WO2011063603A1 - 一种落渣管与一次风室的连接结构 - Google Patents

一种落渣管与一次风室的连接结构 Download PDF

Info

Publication number
WO2011063603A1
WO2011063603A1 PCT/CN2010/001862 CN2010001862W WO2011063603A1 WO 2011063603 A1 WO2011063603 A1 WO 2011063603A1 CN 2010001862 W CN2010001862 W CN 2010001862W WO 2011063603 A1 WO2011063603 A1 WO 2011063603A1
Authority
WO
WIPO (PCT)
Prior art keywords
slag
air chamber
primary air
steel plate
connection structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/CN2010/001862
Other languages
English (en)
French (fr)
Chinese (zh)
Inventor
徐伟俊
黄辉
吴海赟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Boiler Works Co Ltd
Original Assignee
Shanghai Boiler Works Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Boiler Works Co Ltd filed Critical Shanghai Boiler Works Co Ltd
Priority to IN439DEN2012 priority Critical patent/IN2012DN00439A/en
Publication of WO2011063603A1 publication Critical patent/WO2011063603A1/zh
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Classifications

    • F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23—COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23J—REMOVAL OR TREATMENT OF COMBUSTION PRODUCTS OR COMBUSTION RESIDUES; FLUES 
    • F23J1/00—Removing ash, clinker, or slag from combustion chambers
    • F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23—COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23C—METHODS OR APPARATUS FOR COMBUSTION USING FLUID FUEL OR SOLID FUEL SUSPENDED IN  A CARRIER GAS OR AIR 
    • F23C10/00—Fluidised bed combustion apparatus
    • F23C10/18—Details; Accessories
    • F23C10/24—Devices for removal of material from the bed

Definitions

  • the present invention relates to a connection structure of a slag tube and a primary plenum, and more particularly to a slag system suitable for use in a circulating fluidized bed boiler. Background technique
  • the slag pipe is an important component for transporting slag in the circulating fluidized bed (CFB) boiler cold slag system.
  • the uppermost end is located in the furnace above the bottom air distribution plate, and is connected with the bottom air distribution plate. After passing through the primary air chamber, the lowermost end is connected to the slag cooler and is connected to the slag inlet of the slag cooler. Since the slag temperature in the slag pipe is different from the temperature of the primary air in the primary plenum, the expansion coefficient is different, and there is a difference in expansion. If the expansion difference is not absorbed, the slag pipe may be damaged. Disclosure of invention
  • the invention provides a connection structure between a slag pipe and a primary air chamber, which can absorb the difference in expansion between the slag pipe and the primary air chamber, and prevent the slag pipe from being damaged.
  • the present invention provides a connection structure of a slag tube and a primary air chamber, the connection structure comprising a primary air chamber wall panel, a slag tube, and a steel plate.
  • the primary air chamber wall panel is provided with an opening, and the opening size is matched with the outer diameter size of the falling slag tube, and the primary air chamber wall panel can be horizontally arranged or inclined, and the inclined angle when the inclined arrangement is 0 Degree -45 degrees.
  • the slag pipe is sleeved in the opening of the primary air chamber wall plate, the upper end of the slag pipe is connected with the bottom plate of the furnace bottom, and the lower end is connected with the slag cooler.
  • the steel plate is sleeved around the falling slag pipe, and the longitudinal section of the steel plate is arc-shaped, or U-shaped, or V-shaped.
  • the upper end of the steel plate is welded to the slag tube, and the lower end is welded to the primary air chamber wall plate, and the steel plate can be deformed to absorb the difference in expansion between the slag pipe and the primary air chamber wall plate.
  • the connecting structure further comprises a protective cover which is sleeved on the falling slag tube and located on the steel plate
  • the shield covers the steel plate to avoid damage to the steel plate due to leakage of the air distribution plate.
  • the invention can absorb the difference in expansion between the slag pipe and the primary air chamber, and prevent the slag pipe from being damaged.
  • FIG. 1 is a schematic structural view of a connection structure of a slag tube and a primary air chamber provided by the present invention. The best way to implement the invention
  • FIG. 1 it is a schematic structural view of a connection structure between a slag tube and a primary air chamber provided by the present invention, and the connection structure comprises a primary air chamber wall panel 4, a slag tube 2, and a steel plate 1.
  • the primary air chamber wall panel 4 is provided with an opening, the opening size matching the outer diameter dimension of the falling slag tube 2, the primary air chamber wall panel 4 may be horizontally arranged or inclined, and the inclined angle when inclined It is 0 degrees - 45 degrees.
  • the slag tube 2 is sleeved in the opening of the primary air chamber wall panel 4.
  • the upper end of the slag tube 2 is connected to the bottom air distribution plate, and the lower end is connected to the slag cooler.
  • the steel plate 1 is placed around the slag pipe 2. As shown in Fig. 2, the A-A direction of the steel plate 1 is arc-shaped, and may be circular, or U-shaped, or V-shaped.
  • the steel plate 1 has a circular cross section (as shown in FIG. 2, X or a rectangular opening in the middle (as shown in FIG. 3), or a hexagonal shape in the middle opening (as shown in FIG. 4). Or other geometric shapes in the middle opening.
  • the upper end of the steel plate 1 is connected to the falling slag pipe, and the lower end is welded to the primary air chamber wall plate 4.
  • the steel plate 1 can be deformed to absorb the difference in expansion between the slag pipe 2 and the primary air chamber wall plate 4.
  • the connecting structure further comprises a protective cover 3, which is sleeved on the falling slag tube 2, is located at the upper end of the steel plate 1, and the protective cover 3 can adopt a horn shape, and the protective cover 3 covers the steel plate 1 , to avoid damage to the steel plate 1 due to leakage of the air distribution plate.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Building Environments (AREA)
  • Carbon Steel Or Casting Steel Manufacturing (AREA)
  • Manufacture And Refinement Of Metals (AREA)
  • Shielding Devices Or Components To Electric Or Magnetic Fields (AREA)
PCT/CN2010/001862 2009-11-30 2010-11-22 一种落渣管与一次风室的连接结构 Ceased WO2011063603A1 (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
IN439DEN2012 IN2012DN00439A (enExample) 2009-11-30 2010-11-22

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN200920214453.9 2009-11-30
CN2009202144539U CN201539859U (zh) 2009-11-30 2009-11-30 一种落渣管与一次风室的连接结构

Publications (1)

Publication Number Publication Date
WO2011063603A1 true WO2011063603A1 (zh) 2011-06-03

Family

ID=42591312

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2010/001862 Ceased WO2011063603A1 (zh) 2009-11-30 2010-11-22 一种落渣管与一次风室的连接结构

Country Status (4)

Country Link
CN (1) CN201539859U (enExample)
IN (1) IN2012DN00439A (enExample)
TR (1) TR201205810T2 (enExample)
WO (1) WO2011063603A1 (enExample)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103968376A (zh) * 2013-02-06 2014-08-06 青岛顺德电力环保设备有限公司 一种循环流化床锅炉底渣冷却工艺
CN105674255A (zh) * 2016-03-17 2016-06-15 无锡华光锅炉股份有限公司 一种落渣管防磨结构

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201539859U (zh) * 2009-11-30 2010-08-04 上海锅炉厂有限公司 一种落渣管与一次风室的连接结构
CN106568092B (zh) * 2016-10-26 2019-06-11 国投盘江发电有限公司 一种火力发电锅炉中落渣管的管帽结构

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4445443A (en) * 1982-03-31 1984-05-01 Foster Wheeler Energy Corporation Fluidized bed heat exchanger having separating drain and method of operation thereof
US4784533A (en) * 1986-10-14 1988-11-15 Combustion Engineering, Inc. Solids feeder
JPH03128211U (enExample) * 1990-03-30 1991-12-24
JPH06281110A (ja) * 1993-03-31 1994-10-07 Sumitomo Cement Co Ltd 流動層炉からの大塊排出装置
CN201539859U (zh) * 2009-11-30 2010-08-04 上海锅炉厂有限公司 一种落渣管与一次风室的连接结构

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4445443A (en) * 1982-03-31 1984-05-01 Foster Wheeler Energy Corporation Fluidized bed heat exchanger having separating drain and method of operation thereof
US4784533A (en) * 1986-10-14 1988-11-15 Combustion Engineering, Inc. Solids feeder
JPH03128211U (enExample) * 1990-03-30 1991-12-24
JPH06281110A (ja) * 1993-03-31 1994-10-07 Sumitomo Cement Co Ltd 流動層炉からの大塊排出装置
CN201539859U (zh) * 2009-11-30 2010-08-04 上海锅炉厂有限公司 一种落渣管与一次风室的连接结构

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103968376A (zh) * 2013-02-06 2014-08-06 青岛顺德电力环保设备有限公司 一种循环流化床锅炉底渣冷却工艺
CN103968376B (zh) * 2013-02-06 2016-08-31 青岛顺德电力环保设备有限公司 一种循环流化床锅炉底渣冷却工艺
CN105674255A (zh) * 2016-03-17 2016-06-15 无锡华光锅炉股份有限公司 一种落渣管防磨结构

Also Published As

Publication number Publication date
IN2012DN00439A (enExample) 2015-05-15
CN201539859U (zh) 2010-08-04
TR201205810T2 (tr) 2012-06-21

Similar Documents

Publication Publication Date Title
JP2010529399A5 (enExample)
RU2010146291A (ru) Устройство для крепления горелок с системой охлаждения для установки с горелками в газогенераторе с воздушным потоком
CN102132947B (zh) 一种用于密集烤房的加热器
CA2899271C (en) High efficency boiler
CN108662782A (zh) 燃烧换热系统和具有其的燃气热水器
WO2011063613A1 (zh) 一种水冷屏穿过水冷壁的密封结构
CN102132949B (zh) 一种用于密集烤房的加热炉
JP6809207B2 (ja) 車両の熱害防止構造
CN205013106U (zh) 柴油机排气管降噪隔热罩
US20120090590A1 (en) Inducer fan assembly for a gas furnace system
CN210485694U (zh) 循环流化床锅炉返料器放灰管
CN102997406B (zh) 热管式热水加热器
US20170350620A1 (en) Secondary flue restrainer for condensing water heater
CN217482172U (zh) 一种用于空调管的保温保护装置
CN101389920B (zh) 用于冷却热气体的设备
CN214580957U (zh) 一种能够抗震的led灯散热铝件
CN216869169U (zh) 倒焰窑传热装置及具有其的倒焰窑
CN106705008A (zh) 一种集束双套管急冷式余热锅炉结构
CN207540397U (zh) 活性炭回收用烟气降温装置
CN110822704A (zh) 一种燃气节能换热装置及燃气热水器
CN205447733U (zh) 水冷壁管的保护结构和循环流化床锅炉
US9389001B2 (en) Boiler, and a silencer for a flue gas duct in a boiler
JP5746850B2 (ja) 熱交換器
CN206129372U (zh) 催化器及具有其的车辆
CN210833186U (zh) 热交换器结构

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 10832510

Country of ref document: EP

Kind code of ref document: A1

DPE2 Request for preliminary examination filed before expiration of 19th month from priority date (pct application filed from 20040101)
WWE Wipo information: entry into national phase

Ref document number: 439/DELNP/2012

Country of ref document: IN

WWE Wipo information: entry into national phase

Ref document number: 2012/05810

Country of ref document: TR

NENP Non-entry into the national phase

Ref country code: DE

WWE Wipo information: entry into national phase

Ref document number: 1201000800

Country of ref document: TH

122 Ep: pct application non-entry in european phase

Ref document number: 10832510

Country of ref document: EP

Kind code of ref document: A1