WO2011079676A1 - Construction method for supporting layer of double-block ballastless track - Google Patents

Construction method for supporting layer of double-block ballastless track Download PDF

Info

Publication number
WO2011079676A1
WO2011079676A1 PCT/CN2010/079301 CN2010079301W WO2011079676A1 WO 2011079676 A1 WO2011079676 A1 WO 2011079676A1 CN 2010079301 W CN2010079301 W CN 2010079301W WO 2011079676 A1 WO2011079676 A1 WO 2011079676A1
Authority
WO
WIPO (PCT)
Prior art keywords
support layer
mixture
paving
meters
construction
Prior art date
Application number
PCT/CN2010/079301
Other languages
French (fr)
Chinese (zh)
Inventor
赵�智
谢录杲
秦瑞谦
王智勇
白昆华
龚斯昆
赵代强
梅红
万轶
杜建武
宋德佩
Original Assignee
中铁八局集团有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中铁八局集团有限公司 filed Critical 中铁八局集团有限公司
Publication of WO2011079676A1 publication Critical patent/WO2011079676A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B1/00Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway

Definitions

  • the present invention relates to the construction process of a high-speed railway passenger dedicated line, and particularly relates to a double-block ballastless track formed by using a slipform paver to spread a hydraulic mixture in a railway.
  • Support layer construction process BACKGROUND OF THE INVENTION
  • a ballastless track support layer is an intermediate transition layer between the bed of a ballastless track and the surface of a subgrade bed, and is a key process in the construction of a double block ballastless track bed.
  • a concrete support layer structure was set up between the roadbed bed surface and the track bed plate with reference to the road structure design.
  • Slip mode paving technology is a cement concrete pavement forming technology that is widely promoted and used in the construction of highways and airports in China. It is not widely used in railways. It is mainly used in track-slip mode cement concrete pavers.
  • the paving materials mainly include ordinary concrete. Due to the existence of concrete: 1 the concrete strength is higher; 2 the water consumption is larger, the concrete slump is larger; 3 the cementing material is more.
  • the object of the invention is to provide a double-block ballastless track supporting layer construction technology, which has the characteristics of high construction speed and large operation efficiency of the paver, can improve the construction quality of the support layer and reduce The probability of cracking the bed plate and increasing the durability of the structure.
  • a double-block ballastless track supporting layer construction process which comprises the following steps:
  • a double-block ballastless track supporting layer construction process characterized in that it comprises the following steps: First step, reference line setting
  • the center line of the concrete support layer is set by the CPIII control network, and the guide lines on both sides are set, and the distance from the guide line to the line center line is 2. 9 meters, and the height is designed to cover the road surface 50. Cm, the longitudinal distance of the guide line tie rod is 10 meters, and the curved section is 5 meters; the paving uses the nail pile or guide line method to calibrate the pitch of the four corners of the bottom of the paver and the direction of the side mold, check 1 ⁇ 2 times, correct After the error, the paving operation is carried out;
  • the determined raw material weight ratio is: cement, mineral admixture 1%, coarse and fine aggregate ratio 2%, mixing water ratio 1%;
  • the support layer mixture is thoroughly stirred, so that the various materials are uniformly mixed and the colors are the same. Transport to the construction site for use;
  • the third step mixed material transportation
  • the self-unloading automobile car Before the transportation, the self-unloading automobile car is cleaned and covered with canvas during the transportation process of the support layer mixture by the self-unloading automobile. After the mixed material is transported to the construction site, the discharge distance is not limited to the evaporation of water;
  • the mixture is transported to the construction site for sampling, and the water content is measured;
  • the support layer mixture is finished by the excavator: the fabric is evenly distributed within the width of the paving, and the highest level is not higher than the normal height of the top surface of the loose control panel of the paver, while in the auger Below the highest point of the blade, and not to be short of material; after the longitudinal fabric exceeds 5 meters, the paver starts to spread.
  • the outer fabric height is slightly higher, and it is determined within the paving distance of 5 to 10 meters.
  • the main contents of the inspection include: Observing whether the support layer is isolated, if it is repaired immediately; and checking the surface elevation of the support layer, pulling the string between the two reference lines, Use a steel ruler to measure the distance from the string to the surface of the support layer. If the elevation exceeds the allowable error, handle it immediately;
  • the subgrade support layer is dry hard concrete, and the surface of the support layer has a certain roughness in the range of the track bed, so that it can be in good contact with the interface of the track bed.
  • the exposed part of the edge of 35 cm on both sides should be manually covered and smeared to avoid excessive holes. Excessive water absorption causes freezing and thawing damage;
  • the seventh step the support layer slitting, maintenance: Within 12 hours after the support layer is paved, the transverse joint is cut at a pitch of 5 meters in the longitudinal direction. The seam depth is 1/3 of the thickness of the concrete of the support layer. After the slitting work is completed, the surface of the support layer is sprinkled with water and covered with plastic film for 5 days. ;
  • the compactness of the support layer mixture shall be determined by sand blasting every 500 meters.
  • the core shall be sampled every 250 meters.
  • the diameter of the core sample is 150 mm.
  • the compressive strength test shall be carried out to determine the 28-day support layer mixture. The strength of the support layer is evaluated after the test data is completed.
  • Figure 1 is a flow chart of the construction process of the double-block ballastless track support layer.
  • Figure 2 is a gradation plot of a mixture of mineral materials. detailed description
  • the compounding test should be carried out in advance according to the requirements of the “temporary technical conditions for the ballastless track support layer of the passenger dedicated railway line” and the actual indicators such as cement and aggregate at the construction site. .
  • the two aggregates were mixed according to the test ratio, and cement and fly ash were added, and the compaction test was carried out by a compactor to obtain the maximum dry density and the optimum moisture content.
  • a double-block ballastless track supporting layer construction process which comprises the following steps:
  • the center line of the concrete support layer is set by the CPIII control network, and the guide lines on both sides are set, and the distance from the guide line to the line center line is 2. 9 meters, and the height is designed to cover the road surface 50. Cm, the longitudinal distance of the guide line tie rod is 10 meters, and the curved section is 5 meters; the paving uses the nail pile or guide line method to calibrate the pitch of the four corners of the bottom of the paver and the direction of the side mold, check 1 ⁇ 2 times, correct After the error is correct, the paving operation can be carried out;
  • the determined raw material weight ratio is: cement, mineral admixture 1%, coarse and fine aggregate ratio 2%, mixing water ratio 1%; feeding sequence: after the raw material is metered, first put fine aggregate into the mixer, Cement and fly ash, add water after mixing, then add coarse aggregate to the mixer, stir well until it is even;
  • the support layer mixture is fully stirred, so that the various materials are evenly mixed and the colors are consistent, and the mixture is transported to the construction site for use;
  • the third step mixed material transportation
  • the self-unloading automobile car Before the transportation, the self-unloading automobile car is cleaned and covered with canvas during the transportation process of the support layer mixture by the self-unloading automobile. After the mixed material is transported to the construction site, the discharge distance is not limited to the evaporation of water;
  • the mixture is transported to the construction site for sampling, and the water content is measured;
  • the support layer mixture is finished by the excavator: the fabric is evenly distributed within the width of the paving, and the highest level is not higher than the normal height of the top surface of the loose control panel of the paver, while in the auger Below the highest point of the blade, and not to be short of material; after the longitudinal fabric exceeds 5 meters, the paver starts to spread, and when the fabric is in the curved section, the outer fabric height is slightly higher, so that the paving can be paved during the paving process.
  • the machine template forms an extrusion on the mixture to ensure the quality effect of the support layer; determine the optimal vibration frequency, the optimum paving speed and the optimal insertion depth of the tamping rod within a paving distance of 5 to 10 meters;
  • the fifth step the appearance quality check:
  • the main contents of the inspection include: Observing whether the support layer is isolated, if it is repaired immediately; Checking the surface elevation of the support layer and pulling the string between the two baselines , using a steel ruler to measure the distance from the string to the surface of the support layer, if the elevation exceeds the error The difference is allowed, and it is processed immediately;
  • the subgrade support layer is dry hard concrete, and the surface of the support layer has a certain roughness in the range of the track bed, so that it can be in good contact with the interface of the track bed.
  • the exposed part of the edge of 35 cm on both sides should be manually covered and smeared to avoid excessive holes. Excessive water absorption causes freezing and thawing damage;
  • the transverse joint is cut at a pitch of 5 meters in the longitudinal direction.
  • the seam depth is 1/3 of the thickness of the concrete of the support layer.
  • the compactness of the support layer mixture shall be determined by sand blasting every 500 meters.
  • the core shall be sampled every 250 meters.
  • the diameter of the core sample is 150 mm.
  • the compressive strength test shall be carried out to determine the 28-day support layer mixture. The strength of the support layer is evaluated after the test data is completed.
  • the invention has the characteristics of high construction speed and large operation efficiency of the paver, can reach the construction progress of 300 m/day, and can greatly reduce the construction period; can improve the construction quality of the support layer, reduce the cracking probability of the road bed plate and increase the durability of the structure. .

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)
  • Road Repair (AREA)

Abstract

A construction method for a supporting layer of a double-block ballastless track comprises the following steps first, measuring and laying off datum lines, second, preparing mixture, third, producing and transporting mixture, forth, paving the mixture to form the supporting layer, fifth, checking appearance quality, sixth, manually deburring the supporting layer, seventh, cutting joints and curing the supporting layer, eighth, testing and evaluating the supporting layer.

Description

双块式无砟轨道支承层施工工艺 技术领域 本发明涉及高速铁路客运专线修建工艺领域,具体涉及铁路中采用滑模摊 铺机将水硬性混合料摊铺成型的一种双块式无砟轨道支承层施工工艺。 背景技术 无砟轨道支承层是位于无砟轨道道床板和路基基床表层之间的中间过渡 层, 是双块式无砟轨道道床施工中的关键工序。 在国外, 德国开始进行无砟轨 道试验研究时, 参照公路结构设计, 在路基基床表层和道床板之间设置了混凝 土支承层结构。 随着无砟轨道应用范围的拓展, 其工艺方法也由当初的碾压成 型发展到现在的滑模摊铺。 滑模式摊铺技术是目前国内高速公路和机场建设中大力推广和使用的水 泥混凝土路面成型技术, 在铁路中的应用还不是非常广泛, 其主要采用履带滑 模式水泥混泥土摊铺机完成。摊铺的材料主要包括普通混凝土, 由于混凝土存 在的一些情况: ①混凝土强度较高; ②用水量较大, 混凝土塌落度较大; ③胶 凝材料较多。 这些情况的出现一方面导致支承层收缩量加大, 一方面使得支承 层刚度过大, 减弱了其释放应力的能力, 从而加速了道床板开裂的趋势。 为了提高支承层的施工质量,降低道床板开裂几率,增加结构的耐久性能, 一种使用支承层材料为水硬性混合料、采用滑模摊铺机成型技术的施工工艺被 认为是能够解决上述问题的较佳方法。 发明内容  TECHNICAL FIELD The present invention relates to the construction process of a high-speed railway passenger dedicated line, and particularly relates to a double-block ballastless track formed by using a slipform paver to spread a hydraulic mixture in a railway. Support layer construction process. BACKGROUND OF THE INVENTION A ballastless track support layer is an intermediate transition layer between the bed of a ballastless track and the surface of a subgrade bed, and is a key process in the construction of a double block ballastless track bed. In foreign countries, when Germany began the ballastless track test study, a concrete support layer structure was set up between the roadbed bed surface and the track bed plate with reference to the road structure design. With the expansion of the application range of ballastless track, the process has also evolved from the original rolling type to the current slipform paving. Slip mode paving technology is a cement concrete pavement forming technology that is widely promoted and used in the construction of highways and airports in China. It is not widely used in railways. It is mainly used in track-slip mode cement concrete pavers. The paving materials mainly include ordinary concrete. Due to the existence of concrete: 1 the concrete strength is higher; 2 the water consumption is larger, the concrete slump is larger; 3 the cementing material is more. On the one hand, the occurrence of these conditions leads to an increase in the shrinkage of the support layer, on the one hand, the rigidity of the support layer is too large, and the ability to release stress is weakened, thereby accelerating the tendency of the bed plate to crack. In order to improve the construction quality of the support layer, reduce the probability of cracking of the ballast plate, and increase the durability of the structure, a construction process using a support layer material as a hydraulic mixture and a slipform paver molding technique is considered to solve the above problems. The preferred method. Summary of the invention
本发明的目的是提供一种双块式无砟轨道支承层施工工艺,这种施工工艺 具有施工速度快和摊铺机作业功效大的特点, 可提高支承层的施工质量、 降低 道床板开裂几率和增加结构的耐久性能。 The object of the invention is to provide a double-block ballastless track supporting layer construction technology, which has the characteristics of high construction speed and large operation efficiency of the paver, can improve the construction quality of the support layer and reduce The probability of cracking the bed plate and increasing the durability of the structure.
一种双块式无砟轨道支承层施工工艺, 它包括如下步骤:  A double-block ballastless track supporting layer construction process, which comprises the following steps:
1. 一种双块式无砟轨道支承层施工工艺, 其特征在于, 它包括如下步骤: 第一步, 基准线测设  A double-block ballastless track supporting layer construction process, characterized in that it comprises the following steps: First step, reference line setting
在施工前,完成支承层的测量放线工作,通过 CPIII控制网测设混凝土支承 层中线, 进而设置两侧引导线, 引导线到线路中线的距离为 2. 9米, 高度距设 计路基面 50厘米, 引导线拉杆纵向间距为 10米, 曲线地段为 5米; 摊铺采用 钉桩或引导线法校准摊铺机挤压底板四角点高程和侧模前进方向, 校核 1〜2 遍, 正确无误后, 进行摊铺作业;  Before the construction, the measurement and release work of the support layer is completed, and the center line of the concrete support layer is set by the CPIII control network, and the guide lines on both sides are set, and the distance from the guide line to the line center line is 2. 9 meters, and the height is designed to cover the road surface 50. Cm, the longitudinal distance of the guide line tie rod is 10 meters, and the curved section is 5 meters; the paving uses the nail pile or guide line method to calibrate the pitch of the four corners of the bottom of the paver and the direction of the side mold, check 1~2 times, correct After the error, the paving operation is carried out;
第二步, 混合料配制  The second step, the mixture preparation
A.根据试验室推荐的配合比, 在现场进行工艺试验, 综合分析支承层的密 实度及抗压强度指标、 拌和料的和易性、 工作性能、 外观质量因素, 修正支承 层配合比;  A. According to the recommended mixing ratio of the laboratory, carry out the process test on site, comprehensively analyze the compactness and compressive strength index of the support layer, the workability of the mixed material, the work performance, the appearance quality factor, and modify the mix ratio of the support layer;
B.在现场对材料取样, 进行骨料筛分试验, 检査骨料级配情况; 在拌和站 对砂、 石料含水率进行测定, 根据含水率修定理论配合比, 确定施工配合比, 拌和料拌制完成后, 取样测定含水率;  B. Sampling the material at the site, performing the aggregate screening test to check the aggregate gradation; measuring the moisture content of the sand and stone at the mixing station, adjusting the theoretical mix ratio according to the water content, determining the construction mix ratio, mixing After the mixing of the materials is completed, the water content is measured by sampling;
C.确定后的原材料重量比为: 水泥、 矿物掺合料 1%, 粗、 细骨料比例 2%, 拌合水比例 1%;  C. The determined raw material weight ratio is: cement, mineral admixture 1%, coarse and fine aggregate ratio 2%, mixing water ratio 1%;
D.支承层混合料搅拌流程如下:  D. The mixing process of the support layer mixture is as follows:
I»骨着 I» bones
水 粗骨 · 拌 籍  Water, coarse bone, mixed
' 6ΰ教 '6 ΰ ΰ
Figure imgf000004_0001
Figure imgf000004_0001
煤 處  Coal
E.支承层混合料充分搅拌,使各种材料混合均匀、 颜色一致后, 将混合料 运输到施工现场备用; E. The support layer mixture is thoroughly stirred, so that the various materials are uniformly mixed and the colors are the same. Transport to the construction site for use;
第三步, 混合料运输  The third step, mixed material transportation
运输前将自卸式汽车车箱清洗干净,在采用自卸式汽车进行支承层混合料 的运输过程中用帆布覆盖, 混合料运输到施工现场后, 卸料距离以不使水分蒸 发为限;  Before the transportation, the self-unloading automobile car is cleaned and covered with canvas during the transportation process of the support layer mixture by the self-unloading automobile. After the mixed material is transported to the construction site, the discharge distance is not limited to the evaporation of water;
第四步, 支承层混合料摊铺  The fourth step, the support layer mix paving
首先, 摊铺前对基床表层表面进行洒水润湿;  First, sprinkle the surface of the surface of the bed before weaving;
然后, 混合料运输到施工现场后进行取样, 测定含水率;  Then, the mixture is transported to the construction site for sampling, and the water content is measured;
最后, 摊铺时, 支承层混合料通过挖掘机来完成布料: 在摊铺宽度范围内 布料均匀, 最高料位不高于摊铺机前松方控制板顶面的正常高度, 而在螺旋布 料器叶片最高点以下, 且不得缺料; 纵向布料超过 5米后, 启动摊铺机开始摊 铺, 布料时, 在曲线地段, 其外侧布料高度稍高, 在 5〜10米的摊铺距离内确 定最佳振捣频率、 最佳摊铺走行速度和捣固棒最佳插入深度;  Finally, during paving, the support layer mixture is finished by the excavator: the fabric is evenly distributed within the width of the paving, and the highest level is not higher than the normal height of the top surface of the loose control panel of the paver, while in the auger Below the highest point of the blade, and not to be short of material; after the longitudinal fabric exceeds 5 meters, the paver starts to spread. When the fabric is in the curved section, the outer fabric height is slightly higher, and it is determined within the paving distance of 5 to 10 meters. Optimal vibrating frequency, optimum paving speed and optimum insertion depth of the tamping rod;
第五步, 外观质量检查  Step 5, appearance quality check
摊铺完成后, 对支承层的质量进行检查, 检查的主要内容包括: 观察支承 层是否发生离析, 如果有马上进行修补处理; 同时检查支承层表面标高位置, 在两基准线间拉弦线, 用钢尺量测弦线到支承层表面的距离, 如果标高超过误 差允许要求, 立刻处理;  After the paving is completed, the quality of the support layer is checked. The main contents of the inspection include: Observing whether the support layer is isolated, if it is repaired immediately; and checking the surface elevation of the support layer, pulling the string between the two reference lines, Use a steel ruler to measure the distance from the string to the surface of the support layer. If the elevation exceeds the allowable error, handle it immediately;
第六步, 人工修边  Step 6, manual trimming
路基支承层为干硬性混凝土, 道床板范围内支承层表面有一定的粗糙度, 以便能和道床板界面良好接触, 两侧边缘 35厘米外露出部分要人工进行收面 抹光, 避免孔洞过多, 吸水过多造成冻融破坏;  The subgrade support layer is dry hard concrete, and the surface of the support layer has a certain roughness in the range of the track bed, so that it can be in good contact with the interface of the track bed. The exposed part of the edge of 35 cm on both sides should be manually covered and smeared to avoid excessive holes. Excessive water absorption causes freezing and thawing damage;
第七步, 支承层切缝、 养护: 支承层摊铺完成 12小时内, 按纵向 5米间距切割出横向缝, 缝深为支承 层混凝土厚度的 1/3, 在切缝工作完成后, 在支承层表面洒水并覆盖塑料薄膜 养生 5天; The seventh step, the support layer slitting, maintenance: Within 12 hours after the support layer is paved, the transverse joint is cut at a pitch of 5 meters in the longitudinal direction. The seam depth is 1/3 of the thickness of the concrete of the support layer. After the slitting work is completed, the surface of the support layer is sprinkled with water and covered with plastic film for 5 days. ;
第八步, 检测、 评估:  The eighth step, detection, evaluation:
施工完成后, 每隔 500米用灌砂法测定支承层混合料的密实度, 每隔 250 米钻芯取样, 芯样直径为 150毫米, 进行抗压强度测试, 确定 28天的支承层 混合料的强度, 检测资料完成后, 对支承层施工质量进行评估。  After the completion of the construction, the compactness of the support layer mixture shall be determined by sand blasting every 500 meters. The core shall be sampled every 250 meters. The diameter of the core sample is 150 mm. The compressive strength test shall be carried out to determine the 28-day support layer mixture. The strength of the support layer is evaluated after the test data is completed.
由于采用了上述技术方案, 本发明的有益效果是:  Due to the adoption of the above technical solutions, the beneficial effects of the present invention are:
具有施工速度快和摊铺机作业功效大的特点,可达到 300m/天的施工进度, 能大大缩减施工工期; 可提高支承层的施工质量、 降低道床板开裂几率和增加 结构的耐久性能。  It has the characteristics of fast construction speed and high efficiency of paver operation, which can reach the construction progress of 300m/day, which can greatly reduce the construction period; it can improve the construction quality of the support layer, reduce the cracking probability of the track bed and increase the durability of the structure.
附图说明 DRAWINGS
图 1是双块式无砟轨道支承层施工工艺流程流程图。  Figure 1 is a flow chart of the construction process of the double-block ballastless track support layer.
图 2是矿物材料混合物的级配曲线图。 具体实施方式  Figure 2 is a gradation plot of a mixture of mineral materials. detailed description
下面结合附图对本发明作详细说明  The present invention will be described in detail below with reference to the accompanying drawings.
1.支承层配合比试配  1. Support layer matching ratio test
1. 1试配原则  1. 1 trial matching principle
支承层混凝土原材料进场检验合格后, 在正式施工前 2个月应按《客运专 线铁路无砟轨道支承层暂行技术条件》要求并结合施工现场的水泥、 集料等实 际指标提前进行配合比试验。  After the entrance test of the concrete of the supporting layer is qualified, the compounding test should be carried out in advance according to the requirements of the “temporary technical conditions for the ballastless track support layer of the passenger dedicated railway line” and the actual indicators such as cement and aggregate at the construction site. .
1. 2室内试验 1. 2 indoor test
1. 2. 1筛分 根据《普通混凝土用砂、石质量及检验方法标准》 JGJ52-2006 , 首先将粗、 细骨料分别进行筛分试验, 然后将这两种骨料按一定比例进行试配、 筛分, 直 至筛分结果满足 《暂行技术条件》 中混合物的粒径级配 (见表 1. 2. 1 ) 和级配 曲线限值 (见图 2 ), 并绘出曲线图。 1. 2. 1 screening According to JGJ52-2006, the standard for sand and stone quality and test methods for ordinary concrete, the coarse and fine aggregates are first sieved separately, and then the two aggregates are tested and sieved according to a certain ratio until the sieve The scores meet the particle size grading of the mixture in the Interim Technical Conditions (see Table 1. 2. 1) and the grading curve limits (see Figure 2), and plot the graph.
表 1. 2. 1混合物的粒径级配  Table 1. 2. 1 particle size grading of the mixture
Figure imgf000007_0001
Figure imgf000007_0001
1. 2. 2击实  1. 2. 2 compaction
将两种骨料按试验比例混合, 并外加水泥和粉煤灰, 用击实仪进行普氏击 实试验, 得出最大干密度和最优含水率。  The two aggregates were mixed according to the test ratio, and cement and fly ash were added, and the compaction test was carried out by a compactor to obtain the maximum dry density and the optimum moisture content.
1. 2. 3拌合成型  1. 2. 3 mixed type
根据得出的最大干密度和最优含水量计算出理论配合比 (见表 1. 2. 3 ) 以 及各种料的试拌用量放入搅拌机进行拌合, 然后按规定对试件进行密实, 1天 后拆模成型并放入标准养护室进行养护。  Calculate the theoretical mix ratio according to the obtained maximum dry density and optimum water content (see Table 1.2.3) and mix the test materials of various materials into the mixer for mixing, and then compact the test pieces according to the regulations. After 1 day, it was demolded and placed in a standard curing room for curing.
表 1. 2. 3支承层理论配合比 (kg/m3 )
Figure imgf000007_0002
Table 1. 2. Theoretical support ratio of support layer (kg/m3)
Figure imgf000007_0002
1. 2. 4性能测试  1. 2. 4 performance test
将养护 3d、7d、28d的试件进行力学(抗压)性能试验,试验结果见表 1. 2. 4。  The specimens for curing 3d, 7d, and 28d were subjected to mechanical (compression) performance tests. The test results are shown in Table 1. 2. 4.
表 1. 2. 4 支承层力学性能试验结果 要求试验室达 抗压强度 (MPa) Table 1. 2. 4 Test results of mechanical properties of support layer Requires laboratory to achieve compressive strength (MPa)
到强度 (Mpa) 3d 7d 28d  To intensity (Mpa) 3d 7d 28d
^ 15 130 9.7 13.3 19.2  ^ 15 130 9.7 13.3 19.2
150 10.1 14.6 20.1  150 10.1 14.6 20.1
1. 3工艺试验及配合比修正  1. 3 process test and mix correction
1. 3. 1验证试验室配合比 根据试验室推荐的配合比, 在现场进行工艺试验, 实际铺筑试验段, 进行 干密度、 抗压强度等指标检测; 并对照 《暂行技术条件》 的规定值进行验证。 其检测结果见表 1. 3. 1-1、 表 1. 3. 1-2  1.3.1 Verifying the mixing ratio of the laboratory According to the recommended ratio of the laboratory, carry out the process test on site, actually pave the test section, and test the dry density and compressive strength; and compare with the provisions of the Provisional Technical Conditions. The value is verified. The test results are shown in Table 1. 3. 1-1, Table 1. 3. 1-2
表 1. 3. 1-1 灌沙法密实度检测结果  Table 1. 3. 1-1 Sanding method compactness test results
表 1. 3. 1-2 强度检测结果 Table 1. 3. 1-2 Strength test results
Figure imgf000008_0002
Figure imgf000008_0002
1. 3. 2修正支承层配合比 总结工艺试验的结果, 综合分析支承层的密实度及强度指标、 拌和料的和 易性、 工作性能、 外观质量等因素, 修正支承层配合比, 根据分析, 确定修正 后的支承层配合比。 1. 4施工配合比确定 1. 3. 2 Correct the support layer mix ratio to summarize the results of the process test, comprehensively analyze the compactness and strength index of the support layer, the workability of the mix, work performance, appearance quality and other factors, modify the mix ratio of the support layer, according to the analysis , determine the corrected support layer mix ratio. 1. 4 construction mix ratio determination
每次支承层施工前, 必须对砂、 石等原材料进行含水率测试。 根据含水率 的测试结果, 修正理论配合比, 确定最终的施工配合比。  Before each support layer is constructed, the moisture content of sand, stone and other raw materials must be tested. According to the test results of water content, the theoretical mix ratio is corrected to determine the final construction mix ratio.
2.施工工艺  2. Construction process
一种双块式无砟轨道支承层施工工艺, 它包括如下步骤:  A double-block ballastless track supporting layer construction process, which comprises the following steps:
第一步, 基准线测设  First step, baseline measurement
在施工前,完成支承层的测量放线工作:通过 CPIII控制网测设混凝土支承 层中线, 进而设置两侧引导线, 引导线到线路中线的距离为 2. 9米, 高度距设 计路基面 50厘米, 引导线拉杆纵向间距为 10米, 曲线地段为 5米; 摊铺采用 钉桩或引导线法校准摊铺机挤压底板四角点高程和侧模前进方向, 校核 1〜2 遍, 正确无误后, 可进行摊铺作业;  Before the construction, the measurement and release work of the support layer is completed: the center line of the concrete support layer is set by the CPIII control network, and the guide lines on both sides are set, and the distance from the guide line to the line center line is 2. 9 meters, and the height is designed to cover the road surface 50. Cm, the longitudinal distance of the guide line tie rod is 10 meters, and the curved section is 5 meters; the paving uses the nail pile or guide line method to calibrate the pitch of the four corners of the bottom of the paver and the direction of the side mold, check 1~2 times, correct After the error is correct, the paving operation can be carried out;
第二步, 混合料配制  The second step, the mixture preparation
A.根据试验室推荐的配合比, 在现场进行工艺试验, 综合分析支承层的密 实度及抗压强度指标、 拌和料的和易性、 工作性能、 外观质量因素, 修正支承 层配合比;  A. According to the recommended mixing ratio of the laboratory, carry out the process test on site, comprehensively analyze the compactness and compressive strength index of the support layer, the workability of the mixed material, the work performance, the appearance quality factor, and modify the mix ratio of the support layer;
B.在现场对材料取样, 进行骨料筛分试验, 检査骨料级配情况; 在拌和站 对砂、 石料含水率进行测定, 根据含水率修定理论配合比, 确定施工配合比, 拌和料拌制完成后, 取样测定含水率;  B. Sampling the material at the site, performing the aggregate screening test to check the aggregate gradation; measuring the moisture content of the sand and stone at the mixing station, adjusting the theoretical mix ratio according to the water content, determining the construction mix ratio, mixing After the mixing of the materials is completed, the water content is measured by sampling;
C.确定后的原材料重量比为: 水泥、 矿物掺合料 1%, 粗、 细骨料比例 2%, 拌合水比例 1%; 投料顺序: 原材料计量后, 先向搅拌机投入细骨料、 水泥和粉 煤灰, 搅拌均匀后加水, 再向搅拌机投入粗骨料, 充分搅拌至均匀为止;  C. The determined raw material weight ratio is: cement, mineral admixture 1%, coarse and fine aggregate ratio 2%, mixing water ratio 1%; feeding sequence: after the raw material is metered, first put fine aggregate into the mixer, Cement and fly ash, add water after mixing, then add coarse aggregate to the mixer, stir well until it is even;
D.支承层混合料搅拌流程如下: 细 ΐ錄 1 #合水 耜骨弊: » #抖D. The mixing process of the support layer mixture is as follows: 细ΐ录1 #合水耜骨肢: » #抖
Figure imgf000010_0001
Figure imgf000010_0001
'煤:褒處  'Coal: 褒
Ε.支承层混合料充分搅拌,使各种材料混合均匀、 颜色一致后, 将混合料 运输到施工现场备用;  Ε. The support layer mixture is fully stirred, so that the various materials are evenly mixed and the colors are consistent, and the mixture is transported to the construction site for use;
第三步, 混合料运输  The third step, mixed material transportation
运输前将自卸式汽车车箱清洗干净,在采用自卸式汽车进行支承层混合料 的运输过程中用帆布覆盖, 混合料运输到施工现场后, 卸料距离以不使水分蒸 发为限;  Before the transportation, the self-unloading automobile car is cleaned and covered with canvas during the transportation process of the support layer mixture by the self-unloading automobile. After the mixed material is transported to the construction site, the discharge distance is not limited to the evaporation of water;
第四步, 支承层混合料摊铺  The fourth step, the support layer mix paving
首先, 摊铺前对基床表层表面进行洒水润湿;  First, sprinkle the surface of the surface of the bed before weaving;
然后, 混合料运输到施工现场后进行取样, 测定含水率;  Then, the mixture is transported to the construction site for sampling, and the water content is measured;
最后, 摊铺时, 支承层混合料通过挖掘机来完成布料: 在摊铺宽度范围内 布料均匀, 最高料位不高于摊铺机前松方控制板顶面的正常高度, 而在螺旋布 料器叶片最高点以下, 且不得缺料; 纵向布料超过 5米后, 启动摊铺机开始摊 铺, 布料时, 在曲线地段, 其外侧布料高度稍高, 以便在摊铺过程中, 能让摊 铺机模板对混合料形成挤压, 保证支承层的质量效果; 在 5〜10米的摊铺距离 内确定最佳振捣频率、 最佳摊铺走行速度和捣固棒最佳插入深度;  Finally, during paving, the support layer mixture is finished by the excavator: the fabric is evenly distributed within the width of the paving, and the highest level is not higher than the normal height of the top surface of the loose control panel of the paver, while in the auger Below the highest point of the blade, and not to be short of material; after the longitudinal fabric exceeds 5 meters, the paver starts to spread, and when the fabric is in the curved section, the outer fabric height is slightly higher, so that the paving can be paved during the paving process. The machine template forms an extrusion on the mixture to ensure the quality effect of the support layer; determine the optimal vibration frequency, the optimum paving speed and the optimal insertion depth of the tamping rod within a paving distance of 5 to 10 meters;
第五步, 外观质量检査:  The fifth step, the appearance quality check:
摊铺完成后, 对支承层的质量进行检查, 检査的主要内容包括: 观察支承 层是否发生离析, 如果有马上进行修补处理; 同时检查支承层表面标高位置, 在两基准线间拉弦线, 用钢尺量测弦线到支承层表面的距离, 如果标高超过误 差允许要求, 立刻处理; After the paving is completed, the quality of the support layer is checked. The main contents of the inspection include: Observing whether the support layer is isolated, if it is repaired immediately; Checking the surface elevation of the support layer and pulling the string between the two baselines , using a steel ruler to measure the distance from the string to the surface of the support layer, if the elevation exceeds the error The difference is allowed, and it is processed immediately;
第六步, 人工修边:  The sixth step, manual trimming:
路基支承层为干硬性混凝土, 道床板范围内支承层表面有一定的粗糙度, 以便能和道床板界面良好接触, 两侧边缘 35厘米外露出部分要人工进行收面 抹光, 避免孔洞过多, 吸水过多造成冻融破坏;  The subgrade support layer is dry hard concrete, and the surface of the support layer has a certain roughness in the range of the track bed, so that it can be in good contact with the interface of the track bed. The exposed part of the edge of 35 cm on both sides should be manually covered and smeared to avoid excessive holes. Excessive water absorption causes freezing and thawing damage;
第七步, 支承层切缝、 养护:  The seventh step, the support layer slitting, maintenance:
支承层摊铺完成 12小时内, 按纵向 5米间距切割出横向缝, 缝深为支承 层混凝土厚度的 1/3, 在切缝工作完成后, 在支承层表面洒水并覆盖塑料薄膜 养生 5天;  Within 12 hours after the support layer is paved, the transverse joint is cut at a pitch of 5 meters in the longitudinal direction. The seam depth is 1/3 of the thickness of the concrete of the support layer. After the slitting work is completed, the surface of the support layer is sprinkled with water and covered with plastic film for 5 days. ;
第八步, 检测、 评估:  The eighth step, detection, evaluation:
施工完成后, 每隔 500米用灌砂法测定支承层混合料的密实度, 每隔 250 米钻芯取样, 芯样直径为 150毫米, 进行抗压强度测试, 确定 28天的支承层 混合料的强度, 检测资料完成后, 对支承层施工质量进行评估。  After the completion of the construction, the compactness of the support layer mixture shall be determined by sand blasting every 500 meters. The core shall be sampled every 250 meters. The diameter of the core sample is 150 mm. The compressive strength test shall be carried out to determine the 28-day support layer mixture. The strength of the support layer is evaluated after the test data is completed.
本发明具有施工速度快和摊铺机作业功效大的特点, 可达到 300m/天的施 工进度, 能大大缩减施工工期; 可提高支承层的施工质量、 降低道床板开裂几 率和增加结构的耐久性能。  The invention has the characteristics of high construction speed and large operation efficiency of the paver, can reach the construction progress of 300 m/day, and can greatly reduce the construction period; can improve the construction quality of the support layer, reduce the cracking probability of the road bed plate and increase the durability of the structure. .

Claims

权 利 要 求 书 Claim
1. 一种双块式无砟轨道支承层施工工艺, 其特征在于, 它包括如下步骤: 第一步, 基准线测设 A double-block ballastless track supporting layer construction process, characterized in that it comprises the following steps: First step, reference line setting
在施工前,完成支承层的测量放线工作,通过 CPIII控制网测设混凝土支承 层中线, 进而设置两侧引导线, 引导线到线路中线的距离为 2. 9米, 高度距设 计路基面 50厘米, 引导线拉杆纵向间距为 10米, 曲线地段为 5米; 摊铺采用 钉桩或引导线法校准摊铺机挤压底板四角点高程和侧模前进方向, 校核 1〜2 遍, 正确无误后, 进行摊铺作业;  Before the construction, the measurement and release work of the support layer is completed, and the center line of the concrete support layer is set by the CPIII control network, and the guide lines on both sides are set, and the distance from the guide line to the line center line is 2. 9 meters, and the height is designed to cover the road surface 50. Cm, the longitudinal distance of the guide line tie rod is 10 meters, and the curved section is 5 meters; the paving uses the nail pile or guide line method to calibrate the pitch of the four corners of the bottom of the paver and the direction of the side mold, check 1~2 times, correct After the error, the paving operation is carried out;
第二步, 混合料配制  The second step, the mixture preparation
A.根据试验室推荐的配合比, 在现场进行工艺试验, 综合分析支承层的密 实度及抗压强度指标、 拌和料的和易性、 工作性能、 外观质量因素, 修正支承 层配合比;  A. According to the recommended mixing ratio of the laboratory, carry out the process test on site, comprehensively analyze the compactness and compressive strength index of the support layer, the workability of the mixed material, the work performance, the appearance quality factor, and modify the mix ratio of the support layer;
B.在现场对材料取样, 进行骨料筛分试验, 检査骨料级配情况; 在拌和站 对砂、 石料含水率进行测定, 根据含水率修定理论配合比, 确定施工配合比, 拌和料拌制完成后, 取样测定含水率;  B. Sampling the material at the site, performing the aggregate screening test to check the aggregate gradation; measuring the moisture content of the sand and stone at the mixing station, adjusting the theoretical mix ratio according to the water content, determining the construction mix ratio, mixing After the mixing of the materials is completed, the water content is measured by sampling;
C.确定后的原材料重量比为: 水泥、 矿物掺合料 1%, 粗、 细骨料比例 2%, 拌合水比例 1%;  C. The determined raw material weight ratio is: cement, mineral admixture 1%, coarse and fine aggregate ratio 2%, mixing water ratio 1%;
D.支承层混合料搅拌流程如下:
Figure imgf000012_0001
D. The mixing process of the support layer mixture is as follows:
Figure imgf000012_0001
媒. 爽  Media. cool
Ε.支承层混合料充分搅拌,使各种材料混合均匀、 颜色一致后, 将混合料 运输到施工现场备用; 第三步, 混合料运输 Ε. The support layer mixture is fully stirred, so that the various materials are evenly mixed and the colors are consistent, and the mixture is transported to the construction site for use; The third step, mixed material transportation
运输前将自卸式汽车车箱清洗干净,在采用自卸式汽车进行支承层混合料 的运输过程中用帆布覆盖, 混合料运输到施工现场后, 卸料距离以不使水分蒸 发为限;  Before the transportation, the self-unloading automobile car is cleaned and covered with canvas during the transportation process of the support layer mixture by the self-unloading automobile. After the mixed material is transported to the construction site, the discharge distance is not limited to the evaporation of water;
第四步, 支承层混合料摊铺  The fourth step, the support layer mix paving
首先, 摊铺前对基床表层表面进行洒水润湿;  First, sprinkle the surface of the surface of the bed before weaving;
然后, 混合料运输到施工现场后进行取样, 测定含水率;  Then, the mixture is transported to the construction site for sampling, and the water content is measured;
最后, 摊铺时, 支承层混合料通过挖掘机来完成布料: 在摊铺宽度范围内 布料均匀, 最高料位不高于摊铺机前松方控制板顶面的正常高度, 而在螺旋布 料器叶片最高点以下, 且不得缺料; 纵向布料超过 5米后, 启动摊铺机开始摊 铺, 布料时, 在曲线地段, 其外侧布料高度稍高, 在 5〜10米的摊铺距离内确 定最佳振捣频率、 最佳摊铺走行速度和捣固棒最佳插入深度;  Finally, during paving, the support layer mixture is finished by the excavator: the fabric is evenly distributed within the width of the paving, and the highest level is not higher than the normal height of the top surface of the loose control panel of the paver, while in the auger Below the highest point of the blade, and not to be short of material; after the longitudinal fabric exceeds 5 meters, the paver starts to spread. When the fabric is in the curved section, the outer fabric height is slightly higher, and it is determined within the paving distance of 5 to 10 meters. Optimal vibrating frequency, optimum paving speed and optimum insertion depth of the tamping rod;
第五步, 外观质量检查  Step 5, appearance quality check
摊铺完成后, 对支承层的质量进行检查, 检查的主要内容包括: 观察支承 层是否发生离析, 如果有马上进行修补处理; 同时检查支承层表面标高位置, 在两基准线间拉弦线, 用钢尺量测弦线到支承层表面的距离, 如果标高超过误 差允许要求, 立刻处理;  After the paving is completed, the quality of the support layer is checked. The main contents of the inspection include: Observing whether the support layer is isolated, if it is repaired immediately; and checking the surface elevation of the support layer, pulling the string between the two reference lines, Use a steel ruler to measure the distance from the string to the surface of the support layer. If the elevation exceeds the allowable error, handle it immediately;
第六步, 人工修边  Step 6, manual trimming
路基支承层为干硬性混凝土, 道床板范围内支承层表面有一定的粗糙度, 以便能和道床板界面良好接触, 两侧边缘 35厘米外露出部分要人工进行收面 抹光, 避免孔洞过多, 吸水过多造成冻融破坏;  The subgrade support layer is dry hard concrete, and the surface of the support layer has a certain roughness in the range of the track bed, so that it can be in good contact with the interface of the track bed. The exposed part of the edge of 35 cm on both sides should be manually covered and smeared to avoid excessive holes. Excessive water absorption causes freezing and thawing damage;
第七步, 支承层切缝、 养护:  The seventh step, the support layer slitting, maintenance:
支承层摊铺完成 12小时内, 按纵向 5米间距切割出横向缝, 缝深为支承 层混凝土厚度的 1/3, 在切缝工作完成后, 在支承层表面洒水并覆盖塑料薄膜 养生 5天; Within 12 hours after the support layer is paved, the transverse joint is cut at a pitch of 5 meters in the longitudinal direction, and the seam depth is supported. 1/3 of the thickness of the layer of concrete, after the completion of the slitting work, watering the surface of the support layer and covering the plastic film for 5 days;
第八步, 检测、 评估:  The eighth step, detection, evaluation:
施工完成后, 每隔 500米用灌砂法测定支承层混合料的密实度, 每隔 250 米钻芯取样, 芯样直径为 150毫米, 进行抗压强度测试, 确定 28天的支承层 混合料的强度, 检测资料完成后, 对支承层施工质量进行评估。  After the completion of the construction, the compactness of the support layer mixture shall be determined by sand blasting every 500 meters. The core shall be sampled every 250 meters. The diameter of the core sample is 150 mm. The compressive strength test shall be carried out to determine the 28-day support layer mixture. The strength of the support layer is evaluated after the test data is completed.
PCT/CN2010/079301 2009-12-30 2010-11-30 Construction method for supporting layer of double-block ballastless track WO2011079676A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN2009103126617A CN101892613A (en) 2009-12-30 2009-12-30 Construction process of double-block ballastless track supporting layer
CN200910312661.7 2009-12-30

Publications (1)

Publication Number Publication Date
WO2011079676A1 true WO2011079676A1 (en) 2011-07-07

Family

ID=43101948

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2010/079301 WO2011079676A1 (en) 2009-12-30 2010-11-30 Construction method for supporting layer of double-block ballastless track

Country Status (2)

Country Link
CN (1) CN101892613A (en)
WO (1) WO2011079676A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103643618A (en) * 2013-12-24 2014-03-19 江苏华通动力重工有限公司(中外合资) High speed railway supporting layer corner finishing template

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101892613A (en) * 2009-12-30 2010-11-24 中铁八局集团有限公司 Construction process of double-block ballastless track supporting layer
CN103485253B (en) * 2013-08-26 2015-12-23 广西柳工机械股份有限公司 Pavement spread construction method
CN107299585A (en) * 2017-07-05 2017-10-27 温州市华宏市政园林工程建设有限公司 A kind of municipal road construction method
CN110306382A (en) * 2019-08-06 2019-10-08 深圳市市政设计研究院有限公司 A kind of slding form operation method of underground railway track substrate large fluidity spread concrete

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0913302A (en) * 1995-07-04 1997-01-14 Nippon Kogen Concrete Kk Installation method and structure of directly connected sleeper
CN101892613A (en) * 2009-12-30 2010-11-24 中铁八局集团有限公司 Construction process of double-block ballastless track supporting layer

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0913302A (en) * 1995-07-04 1997-01-14 Nippon Kogen Concrete Kk Installation method and structure of directly connected sleeper
CN101892613A (en) * 2009-12-30 2010-11-24 中铁八局集团有限公司 Construction process of double-block ballastless track supporting layer

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
YUAN, XINLI: "Construction method for double-block ballastless track of overall test section in Wuhan of passenger line from Wuhan to Guangzhou architecture", GUANGZHOU ARCHITECTURE, no. 24, 20 December 2009 (2009-12-20), pages 56 - 58 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103643618A (en) * 2013-12-24 2014-03-19 江苏华通动力重工有限公司(中外合资) High speed railway supporting layer corner finishing template
CN103643618B (en) * 2013-12-24 2016-05-25 江苏华通动力重工有限公司(中外合资) High-speed railway supporting course corner troweling template

Also Published As

Publication number Publication date
CN101892613A (en) 2010-11-24

Similar Documents

Publication Publication Date Title
Kevern et al. Mixture Proportion Development and Performance Evaluation of Pervious Concrete for Overlay Applications.
Khan et al. Investigating the mechanical properties and fuel spillage resistance of semi-flexible pavement surfacing containing irradiated waste PET based grouts
WO2011079676A1 (en) Construction method for supporting layer of double-block ballastless track
CN111946021A (en) High belite sulphoaluminate cement non-partition crystal grindstone ground construction method
Berry et al. Properties of pervious concrete incorporating recycled concrete aggregate
Ahammed et al. Acoustic absorption of conventional pavements
Mukherjee et al. Laboratory characterization of a cement grouted bituminous macadam made with Portland slag cement
Delatte et al. Improved management of RCC pavement technology
CN102305849A (en) Method for evaluating structure type of bituminous mixture based on pavement core sample
Juradin et al. Impact of fibre incorporation and compaction method on properties of pervious concrete
Mamirov Using theoretical and experimental particle packing for aggregate gradation optimization to reduce cement content in pavement concrete mixtures
Kim Roller-compacted concrete shoulder construction on interstate highway in Georgia
Akiije Characteristic and effects of a superplasticizer quantity variation in some concrete strengths optimization
Bordelon et al. Flowable fibrous concrete for thin concrete inlays
Isa et al. The use of rubber manufacturing waste as concrete additive
Corinaldesi et al. Carbon dioxide uptake by recycled-aggregate no-fines concrete
Zhong et al. Research on Impact Factors of Workability of Roller Compacted Concrete Based on Modified Vebe Test
Brand et al. Load capacity of concrete slabs with recycled aggregates
Lomboy et al. Semi-flowable self-consolidating concrete and its application
George Soil stabilization field trial: interim report I.
Zhuge Comparison the performance of recycled and quarry aggregate and their effect on the strength of permeable concrete
Wilkinson et al. Development of resilient and environmentally responsible highway infrastructure solutions using geopolymer cement concrete
Alkaissi et al. Prediction model of elastic modulus for granular road bases
Kevern et al. Low-cost techniques for improving the surface durability of pervious concrete
Leek et al. An investigation into the performance of recycled concrete aggregate as a base course material in road pavements

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 10840465

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 10840465

Country of ref document: EP

Kind code of ref document: A1