

1. A method for controlling a modular converter (10),
the modular converter comprising a plurality of converter modules (22) adapted for converting an input voltage into an output voltage to be supplied to a load (16),
the method comprising the steps:
receiving a control input reference vector (48), a control input vector (50) and a control input parameter vector (51);
determining a control output reference vector (52) from the control input reference vector (48), the control input vector (50) and the control input parameter vector (51) in a first control stage (42); and
controlling the converter modules (22) by generating switching signals (56) based on the control output reference vector (52) in a further control stage (46);
wherein the control output reference vector (52) is determined by:
predicting at least one future state (96) of the modular converter (10) with a prediction model (80) of the modular converter (10), wherein the prediction model
(80) is adapted for calculating the future state of the modular converter (10) based on an actual state (94) of the converter, a state of the modular converter (10) comprising current values and/or voltage values of the modular converter (10);
optimizing the at least one future state (96) with respect to an objective function, wherein the objective function is based on a cost value associated with switching costs of the converter modules (22); and
determining the control output reference vector (52) from the future state (96). 2. The method of claim 1, wherein the modular converter (10) controlled by the method is a modular multi-level converter wherein each converter module of the modular multi-level converter comprises two power connectors, at least two power semiconductors (28) and a capacitor (32), wherein the power connectors (28) are short-circuited in a first switching state of the power semiconductors (28) and are connected to the capacitor (32) in a second switching state of the power semiconductors (28).
3. The method of claim 1 or 2, further comprising the steps of:
determining a voltage vector (54) from the control output reference vector (52) in a second control stage with a modulator (44); controlling the converter modules (22) by generating switching signals (56) from the voltage vector (54) in a third control stage (46).
4. The method of one of the claims 1 to 3,
wherein the control input reference vector is a current reference vector (48), the control input vector is an actual current vector (50) and the control input parameter vector is an actual voltage vector (51); and/or
wherein the control output reference vector is a voltage reference vector (52).
5. The method of one of the claims 1 to 4,
wherein a sequence (96) of future states is predicted for a plurality of time steps in the future;
wherein the control output reference vector (52) is determined from the next future state associated with the next time step.
6. The method of one of the claims 1 to 5,
wherein the prediction model (80) is based on linear equations relating voltages and/or currents at a time step with voltages and/or currents at a next time step.
7. The method of one of the preceding claims,
wherein the prediction model (80) comprises a model of the converter modules (22) and/or a model of the load (16).
8. The method of one of the preceding claims, further comprising the step of:
compensating a time delay caused by the determination of the control output reference vector (52) by predicting currents at the next time step with the use of actual voltages and/or currents.
The method of one of the preceding claims,
wherein the objective function minimizes a change in the evolution of the control output reference vector (52).
The method of one of the preceding claims, wherein the objective function is based on a vector norm.
11. The method of one of the preceding claims,
wherein the objective function is based on a quadratic and/or linear norm.
12. The method of one of the preceding claims, further comprising the steps of:
controlling the converter modules (22) by generating switching signals (56) from a rounded control output reference vector (52).
13. The method of one of the preceding claims, further comprising the steps of:
detecting a converter module (22) with a fault;
short-circuiting the detected converter module (22);
removing the short-circuited converter model (22) from the prediction model (80).
14. A controller (42) for controlling a modular converter (10), wherein the controller is adapted for performing the steps of:
predicting at least one future state (96) of the modular converter (10) with a prediction model (80) of the modular converter (10), wherein the prediction model (80) is adapted for calculating the future state of the modular converter (10) based on an actual state (94) of the converter, a state of the modular converter (10) comprising current values and/or voltage values of the modular converter (10);
optimizing the at least one future state (96) with respect to an objective function, wherein the objective is based on a cost value associated with switching costs of converter modules (22) of the modular converter (10); and
determining a control output reference vector (52) from the future state (96).
15. A modular converter (10) for supplying a load (16) with electrical voltages, the modular converter (10) comprising:
a plurality of converter modules (22) comprising semiconductor switches (28) and a capacitor (32);
a first controller according to claim 13, the first controller generating a control output reference vector;
a further controller for generating switching signals for the converter modules based on the control output reference vector. The modular converter (10) of claim 15,
wherein the modular converter is a modular multi-level converter.
PCT/EP2013/067791 2012-08-28 2013-08-28 Controlling a modular converter in two stages WO2014033155A1 (en)

Priority Applications (4)

Application Number Priority Date Filing Date Title
EP13758794.5A EP2891240A1 (en) 2012-08-28 2013-08-28 Controlling a modular converter in two stages
CN201380045206.XA CN104584414B (en) 2012-08-28 2013-08-28 Control the modular converter of two-stage
BR112015004285A BR112015004285A2 (en) 2012-08-28 2013-08-28 control of a two-stage modular converter
US14/629,674 US9590530B2 (en) 2012-08-28 2015-02-24 Controlling a modular converter in two stages

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
EP12181995 2012-08-28
EP12181995.7 2013-08-28

Related Child Applications (1)

Application Number Title Priority Date Filing Date
US14/629,674 Continuation US9590530B2 (en) 2012-08-28 2015-02-24 Controlling a modular converter in two stages

Publications (1)

Publication Number Publication Date
WO2014033155A1 true WO2014033155A1 (en) 2014-03-06

Family

ID=46799076

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/EP2013/067791 WO2014033155A1 (en) 2012-08-28 2013-08-28 Controlling a modular converter in two stages

Country Status (5)

Country Link
US (1) US9590530B2 (en)
EP (1) EP2891240A1 (en)
CN (1) CN104584414B (en)
BR (1) BR112015004285A2 (en)
WO (1) WO2014033155A1 (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AT513776A3 (en) * 2014-04-08 2015-05-15 Avl List Gmbh Method and controller for model-predictive control of a multiphase DC / DC converter
WO2015136552A3 (en) * 2014-03-12 2015-12-10 Indian Institute Of Technology Bombay A modular multilevel converter (mmc) sub-module structure for reducing switching losses
EP2978122A1 (en) 2014-07-22 2016-01-27 ABB Technology AG Model predictive control of a modular multilevel converter
US9515574B2 (en) 2014-11-17 2016-12-06 General Electric Company Modular embedded multi-level converter with midpoint balancing
WO2017102373A1 (en) * 2015-12-16 2017-06-22 General Electric Technology Gmbh Voltage balancing of voltage source converters
FR3054754A1 (en) * 2016-08-01 2018-02-02 Supergrid Institute METHOD FOR CONTROLLING A MULTI-LEVEL MODULAR CONVERTER
CN110492516A (en) * 2019-07-29 2019-11-22 南方电网科学研究院有限责任公司 A kind of extra-high voltage Multi-end flexible direct current transmission converter station system and its control method
EP3614218A1 (en) 2018-08-22 2020-02-26 Technische Hochschule Nuernberg Georg-Simon-Ohm Cascaded continuous and finite model predictive control for mechatronic systems

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102012216469A1 (en) * 2012-09-14 2014-03-20 Robert Bosch Gmbh Energy supply system and method for driving coupling devices of an energy storage device
US10530275B2 (en) * 2016-10-21 2020-01-07 Abb Schweiz Ag Control of DC-to-AC modular multilevel converter
RU2644397C1 (en) * 2016-11-21 2018-02-12 Общество с ограниченной ответственностью "Системы Постоянного Тока" Method for suppressing parasite inphase leakage current in three-phase converter
JP6437164B1 (en) * 2017-03-03 2018-12-12 三菱電機株式会社 Power conversion apparatus and communication method
EP3496261B1 (en) * 2017-12-07 2023-11-22 ABB Schweiz AG Control and modulation of a converter
EP3614552B1 (en) * 2018-08-24 2021-05-19 General Electric Technology GmbH Voltage source converter
EP3780366A1 (en) * 2019-08-13 2021-02-17 Vestas Wind Systems A/S Dc chopper for mmc cell with integrated chopper resistor
CN114710055B (en) * 2022-04-26 2022-10-28 南京理工大学 Two-parallel power converter model prediction control method based on finite set single vector

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030163296A1 (en) * 2002-02-28 2003-08-28 Zetacon Corporation Predictive control system and method
DE102005060354A1 (en) * 2005-12-16 2007-06-21 Siemens Ag Modular inverter system
WO2009016113A1 (en) * 2007-07-27 2009-02-05 Abb Research Ltd Controlling a power system
WO2011036011A1 (en) * 2009-09-25 2011-03-31 Siemens Aktiengesellschaft Method for controlling an inverter and arrangement for controlling an inverter
EP2348627A1 (en) * 2010-01-25 2011-07-27 ABB Research Ltd. Converter circuit and method for operating a multilevel converter circuit

Family Cites Families (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3034275A1 (en) * 1980-09-11 1982-04-22 Siemens AG, 1000 Berlin und 8000 München DEVICE FOR DETERMINING THE PARAMETER VALUES FOR STANDAL RESISTANCE, MAIN INDUCTIVITY AND SPREADING INDUCTIVITY OF AN ASYNCHRONOUS MACHINE
US5619406A (en) * 1995-06-16 1997-04-08 Wisconsin Alumni Research Foundation Modulator for resonant link converters
JP3426939B2 (en) * 1997-10-30 2003-07-14 株式会社東芝 Control device for self-excited current source power converter
EP1347565A4 (en) * 2000-12-07 2007-03-14 Yaskawa Denki Seisakusho Kk Three-level neutral point clamping pwm inverter and neutral point voltage controller
US20020195986A1 (en) * 2001-03-26 2002-12-26 Siemens Aktiengesellschaft Method and apparatus for connecting a converter to an asynchronous machine
DE10135286B4 (en) * 2001-07-19 2006-04-27 Siemens Ag Method and device for bridging short-term power failures in a matrix converter
US7148669B2 (en) * 2004-02-02 2006-12-12 The Regents Of The University Of Colorado, A Body Corporate Predictive digital current controllers for switching power converters
US7558089B2 (en) * 2005-12-13 2009-07-07 Advanced Energy Conversion, Llc Method and apparatus for space vector modulation in multi-level inverters
CA2671817C (en) * 2006-12-08 2016-09-13 Siemens Aktiengesellschaft Control of a modular converter with distributed energy stores
EP2100366B1 (en) * 2006-12-08 2017-07-19 Siemens Aktiengesellschaft Production of an active power equilibrium of the phase modules of a converter
US7969756B1 (en) * 2007-04-16 2011-06-28 Lockheed Martin Corporation Real-time switching regulator monitor
EP2161822A4 (en) * 2007-05-29 2013-10-23 Univ Nagasaki Nat Univ Corp Prediction control system
US7710082B2 (en) * 2007-10-18 2010-05-04 Instituto Potosino De Investigacion Cientifica Y Technologica (Ipicyt) Controller for the three-phase cascade multilevel converter used as shunt active filter in unbalanced operation with guaranteed capacitors voltages balance
TW201041404A (en) * 2009-03-06 2010-11-16 Sony Corp Image processing device and method
CN101710797B (en) * 2009-12-07 2012-07-25 哈尔滨工业大学 Current forecasting dead-beat control method of Z source type interconnected inverter and control device thereof
EP2534748B1 (en) * 2010-02-11 2018-10-17 Siemens Aktiengesellschaft Control of a modular multilevel converter with an observer for the currents and an estimator for the energy of the intermediate circuit
JP5146478B2 (en) * 2010-03-18 2013-02-20 株式会社デンソー Rotating machine control device
CN103069707A (en) * 2010-09-24 2013-04-24 富士电机株式会社 Power conversion apparatus and method of controlling thereof
US20130308235A1 (en) * 2011-02-01 2013-11-21 Siemens Aktiengesellschaft Method for eliminating a fault on a high-voltage dc line, system for transmitting an electric current via a high-voltage dc line, and converter
US20140334206A1 (en) * 2011-08-02 2014-11-13 Power-One Italy S.P.A. Method for balancing capacitors in an inverter
CN103828213B (en) * 2011-09-26 2017-02-22 大金工业株式会社 power converter control method
GB201120640D0 (en) * 2011-11-30 2012-01-11 Univ Birmingham Power converter
JP5894777B2 (en) * 2011-12-07 2016-03-30 株式会社日立製作所 Power converter
KR101621994B1 (en) * 2011-12-30 2016-05-17 엘에스산전 주식회사 Control apparatus for regenerative medium voltage inverter
EP2634909B1 (en) * 2012-03-02 2017-02-15 ABB Research Ltd. Method for controlling a grid-connected boost-buck full-bridge current-source inverter cascade for photovoltaic applications and device
KR101410731B1 (en) * 2013-02-13 2014-06-24 한국전기연구원 Method for suppressing circulating currents from modular multi-level converter based high voltage direct-current system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030163296A1 (en) * 2002-02-28 2003-08-28 Zetacon Corporation Predictive control system and method
DE102005060354A1 (en) * 2005-12-16 2007-06-21 Siemens Ag Modular inverter system
WO2009016113A1 (en) * 2007-07-27 2009-02-05 Abb Research Ltd Controlling a power system
WO2011036011A1 (en) * 2009-09-25 2011-03-31 Siemens Aktiengesellschaft Method for controlling an inverter and arrangement for controlling an inverter
EP2348627A1 (en) * 2010-01-25 2011-07-27 ABB Research Ltd. Converter circuit and method for operating a multilevel converter circuit

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2015136552A3 (en) * 2014-03-12 2015-12-10 Indian Institute Of Technology Bombay A modular multilevel converter (mmc) sub-module structure for reducing switching losses
AT513776A3 (en) * 2014-04-08 2015-05-15 Avl List Gmbh Method and controller for model-predictive control of a multiphase DC / DC converter
AT513776B1 (en) * 2014-04-08 2015-09-15 Avl List Gmbh Method and controller for model-predictive control of a multiphase DC / DC converter
EP2978122A1 (en) 2014-07-22 2016-01-27 ABB Technology AG Model predictive control of a modular multilevel converter
WO2016012347A1 (en) 2014-07-22 2016-01-28 Abb Technology Ag Model predictive control of a modular multilevel converter
US9515574B2 (en) 2014-11-17 2016-12-06 General Electric Company Modular embedded multi-level converter with midpoint balancing
WO2017102373A1 (en) * 2015-12-16 2017-06-22 General Electric Technology Gmbh Voltage balancing of voltage source converters
FR3054754A1 (en) * 2016-08-01 2018-02-02 Supergrid Institute METHOD FOR CONTROLLING A MULTI-LEVEL MODULAR CONVERTER
WO2018024977A1 (en) * 2016-08-01 2018-02-08 Supergrid Institute Method for controlling a multi-level modular converter
CN109565247A (en) * 2016-08-01 2019-04-02 超级电力研究所有限公司 Method for the more level translators of control moduleization
EP3614218A1 (en) 2018-08-22 2020-02-26 Technische Hochschule Nuernberg Georg-Simon-Ohm Cascaded continuous and finite model predictive control for mechatronic systems
CN110492516A (en) * 2019-07-29 2019-11-22 南方电网科学研究院有限责任公司 A kind of extra-high voltage Multi-end flexible direct current transmission converter station system and its control method

Also Published As

Publication number Publication date
US20160079883A9 (en) 2016-03-17
CN104584414A (en) 2015-04-29
BR112015004285A2 (en) 2017-07-04
CN104584414B (en) 2016-10-26
EP2891240A1 (en) 2015-07-08
US9590530B2 (en) 2017-03-07
US20150171769A1 (en) 2015-06-18

Similar Documents

Publication Publication Date Title
US9590530B2 (en) Controlling a modular converter in two stages
KR101584057B1 (en) Controlling a modular converter
Huang et al. Priority sorting approach for modular multilevel converter based on simplified model predictive control
US10074978B2 (en) Model predictive control of a modular multilevel converter
Shadmand et al. Model predictive control of a capacitorless matrix converter-based STATCOM
Wei et al. Model predictive control of capacitor voltage balancing for cascaded modular DC–DC converters
US10114076B2 (en) Semiconductor device for hybrid energy storage systems
CN105787224B (en) Modeling method of modular multilevel converter non-loop current simulation model
CN109565248B (en) Two-stage control of converter system with floating unit
EP2884653B1 (en) Improvements in or relating to the control of converters
Kieferndorf et al. Model predictive control of the internal voltages of a five-level active neutral point clamped converter
Almaktoof et al. Finite-set model predictive control and DC-link capacitor voltages balancing for three-level NPC inverters
Sleiman et al. Model predictive control of a dual output seven-level rectifier
Cortes et al. Predictive control of a grid-connected cascaded H-bridge multilevel converter
Cortes et al. Finite-states model predictive control of a four-level diode-clamped inverter
González et al. Modular multilevel converter for large-scale photovoltaic generation with reactive power flow and unbalanced active power extraction capabilities
Hamayoon et al. Modified Reduced Indirect Finite Control Set Model Predictive Control of Modular Multilevel Converters
Stolze et al. Model predictive control of a flying capacitor converter with output LC filter for UPS applications
Izadinia et al. Optimized current control of vienna rectifier using finite control set model predictive control
Mohamed et al. Three-phase inverter with output LC filter using predictive control for UPS applications
Kaletsanos et al. Sliding mode control for cascaded H-bridge boost rectifiers
Gaouzi et al. Model predictive control of an inverter for electric vehicles applications
Sharma et al. Indirect model predictive control of grid connected modular multilevel converter
US11799409B2 (en) Medium voltage variable frequency drive with artificial intelligence
Hamayoon et al. Bisection Algorithm based Indirect Finite Control Set Model Predictive Control for Modular Multilevel Converters

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 13758794

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

REG Reference to national code

Ref country code: BR

Ref legal event code: B01A

Ref document number: 112015004285

Country of ref document: BR

ENP Entry into the national phase

Ref document number: 112015004285

Country of ref document: BR

Kind code of ref document: A2

Effective date: 20150226