WO2013065394A1 - Dispositif de contrôle et dispositifs devant être contrôlés - Google Patents
Dispositif de contrôle et dispositifs devant être contrôlés Download PDFInfo
- Publication number
- WO2013065394A1 WO2013065394A1 PCT/JP2012/072098 JP2012072098W WO2013065394A1 WO 2013065394 A1 WO2013065394 A1 WO 2013065394A1 JP 2012072098 W JP2012072098 W JP 2012072098W WO 2013065394 A1 WO2013065394 A1 WO 2013065394A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- power consumption
- control
- request
- control target
- energy saving
- Prior art date
Links
Images
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J13/00—Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J13/00—Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
- H02J13/00004—Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by the power network being locally controlled
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/12—Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
- H02J3/14—Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load by switching loads on to, or off from, network, e.g. progressively balanced loading
-
- G—PHYSICS
- G08—SIGNALLING
- G08C—TRANSMISSION SYSTEMS FOR MEASURED VALUES, CONTROL OR SIMILAR SIGNALS
- G08C2201/00—Transmission systems of control signals via wireless link
- G08C2201/10—Power supply of remote control devices
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2310/00—The network for supplying or distributing electric power characterised by its spatial reach or by the load
- H02J2310/10—The network having a local or delimited stationary reach
- H02J2310/12—The local stationary network supplying a household or a building
- H02J2310/14—The load or loads being home appliances
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B70/00—Technologies for an efficient end-user side electric power management and consumption
- Y02B70/30—Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B70/00—Technologies for an efficient end-user side electric power management and consumption
- Y02B70/30—Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
- Y02B70/3225—Demand response systems, e.g. load shedding, peak shaving
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S20/00—Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
- Y04S20/20—End-user application control systems
- Y04S20/222—Demand response systems, e.g. load shedding, peak shaving
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S20/00—Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
- Y04S20/20—End-user application control systems
- Y04S20/242—Home appliances
Definitions
- the present invention relates to a technique for performing power saving control of devices installed in a home, a building, a store, or the like when power is insufficient.
- Patent Document 1 discloses, for example, controlling electric power of a home appliance connected to a network from a controller via the network.
- Patent Document 1 discloses that a control device (controller) that controls home appliances controls home appliances such as an air conditioner and a television via a network.
- the control device issues an instruction to control the power to the home appliance, and if the home appliance executes this, the power consumption can be reduced.
- control device issues an instruction for power suppression to the home appliance
- the controller recognizes the temperature setting interface of the air conditioner, grasps the condition of the air conditioner using the interface, raises the set temperature if cooling, and can be used for heating. For example, it is necessary to perform control such as lowering the set temperature.
- an object of the present invention is to enable the control device to perform power saving control without being aware of the type of control target device such as home appliances and the state of each device.
- the control device does not need to know the state of the device to be controlled and the detailed interface for control, and controls data requesting reduction in power consumption when power consumption reduction is necessary. It is only necessary to transmit to the target device, and power consumption can be easily reduced.
- the control target device can reduce the power consumption according to the degree of the request for the power consumption reduction. . Thereby, it becomes possible to reduce power consumption, without impairing a user's comfort as much as possible.
- control device can notify the user that the control target device is requested to reduce power consumption and that the control target device is required to reduce power consumption.
- FIG. 1 is a diagram showing a schematic configuration of a system according to an embodiment of the present invention. First, the outline of the present embodiment will be described with reference to FIG.
- 100 is a control device.
- the control device 100 controls the control target devices 110a to 110n and receives data from the server 200 via the network 140.
- devices 110a to n are devices to be controlled.
- devices to be controlled include devices such as air conditioners, televisions, refrigerators, heat pump water heaters, and air purifiers.
- the GW apparatus 120 is a GW device.
- the GW apparatus 120 transfers communication data between the internal network 140 and the Internet 160.
- the power meter 130 is a power meter.
- the power meter is installed in a distribution board or outlet, and measures power consumption of the entire house and power consumption of each control target device. Note that current consumption may be used instead of power consumption. In that case, the power consumption may be the current consumption.
- the measured value is transmitted to the control device 100 via the measuring device network 150.
- the power meter 130 is not essential.
- the 140 is an internal network.
- the internal network is configured using, for example, Ethernet (registered trademark), wireless LAN, 802.15.4, or the like.
- the internal network is set up in a range such as a home or a store.
- the measuring instrument network 150 is a network for measurement equipment.
- the measurement device network is configured using RS-485, 802.15.4, Ethernet (registered trademark), or the like.
- the measuring instrument network 150 may be shared with the internal network 140.
- AMI Advanced Metering Infrastructure
- the power generation amount of the solar power generation facility 170 can be measured by the power meter 130. In the present invention, the solar power generation facility 170 is not essential.
- the 180 is a power storage facility, and is charged with a lead storage battery or a lithium ion battery.
- the power storage facility may have a communication function, and in that case, the power storage amount can be monitored from the control device.
- the power storage facility 180 is not essential.
- the server 200 is a server.
- the server 200 monitors the power consumption and power generation in the area, and transmits an energy saving request described later to the control device 100 as necessary.
- reference numeral 101 denotes a control unit, which executes various processes related to peripheral control, data processing, communication processing, and the like.
- Reference numeral 102 denotes a recording unit, such as a ROM, a RAM, or a flash memory.
- the recording unit 102 stores programs and data, and is used in a work area when executing the programs.
- the power measuring unit 103 is a power measuring unit, for example, communication hardware and control software such as RS-485, 802.15.4, Ethernet.
- the power measuring unit 103 performs processing for receiving power consumption data from the power measuring instrument 130 and passing it to the control unit 101. In the case of a configuration that does not use the power meter 130, the power measuring unit 103 is not necessary.
- the communication processing unit 104 is a communication processing unit, for example, Ethernet, wireless LAN, communication hardware such as 802.15.4, and control software.
- the communication processing unit 104 transmits / receives data to / from the server 200 and transmits / receives data to / from the control target device 110.
- 101 to 104 are buses for connecting each part.
- control target device 110 Next, the configuration of the control target device 110 will be described with reference to FIG.
- reference numeral 112 denotes a communication processing unit, for example, communication hardware such as Ethernet, wireless LAN, 802.15.4, and control software.
- the communication processing unit 112 transmits / receives data to / from the control device 100.
- the 111 is a device control unit.
- the configuration of the device control unit 111 varies depending on devices such as an air conditioner, a television, a refrigerator, a heat pump water heater, and an air purifier.
- the device control unit 111 performs overall device control such as device state setting, device operation control, and user interface control.
- FIG. 4 shows an example in which the control device 100 and the GW device 120 are the same casing.
- the control device 100b in which the control device 100 and the GW device 120 are integrated has a configuration in which an external communication processing unit 106 and a routing processing unit 107 are added to the control device 100.
- the external communication processing unit 106 is, for example, communication hardware such as Ethernet and control software.
- the external communication processing unit 106 connects to the Internet 160 and transmits / receives data to / from the server.
- the routing processing unit 107 performs data transfer control between the internal network 140 and the Internet 160.
- the control device 100 consumes the control target device 110 when there is a request for energy saving from the server 200, or when the power consumption within the range managed by the control device 100 (hereinafter referred to as total power consumption) exceeds a certain threshold. Require operation (energy saving operation) to reduce power consumption. Further, when there is a request for energy saving from the server 200 and when the power consumption within the range managed by the control device 100 is below a certain threshold, the cancellation of the energy saving operation is transmitted to the control target device 110. Note that the determination based on the total power consumption may or may not be used.
- 300a to c are energy saving request data, and 310 is energy saving cancellation data. There are several patterns in the energy saving request data 300.
- 300a is simply an example of transmitting a request to reduce power consumption.
- Reference numeral 300b is an example of a request for suppressing the power consumption in the range managed by the control device 100 to a predetermined value (4 KW in the figure) or less.
- 300c is an example of a request for reducing the power consumption within a range managed by the control device 100 by a certain ratio (10% in the figure).
- the energy saving release data 310 transmits to the control device 100 that the energy saving request is released.
- the overall power consumption monitoring process 400 for determining whether or not the power consumption within the range managed by the control device 100 has exceeded a certain threshold will be described with reference to the flowchart of FIG.
- the overall power consumption monitoring process 400 is periodically activated by, for example, a timer.
- the range managed by the control device 100 is, for example, power consumption of the entire house, power consumption of the entire store, and the entire building.
- the overall power consumption monitoring process 400 first, the overall power consumption is measured using the data measured by the power meter 130 (step 401). Next, it is determined whether the current state is the “normal state” or the “energy saving state” (step 402). In the normal state, it is determined whether or not the total power consumption measured in step 401 is equal to or greater than a predetermined threshold value (step 403). If the total power consumption is less than the upper threshold, the process is terminated. If the total power consumption is greater than or equal to a certain threshold (upper limit threshold), an “energy saving event” is issued (step 404). Then, the state is changed to “energy saving state” (step 405), and the process is terminated.
- a predetermined threshold value a predetermined threshold value
- step 402 it is determined whether or not the total power consumption measured in step 401 is equal to or greater than a predetermined threshold (lower threshold) (step 403). If the total power consumption is greater than or equal to the lower threshold value, the process ends. If the total power consumption is less than the lower limit threshold value, an “energy saving cancellation event” is issued (step 407). Then, the state is changed to “normal state” (step 405), and the process is terminated.
- a predetermined threshold lower threshold
- reference numeral 500 denotes communication data exchanged with the control target device 110.
- the communication data 500 includes a transmission destination 501, a transmission source 502, and a command / response 503.
- the transmission destination 501 is an identifier for identifying the transmission destination of the communication data 500.
- the transmission destination stores the IP address of the transmission destination device (the control device 100 or the control target device 110).
- a broadcast address IP multicast address in the case of an IP network
- the internal network 140 is an IP network using Ethernet, but the internal network used in the present invention is not limited to this.
- the transmission source 502 is an identifier for identifying the transmission source of the communication data 500.
- the transmission source stores the IP address of the transmission source device (the control device 100 or the control target device 110).
- the command / response 503 is an energy saving request or a response to the energy saving request.
- the command / response 503 stores 503a to 503c.
- a response 503d is stored.
- the command / response 503a is used when the control target device 110 is requested to save energy.
- information on how much energy is required is not included and depends on each device.
- the command / response 503b is used to transmit a request and level of energy saving operation to the control target device 110.
- the level is, for example, 1 to 3, and as the level changes from 1 to 3, the demand for energy saving is stronger. That is, the control target device 110 operates so that the power consumption is lower at the level 3 than at the level 1 and the level 3. Specifically, how much power consumption is reduced depends on the device. Thereby, finer energy saving control becomes possible.
- the command / response 503c is used to notify the control target device 110 that the energy saving request is cancelled.
- the control target device 110 Upon receiving the command / response 503c, the control target device 110 cancels the energy saving control and enters a normal operation state.
- the response 503d stores how the control target device 110 received the energy saving request and the energy saving release request and responded. For example, OK, NG, etc.
- the energy saving request process 600 is activated when an “energy saving event” occurs in the overall power consumption monitoring process 400 or when the control apparatus 100 receives the energy saving request data 300 received from the server 200.
- an energy saving request transmission process 610 is executed.
- the user may be asked whether or not to execute the energy saving request transmission process 610.
- a screen for confirming whether or not to execute the energy saving request is displayed to the user, and when the user selects to execute the energy saving request transmission process 610, the energy saving request process 610 is executed and the execution is not selected. In such a case, the energy saving request transmission process 610 is not executed.
- a method of displaying a screen to be confirmed by the user there is a method of mounting a WWW server function in the control device 100 and confirming using a browser function such as a PC.
- the energy saving cancellation process 620 is activated when an “energy saving cancellation event” occurs in the overall power consumption monitoring process 400 or when the control apparatus 100 receives the energy saving cancellation data 310 received from the server 200.
- an energy saving request transmission process 630 is executed.
- communication data 500 is created and transmitted to the control target device 110 via the internal network 140 (step 611).
- the destination 501 stores an IP multicast address
- the source 503 stores the IP address of the control device 100
- the command / response 503 stores a command / response 503a for requesting reduction of power consumption.
- the communication data 500 broadcasted in step 611 is received by the control target devices 110a to 110n.
- the energy saving request reception process 650 is activated.
- the device control unit 111 of the control target device 110 changes settings such as the operation mode so that the power consumption of the control target device 110 is reduced (step 651).
- the operation that reduces power consumption differs depending on the type of device, and includes the following operations. In addition to reducing power consumption, there is a method of controlling in a direction to reduce reactive power. If the power consumption is already sufficiently low, there is a case where nothing is changed. Also, the operation mode in step 651 may be determined in advance and the same operation may always be performed. A display example is shown in FIG.
- ⁇ For TV Decrease screen brightness
- ⁇ For air conditioner Increase the set temperature for cooling. In the case of heating, lower the set temperature. Or stop.
- Refrigerator weaken the operation mode.
- -Heat pump water heater Stops boiling.
- -EV charger Reduces charging power to EV or stops charging to EV.
- step 651 it may be determined that the control target device 110 should be controlled so that the power consumption is minimized.
- the communication data 500 including the command / response 503a for requesting the reduction of power consumption is transmitted in step 611, the power consumption can be minimized.
- communication data 500 is created and transmitted to the control target device 110 via the internal network 140 (step 631).
- an IP multicast address is stored in the transmission destination 501
- an IP address of the control device 100 is stored in the transmission source 503
- a command / response 503 c for instructing energy saving cancellation is stored in the command / response 503.
- the communication data 500 broadcasted in Step 631 is received by the control target devices 110a to 110n.
- the energy saving cancellation receiving process 660 is activated.
- the device control unit 111 of the device to be controlled 110 returns the setting of the operation state set in step 651 to the original state (step 661).
- the command / response 503 stores the energy saving request 503a.
- the command / response 503b for instructing the power consumption reduction request and the request level is used. You can also.
- the method for determining the level at that time is, for example, as follows (level determination method).
- the energy saving control data 600a is received from the server 200 and the energy saving control process 600 is activated
- a predetermined level is entered.
- the level is set by comparing the total power consumption measured by the power meter 130 with the request value in the energy saving request data 300b. To do. For example, the level is 1 if the difference between the total power consumption and the required value is less than 1 kW, the level 2 if it is 1 kW or more and less than 1.5 kW, and the level 3 if it is 1.5 kW or more.
- the level is set according to the instructed reduction rate. For example, if the reduction amount is less than 10%, the level is 1; if the reduction amount is 10% or more and less than 20%, the level is 2;
- step 651 the control target device 110 that has received the command / response 503b performs energy-saving control according to the level.
- Each device may perform different control depending on the level, or may perform the same control.
- a TV-Level 1 Decrease screen brightness by 10%
- -Level 2 Increase screen brightness by 20 %
- Reduce-Level 3 Reduce screen brightness by 30%.
- -Level 2 Increase the set temperature by 2 degrees for cooling. In the case of heating, the set temperature is lowered twice.
- -Level 3 Stops air conditioner operation.
- Refrigerator -Level 1: Set the operation mode in the middle-Level 2: Decrease the operation mode-Level 3: Reduce the operation mode-Heat pump water heater-Level 1: Stop boiling-Level 2: Boiling Stop leveling-Level 3: Stop boiling-EV charger-Level 1: Reduce charge power by 10%-Level 2: Reduce charge power by 50%-Level 3: Stop charging
- the control device 100 receives the energy saving request data 300 from the server 200 (that is, when there is not enough power in the area) or when the overall power consumption increases and an “energy saving event” occurs (that is, When the power consumption amount at home or in the store approaches the contracted power consumption amount), the power consumption in the control target device 110 can be reduced, and stable power supply or The breaker can be prevented from falling.
- the control device 100 when the “energy saving event” occurs in the overall power consumption monitoring process 400 or when the control device 100 receives the energy saving request data 300 received from the server 200, all of the controlled devices 110 are controlled. However, it is also possible to request power saving only for a high-priority device. In addition, when there is a power generation facility such as solar power generation or a power storage facility such as a storage battery, the control target device 110 can be requested to save power or not depending on the power generation status or the power storage status. Thereby, it becomes possible to save power without impairing the user's comfort.
- the device management table 700 is recorded in the storage unit 102 of the control device 100.
- the device management table 700 is composed of one or more device management records 710a-n.
- the device management record 710 includes an address 711, a name 712, a priority 713, an energy saving correspondence 714, and a state 715.
- the address 711 is an identifier for identifying the control target device, for example, the IP address of the device.
- the name 712 is the name of the device identified by the address 711.
- the priority 713 is a priority when performing energy saving control, and is a numerical value of 1 to 3, for example.
- the energy saving response 714 is a flag indicating whether or not the device specified by the address 711 is compatible with the energy saving request, and is, for example, “corresponding” or “not supporting”.
- a state 715 is a state of the device. Examples of the state of the device include “normal state” and “energy saving state”.
- Registration of data in the device management table 700 can be performed using protocols such as UPnP (Universal Plug & Play).
- UPnP Universal Plug & Play
- the control target device 110 transmits information necessary for registration to the control device 100 using UPnP.
- control device 100 is equipped with a WWW server function and is set via the internal network 140 using a browser function such as a PC.
- a browser function such as a PC.
- FIG. 1 An example of a screen displayed on a browser function such as a PC is shown in FIG.
- the 750 in the figure is an example of a screen displayed by the browser.
- the user inputs a device name 751, an address 752, a priority level 753, and an energy saving response 754.
- the registration button 760 is pressed.
- information is transmitted to the WWW server, and a new device management record 710 is created and registered in the device management table 700.
- the address 711 stores an address 752
- the name 712 stores a device name 751
- the priority 713 stores a priority 753,
- the energy saving response 714 stores an energy saving response 754.
- the state 715 is a “normal state”.
- the energy saving control processing 600 is started. Start 800.
- the energy saving control process 800 will be described with reference to the flowchart of FIG.
- the power generation amount of the photovoltaic power generation facility is measured using the power meter 130 or the like, and the storage capacity of the power storage facility is acquired via the internal network 140, the measurement device network 150, or the like (step) 801).
- it is determined whether or not energy saving is necessary is made as follows, for example. ⁇ When an “energy-saving event” occurs: Judgment that energy-saving is necessary ⁇
- energy-saving request data 300a is received: Compare the power generation amount of the solar power generation facility with the total power consumption, and the power generation amount of the solar power generation facility is large If it is not necessary, it is necessary.
- step 802 If it is determined in step 802 that energy saving is unnecessary, the process is terminated. If it is determined in step 802 that energy saving is necessary, an energy saving level is determined (step 803).
- the energy saving level determination uses, for example, the level determination method described in the first embodiment.
- the priority of energy saving is determined (step 804).
- the priority of energy saving is determined as follows, for example.
- the priority is set to 1 (that is, only the control target device 110 with the priority 1 is targeted) To do).
- the priority is set to 2 (that is, the control target device 110 with the priority 1 or 2 is To be eligible).
- the priority is set to 3 (that is, the control target device 110 with the priority 1 to 3 is targeted) To do).
- step 805 it is determined whether or not the processing in step 806 and subsequent steps has been completed for all devices registered in the device management table 700 (step 805). If the process has been completed for all devices, the process ends. If not completed, the device management record 710 corresponding to the device for which processing has not been completed is selected from the device management table 700, and the energy saving response 714 is checked (step 806). If the energy saving response 714 is “not supported”, the process returns to step 805. If the energy saving response 714 is “response”, the priority 713 is checked (step 807). If the priority 713 is larger than the priority determined in step 804, the process returns to step 805. When the priority 713 is a value equal to or lower than the priority determined in step 804, an energy saving request transmission process 810 described later is executed.
- the energy saving cancellation process 820 is activated when an “energy saving cancellation event” occurs or when the controller 100 receives the energy saving cancellation data 310 received from the server 200.
- step 821 it is determined whether or not the processing from step 821 is completed for all devices registered in the device management table 700 (step 801). If the process has been completed for all devices, the process ends. If not completed, the device management record 710 corresponding to the device for which processing has not been completed is selected from the device management table 700, and the status 715 is checked (step 822). When the state 715 is “normal state”, the process returns to step 821. The state 715 is “energy saving state”, and an energy saving cancellation process 830 described later is executed. Thereafter, the process returns to step 821.
- communication data 500 is created and transmitted to the control target device 110 via the internal network 140 (step 611).
- the destination 501 is the address 711 of the device management record 710 selected in step 822
- the transmission source 503 is the IP address of the control device 100
- the command / response 503 is a command / response requesting power consumption reduction.
- 503b is stored.
- the level determined in step 803 is stored in the level.
- the communication data 500 transmitted in step 611 is received by the control target device 110 specified by the address 711.
- the energy saving request reception process 850 is activated.
- the device control unit 111 of the control target device 110 changes the setting such as the operation mode so that the power consumption of the device is reduced (step 651).
- the communication data 500 is created and transmitted to the control device 100 via the internal network 140 (step 853).
- the transmission destination 501 is the IP address of the control device 100
- the transmission source 502 is the IP address of the control target device 110
- the command / response 503d is “OK” when the operation of the device is changed. In this case, “NG” is stored.
- the control device 100 receives the communication data 530 transmitted in step 853.
- the content of the command / response 503d is confirmed. If “OK”, the state 715 of the device management record 710 selected in step 822 is set to “energy saving state”, and if “NG”, the state is not changed (step 812).
- the communication data 500 is created and transmitted to the control target device 110 via the internal network 140 (step 831).
- the destination 501 includes the address 711 of the device management record 710 selected in step 822
- the transmission source 503 includes the IP address of the control device 100
- the command / response 503 includes a command / response 503c for canceling the energy saving request.
- the communication data 500 transmitted in step 831 is received by the control target device 110 specified by the address 711.
- the energy saving cancellation receiving process 860 is activated.
- the setting of the operation state set in step 651 is returned to the original state in the device control unit 111 of the control target device 110 as in the energy saving release reception process 660 (step 661).
- the communication data 500 is created and transmitted to the control device 100 via the internal network 140 (step 853).
- the IP address of the control device 100 is stored in the transmission destination 501
- the IP address of the control target device 110 is stored in the transmission source 502, and “OK” is stored in the command / response 503d.
- the control device 100 receives the communication data 530 transmitted in step 863.
- the contents of the command / response 503d are confirmed. If “OK”, the state 715 of the device management record 710 selected in step 822 is set to “normal state”, and if “NG”, the state is not changed (step 832).
- the control device 100 even when the control device 100 receives the energy saving request data 300 from the server 200 or when an “energy saving event” occurs, the control device 100 does not necessarily depend on the amount of power generated by the solar power generation facility or the amount of power stored in the storage battery. There is no need for the control target device 110 to perform a power saving operation, and the user can use the device more comfortably. Moreover, since it is possible to save power with priorities, it is possible to save power more flexibly. Furthermore, since unnecessary data is not sent to a device that cannot respond to the power saving request, network traffic can be reduced.
- the user is not notified that the operation is performed with reduced power consumption.
- the user can also be notified.
- a variable (control device mode management variable) related to the energy saving mode for managing the state is provided.
- the control device mode management variable is set to “energy saving state”.
- the control device mode management variable is set to “normal state”.
- the control device 100 is provided with a display function 900 such as an LED so that it is turned on when the control device mode management variable is in the “energy saving state” and turned off when in the normal state (FIG. 18A). .
- the control device 100 when the control device 100 is equipped with a WWW server function and accessed via the internal network 140 using a browser function such as a PC, the content of the mode management variable is displayed on the browser screen 910. You may make it display (FIG.18 (b)).
- control target device 110 a variable (control target device mode management variable) related to the energy saving mode for managing the state is provided. Then, when the energy saving request reception process 650 is executed in the control target device 110, the control target device mode management variable is set to the “energy saving state”. When the energy saving release transmission process 610 is executed, the control target device mode management variable is set to “normal state”.
- the control target device 110 is provided with a display function 950 such as an LED so that the control target device mode management variable is turned on when it is in the “energy saving state” and is turned off when it is in the normal state (FIG. 19A). ), Air conditioner example).
- control target device 110 having a display function such as a television
- the fact may be displayed on the screen 960 when the control target device mode management variable is “energy saving state”, and nothing may be displayed in the normal state.
- the user can be notified that the energy saving operation state is set. Thereby, even if operation
- Example 2 Although the above demonstrated in the case of Example 1, it cannot be overemphasized that the same process can be performed also in Example 2.
- Control apparatus 110
- Control object apparatus 120
- Electric power meter 130
- Internal network 150
- Network for measurement apparatuses 160
- Internet 170
- Solar power generation equipment 180
- Power storage equipment 200 Server
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Selective Calling Equipment (AREA)
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
Abstract
Quand il n'y a pas suffisamment de puissance dans un système comprenant un dispositif de contrôle et un dispositif devant être contrôlé par le dispositif de contrôle, le dispositif devant être contrôlé doit connaître le statut du dispositif devant être contrôlé, ou bien il doit connaître le procédé de contrôle qui est utilisé afin de réduire la puissance du dispositif devant être contrôlé et économiser sa puissance. Dans ce cas, le contrôle devient complexe. Afin de résoudre ce problème, la présente invention se rapporte à un dispositif de contrôle qui est connecté, sur un réseau, à une pluralité de dispositifs devant être contrôlés qui consomment de la puissance, ledit dispositif de contrôle contrôlant ladite puissance. Le dispositif de contrôle selon l'invention comprend : un module de réception qui reçoit, d'une source externe, une demande de réduire une consommation d'énergie ; et un module de transmission qui transmet, à un dispositif devant être contrôlé, la demande de réduction de la consommation d'énergie. Quand une demande de réduire une consommation d'énergie est reçue par le module de réception, ledit dispositif de contrôle commande qu'une demande de réduire la consommation de puissance soit transmise, du module de transmission au dispositif devant être contrôlé.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2011238189A JP2013098672A (ja) | 2011-10-31 | 2011-10-31 | 制御装置及び制御対象機器 |
JP2011-238189 | 2011-10-31 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2013065394A1 true WO2013065394A1 (fr) | 2013-05-10 |
Family
ID=48191753
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/JP2012/072098 WO2013065394A1 (fr) | 2011-10-31 | 2012-08-31 | Dispositif de contrôle et dispositifs devant être contrôlés |
Country Status (2)
Country | Link |
---|---|
JP (1) | JP2013098672A (fr) |
WO (1) | WO2013065394A1 (fr) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2015104740A1 (fr) * | 2014-01-10 | 2015-07-16 | パナソニックIpマネジメント株式会社 | Système de commande et tableau de distribution |
JP2016033817A (ja) * | 2014-07-28 | 2016-03-10 | 国立研究開発法人宇宙航空研究開発機構 | 電力制御システム、方法、及び、情報伝達能力制御システム、方法 |
JP2018027010A (ja) * | 2017-09-29 | 2018-02-15 | 三菱電機株式会社 | 電力計測装置、抑制レベル通知方法及びプログラム |
WO2018047269A1 (fr) * | 2016-09-08 | 2018-03-15 | 三菱電機株式会社 | Dispositif de commande, procédé de commande, et programme |
US10050799B2 (en) | 2014-01-28 | 2018-08-14 | Patched Conics, LLC. | Power control system and method, and information communication ability control system and method |
JPWO2018047263A1 (ja) * | 2016-09-08 | 2019-03-07 | 三菱電機株式会社 | 消費電力調整装置、消費電力調整システム、消費電力調整方法、及び、プログラム |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6036510B2 (ja) * | 2013-04-18 | 2016-11-30 | 株式会社バッファロー | 通信システム、通信機器、制御方法、および、コンピュータプログラム |
JP6207927B2 (ja) * | 2013-08-27 | 2017-10-04 | 東芝ライフスタイル株式会社 | 家電制御システム |
JP6181486B2 (ja) * | 2013-09-06 | 2017-08-16 | シャープ株式会社 | 通信システム、サーバ装置、携帯端末装置、および情報処理方法 |
JP6369238B2 (ja) * | 2014-09-03 | 2018-08-08 | 株式会社デンソー | 屋内気圧調整システム |
US20200081856A1 (en) * | 2017-01-12 | 2020-03-12 | Mitsubishi Electric Corporation | Interface device |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1145782A (ja) * | 1997-07-28 | 1999-02-16 | Matsushita Electric Works Ltd | 調光監視制御システム |
JP2001069668A (ja) * | 1999-08-27 | 2001-03-16 | Matsushita Seiko Co Ltd | 電力管理装置 |
-
2011
- 2011-10-31 JP JP2011238189A patent/JP2013098672A/ja active Pending
-
2012
- 2012-08-31 WO PCT/JP2012/072098 patent/WO2013065394A1/fr active Application Filing
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1145782A (ja) * | 1997-07-28 | 1999-02-16 | Matsushita Electric Works Ltd | 調光監視制御システム |
JP2001069668A (ja) * | 1999-08-27 | 2001-03-16 | Matsushita Seiko Co Ltd | 電力管理装置 |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2015104740A1 (fr) * | 2014-01-10 | 2015-07-16 | パナソニックIpマネジメント株式会社 | Système de commande et tableau de distribution |
JPWO2015104740A1 (ja) * | 2014-01-10 | 2017-03-23 | パナソニックIpマネジメント株式会社 | 制御システムおよび分電盤 |
US10050799B2 (en) | 2014-01-28 | 2018-08-14 | Patched Conics, LLC. | Power control system and method, and information communication ability control system and method |
JP2016033817A (ja) * | 2014-07-28 | 2016-03-10 | 国立研究開発法人宇宙航空研究開発機構 | 電力制御システム、方法、及び、情報伝達能力制御システム、方法 |
JP2017158430A (ja) * | 2014-07-28 | 2017-09-07 | 国立研究開発法人宇宙航空研究開発機構 | 電力制御システム、方法、及び、情報伝達能力制御システム、方法 |
WO2018047269A1 (fr) * | 2016-09-08 | 2018-03-15 | 三菱電機株式会社 | Dispositif de commande, procédé de commande, et programme |
JPWO2018047263A1 (ja) * | 2016-09-08 | 2019-03-07 | 三菱電機株式会社 | 消費電力調整装置、消費電力調整システム、消費電力調整方法、及び、プログラム |
JP2018027010A (ja) * | 2017-09-29 | 2018-02-15 | 三菱電機株式会社 | 電力計測装置、抑制レベル通知方法及びプログラム |
Also Published As
Publication number | Publication date |
---|---|
JP2013098672A (ja) | 2013-05-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2013065394A1 (fr) | Dispositif de contrôle et dispositifs devant être contrôlés | |
JP6541188B2 (ja) | 電力供給システム、電力制御装置、電力受電装置、電力供給制御方法および電力制御方法 | |
US20080106146A1 (en) | Management System for In-House Power Quantity Consumed | |
US10310460B2 (en) | Management device, management system, management method, and program | |
JP2014072561A (ja) | 家電機器遠隔監視システム | |
JP5952416B2 (ja) | 管理方法、制御装置及び通信処理デバイス | |
JPH11313441A (ja) | 家庭内電力dsmシステム | |
JP2009254219A (ja) | 電力制御装置及びプログラム | |
JP6028044B2 (ja) | 電力制御システム、制御装置、及び電力制御方法 | |
JP5439424B2 (ja) | 制御装置 | |
CN105650809A (zh) | 一种智能家居设备的控制方法、设备及系统 | |
JP2017195774A (ja) | 被制御装置、制御装置、装置制御方法及び装置制御システム | |
JPWO2014051039A1 (ja) | 管理システム、管理方法及び機器 | |
WO2019082426A1 (fr) | Dispositif de gestion d'énergie, système de gestion d'énergie, et procédé de gestion d'énergie | |
JP2017153361A (ja) | 電力制御装置及び機器 | |
JP6802833B2 (ja) | 管理システム、管理方法、操作端末及び制御装置 | |
KR20130063949A (ko) | 전력사용모드 결정 장치 및 방법 | |
JP2016220488A (ja) | 需要家通信装置、需要家通信方法及び需要家通信システム | |
WO2015079493A1 (fr) | Système de gestion d'énergie, dispositif de mesure de puissance, dispositif de charge, adaptateur de communication, contrôleur de système, procédé de gestion d'énergie et programme | |
KR101732628B1 (ko) | 소비 전력 제어를 위한 전력관리장치 및 그 동작 방법 | |
WO2015174014A1 (fr) | Dispositif commandé à distance, système de commande qui comprend ledit dispositif et procédé de commande utilisé avec ledit dispositif | |
WO2015115571A1 (fr) | Dispositif de commande et procédé de commande | |
JP5131145B2 (ja) | 電力制御システム及び電力制御システムの制御方法 | |
US10186864B2 (en) | Method of controlling the electrical regulation of an electrical installation as a function of curtailment settings | |
JP2018201282A (ja) | 通信装置、及び通信システム |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 12846190 Country of ref document: EP Kind code of ref document: A1 |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 12846190 Country of ref document: EP Kind code of ref document: A1 |