WO2012049972A1 - 蓄電池を含む電源システム - Google Patents
蓄電池を含む電源システム Download PDFInfo
- Publication number
- WO2012049972A1 WO2012049972A1 PCT/JP2011/072271 JP2011072271W WO2012049972A1 WO 2012049972 A1 WO2012049972 A1 WO 2012049972A1 JP 2011072271 W JP2011072271 W JP 2011072271W WO 2012049972 A1 WO2012049972 A1 WO 2012049972A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- storage battery
- discharge
- charging
- power
- current value
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Images
Classifications
-
- H—ELECTRICITY
- H05—ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
- H05B—ELECTRIC HEATING; ELECTRIC LIGHT SOURCES NOT OTHERWISE PROVIDED FOR; CIRCUIT ARRANGEMENTS FOR ELECTRIC LIGHT SOURCES, IN GENERAL
- H05B47/00—Circuit arrangements for operating light sources in general, i.e. where the type of light source is not relevant
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for AC mains or AC distribution networks
- H02J3/38—Arrangements for feeding a single network from two or more generators or sources in parallel; Arrangements for feeding already energised networks from additional generators or sources in parallel
- H02J3/381—Dispersed generators
-
- H—ELECTRICITY
- H05—ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
- H05B—ELECTRIC HEATING; ELECTRIC LIGHT SOURCES NOT OTHERWISE PROVIDED FOR; CIRCUIT ARRANGEMENTS FOR ELECTRIC LIGHT SOURCES, IN GENERAL
- H05B47/00—Circuit arrangements for operating light sources in general, i.e. where the type of light source is not relevant
- H05B47/20—Responsive to malfunctions or to light source life; for protection
-
- H—ELECTRICITY
- H05—ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
- H05B—ELECTRIC HEATING; ELECTRIC LIGHT SOURCES NOT OTHERWISE PROVIDED FOR; CIRCUIT ARRANGEMENTS FOR ELECTRIC LIGHT SOURCES, IN GENERAL
- H05B47/00—Circuit arrangements for operating light sources in general, i.e. where the type of light source is not relevant
- H05B47/20—Responsive to malfunctions or to light source life; for protection
- H05B47/25—Circuit arrangements for protecting against overcurrent
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2101/00—Supply or distribution of decentralised, dispersed or local electric power generation
- H02J2101/20—Dispersed power generation using renewable energy sources
- H02J2101/22—Solar energy
- H02J2101/24—Photovoltaics
-
- H—ELECTRICITY
- H05—ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
- H05B—ELECTRIC HEATING; ELECTRIC LIGHT SOURCES NOT OTHERWISE PROVIDED FOR; CIRCUIT ARRANGEMENTS FOR ELECTRIC LIGHT SOURCES, IN GENERAL
- H05B47/00—Circuit arrangements for operating light sources in general, i.e. where the type of light source is not relevant
- H05B47/20—Responsive to malfunctions or to light source life; for protection
- H05B47/28—Circuit arrangements for protecting against abnormal temperature
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/50—Photovoltaic [PV] energy
- Y02E10/56—Power conversion systems, e.g. maximum power point trackers
Definitions
- the present invention relates to a power supply system including a storage battery.
- a power supply system that combines a commercial power supply and a storage battery has begun to be used. That is, according to the time fluctuation of the load, when the load is large, in addition to the power from the commercial power supply, the discharge power from the storage battery is supplied to the load, and when the load is small, the commercial power supply is charged to the storage battery.
- the power supply from is averaged over time.
- a photovoltaic power generation system and a fuel cell system which have been developed in recent years, are also combined with the power supply system.
- the present invention includes a storage battery and a discharge switch provided in a discharge line that supplies power to a load connected to the storage battery, and a current flowing through the discharge line is equal to or higher than a predetermined first discharge reference current value.
- a discharge switch When the discharge switch is opened and the current flowing through the discharge line is greater than or equal to a second discharge reference current value smaller than the first discharge reference current value and less than the first discharge reference current value, the discharge switch is opened for a predetermined period.
- the storage battery is disconnected from the load, the discharge switch is closed after a predetermined period, and the storage battery is reconnected to the load.
- the discharge switch is closed. It is a power supply system.
- the present invention includes a storage battery and a charging switch provided on a charging line for charging the storage battery from an electric power source, and when the current flowing through the charging line becomes equal to or higher than a predetermined first charging base current value.
- the charge switch is opened, and the current flowing through the charge line becomes a second charge reference current value smaller than the first charge reference current value and less than the first charge reference current value, the charge switch is intermittently opened and The power supply system is in a closed state, and the charge switch is closed when the current flowing through the charging line becomes less than the second charging reference current value.
- the present invention can provide a power supply system capable of preventing performance deterioration due to charging / discharging between storage batteries.
- the power supply system 100 in the embodiment of the present invention includes a power management system 102, a storage battery assembly 104, a solar battery system 106, and a system power supply 108 as shown in FIG.
- the power supply system 100 is used to supply power to the load 110.
- a thick solid line indicates a power flow
- a thin solid line indicates a signal flow.
- the solar cell system 106 and the system power supply 108 are used as power sources.
- the system power supply 108 is a single-phase or three-phase power supply, and may be supplied from an external power company by combining power generated by various power generation methods such as hydropower generation, nuclear power generation, and thermal power generation. it can.
- the solar cell system 106 can be a large-scale solar power generation system of 1 MW, for example. However, it is not limited to these, You may include other electric power sources, such as a fuel cell and a wind power generation system.
- the storage battery assembly 104 is provided to supply power corresponding to the required power of the load 110. 2 and 3, the storage battery assembly 104 includes a storage battery pack 44 in which a plurality of storage battery cells 46 are combined, a storage battery control unit 42 in which a plurality of storage battery packs 44 are combined, and a storage battery unit in which a plurality of storage battery control units 42 are combined. As shown in FIG.
- the storage battery assembly 104 is configured as follows. In the present embodiment, as shown in FIG. 2, eight power converters 28 are provided, the storage battery assembly 104 is divided into eight, and one power converter 28 is assigned to each to perform power management. Each power converter 28 is assigned five storage battery units 40. That is, a total of 40 storage battery units 40 are provided, and each of the 5 storage battery units 40 is connected to one power converter 28.
- the power line is indicated by a solid line and the signal line is indicated by a broken line.
- FIG. 3 shows one storage battery unit 40 in FIG. 2 extracted in detail.
- One storage battery unit 40 is configured by connecting storage battery control units (storage battery pack trains) 42 in which storage battery packs 44 are connected in series as necessary in parallel as necessary.
- storage battery control units storage battery pack trains
- five storage battery packs 44 are connected in series to form one storage battery control unit 42
- four storage battery control units 42 are connected in parallel to form one storage battery unit 40.
- one storage battery unit 40 is composed of 20 storage battery packs 44.
- one storage battery pack 44 is shown enlarged.
- One storage battery unit 40 is provided with one sub-controller 24 and one switch circuit 30 respectively.
- the switch circuit 30 is provided with one selection switch SW ⁇ b> 1 for each storage battery control unit 42.
- the storage battery control unit 42 is connected to the discharge line L1 via the selection switch SW1.
- the selection switch SW1 is controlled to open / close in response to an open / close control signal from the sub-controller 24. That is, the storage battery control unit 42 is a minimum unit of control when the storage battery is connected to the discharge line L1.
- the switch circuit 30 includes an overcurrent protection circuit 200 that connects the storage battery control unit 42 to the load 110 via the discharge line L1. The function of the overcurrent protection circuit 200 will be described later.
- the storage battery control unit 42 included in one storage battery unit 40 is connected to the charging line L2 via the resistor R, respectively.
- the resistance R is preferably set to a resistance value that prevents a large current from adversely flowing between the storage battery control units 42. For example, if the output voltage of the storage battery control unit 42 is in the range of about 200 to 250 volts (V), the resistance R is preferably set to several tens to several hundreds ohms ( ⁇ ).
- a switch SW2 is provided on the charging line L2.
- the charge / discharge state between the storage battery control units 42 can be made uniform via the discharge line L1.
- the state of charge can be equalized more quickly.
- the switch circuit 30 is also provided with charging switches SW3 and SW4.
- the charging switch SW3 connected state
- the power generated by the solar cell system 106 can be supplied to the storage battery control unit 42, and the storage battery control unit 42 can be charged.
- the power supplied from the system power supply 108 can be supplied to the storage battery control unit 42, and the storage battery control unit 42 can be charged.
- a current sensor 52 is provided for each storage battery control unit 42 of the storage battery unit 40, and the current of each storage battery control unit 42 is detected.
- a voltage sensor 54 is provided in each of the 13 sets of parallel storage battery cells 46 connected in series in the storage battery pack 44. The voltage between terminals of the parallel assembly of the storage battery cells 46 is detected by the voltage sensor 54 as a cell voltage. In FIG. 3, only one voltage sensor 54 is shown for the sake of simplicity.
- the temperature of the storage battery pack 44 is detected by the temperature sensor 56 as the pack temperature.
- a plurality of temperature sensors 56 may be provided for each storage battery pack 44. These data are acquired by the sub-controller 24.
- the sub-controller 24 uses these data and the charge / discharge state (SOC: State Of Charge) calculated from these data as unit state data S3 and S6 indicating the state of each storage battery unit 40, and the master controller 22 and the storage battery power management device 12 Output to. Moreover, when the malfunction has arisen in the storage battery unit 40 which comprises the storage battery assembly 104, the sub controller 24 includes the information for specifying the malfunctioning storage battery unit 40 in unit state data S3, S6. To send.
- SOC State Of Charge
- the number of combinations of the storage battery cell 46, the storage battery pack 44, the storage battery control unit 42, and the storage battery unit 40 may be appropriately changed according to the specifications of the power supply system 100.
- a lithium ion battery can be used as a storage battery, you may apply other secondary batteries.
- a nickel metal hydride battery, a nickel cadmium battery, a manganese battery, or the like may be applied.
- the power supply system 100 is provided to supply power to a load 110 including general lighting, general air conditioning, kitchen appliances, display cases, air conditioning equipment, and the like of a factory facility.
- the load 110 is provided with a power management device 110a.
- the power management device 110a includes a load power management device 10, a storage battery power management device 12, and a total power monitoring device 14.
- the load power management apparatus 10 acquires load side information data S9 indicating the required power of the load 110.
- the load-side information data S9 includes the total required power requirement amount of the load 110 necessary for the system controller 20 to be described later to set the overall charge / discharge control command S1.
- the load power management device 10 is internally an aggregate of four systems of load power management devices.
- the storage battery power management device 12 includes unit state data S6 indicating the state of each storage battery unit 40 included in the storage battery assembly 104 and power converter management data S7 indicating each state of the power converter 28 included in the power supply system 100. Receive. The storage battery power management device 12 transfers these pieces of information to the total power monitoring device 14.
- Unit state data S6 includes information used to generate overall charge / discharge control command S1. In the unit state data S6, as described above, when any of the data such as the voltage, temperature, current, and SOC of the storage battery constituting the storage battery assembly and the storage battery unit 40 constituting the storage battery assembly 104 is defective. Contains information indicating these defects.
- the information regarding the malfunction of the power converter 28 related to the setting of the whole charge / discharge control command S1 is included in the power converter management data S7.
- the power converter management data S7 For example, when any of the power converters 28 has a problem such as a failure, information for specifying the power converter 28 in which the problem has occurred is included.
- the total power monitoring device 14 receives the load side information data S9 from the load power management device 10 and the unit state data S6 and the power converter management data S7 from the storage battery power management device 12, and is necessary for charge / discharge control from these information. Extract data.
- the total power monitoring device 14 outputs the extracted information to the system controller 20 as a system management signal S8.
- the system management signal S8 is transmitted at a cycle of once every 1 s, for example.
- the power management system 102 includes a system controller 20, a master controller 22, a sub controller 24, a power converter management unit 26, a power converter 28, and a switch circuit 30, as shown in FIG.
- the power management system 102 is configured as a hierarchical control system, and includes a top-level system controller 20, a master controller 22 belonging to a lower level of the system controller 20, a power converter management unit 26 and a master belonging to a lower level of the master controller 22. Control is hierarchized from the upper level to the lower level with the sub-controller 24 independent of the controller 22.
- the system controller 20 has a function of performing integrated power management of the power supply system 100.
- the master controller 22 is a control device that receives the entire charge / discharge control command S ⁇ b> 1 from the system controller 20 and performs charge / discharge control for the entire storage battery assembly 104.
- the power converter management unit 26 controls processing such as power conversion and voltage conversion in each of the power converters 28 included in the power supply system 100.
- the sub-controller 24 is provided for each storage battery unit 40 included in the storage battery assembly 104 and controls charging / discharging in each storage battery unit 40.
- the system controller 20 receives the system management signal S8 including the load information data S9, the storage battery information signal S6, and the power converter management data S7 from the power management apparatus 110a, and performs charge / discharge control for the entire power supply system 100 based on these information.
- An overall charge / discharge control command S1 which is a command, is generated and output.
- the system controller 20 calculates charging / discharging conditions satisfying the total required power requirement of the load 110 from the charging / discharging capacity of the storage battery assembly 104 in consideration of the states of the storage battery unit 40 and the power converter 28. This is transmitted to the master controller 22 as an overall charge / discharge control command S1.
- the system controller 20 also includes information on the charge / discharge capacity of the storage battery unit 40 connected to the power converter 28 in which the problem has occurred and the charge / discharge capacity of the storage battery unit 40 in which the problem has occurred.
- a charging / discharging condition satisfying the total required power requirement of the load 110 is obtained and transmitted to the master controller 22 as an entire charging / discharging control command S1.
- the charge / discharge conditions are indicated by the electric energy and the time, for example, “Charge at XX kW for YY seconds”.
- a charge upper limit voltage and “charge XX kW until the voltage reaches ZZV” specify a discharge lower limit voltage to discharge to ZZV
- SOC and charge / discharge May be commanded.
- the SOC is the SOC (charge / discharge state) in a state where the electric power is stored at the maximum
- the SOC (charge / discharge state) in each electric power storage state is expressed as a percentage based on the SOC. is there.
- the entire charge / discharge control command S1 Since the entire charge / discharge control command S1 is irregularly transmitted only when necessary, the entire charge / discharge control command S1 may not be transmitted for a considerably long time in some cases. In such a case, as the master controller 22 that receives the overall charge / discharge control command S1, the system controller 20 may not be able to determine whether the system controller 20 does not transmit because it is normal but not necessary, or does not transmit because there is a problem. There is. Accordingly, a confirmation signal S2 for confirming whether or not the system controller 20 is normal is transmitted from the master controller 22 to the system controller 20 at an appropriate period. The system controller 20 responds with a response signal when normal.
- the master controller 22 determines that the system controller 20 is normal if a response signal is returned from the system controller 20, and determines that the system controller 20 is defective if no response signal is returned from the system controller 20. it can. An appropriate period may be 10 minutes, for example. When it is determined that there is a defect, processing such as presenting the fact to the user may be performed.
- the master controller 22 has a function of receiving the overall charge / discharge control command S1 from the system controller 20 and transmitting the aggregate charge / discharge control command S5 for each power converter 28 to the power converter management unit 26.
- the master controller 22 includes the power converter management data S4 that is the state data of the power converter 28 from the power converter management unit 26 and the sub-controller 24 provided in each storage battery unit 40 included in the storage battery assembly 104.
- the determination can be made by applying the unit state data S3 or the like to a predetermined conditional expression.
- the assembly charge / discharge control command S5 is transmitted / received at a cycle of 100 ms, and the power converter management data S4 and the unit state data S3 are transmitted / received at a cycle of 1 s, for example.
- the overall charge / discharge control command S1 is a command value indicating the overall charge / discharge amount of the storage battery assembly 104 transmitted to the master controller 22, but the aggregate charge / discharge control command S5 is the overall charge / discharge control command S1.
- the individual command value of the assembly charge / discharge control command S5 is a value when the command value of the overall charge / discharge control command S1 is divided evenly by the number of power converters 28.
- Other command values may be used.
- the power converter management data S4 when it is transmitted by the power converter management data S4 that there is a malfunction in any of the power converters 28 controlled by the power converter management unit 26, a part of the charge / discharge control command S1 is charged.
- the assembly charge / discharge control command S5 with the content of which discharge is restricted is transmitted to the power converter management unit 26.
- the power converter management data S4 includes information indicating a malfunction of the power converter 28, and the unit state data S3 includes information indicating a malfunction of the storage battery unit 40.
- the master controller 22 uses the other storage battery units except for the storage battery unit 40 in which the malfunction occurs in the storage battery units 40 connected to the other power converters 28 except for the power converter 28 in which the malfunction occurred.
- An aggregate charge / discharge control command S5 for controlling each power converter 28 is generated and output to the power converter management unit 26 so that the charge / discharge state required by the overall charge / discharge control command S1 is satisfied.
- the master controller 22 transmits data having the same content as the power converter management data S4 received from the power converter management unit 26 to the storage battery power management apparatus 12 as power converter management data S7.
- the power converter management data S7 may be transmitted at a transmission cycle longer than the transmission cycle of the power converter management data S4. For example, when the power converter management data S4 is transmitted every second, the power converter management data S7 may be transmitted every 10 seconds.
- the power converter management data S7 includes information for 10 times of the power converter management data S4. Of course, other transmission periods may be used, and the transmission periods of the power converter management data S4 and the power converter management data S7 may be the same.
- the sub-controller 24 is provided for each storage battery unit 40 as described above, and performs open / close control of switches included in the switch circuit 30 provided in each storage battery unit 40 according to the state of each storage battery unit 40.
- the sub-controller 24 turns on the overcurrent protection circuit 200 and the charge switches SW3 and SW4 (connected state) when the power source (not shown) of the storage battery unit 40 is turned on and the charging / discharging conditions are satisfied, and charging / discharging from the storage battery unit 40 is performed. Start discharging.
- the sub-controller 24 is detected by a current value detected by a current sensor 52 provided in each storage battery control unit 42, a voltage value detected by a voltage sensor 54, and a temperature sensor 56 provided in each storage battery unit 40.
- the state of the storage battery pack 44 and the storage battery control unit 42 is determined based on the temperature to be detected and the reference voltage detected by the voltage sensor 60 provided in the discharge line L1, and the switch corresponding to the storage battery control unit 42 according to the determination result SW1 open / close control is performed.
- the sub-controller 24 is detected by a current value detected by a current sensor 52 provided in each storage battery control unit 42, a voltage value detected by a voltage sensor 54, and a temperature sensor 56 provided in each storage battery unit 40. If it is determined that there is a malfunction in the state of the storage battery pack 44 or the storage battery control unit 42 based on the temperature and the reference voltage detected by the voltage sensor 60 provided in the discharge line L1, a malfunction has occurred.
- the storage battery control unit 42 including the storage battery pack 44 is disconnected from the discharge line L1. Specifically, a process of opening the switch SW1 (SW1 (1) to SW1 (4)) corresponding to the storage battery control unit 42 including the storage battery pack 44 in which the failure occurs is performed. Further, the sub-controller 24 transmits information indicating the malfunction of the storage battery pack 44 and the storage battery control unit 42 to the master controller 22 and the storage battery power management device 12 as unit state data S3 and S6.
- the determination of the malfunction is made when the current detected by the current sensor 52 exceeds a threshold calculated from a predetermined conditional expression, when the cell voltage detected by the voltage sensor 54 exceeds a predetermined threshold range, the temperature sensor 56 Can be performed in comparison with a predetermined condition, such as when the pack temperature detected by the above exceeds a predetermined threshold.
- the sub-controller 24 transmits information indicating the malfunction of the storage battery unit 40 to the master controller 22 and the storage battery power management apparatus 12 as unit state data S3 and S6.
- the sub-controller 24 transmits data having the same contents as the unit state data S3 transmitted to the master controller 22 to the storage battery power management apparatus 12 as unit state data S6.
- the unit state data S6 may be transmitted at a transmission cycle longer than the transmission cycle of the unit state data S3.
- the unit state data S6 may be transmitted every 10 seconds.
- the unit state data S6 includes information for 10 times of the unit state data S3.
- other transmission periods may be used, and the transmission periods of the unit state data S3 and the unit state data S6 may be the same.
- the power converter management unit 26 receives the assembly charge / discharge control command S5 from the master controller 22 and controls each power converter 28 to be controlled.
- power supply system 100 as shown in FIG. 2, there are eight power converters 28 to be controlled by power converter management unit 26.
- the present invention is not limited to this, and the number of power converters 28 may be changed as appropriate.
- the power converter 28 performs power conversion between the AC power of the system power supply 108 and the DC power of the storage battery assembly 104, voltage conversion between the DC voltage of the solar battery system 106 and the DC voltage of the storage battery assembly 104, and the storage battery. It has a function of performing power conversion between the DC power of the assembly 104 and the AC power of the load 110, voltage conversion between the DC voltage of the storage battery assembly 104 and the DC voltage of the load 110, and the like. Specifically, a bidirectional cross current conversion circuit, a bidirectional voltage conversion circuit, and the like are configured as necessary.
- the power converter management unit 26 charges the storage battery assembly 104 from the solar cell system 106 or the system power supply 108 or discharges the storage battery assembly 104 to the load 110 in accordance with the assembly charge / discharge control command S5.
- the power conversion and voltage conversion in each power converter 28 are controlled.
- any of the power converters 28 under the control of the power converter management unit 26 is defective, or when a charge / discharge prohibition command or a standby command is output from the master controller 22, The operation of the defective power converter 28 is set in a standby state, and information indicating the problem of the power converter 28 is transmitted to the master controller 22 as power converter management data S4.
- the assembly charge / discharge control command S5 is “the first power converter 28 is discharged at 40 kW, the second power converter 28 is If the content is “discharge at 40 kW..., The eighth power converter 28 is discharged at 40 kW”, the power converter management unit 26 supplies power from each power converter 28 to the load 110 at 40 kW. The voltage conversion and power conversion in each power converter 28 are controlled.
- the assembly charge / discharge control command S5 is “the first power converter 28 is charged at 40 kW, the second power converter 28 is charged at 40 kW, and the eighth power converter 28 is charged at 40 kW”.
- the power converter management unit 26 performs voltage conversion and power conversion in each power converter 28 such that charging is performed at 40 kW from the solar cell system 106 and the system power supply 108 via each power converter 28. To control.
- the system controller 20 determines the overall charging / discharging conditions of the storage battery assembly 104 in accordance with the total required power requirement of the load 110 and sets it as the entire charging / discharging control command S1. Then, the master controller 22 performs specific control of each power converter 28 in consideration of the power converter 28 and the storage battery unit 40 in which a failure has occurred so as to satisfy the charge / discharge control command in the overall charge / discharge control command S1.
- the assembly charge / discharge control command S5 is generated, and each power converter 28 is controlled by the power converter management unit 26 lower than the master controller 22.
- the power converter management unit 26 does not control the host system controller 20 and the master controller 22, and the power converter 28 and the storage battery unit 40 connected thereto. Process to disconnect. Further, the sub-controller 24 controls connection / disconnection of the storage battery control unit 42 included in each storage battery unit 40 when the storage battery unit 40 has a problem, regardless of control by the host system controller 20 and the master controller 22. I do. As described above, by performing hierarchical control, even if a malfunction occurs in the power converter 28 or the storage battery unit 40, the storage battery assembly 104 can be handled as if it were one battery, as viewed from the system controller 20. it can. Further, it is possible to reduce the processing load of the higher-order control system and flexibly cope with changes in the system configuration.
- overcurrent protection circuit 200 is provided in switch circuit 30 for each storage battery unit 40.
- the overcurrent protection circuit 200 includes a discharge switch Q1, switches Q2, Q3, a photovolt U1, a photocoupler U2, a comparator CMP1, a timer element TM1, and a resistor Rx.
- the discharge switch Q1 can be an FET, and the switches Q2 and Q3 can be bipolar transistors.
- the resistor Rx can be a substrate resistance formed integrally with the overcurrent protection circuit 200.
- the overcurrent protection circuit 200 is provided on the discharge line L1 from the storage battery control unit 42 to the load 110, and disconnects the storage battery control unit 42 and the load 110 when an overcurrent flows through the discharge line L1. It has a function.
- the sub-controller 24 applies a high-level discharge control signal to the control terminal T1.
- a voltage is applied to the photodiode D1 of the photovolt U1, and the photodiode D1 emits light.
- the photodiode D1 is paired with the photoelectric conversion element P1, and the voltage at the terminal T2 of the photoelectric conversion element P1 rises due to light emission of the photodiode D1.
- the discharge switch Q1 is turned on, and the storage battery control unit 42 is connected to the load 110 via the discharge switch Q1 and the resistor Rx.
- the overcurrent protection circuit 200 is used when the current flowing through the discharge line L1 becomes equal to or greater than a predetermined first discharge reference current value and when the current exceeds a second discharge reference current value smaller than the first discharge reference current value. It has a function to perform two-stage overcurrent protection.
- the first discharge reference current value is, for example, 900 amperes (A)
- the second discharge reference current value is, for example, 30 amperes (A).
- the comparator CMP1 gives an ON signal (low level signal) to the trigger terminal T4 of the timer element TM1 when the voltage of the terminal T3 becomes equal to or higher than the reference voltage Vref1, and starts the timer element TM1.
- the reference voltage Vref1 is a voltage obtained by dividing the power supply voltage Vcc by the resistors Ra and Rb.
- a voltage corresponding to the current flowing through the load 110 via the discharge line L1 is input to the terminal T3.
- a resistor is provided in the discharge line L1, and a voltage generated in the resistor in accordance with a current flowing through the load 110 via the discharge line L1 may be input to the terminal T3.
- the timer element TM1 is activated for a certain period of time when an on signal is given to the trigger terminal T4, and turns on the switch Q2 for the period of activation.
- the switch Q2 When the switch Q2 is turned on, the anode side of the photodiode D1 is grounded via the switch Q2, so that the photovolt U1 is turned off, and the discharge switch Q1 is turned off.
- the storage battery control unit 42 is disconnected from the load 110 during the time when the timer element TM1 is activated.
- the terminal voltage of the resistor Rx increases, and the switch Q3 is turned on when the current flowing through the discharge line L1 becomes equal to or higher than the first discharge reference current value.
- the switch Q3 is turned on, the voltage at the terminal T2 is lowered via the photodiode D2 and the switch Q3, and the discharge switch Q1 is turned off. Thereby, the storage battery control unit 42 is disconnected from the load 110.
- the photodiode D2 of the photocoupler U2 emits light.
- the photodiode D2 is paired with the phototransistor P2, a current flows through the phototransistor P2 due to light emission of the photodiode D2, and an ON signal is given to the trigger terminal T4 of the timer element TM1. Accordingly, as described above, the photovolt U1 and the discharge switch Q1 are turned off, and the storage battery control unit 42 is disconnected from the load 110 during the time when the timer element TM1 is activated.
- the discharge switch Q1 is intermittently interrupted by using the timer element TM1 as the necessity of suppressing the discharge. Further, when the current flowing through the discharge line L1 becomes equal to or higher than the first discharge reference current value, it is assumed that an excessive current with high urgency has flowed, and the discharge switch does not go through a circuit that takes time for processing such as the timer element TM1. Q1 is cut off and the discharge from the storage battery control unit 42 is completely stopped.
- a high level discharge control signal is applied from the sub controller 24 to the control terminal T1, but the master controller 22 controls the control terminal T1.
- a high-level discharge control signal may be applied to T1.
- the overcurrent protection circuit 200 is provided between the storage battery control unit 42 and the load 110.
- the storage battery control unit 42 and the load 110 are connected via an inverter or a converter. In this case, it may be provided between the storage battery control unit 42 and the inverter or converter.
- the overcurrent protection circuit 200 is provided for each storage battery unit 40, but may be provided in common for a plurality of storage battery units 40 connected to a common load 110.
- the overcurrent protection circuit 200 is provided from the connection point where the plurality of storage battery control units 40 are connected in parallel to the load 110 in the discharge line L1.
- the overcurrent protection circuit 200 is preferably controlled by the master controller 22.
- the sub-controller 24 performs overcurrent protection processing during charging.
- the sub-controller 24 reads the charging current value flowing through the charging line L2 from the current sensor 62 provided on the charging line L2.
- the sub-controller 24 has two stages when the current flowing through the charging line L2 becomes equal to or greater than a predetermined first charge reference current value and when the current exceeds a second charge reference current value smaller than the first discharge reference current value.
- the first charging reference current value is, for example, 200 amperes (A)
- the second charging reference current value is, for example, 30 amperes (A).
- the sub-controller 24 connects and disconnects the charging switch SW3 with a predetermined cycle and on-duty when the read charging current value becomes equal to or higher than the second charging reference voltage. Further, when the read charging current value becomes equal to or higher than the first power receiving reference voltage, the sub-controller 24 completely turns off the charging switch SW3.
- the charging switch SW3 is controlled by the sub-controller 24.
- the overcurrent protection circuit 202 may be provided on the charging line L2 as with the discharging line L1. Good.
- the sub-controller 24 may apply a high-level charging control signal to the control terminal T1.
- the voltage applied to the terminal T3 may be made equal to the reference voltage Vref1 when the current flowing through the charging line L2 becomes the second charging reference current value (30 amperes (A)).
- the charging switch SW3 or the overcurrent protection circuit 202 is provided for each storage battery unit 40, but is common to the plurality of storage battery units 40 connected to the solar battery system 106 and the system power supply 108. It is good also as a structure provided in.
- the charging switch SW3 or the overcurrent protection circuit 202 is provided between the connection point where the plurality of storage battery control units 40 are connected in parallel on the charging line L2 to the solar cell system 106 serving as the power source and the system power supply 108. It is done.
- the charge switch SW3 or the overcurrent protection circuit 202 is preferably controlled by the master controller 22.
- an overcurrent protection circuit 200 is provided on the discharge line L1, or an overcurrent is provided on the charge line L2.
- a current protection circuit 202 may be provided.
- the selection switch SW1 and the switch SW2 may be replaced with the configuration of the overcurrent protection circuit 200. That is, the selection switch SW1 is replaced with the switch Q1 of the overcurrent protection circuit 200 (202), and the opening and closing of the switch Q1 is controlled according to the magnitude of the charge / discharge current of each power storage control unit 42. Further, the switch SW2 is replaced with the switch Q1 of the overcurrent protection circuit 200 (202), and the opening and closing of the switch Q1 is controlled according to the magnitude of the charging current flowing through the charging line L2. At this time, it is preferable that the first charging reference current value and the second charging reference current value are appropriately set to values suitable for each protection.
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Charge And Discharge Circuits For Batteries Or The Like (AREA)
- Secondary Cells (AREA)
Abstract
蓄電池制御単位42と、蓄電池制御単位42に接続され負荷110へ電力を供給する放電ラインL1上に設けられ、蓄電池制御単位42と負荷110との間に設けられた放電スイッチQ1とを含み、放電ラインL1を流れる電流が第1放電基準電流値以上となった場合に放電スイッチQ1を開状態とし、放電ラインL1を流れる電流が第1放電基準電流値よりも小さい第2放電基準電流値以上第1放電基準電流値未満となった場合に放電スイッチQ1を所定期間開状態として蓄電池制御単位42と負荷110とを切り離し、所定期間後に放電スイッチQ1を閉状態として蓄電池制御単位42と負荷110と再度接続し、放電ラインL1を流れる電流が第2放電基準電流値未満となった場合に放電スイッチQ1を閉状態とする。
Description
本発明は、蓄電池を含む電源システムに関する。
電力の有効的な利用を図るために商用電源と蓄電池とを組み合わせた電源システムが利用され始めている。すなわち、負荷の時間的な変動に合わせて、負荷が大きいときには商用電源からの電力に加えて蓄電池からの放電電力を負荷へ供給し、負荷が小さいときには商用電源から蓄電池へ充電を行い、商用電源からの電力供給を時間的に平均化するものである。また、近年開発が進んでいる太陽光発電システムや燃料電池システムも電源システムに組み合わせられている。
このような電源システムにおいて、蓄電池への充電を行う際及び蓄電池から負荷へ放電を行う際に充放電電流が大きくなり過ぎると急激な充放電によって蓄電池の劣化や長期的な寿命へ悪影響を及ぼすおそれがある。
本発明は、蓄電池と、蓄電池に接続される負荷へ電力を供給する放電ラインに設けられた放電スイッチと、を備え、放電ラインを流れる電流が所定の第1放電基準電流値以上となった場合に放電スイッチを開状態とし、放電ラインを流れる電流が第1放電基準電流値よりも小さい第2放電基準電流値以上第1放電基準電流値未満となった場合に放電スイッチを所定期間開状態として蓄電池と負荷とを切り離し、所定期間後に放電スイッチを閉状態として蓄電池と負荷と再度接続し、放電ラインを流れる電流が第2放電基準電流値未満となった場合に放電スイッチを閉状態とする、電源システムである。
本発明は、蓄電池と、蓄電池へ電力源から充電を行うための充電ラインに設けられた充電スイッチと、を備え、充電ラインを流れる電流が所定の第1充電基電流値以上となった場合に充電スイッチを開状態とし、充電ラインを流れる電流が第1充電基準電流値よりも小さい第2充電基準電流値以上第1充電基準電流値未満となった場合に充電スイッチを断続的に開状態及び閉状態とし、充電ラインを流れる電流が第2充電基準電流値未満となった場合に充電スイッチを閉状態とする、電源システムである。
本発明は、蓄電池間の充放電による性能劣化を防ぐことができる電源システムを提供することができる。
本発明の実施の形態における電源システム100は、図1に示すように、電源管理システム102、蓄電池集合体104、太陽電池システム106及び系統電源108を含んで構成される。電源システム100は、負荷110に電力を供給するために用いられる。なお、図1において、太い実線は電力の流れを示し、細い実線は信号の流れを示す。
本実施の形態では、太陽電池システム106及び系統電源108を電力源としている。系統電源108は、単相又は3相等の電源であり、水力発電、原子力発電、火力発電等の様々な発電方式で発電された電力を組み合わせて外部の電力会社から供給されるものとすることができる。また、太陽電池システム106は、例えば1MWの大規模な太陽光発電システムとすることができる。ただし、これらに限定されるものではなく、燃料電池や風力発電システム等の他の電力源を含めてもよい。
蓄電池集合体104は、負荷110の必要電力に応じた電力を供給するために設けられる。蓄電池集合体104は、図2及び図3に示すように、蓄電池セル46を複数組み合わせた蓄電池パック44、蓄電池パック44を複数組み合わせた蓄電池制御単位42、及び蓄電池制御単位42を複数組み合わせた蓄電池ユニット40のように階層的に構成される。
具体的には、蓄電池集合体104は以下のように構成される。本実施の形態では、図2に示すように、8個の電力変換器28を設け、蓄電池集合体104を8つに分けて、それぞれに1つの電力変換器28を割り当てて電力管理を行う。各電力変換器28には、5個の蓄電池ユニット40が割り当てられる。すなわち、全体で40個の蓄電池ユニット40を設け、5個の蓄電池ユニット40毎が1つの電力変換器28に接続される。なお、図2では、電力線を実線で、信号線を破線で示している。
図3は、図2における1つの蓄電池ユニット40を抜き出し、その構成を詳細に示している。1つの蓄電池ユニット40は、蓄電池パック44を必要に応じて直列接続した蓄電池制御単位(蓄電池パック列)42を、必要に応じて並列に接続して構成される。図3の例では、5個の蓄電池パック44を直列接続して1つの蓄電池制御単位42を形成し、その蓄電池制御単位42を4列並列接続して、1つの蓄電池ユニット40が構成されている。本実施の形態では、1つの蓄電池ユニット40は、20個の蓄電池パック44から構成される。
さらに、図3には、1つの蓄電池パック44の内部構成が拡大されて示されている。本実施の形態では、1つの蓄電池パック44は、蓄電池の単位である蓄電池セル46を24個並列に接続したものを、直列に13組接続して構成される。つまり、各蓄電池パック44は、24×13=312個の蓄電池セル46から構成される。
1つの蓄電池ユニット40には、それぞれ1つのサブコントローラ24と、1つのスイッチ回路30とが設けられる。スイッチ回路30には、図4に示すように、蓄電池制御単位42毎に1つの選択スイッチSW1が設けられている。蓄電池制御単位42は、選択スイッチSW1を介して放電ラインL1に接続される。選択スイッチSW1は、サブコントローラ24からの開閉制御信号に応じて開閉制御される。すなわち、蓄電池制御単位42は、蓄電池を放電ラインL1に接続する際の制御の最小単位となる。
さらに、スイッチ回路30は、放電ラインL1を介して、蓄電池制御単位42を負荷110に接続する過電流保護回路200を含む。過電流保護回路200の機能については後述する。
また、1つ蓄電池ユニット40に含まれる蓄電池制御単位42は、それぞれ抵抗Rを介して充電ラインL2に接続される。これにより、蓄電池制御単位42間には2つの抵抗Rを介して相互に充放電電流が流れ、蓄電池制御単位42の充電状態が均等化される。抵抗Rは、蓄電池制御単位42間に悪影響を及ぼすような大きな電流が流れないような抵抗値とすることが好適である。例えば、蓄電池制御単位42の出力電圧が約200~250ボルト(V)の範囲であれば、抵抗Rは数十~数百オーム(Ω)に設定することが好適である。
さらに、充電ラインL2には、スイッチSW2が設けられる。スイッチSW2をオン(接続状態)とすることによって、放電ラインL1を介して蓄電池制御単位42間の充放電状態を均一化させることができる。この場合、1つの抵抗Rを介して蓄電池制御単位42間で充放電を行うことができるので、より迅速に充電状態を均一化させることができる。
スイッチ回路30には、充電スイッチSW3及びSW4も設けられる。充電スイッチSW3をオン(接続状態)とすることによって、太陽電池システム106で生成された電力を蓄電池制御単位42へ供給することができ、蓄電池制御単位42を充電することができる。また、充電スイッチSW3及びSW4の両方をオン(接続状態)とすることによって、系統電源108から供給される電力を蓄電池制御単位42へ供給することができ、蓄電池制御単位42を充電することができる。
さらに、蓄電池ユニット40の蓄電池制御単位42毎に電流センサ52が設けられ、各蓄電池制御単位42の電流が検出される。また、蓄電池パック44の直列に接続される13組の蓄電池セル46の並列集合体の各々には電圧センサ54が設けられる。蓄電池セル46の並列集合体の端子間電圧はセル電圧として電圧センサ54によって検出される。なお、図3では、図を簡略に示すために電圧センサ54を一つのみ図示している。また、蓄電池パック44の温度はパック温度として温度センサ56によって検出される。なお、蓄電池パック44毎に複数の温度センサ56を設けてもよい。これらのデータはサブコントローラ24により取得される。サブコントローラ24は、これらのデータ及びこれらのデータから算出した充放電状態(SOC:State Of Charge)を各蓄電池ユニット40の状態を示すユニット状態データS3,S6としてマスタコントローラ22及び蓄電池電力管理装置12へ出力する。また、蓄電池集合体104を構成する蓄電池ユニット40に不具合が生じている場合には、サブコントローラ24は、不具合を生じている蓄電池ユニット40を特定するための情報をユニット状態データS3,S6に含めて送信する。
なお、蓄電池セル46、蓄電池パック44、蓄電池制御単位42及び蓄電池ユニット40の組み合わせの数は電源システム100の仕様に応じ適宜変更してもよい。また、蓄電池としてリチウムイオン電池を用いることができるが、これ以外の2次電池を適用してもよい。例えば、ニッケル水素電池、ニッケルカドミウム電池、マンガン電池等を適用してもよい。
電源システム100は、工場施設の一般照明、一般空調、厨房器具、展示ケース、空調設備等を含む負荷110へ電力を供給するために設けられる。
負荷110には、電力管理装置110aが設けられる。電力管理装置110aは、負荷電力管理装置10、蓄電池電力管理装置12及び総合電力監視装置14を含んで構成される。
負荷電力管理装置10は、負荷110の必要電力を示す負荷側情報データS9を取得する。負荷側情報データS9は、後述するシステムコントローラ20が全体充放電制御指令S1を設定できるために必要な負荷110の全体の必要電力要求量を含む。図1に示すように、負荷110が4系統に区分されるときは、負荷電力管理装置10は、内部的に4系統の負荷電力管理装置の集合体とされる。
蓄電池電力管理装置12は、蓄電池集合体104に含まれる蓄電池ユニット40の各々の状態を示すユニット状態データS6及び電源システム100に含まれる電力変換器28の各々の状態を示す電力変換器管理データS7を受信する。蓄電池電力管理装置12は、これらの情報を総合電力監視装置14へ転送する。ユニット状態データS6は、全体充放電制御指令S1の生成に利用される情報を含む。ユニット状態データS6には、上記のように、蓄電池集合体を構成する蓄電池の電圧、温度、電流、SOC等のデータ及び蓄電池集合体104を構成する蓄電池ユニット40のいずれかに不具合がある場合にはこれらの不具合を示す情報が含まれる。また、電力変換器管理データS7には、全体充放電制御指令S1の設定に関係する電力変換器28の不具合に関する情報が含まれる。例えば、電力変換器28のいずれかに故障等の不具合がある場合、不具合が生じている電力変換器28を特定するための情報が含まれる。
総合電力監視装置14は、負荷電力管理装置10から負荷側情報データS9並びに蓄電池電力管理装置12からユニット状態データS6及び電力変換器管理データS7を受けて、これらの情報から充放電制御に必要なデータを抽出する。総合電力監視装置14は、抽出された情報をシステム管理信号S8としてシステムコントローラ20へ出力する。システム管理信号S8の送信は、例えば1sに1回の周期で行われる。
電源管理システム102は、図1に示すように、システムコントローラ20、マスタコントローラ22、サブコントローラ24、電力変換器管理部26、電力変換器28及びスイッチ回路30を含んで構成される。電源管理システム102は、階層的な制御システムとして構成されており、最上位のシステムコントローラ20、システムコントローラ20の下位に属するマスタコントローラ22、マスタコントローラ22の下位に属する電力変換器管理部26及びマスタコントローラ22から独立しているサブコントローラ24と上位から下位に向かって制御が階層化されている。
システムコントローラ20は、電源システム100の電力管理を統合的に行う機能を有する。マスタコントローラ22は、システムコントローラ20からの全体充放電制御指令S1を受けて、蓄電池集合体104の全体を1つとして充放電制御するための制御装置である。電力変換器管理部26は、電源システム100に含まれる電力変換器28の各々における電力変換及び電圧変換等の処理を制御する。サブコントローラ24は、蓄電池集合体104に含まれる蓄電池ユニット40毎に設けられ、それぞれの蓄電池ユニット40での充放電を制御する。以下、これらの構成要素について説明する。
システムコントローラ20は、電力管理装置110aから負荷情報データS9、蓄電池情報信号S6及び電力変換器管理データS7を含むシステム管理信号S8を受け、これらの情報に基づいて電源システム100の全体に対する充放電制御指令である全体充放電制御指令S1を生成して出力する。
具体的には、システムコントローラ20は、蓄電池ユニット40及び電力変換器28の状態を考慮して、蓄電池集合体104の充放電容量から負荷110の全体の必要電力要求量を満たす充放電条件を求めて、これを全体充放電制御指令S1としてマスタコントローラ22に送信する。また、好ましくは、システムコントローラ20は、不具合が生じている電力変換器28に接続されている蓄電池ユニット40の充放電の容量、および不具合が生じている蓄電池ユニット40の充放電の容量に関する情報も考慮して、蓄電池集合体104の充放電容量から負荷110の全体の必要電力要求量を満たす充放電条件を求めて、これを全体充放電制御指令S1としてマスタコントローラ22に送信する。
全体充放電制御指令S1は、例えば「XXkWでYY秒間充電すること」等のように、充放電条件が電力量と時間とで示される。この他に、充電上限電圧を指定して「電圧がZZVになるまでXXkW充電すること」としてもよく、放電下限電圧を指定してZZVまで放電することとしてもよく、SOCを指定して充放電を指令するものとしてもよい。ここで、SOCとは、電力を最大に貯蔵した状態におけるSOC(充放電状態)を100とし、それを基準にして電力の各貯蔵状態でのSOC(充放電状態)を百分率で表したものである。
全体充放電制御指令S1は、必要なときにのみ不定期に送信されるので、場合によってはかなりの長時間の間、全体充放電制御指令S1が送信されないことが生じ得る。そのような場合に、全体充放電制御指令S1を受け取るマスタコントローラ22としては、システムコントローラ20が、正常だが必要がないため送信してこないのか、不具合があるから送信してこないのかを判定できないおそれがある。そこで、システムコントローラ20が正常であるか否かを確認するための確認信号S2が、マスタコントローラ22からシステムコントローラ20に適当な周期で送信される。システムコントローラ20は、正常のときは応答信号で返答する。マスタコントローラ22は、システムコントローラ20から応答信号の返信があればシステムコントローラ20が正常であると判定し、システムコントローラ20から応答信号の返信がなければシステムコントローラ20に不具合があると判定することができる。適当な周期としては、例えば10分とすることができる。不具合があると判定された場合にはユーザにその旨を呈示する等の処理を行ってもよい。
マスタコントローラ22は、システムコントローラ20から全体充放電制御指令S1を受け、それぞれの電力変換器28に対する集合体充放電制御指令S5を電力変換器管理部26に送信する機能を有する。
また、マスタコントローラ22は、電力変換器管理部26から電力変換器28の状態データである電力変換器管理データS4と、蓄電池集合体104に含まれる各蓄電池ユニット40に設けられたサブコントローラ24から各々の蓄電池ユニット40の状態を示すユニット状態データS3とを受け取り、電力変換器管理データS4とユニット状態データS3とに基づいてシステムコントローラ20から送信された全体充放電制御指令S1をそのまま実行できるか否か判断し、判断の結果に基づいて、集合体充放電制御指令S5を電力変換器管理部26に送信する。判断は、例えば、ユニット状態データS3等を予め定めた条件式に当てはめて行うものとすることができる。集合体充放電制御指令S5は、100msの周期で送受信が行われ、電力変換器管理データS4、ユニット状態データS3は、例えば1s周期で送受信が行われる。
全体充放電制御指令S1は、マスタコントローラ22に対して送信される蓄電池集合体104の全体の充放電量を示す指令値であるが、集合体充放電制御指令S5は、全体充放電制御指令S1での指令値を電力変換器28毎に分解した指令値となる。図2に示すように、電力変換器管理部26に対して8個の電力変換器28が設けられている場合、全体充放電制御指令S1が「320kWで1800秒間放電」という内容であったとすると、集合体充放電制御指令S5は、「第1の電力変換器28は40kWで放電、第2の電力変換器28は40kWで放電・・・第8の電力変換器28は40kWで放電」という内容になる。なお、この具体例では、集合体充放電制御指令S5の個別の指令値は、全体充放電制御指令S1の指令値を電力変換器28の個数で均等に割ったときの値となっているが、これ以外の個別の指令値とされることもある。例えば、電力変換器管理データS4によって、電力変換器管理部26が制御する電力変換器28のいずれかに不具合があることが送信されているときは、全体充放電制御指令S1の一部の充放電が制限された内容の集合体充放電制御指令S5が電力変換器管理部26に送信される。具体的には、電力変換器管理データS4には電力変換器28の不具合を示す情報が含まれており、ユニット状態データS3には、蓄電池ユニット40の不具合を示す情報が含まれているので、マスタコントローラ22は、不具合が生じた電力変換器28を除いた他の電力変換器28について、それに接続された蓄電池ユニット40の中で不具合が生じた蓄電池ユニット40を除いた他の蓄電池ユニットによって、全体充放電制御指令S1で要求される充放電状態が満たされるように、各電力変換器28を制御する集合体充放電制御指令S5を生成して、電力変換器管理部26へ出力する。
また、マスタコントローラ22は、電力変換器管理部26から受け取った電力変換器管理データS4と同じ内容のデータを電力変換器管理データS7として蓄電池電力管理装置12に送信する。電力変換器管理データS7は、電力変換器管理データS4の送信周期よりも長い送信周期で送信するものとしてもよい。例えば、電力変換器管理データS4を1秒毎に送信する場合、電力変換器管理データS7は10秒毎に送信すればよい。この場合、電力変換器管理データS7には、電力変換器管理データS4の10回分の情報が含まれる。勿論、これ以外の送信周期としてもよく、電力変換器管理データS4と電力変換器管理データS7の送信周期を同じとしてもよい。
サブコントローラ24は、上記のように蓄電池ユニット40毎に設けられ、各蓄電池ユニット40の状態に応じて各蓄電池ユニット40に設けられたスイッチ回路30に含まれるスイッチの開閉制御を行う。サブコントローラ24は、蓄電池ユニット40の電源(図示しない)がオンされ、充放電の条件が整うと、過電流保護回路200及び充電スイッチSW3及びSW4をオン(接続状態)として蓄電池ユニット40からの充放電を開始させる。
また、サブコントローラ24は、各蓄電池制御単位42に設けられた電流センサ52で検出される電流値及び電圧センサ54で検出される電圧値、各蓄電池ユニット40に設けられた温度センサ56で検出される温度並びに放電ラインL1に設けられた電圧センサ60で検出される基準電圧に基づいて蓄電池パック44や蓄電池制御単位42の状態を判断し、その判断結果に応じて蓄電池制御単位42に対応するスイッチSW1の開閉制御を行う。
例えば、サブコントローラ24は、各蓄電池制御単位42に設けられた電流センサ52で検出される電流値及び電圧センサ54で検出される電圧値、各蓄電池ユニット40に設けられた温度センサ56で検出される温度並びに放電ラインL1に設けられた電圧センサ60で検出される基準電圧に基づいて蓄電池パック44や蓄電池制御単位42の状態に不具合が乗じていると判断される場合には、不具合が生じている蓄電池パック44を含む蓄電池制御単位42を放電ラインL1から切り離す処理を行う。具体的には、不具合が生じている蓄電池パック44を含む蓄電池制御単位42に対応するスイッチSW1(SW1(1)~SW1(4))を開放する処理を行う。また、サブコントローラ24は、蓄電池パック44や蓄電池制御単位42の不具合を示す情報をユニット状態データS3,S6としてマスタコントローラ22および蓄電池電力管理装置12に送信する。
不具合の判断は、電流センサ52の検出される電流が予め定めた条件式から算出される閾値を超えるとき、電圧センサ54によって検出されるセル電圧が予め定めた閾値範囲を超えるとき、温度センサ56によって検出されるパック温度が予め定めた閾値を超えるとき等のように、予め定めた条件と比較して行うことができる。
また、サブコントローラ24は、上記のように、蓄電池ユニット40の不具合を示す情報をユニット状態データS3,S6としてマスタコントローラ22および蓄電池電力管理装置12に送信する。サブコントローラ24は、マスタコントローラ22へ送信したユニット状態データS3と同じ内容のデータをユニット状態データS6として蓄電池電力管理装置12に送信する。ここで、ユニット状態データS6は、ユニット状態データS3の送信周期よりも長い送信周期で送信するものとしてもよい。例えば、ユニット状態データS3を1秒毎に送信する場合、ユニット状態データS6は10秒毎に送信すればよい。この場合、ユニット状態データS6には、ユニット状態データS3の10回分の情報が含まれる。勿論、これ以外の送信周期としてもよく、ユニット状態データS3とユニット状態データS6の送信周期を同じとしてもよい。
電力変換器管理部26は、マスタコントローラ22から集合体充放電制御指令S5を受け、制御対象となる電力変換器28の各々を制御する。本実施の形態における電源システム100では、図2に示すように、電力変換器管理部26の制御対象となる電力変換器28を8個としている。ただし、これに限定されるものではなく、電力変換器28の数は適宜変更してもよい。
電力変換器28は、系統電源108の交流電力と蓄電池集合体104の直流電力との間の電力変換、太陽電池システム106の直流電圧と蓄電池集合体104の直流電圧との間の電圧変換、蓄電池集合体104の直流電力と負荷110の交流電力との間の電力変換、蓄電池集合体104の直流電圧と負荷110の直流電圧との間の電圧変換等を行う機能を有する。具体的には、必要に応じて双方向直交流変換回路、双方向電圧変換回路等を含んで構成される。
電力変換器管理部26は、集合体充放電制御指令S5に従って、太陽電池システム106や系統電源108から蓄電池集合体104へ充電を行ったり、蓄電池集合体104から負荷110へ放電を行ったりする際に各電力変換器28における電力変換及び電圧変換を制御する。また、電力変換器管理部26の制御下にある電力変換器28のいずれかに不具合がある場合や、マスタコントローラ22からの充放電の禁止指令、または待機指令が出力されている場合には、その不具合の電力変換器28の動作を待機状態にさせて、電力変換器28の不具合を示す情報を電力変換器管理データS4としてマスタコントローラ22に送信する。
例えば、図2に示すように8個の電力変換器28が設けられており、集合体充放電制御指令S5が「第1の電力変換器28は40kWで放電、第2の電力変換器28は40kWで放電・・・第8の電力変換器28は40kWで放電」という内容であれば、電力変換器管理部26は、各電力変換器28から負荷110へそれぞれ40kWで電力が供給されるように各電力変換器28における電圧変換及び電力変換を制御する。また、集合体充放電制御指令S5が「第1の電力変換器28は40kWで充電、第2の電力変換器28は40kWで充電・・・第8の電力変換器28は40kWで充電」という内容であれば、電力変換器管理部26は、各電力変換器28を介して太陽電池システム106や系統電源108からそれぞれ40kWで充電が行われるように各電力変換器28における電圧変換及び電力変換を制御する。
以上のように、システムコントローラ20では負荷110の全体の必要電力要求量に応じて、蓄電池集合体104の全体の充放電条件を決定して全体充放電制御指令S1とする。そして、マスタコントローラ22では全体充放電制御指令S1での充放電制御指令を満たすように、不具合が生じている電力変換器28および蓄電池ユニット40を考慮した具体的な各電力変換器28の制御のための集合体充放電制御指令S5を生成し、マスタコントローラ22より下位の電力変換器管理部26によって各電力変換器28を制御する。このとき、電力変換器管理部26は、電力変換器28に不具合が生じた場合は、上位のシステムコントローラ20およびマスタコントローラ22による制御によらず、電力変換器28およびそれに接続される蓄電池ユニット40を切り離す処理を行う。また、サブコントローラ24は、蓄電池ユニット40に不具合が生じた場合は、上位のシステムコントローラ20およびマスタコントローラ22による制御によらず、各蓄電池ユニット40に含まれる蓄電池制御単位42の接続・切離しの制御を行う。このように、階層的な制御を行うことによって、電力変換器28や蓄電池ユニット40に不具合が生じても、システムコントローラ20から見て、蓄電池集合体104をあたかも1つの電池のように扱うことができる。また、より上位の制御系の処理の負担を軽減し、システム構成の変更に柔軟に対応することを可能とする。
<異常放電時の処理>
本実施の形態における電源システム100では、蓄電池ユニット40毎にスイッチ回路30に過電流保護回路200が設けられている。
本実施の形態における電源システム100では、蓄電池ユニット40毎にスイッチ回路30に過電流保護回路200が設けられている。
過電流保護回路200は、図5に示すように、放電スイッチQ1、スイッチQ2、Q3、フォトボルU1、フォトカプラU2、コンパレータCMP1、タイマー素子TM1、抵抗Rxを含んで構成される。放電スイッチQ1はFET、スイッチQ2、Q3はバイポーラトランジスタとすることができる。なお、抵抗Rxは、過電流保護回路200と一体に形成された基板抵抗とすることができる。
過電流保護回路200は、図4に示すように、蓄電池制御単位42から負荷110までの放電ラインL1上に設けられ、放電ラインL1に過電流が流れると蓄電池制御単位42と負荷110とを切り離す機能を有する。
蓄電池ユニット40から負荷110への放電条件が整うと、サブコントローラ24は制御端子T1にハイレベルの放電制御信号を印加する。これにより、フォトボルU1のフォトダイオードD1に電圧が印加され、フォトダイオードD1が発光する。フォトダイオードD1は光電変換素子P1とペアになっており、フォトダイオードD1の発光により光電変換素子P1の端子T2の電圧が上昇する。これによって、放電スイッチQ1がオン状態となり、放電スイッチQ1及び抵抗Rxを介して蓄電池制御単位42が負荷110に接続される。
過電流保護回路200は、放電ラインL1に流れる電流が所定の第1放電基準電流値以上となった場合、及び第1放電基準電流値よりも小さい第2放電基準電流値以上となった場合の2段階の過電流保護を行う機能を有している。第1放電基準電流値は、例えば、900アンペア(A)であり、第2放電基準電流値は、例えば、30アンペア(A)である。
コンパレータCMP1は、端子T3の電圧が基準電圧Vref1以上となった場合にタイマー素子TM1のトリガ端子T4にオン信号(ローレベル信号)を与え、タイマー素子TM1を起動させる。ここで、基準電圧Vref1は、電源電圧Vccを抵抗Ra,Rbで分圧した電圧である。端子T3には、放電ラインL1を介して負荷110に流れる電流に応じた電圧が入力される。具体的には、放電ラインL1に抵抗を設け、放電ラインL1を介して負荷110に流れる電流に応じてその抵抗に発生する電圧を端子T3に入力すればよい。このとき、放電ラインL1を介して負荷110に流れる電流が第2放電基準電流値(30アンペア(A))となったときに基準電圧Vref1に等しくなるように抵抗値を設定することが好適である。
タイマー素子TM1は、トリガ端子T4にオン信号が与えられると一定時間起動され、起動している時間だけスイッチQ2をオン状態にする。スイッチQ2がオン状態になると、フォトダイオードD1のアノード側がスイッチQ2を介して接地されるのでフォトボルU1がオフになり、さらに放電スイッチQ1がオフ状態となる。これによって、タイマー素子TM1が起動されている時間は蓄電池制御単位42が負荷110から切り離される。
また、さらに大きな過大電流が流れた場合には抵抗Rxの端子電圧が上昇し、放電ラインL1に流れる電流が第1放電基準電流値以上となるとスイッチQ3がオン状態となる。スイッチQ3がオン状態となると、フォトダイオードD2及びスイッチQ3を介して端子T2の電圧が低下して放電スイッチQ1がオフ状態となる。これにより、蓄電池制御単位42が負荷110から切り離される。
さらに、フォトカプラU2のフォトダイオードD2が発光する。フォトダイオードD2はフォトトランジスタP2とペアになっており、フォトダイオードD2の発光によりフォトトランジスタP2に電流が流れ、タイマー素子TM1のトリガ端子T4にオン信号が与えられる。これにより、上記のように、フォトボルU1及び放電スイッチQ1がオフ状態となり、タイマー素子TM1が起動されている時間は蓄電池制御単位42が負荷110から切り離される。
以上のように、本実施の形態では、放電ラインL1に流れる電流が第2放電基準電流値以上第1放電基準電流値未満の範囲に入った場合、緊急性は低いが蓄電池制御単位42からの放電を抑制する必要があるものとしてタイマー素子TM1を用いて放電スイッチQ1を断続的に遮断する。さらに、放電ラインL1に流れる電流が第1放電基準電流値以上となった場合、緊急性が高い過大電流が流れたものとして、タイマー素子TM1等の処理に時間が掛る回路を経ずに放電スイッチQ1を遮断して蓄電池制御単位42からの放電を完全に停止させる。
なお、本実施の形態では、蓄電池ユニット40から負荷110への放電条件が整うと、サブコントローラ24から制御端子T1にハイレベルの放電制御信号を印加するものとしたが、マスタコントローラ22から制御端子T1にハイレベルの放電制御信号を印加するものとしてもよい。
また、本実施の形態では、過電流保護回路200は、蓄電池制御単位42と負荷110との間に設ける構成としたが、蓄電池制御単位42と負荷110とがインバータやコンバータを介して接続される場合、蓄電池制御単位42とインバータやコンバータとの間に設けてもよい。
また、本実施の形態では、過電流保護回路200は各蓄電池ユニット40毎に設けられる構成としたが、共通の負荷110に接続される複数の蓄電池ユニット40に共通に設ける構成としてもよい。この場合、過電流保護回路200は、放電ラインL1において複数の蓄電池制御ユニット40が並列に接続された接続点から負荷110までの間に設けられる。このとき、過電流保護回路200は、マスタコントローラ22によって制御されることが好適である。
<異常充電時の処理>
本実施の形態における電源システム100では、サブコントローラ24によって充電時の過電流保護処理が行われる。
本実施の形態における電源システム100では、サブコントローラ24によって充電時の過電流保護処理が行われる。
サブコントローラ24は、充電ラインL2に設けられた電流センサ62から充電ラインL2を流れる充電電流値を読み取る。サブコントローラ24は、充電ラインL2に流れる電流が所定の第1充電基準電流値以上となった場合、及び第1放電基準電流値よりも小さい第2充電基準電流値以上となった場合の2段階の過電流保護を行う機能を有している。第1充電基準電流値は、例えば、200アンペア(A)であり、第2充電基準電流値は、例えば、30アンペア(A)である。
サブコントローラ24は、読み取った充電電流値が第2充電基準電圧以上となった場合、充電スイッチSW3を所定の周期及びオンデューティで接続及び遮断させる。また、サブコントローラ24は、読み取った充電電流値が第1受電基準電圧以上となった場合、充電スイッチSW3を完全に遮断状態とする。
以上のように、本実施の形態では、充電ラインL2に流れる電流が第2充電基準電流値以上第1放電基準電流値未満の範囲に入った場合、緊急性は低いが蓄電池制御単位42への充電を抑制する必要があるものとして充電スイッチSW3を断続的に遮断する。さらに、充電ラインL2に流れる電流が第1充電基準電流値以上となった場合、緊急性が高い過大電流が流れたものとして、充電スイッチSW3を遮断して蓄電池制御単位42への充電を完全に停止させる。
なお、本実施の形態では、サブコントローラ24によって充電スイッチSW3を制御する構成としたが、図6に示すように、放電ラインL1と同様に充電ラインL2に過電流保護回路202を設ける構成としてもよい。このとき、蓄電池ユニット40の充電条件が整うと、サブコントローラ24は制御端子T1にハイレベルの充電制御信号が印加するものとすればよい。また、端子T3に印加される電圧は、充電ラインL2に流れる電流が第2充電基準電流値(30アンペア(A))となったときに基準電圧Vref1に等しくなるようにすればよい。
また、本実施の形態では、充電スイッチSW3又は過電流保護回路202は各蓄電池ユニット40毎に設けられる構成としたが、太陽電池システム106及び系統電源108に接続される複数の蓄電池ユニット40に共通に設ける構成としてもよい。この場合、充電スイッチSW3又は過電流保護回路202は、充電ラインL2において複数の蓄電池制御ユニット40が並列に接続された接続点から電力源となる太陽電池システム106及び系統電源108までの間に設けられる。このとき、充電スイッチSW3又は過電流保護回路202は、マスタコントローラ22によって制御されることが好適である。
また、図7に示すように、放電ラインL1と充電ラインL2とが別々に設けられている構成においても同様に、放電ラインL1上に過電流保護回路200を設けたり、充電ラインL2上に過電流保護回路202を設けたりしてもよい。
また、選択スイッチSW1やスイッチSW2を過電流保護回路200の構成で置き換える構成としてもよい。すなわち、選択スイッチSW1を過電流保護回路200(202)のスイッチQ1に置き換え、各蓄電制御単位42の充放電電流の大きさに応じてスイッチQ1の開閉を制御するように構成する。また、スイッチSW2を過電流保護回路200(202)のスイッチQ1に置き換え、充電ラインL2を流れる充電電流の大きさに応じてスイッチQ1の開閉を制御するように構成する。このとき、第1充電基準電流値及び第2充電基準電流値は、それぞれの保護に適した値に適宜設定することが好適である。
10 負荷電力管理装置、12 蓄電池電力管理装置、14 総合電力監視装置、20 システムコントローラ、22 マスタコントローラ、24 サブコントローラ、26 電力変換器管理部、28 電力変換器、30 スイッチ回路、40 蓄電池ユニット、42 蓄電池制御単位、44 蓄電池パック、46 蓄電池セル、52 電流センサ、54 電圧センサ、56 温度センサ、60 電圧センサ、62 強制開放回路、100 電源システム、102 電源管理システム、104 蓄電池集合体、106 太陽電池システム、108 系統電源、110 負荷、200 過電流保護回路。
Claims (5)
- 蓄電池と、
前記蓄電池に接続される負荷へ電力を供給する放電ラインに設けられた放電スイッチと、を備え、
前記放電ラインを流れる電流が所定の第1放電基準電流値以上となった場合に前記放電スイッチを開状態とし、
前記放電ラインを流れる電流が前記第1放電基準電流値よりも小さい第2放電基準電流値以上前記第1放電基準電流値未満となった場合に前記放電スイッチを所定期間開状態として前記蓄電池と前記負荷とを切り離し、前記所定期間後に前記放電スイッチを閉状態として前記蓄電池と前記負荷と再度接続し、
前記放電ラインを流れる電流が前記第2放電基準電流値未満となった場合に前記放電スイッチを閉状態とすることを特徴とする電源システム。 - 請求項1に記載の電源システムであって、
前記放電ラインを流れる電流が前記第2放電基準電流値以上前記第1放電基準電流値未満となった場合に起動されるタイマー素子を備え、
前記タイマー素子は、起動された後に前記所定期間だけ前記放電スイッチを開状態とし、前記所定期間後に前記放電スイッチを閉状態とすることを特徴とする電源システム。 - 請求項1に記載の電源システムであって、
前記放電スイッチは、前記放電ラインにおいて前記蓄電池を構成する複数の蓄電池ユニットが並列に接続された接続点から前記負荷までの間に設けられていることを特徴とする電源システム。 - 蓄電池と、
前記蓄電池へ電力源から充電を行うための充電ラインに設けられた充電スイッチと、
を備え、
前記充電ラインを流れる電流が所定の第1充電基電流値以上となった場合に前記充電スイッチを開状態とし、
前記充電ラインを流れる電流が前記第1充電基準電流値よりも小さい第2充電基準電流値以上前記第1充電基準電流値未満となった場合に前記充電スイッチを断続的に開状態及び閉状態とし、
前記充電ラインを流れる電流が前記第2充電基準電流値未満となった場合に前記充電スイッチを閉状態とすることを特徴とする電源システム。 - 請求項4に記載の電源システムであって、
前記充電スイッチは、前記充電ラインにおいて前記蓄電池を構成する複数の蓄電池ユニットが並列に接続された接続点から前記電力源までの間に設けられていることを特徴とする電源システム。
Applications Claiming Priority (4)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2010-233119 | 2010-10-15 | ||
| JP2010-233120 | 2010-10-15 | ||
| JP2010233120 | 2010-10-15 | ||
| JP2010233119 | 2010-10-15 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2012049972A1 true WO2012049972A1 (ja) | 2012-04-19 |
Family
ID=45938203
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/JP2011/072271 Ceased WO2012049972A1 (ja) | 2010-10-15 | 2011-09-28 | 蓄電池を含む電源システム |
Country Status (1)
| Country | Link |
|---|---|
| WO (1) | WO2012049972A1 (ja) |
Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2008013299A1 (en) * | 2006-07-27 | 2008-01-31 | Citizen Holdings Co., Ltd. | Electronic device |
-
2011
- 2011-09-28 WO PCT/JP2011/072271 patent/WO2012049972A1/ja not_active Ceased
Patent Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2008013299A1 (en) * | 2006-07-27 | 2008-01-31 | Citizen Holdings Co., Ltd. | Electronic device |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP5587421B2 (ja) | 電源システム | |
| JPWO2012049963A1 (ja) | 蓄電池を含む電源システム | |
| JP7212650B2 (ja) | 直列電池充電及び形成用のシステム及び方法 | |
| WO2012050004A1 (ja) | 電源システム | |
| US9300016B2 (en) | Battery system and energy storage system | |
| US8217624B2 (en) | Power storage system | |
| US10976369B2 (en) | Load test system | |
| JPWO2012124238A1 (ja) | 電源システム | |
| US20130141828A1 (en) | Power source apparatus formed by combining a plurality of modules | |
| US9300166B2 (en) | Battery management system and driving method thereof | |
| JP2013542706A (ja) | バッテリーバランシングシステム | |
| TW201832442A (zh) | 不斷電系統(ups)之轉換電路裝置 | |
| CN105075054A (zh) | 电力转换装置、控制系统和控制方法 | |
| WO2008151659A2 (en) | System and method for equalizing state of charge in a battery system | |
| JP2012090376A (ja) | 電源システム | |
| CN111384763A (zh) | 一种电能变换与控制装置以及具有该装置的储能系统 | |
| CN205160115U (zh) | 电池管理系统 | |
| CN117578539A (zh) | 一种储能系统 | |
| CN117013631A (zh) | 一种光储系统 | |
| US12463264B2 (en) | Method for operating storage battery system | |
| JP2020018095A (ja) | 電源システム及び電力の系統連系システム | |
| JP2012191820A (ja) | 電源システム | |
| CN118983911A (zh) | 一种超级电容电池模组及其控制方法 | |
| KR20210019841A (ko) | 태양광 발전을 이용한 배터리 충방전 제어장치 | |
| WO2012127983A1 (ja) | 電源システム |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 11832410 Country of ref document: EP Kind code of ref document: A1 |
|
| NENP | Non-entry into the national phase |
Ref country code: DE |
|
| 122 | Ep: pct application non-entry in european phase |
Ref document number: 11832410 Country of ref document: EP Kind code of ref document: A1 |
|
| NENP | Non-entry into the national phase |
Ref country code: JP |