WO2006026888A1 - An incline bed and horizontal push method for constructing a dam with rolled concrete - Google Patents

An incline bed and horizontal push method for constructing a dam with rolled concrete Download PDF

Info

Publication number
WO2006026888A1
WO2006026888A1 PCT/CN2004/000880 CN2004000880W WO2006026888A1 WO 2006026888 A1 WO2006026888 A1 WO 2006026888A1 CN 2004000880 W CN2004000880 W CN 2004000880W WO 2006026888 A1 WO2006026888 A1 WO 2006026888A1
Authority
WO
WIPO (PCT)
Prior art keywords
concrete
dam
construction
pouring
layer
Prior art date
Application number
PCT/CN2004/000880
Other languages
French (fr)
Chinese (zh)
Inventor
Lichen Yang
Guangran Yang
Original Assignee
Lichen Yang
Guangran Yang
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Lichen Yang, Guangran Yang filed Critical Lichen Yang
Priority to PCT/CN2004/000880 priority Critical patent/WO2006026888A1/en
Publication of WO2006026888A1 publication Critical patent/WO2006026888A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • E02B3/102Permanently installed raisable dykes
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Definitions

  • the present invention relates to a method of construction of a river dam for a water conservancy project. Specifically, the present invention relates to a sloping layer flat tiling method for damming concrete construction. Background technique
  • the RCC dam construction which is now commonly used, is called horizontal paving. It is carried out on the horizontal storage surface. If the casting surface is small, the amount of stencil is greatly increased, and the surrounding storage surface is 10 The rim is restrained and the construction speed is reduced because only the large warehouse surface can be poured horizontally. In this way, when the concrete preparation and supply capacity is under a given condition, each paving is laminated, it needs to wait, the time required. As a result, the mechanical properties of the concrete bond layer are thus reduced. Under high temperature or rainfall conditions, it is more prominent, and construction is forced to stop, which is prone to quality accidents. This limits the rapid and economic construction of difficult concrete dams.
  • the present invention is directed to overcoming the deficiencies in the prior art described above, and to provide a high-rise, high-quality, economical, and large-volume RCC dam construction method.
  • the object of the present invention can be achieved by the following measures:
  • the direction of the construction of the inclined layer is the same as that of the warehouse.
  • the pouring is 3 - 15 layers, and the thickness of the casting layer is 0.9 - 4. 5m.
  • the amount of 2000 - 90000m 3 , the slope of the slope is 1: 8 - 1: 25 for the lofting, on the foundation rock surface of the dam bank slope, the beginning and the end of the concrete pouring are in the same direction as the construction direction.
  • the structure, the specified position of the rolling layer of each numbered layer is marked by the surveying; the seam surface is roughed, and the "old" concrete layer before the laying of the sand pad is treated twice, first
  • the 40MPa high-pressure jet water is used for the first time, before the adjacent pouring construction, the area along the horizontal strip of the slope foot, the surface adhesion is removed by the pouring construction.
  • Contaminants until fresh, dry and anhydrous film state; RCC mixing, transportation, construction level paving mortar, inclined layer paving, inclined layer rolling, horizontal strips of sloped slope feet, front The edge is 30 - 50CD1 as the "side limit", not laminated, the inclined layer rolling and the wheel track overlap 0.
  • the inclined layer flat push 0 paving method the width of the horizontal strip along the slope front Less than the width of the inclined layer paving, ⁇ the interval between the construction joints is less than the time of the inclined layer rolling cycle; the closing surface of the RCC pouring construction is close to the dam body and the downstream template is the first vibrating and dense After 90-120min, the coagulation hardening in the construction reaches the correction page (Article 91)
  • the curved wave plate vibrator When reshaping the state, use the curved wave plate vibrator to vibrate to increase the penetration diameter of the construction joint and improve the tensile mechanical properties.
  • the dam body roller compacted concrete is used for vibration-free rolling and direct slurry to improve the construction joint and compact.
  • the artificial boring method is used to form the induction joint before the pouring of the upper layer of RCC, and the stress is set as the drainage hole;
  • the slitting and nuclear density detection are carried out, and at the same time, the slurry is applied to the transition zone between the adjacent formwork, the structure of the dam body and the traditional concrete joint, and the milled concrete is used for the transition zone treatment; and then the health preservation and low temperature protection are carried out until the next pouring lift cycle.
  • Figure 1 The process flow of the inclined layer push-pull method.
  • Fig. 2 Plane diagram of the inclined layer paving method: 1. The extent of the pouring layer, 2. The layer of the inclined layer, 3. The horizontal strip of the inclined slope, 4. The order of the paving strip, 5. The concrete pouring The short side dimensions of the warehouse face gallery, 6. The length dimension of the contour of the concrete pouring bin.
  • Fig. 3 is a schematic cross-sectional view of the inclined layer paving method: 11. Thickness of the inclined layer, 12. Length of the top surface of a diagonal layer, 13. Slope of the inclined layer level 1: 8 - 1: 25, 14. Construction occupation direction, 15. The height of the lift of the planned concrete placement, 16. The length of the slope of each inclined slope, 17. The top surface (the end surface of the concrete pouring lift), 18. The construction level of the old concrete.
  • Fig. 4 Schematic diagram of the opening of the oblique layer paving method: 01. The thickness of the inclined layer 02. The length of the top surface of a diagonal layer, the slope of the layer of the inclined layer of 03. 1. 8-1. 25, 04. Construction occupation direction, 05 The height of the lift of the planned concrete pouring, 06. The reserved level of the opening is about 10m, 07. The length of each horizontal slope is ⁇ 1111, 08. The top surface (the end surface of the concrete pouring lift), 09. Construction level of old concrete.
  • Fig.5 Schematic diagram of the cross-section of the inclined layer paving method: 21.
  • the thickness of the inclined layer, 22. The length of the top surface of the inclined layer, 23.
  • the slope of the inclined layer layer, 24. The adjacent section of the closing section (or the abutment)
  • the reserved level of the rock face is about 10m long. 25.
  • the abutment rock slope is not required), and the horizontally crushed layer is entrained, 27. the top surface (the end surface of the concrete pouring lift), 28.
  • Fig. 6 Schematic diagram of the lift profile of the dam body: 31. Height of the pouring lift: nxO. 3m (n is a positive integer), 32, 33 adjacent to the upper and lower formwork, vibrating with a curved wave plate vibrating machine, 34. Pressed concrete, 35, 36. Upper and lower rich slurry compacted concrete and dam body RCC interface (Christmas tree effect).
  • the inclined layer flat push paving method is used for RCC construction, separate bin stage, normal pouring stage and closing correction page (fine ⁇ Article 91)
  • the construction occupation direction is determined according to factors such as concrete production, supply capacity, dam size and detail structure. For example, under normal temperature conditions, the concrete production capacity is 250m 3 /h.
  • the best construction plan is to take the longitudinal direction, that is, to open the dam shoulder from the starting point of concrete supply into the dam. And at the beginning of the dam shoulder to close the warehouse. There is no formwork between the dam sections, and the seam is made by a vibrating slitting machine.
  • the dam width is large, and it can be divided vertically and vertically. From the downstream to the upstream, the construction is carried out from one end of the bank slope.
  • Inclined slope 1 8-1: 25 variation range is available, based on the strength of the supplied concrete supply (mVh) and the slope is slow; slope 2. 3. ⁇ 7. 1. The cosine function of the elevation angle is > 99. This indicates that the attenuation of the vibratory rolling function on the level of the inclined layer is slight; it does not damage the concrete mixture against separation.
  • the present invention particularly emphasizes: First, the application of high pressure (about 40 MPa) spray water blistering treatment as shown in Figure 3.18, as long as the continuous casting time allows, when the roller compacted concrete reaches 20% of the design age strength Beginning to blister, the blistering exposes a good calcium carbonate crystalline film with a firm surface to the concrete without requiring the bulging of the aggregate; because the cementation strength depends on the cement granules rather than the coarse aggregates; second, the concrete is poured Before paving the mortar mat, remove the contaminants from the pouring construction to clean, and become semi-dry, state (if the rain can be blown by compressed air or negative pressure machine to absorb surface water); third, in the treatment Immediately spread the mortar on the surface of the warehouse (the strength of the mortar is greater than the strength of the roller compacted concrete 1 ⁇ 2), then cover the RCC, and immediately vibrate and compact; Fourth, when the longitudinal construction, the dam body compacted concrete and The upstream self-seepage anti-seepage RCC shall occupy the width of
  • the horizontal strip width of the slope foot should be less than the horizontal width of one inclined layer, that is, Figure 3, 16 ⁇ 12, the purpose is to construct the horizontal strip RCC with less than one inclined layer. Time period.
  • One or more of these measures are beneficial to the compaction of the laminated concrete layer and the mechanical properties of the RCC body.
  • the inclined layer flat-pushing method requires the process technology of RCC transportation, paving to eliminate the separation of the physical aggregate, and the nuclear density meter detection after the slitting and rolling, and the horizontal paving method: 3 ⁇ 4 condensation
  • the earthwork skill is the same, and the inclined layer flat push paving method can intuitively and conveniently carry out the construction work of the construction layer joint without interference, and can ensure that the crushed layer is compacted in a plastic state, and the practice has shown that the compacted layer is compacted. Very little can be detected from the core of the dam.
  • the slurry-grinding RCC is mixed with a correction sheet of about 7% of the cement material (Article 9 1) 93% of the RCC mixture is vibrated with a plug-in vibrator; the cementitious material slurry is mixed with special properties (retardation, durability, anti-seepage, micro-expansion) admixture, the ratio of which is determined by experiment and used High-speed mixing, high-speed mixer (>900rpm) can fully pulverize cement particles, which can slow down sedimentation and coagulation; pipeline pumping for reinforced concrete on the dam, roller compacted concrete construction, roller compacted concrete paving after artificial bottoming
  • the middle and second layers are sprayed with a slurry volume of about 2L/m 2 (rolling layer thickness of 0.3m).
  • the concrete is closed and the vibrating compact is dense.
  • the slurry-rich compacted roller compacted concrete is beneficial to the RCC and the dam structure.
  • Synchronous pouring lift construction first vibrating and solidifying compacted RCC and vibrating simultaneously with RCC Rolling, the roller requires 10-20 cm on the tapped and solidified roller compacted concrete. Therefore, the slurry-rich compacted RCC is only required to be paved to a width of 30 cm adjacent to the downstream of the dam; the upstream of the dam is determined according to the designed anti-seepage structure requirements. This constitutes a full-faced RCC building of any shape.
  • Roller compacted concrete dams are mechanized construction, requiring a small number of manuals to coordinate, dynamic quality management and process requirements for key technical parts.
  • the advantages of RCC dam construction (investment and short construction period) can be fully utilized to replace the traditional concrete dam (1936 US, Hoover dam dam construction method) will become possible. This is the significance and role of the present invention.
  • the quality of RCC is inextricably linked with several time parameters.
  • the inclined layer paving method is the only method that may meet this time requirement.
  • the American Concrete Institute has requested: a. Roller compacted concrete The time from the exit to the completion of the crushing does not exceed 40 minutes.
  • the layering material of the layer and the seam surface shall not exceed 15 minutes from paving to covering.
  • the method can be used both horizontally and vertically. Therefore, its rolling layer or construction joint can be inclined to the upstream, which is beneficial to the stability of the dam.
  • the interval between floors is reduced.
  • the new and old concrete joints are the key parts of the quality. They account for about the area of the slopes within 1 / 10 of the area of the inclined layer. It is easy to ensure the construction joints with this method.
  • the freshness of the surface pad sand pad is covered with concrete in a very short time without being subjected to the rolling of the construction machine, and compacted and compacted to obtain the most reliable seam surface impermeability and cementing firmness.
  • the method is more suitable for construction under special conditions, such as rainy days, high temperature sunshine or low temperature season construction.
  • the length of the dam section should be 10m (15 ⁇ in the mild area).
  • the dam is poured in the upper dam. The construction process is followed by hand-drilling to induce the diameter of the hole 38 legs; terminate the stress relief hole diameter
  • the present invention utilizes the health stop time on the receiving surface, in the large The slabs of the concrete are poured.
  • the depth of the drill is 0. 7 times the concrete pouring.
  • the diameter of the drilled hole is 38 mm, the spacing is 10 cm, and the drilling depth is 0. 7 times the concrete pouring.
  • the diameter of the drilling stress relief hole is 150 mm, the inducing hole is backfilled with drilling slag or dry sand, the stress relief hole is blocked with wooden board, measuring and recording, drilling, connecting the upper and lower, and the bottom is connected with the drainage gallery.
  • dam seepage water It satisfies the "seepage control and anti-seepage structure of RCC dam" itself, stable anti-seepage effect, adaptability to deformation, convenient construction and no interference.
  • Table 2 The values listed in Table 2 indicate that the inclined layer flat push paving is most suitable for the large warehouse surface at the same lift height.
  • the efficiency of the horizontal layer paving method is 100, and the inclined layer paving method is 143.
  • Table 3 comparison of the flat layer paving method and the inclined layer flat paving method and superiority.
  • Jiangya dam to dam RCC performance for example, the swash layer placing method than the 30% efficiency level layer paving method, improving economic efficiency RMB26. 40 membered / m 3, eliminating the need for templates and Gap
  • the economic benefit of the slurry-rich slurry on both sides is RMB 2.30/m 3 .
  • the construction of the river dam water conservancy project is a social basic industry for flood control and disaster mitigation, and the discovery of water conservancy and power resources.
  • the application of this patented technology simplifies the construction process, ensures quality, speeds up the progress, and early exerts the project efficiency, which will certainly produce significant social benefits. .

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

An incline bed and horizontal push method for constructing a dam with rolled concrete comprises the following steps: laying-out, slot surface green cutting, mixing roller compacted concrete, transporting, inclined-layer paving, cutting joint, nuclear density testing, applying simultaneously mortar-enriched compact roller concrete at joints of adjacent shuttering, constructions inside the dam and the like, curing and low-temperature protection, furthermore, processing dense treat against the pouring bin surface for the lift range of the rolled concrete, as well as arranging induction joints in the water drawing surface of the dam. Applying the method to the construction of the large volume concrete dam offers advantage of high speed and quality, low cost, durability, and minimum adverse effect due to high or low temperature and rainy weather.

Description

用于碾压混凝土筑坝施工的斜层平推铺筑法 技术领域  Inclined layer flattening paving method for roller compacted concrete dam construction
本发明涉及水利工程的栏河坝施工的方法, 具体地说, 本发明涉及用于碾 5 压混凝土筑坝施工的斜层平推铺筑法。 背景技术  The present invention relates to a method of construction of a river dam for a water conservancy project. Specifically, the present invention relates to a sloping layer flat tiling method for damming concrete construction. Background technique
迄至今日, 现在已经通用的碾压混凝土筑坝施工, 即称水平铺筑法, 是在 水平仓面上进行, 如果选择浇筑仓面较小, 则模板量大大增加, 又受周边仓面 10 轮靡的制约, 施工速度下降, 因为, 只能取大仓面水平浇筑的方式, 这样, 当 混凝土制备和供应能力在给定的条件下, 每铺筑碾压一层, 需要等待, 所需时 间就长, 混凝土结合层面胶结的力学性能因此而降低。 在高温或降雨条件下, 显得更突出, 往往施工被迫停止, 易发生质量事故, 这样就限制了艰压混凝土 筑坝快速和经济施工特点的发挥。  Up to now, the RCC dam construction, which is now commonly used, is called horizontal paving. It is carried out on the horizontal storage surface. If the casting surface is small, the amount of stencil is greatly increased, and the surrounding storage surface is 10 The rim is restrained and the construction speed is reduced because only the large warehouse surface can be poured horizontally. In this way, when the concrete preparation and supply capacity is under a given condition, each paving is laminated, it needs to wait, the time required. As a result, the mechanical properties of the concrete bond layer are thus reduced. Under high temperature or rainfall conditions, it is more prominent, and construction is forced to stop, which is prone to quality accidents. This limits the rapid and economic construction of difficult concrete dams.
L5  L5
本发明的公开  Disclosure of the present invention
本发明自的在于克服上述现有技术中的不足之处, 而提供一秤高速麾的、 高质量的、 经济耐 的、 大体积碾压混凝土筑坝施工的斜层平推筑坝法。  The present invention is directed to overcoming the deficiencies in the prior art described above, and to provide a high-rise, high-quality, economical, and large-volume RCC dam construction method.
本发明的目的可以通过以下措施来达到: 斜层平推铺筑法的工艺流程, 包 The object of the present invention can be achieved by the following measures: The process flow of the inclined layer push-pull method, package
20 括在斜层平推铺筑的施工方向与仓面的 度方向一致, 浇筑升程 3 - 15个碾压 层, 浇筑层厚度 0. 9 - 4. 5m, 每个斜层铺筑的混凝土方量 2000 - 90000m3, 斜层 坡度 1: 8 - 1: 25进行放样, 在大坝岸坡基础岩面上、 混凝土浇筑的起始和终 了的端部与施工方向一致的侧向才莫板、 构造物, 经测绘标定出每个编号斜层碾 压的确定位置; 缝面冲毛, 铺筑砂桨前的 "老" 混凝土层面分两次处理, 第一20 The direction of the construction of the inclined layer is the same as that of the warehouse. The pouring is 3 - 15 layers, and the thickness of the casting layer is 0.9 - 4. 5m. The amount of 2000 - 90000m 3 , the slope of the slope is 1: 8 - 1: 25 for the lofting, on the foundation rock surface of the dam bank slope, the beginning and the end of the concrete pouring are in the same direction as the construction direction. , the structure, the specified position of the rolling layer of each numbered layer is marked by the surveying; the seam surface is roughed, and the "old" concrete layer before the laying of the sand pad is treated twice, first
25 次, 在计划浇筑施工和在混凝土浇筑之前, 用 40MPa高压喷射水冲毛, 第二次, 在临近浇筑施工进占之前, 沿坡脚水平条带的区域, 清除表面附着的由浇筑施 工带来的污染物, 直至新鲜、 面干而无水膜状态; 碾压混凝土拌和、 运输、 施 工缝层面摊铺砂浆、 斜层摊铺、 斜层碾压, 其中斜层坡脚的水平条带, 前缘留 出 30 - 50CD1作为 "侧限", 不予碾压, 斜层碾压与轮迹搭接 0. 5— lm,斜层平推 0 铺筑法施工前沿坡脚的水平条带的宽度小于斜层铺筑的进占宽度, ^使施工缝 的间隔时间少于斜层碾压周期的时间; 碾压混凝土浇筑施工停歇的收仓面邻近 坝体上、 下游模板处第一次振捣致密之后 90-120min, 施工中混凝 硬化达到 更正页(细则第 91条) 重塑状态时, 再用曲波板振动器振实, 以加长施工缝的渗径, 提高抗拉力学性 能; 坝体碾压混凝土用无振碾压直致泛浆, 以提高施工缝结合致密性, 为预防 坝体(特别上游坝面)出现裂缝, 则在上层碾压混凝土浇筑之前的的停歇时间, 采用人工造孔的方法形成诱导缝, 并设置应力#放孔兼作排水孔; 继而, 进行 切缝、 核子密度检测, 同时在邻近模板、 坝体内构造物和传统混凝土交接部位 应用富浆振实的碾压混凝土作过渡带处理; 进而养生、 低温防护直至下一个浇 筑升程循环。 25 times, before the planned pouring construction and before the concrete pouring, the 40MPa high-pressure jet water is used for the first time, before the adjacent pouring construction, the area along the horizontal strip of the slope foot, the surface adhesion is removed by the pouring construction. Contaminants, until fresh, dry and anhydrous film state; RCC mixing, transportation, construction level paving mortar, inclined layer paving, inclined layer rolling, horizontal strips of sloped slope feet, front The edge is 30 - 50CD1 as the "side limit", not laminated, the inclined layer rolling and the wheel track overlap 0. 5 - lm, the inclined layer flat push 0 paving method the width of the horizontal strip along the slope front Less than the width of the inclined layer paving, ^ the interval between the construction joints is less than the time of the inclined layer rolling cycle; the closing surface of the RCC pouring construction is close to the dam body and the downstream template is the first vibrating and dense After 90-120min, the coagulation hardening in the construction reaches the correction page (Article 91) When reshaping the state, use the curved wave plate vibrator to vibrate to increase the penetration diameter of the construction joint and improve the tensile mechanical properties. The dam body roller compacted concrete is used for vibration-free rolling and direct slurry to improve the construction joint and compact. To prevent the occurrence of cracks in the dam (especially the upstream dam surface), the artificial boring method is used to form the induction joint before the pouring of the upper layer of RCC, and the stress is set as the drainage hole; The slitting and nuclear density detection are carried out, and at the same time, the slurry is applied to the transition zone between the adjacent formwork, the structure of the dam body and the traditional concrete joint, and the milled concrete is used for the transition zone treatment; and then the health preservation and low temperature protection are carried out until the next pouring lift cycle.
对附图的简要说明  Brief description of the drawing
图 1 斜层平推铺筑法的工艺流程。  Figure 1 The process flow of the inclined layer push-pull method.
图 2 斜层平推铺筑法的平面示意图: 1. 正在浇筑层面的范围, 2. 斜层层 面, 3. 斜层坡脚的水平条带, 4. 摊铺条带顺序, 5. 混凝土浇筑仓面轮廊的短 边尺寸, 6. 混凝土浇筑仓面轮廓的长度尺寸。  Fig. 2 Plane diagram of the inclined layer paving method: 1. The extent of the pouring layer, 2. The layer of the inclined layer, 3. The horizontal strip of the inclined slope, 4. The order of the paving strip, 5. The concrete pouring The short side dimensions of the warehouse face gallery, 6. The length dimension of the contour of the concrete pouring bin.
图 3斜层平推铺筑法的剖面示意图: 11. 斜层厚度, 12. 一个斜层顶面的 长度, 13. 斜层层面的坡度 1 : 8 - 1 : 25, 14. 施工进占方向, 15. 规划的混 凝土浇筑的升程高度, 16. 每次斜层坡脚的进占长度, 17. 顶面 (混凝土浇筑 升程的终结面), 18. 老混凝土的施工层面。  Fig. 3 is a schematic cross-sectional view of the inclined layer paving method: 11. Thickness of the inclined layer, 12. Length of the top surface of a diagonal layer, 13. Slope of the inclined layer level 1: 8 - 1: 25, 14. Construction occupation direction, 15. The height of the lift of the planned concrete placement, 16. The length of the slope of each inclined slope, 17. The top surface (the end surface of the concrete pouring lift), 18. The construction level of the old concrete.
图 4斜层平推铺筑法开仓剖面示意图: 01.斜层厚度 02.一个斜层顶面的 长度, 03斜层层面的坡度 1. 8-1. 25, 04.施工进占方向, 05.规划的混凝土浇筑 的升程高度, 06.开仓预留的水平长 10m左右, 07.每个水平坡脚进占长度<1111, 08.顶面(混凝土浇筑升程的终结面), 09.老混凝土的施工层面。  Fig. 4 Schematic diagram of the opening of the oblique layer paving method: 01. The thickness of the inclined layer 02. The length of the top surface of a diagonal layer, the slope of the layer of the inclined layer of 03. 1. 8-1. 25, 04. Construction occupation direction, 05 The height of the lift of the planned concrete pouring, 06. The reserved level of the opening is about 10m, 07. The length of each horizontal slope is <1111, 08. The top surface (the end surface of the concrete pouring lift), 09. Construction level of old concrete.
图 5斜层平推铺筑法收仓剖面示意图: 21.斜层厚度, 22.—个斜层顶面的长 度, 23.斜层层面的坡度, 24.收仓段邻近模板 (或坝肩岩面)预留的水平长 10m 左右, 25.规划的混凝土浇筑的升程高度, 26.为了调节不使浇筑面积越来越小, 并兼顾碾压层间塑性结合性能的要求,(遇有坝肩岩面坡则不需要),而夹带的水 平碾压层面, 27.顶面(混凝土浇筑升程的终结面), 28.老混凝土的施工层面。  Fig.5 Schematic diagram of the cross-section of the inclined layer paving method: 21. The thickness of the inclined layer, 22. The length of the top surface of the inclined layer, 23. The slope of the inclined layer layer, 24. The adjacent section of the closing section (or the abutment) The reserved level of the rock face is about 10m long. 25. The height of the lift of the planned concrete pouring. 26. In order to adjust, the pouring area is not getting smaller and smaller, and the plastic bond performance between the laminated layers is required. The abutment rock slope is not required), and the horizontally crushed layer is entrained, 27. the top surface (the end surface of the concrete pouring lift), 28. The construction level of the old concrete.
图 6 坝体浇筑升程剖面示意图: 31.浇筑升程高度: nxO. 3m (n 为正整数), 32、 33 邻近上、 下游模板处用曲波板振动机振实, 34.无振碾压混凝土, 35、 36.上、 下游富浆振实混凝土与坝体碾压混凝土界面(圣诞树效应)。  Fig. 6 Schematic diagram of the lift profile of the dam body: 31. Height of the pouring lift: nxO. 3m (n is a positive integer), 32, 33 adjacent to the upper and lower formwork, vibrating with a curved wave plate vibrating machine, 34. Pressed concrete, 35, 36. Upper and lower rich slurry compacted concrete and dam body RCC interface (Christmas tree effect).
图 7碾压混凝土重力坝坝面施工示意图: 41.设计的坝体分缝, 42.诱导缝 (令 ab=bc 10m) (温和地区 15m) , 43.应力幹放孔, 44.斜层平推筑坝法示意。 实施本发明的最佳技术方案  Figure 7 Schematic diagram of the construction of the RCC gravity dam surface: 41. Designed dam body joints, 42. Induced joints (order ab=bc 10m) (moderate area 15m), 43. Stress dry holes, 44. The method of pushing the dam is indicated. Best technical solution for implementing the invention
斜层平推铺筑法进行碾压混凝土施工、 分开仓阶段、 正常浇筑阶段和收仓 更正页(细^第 91条) 阶段, 分别如图 4、 图 3、 图 5作了理义已明的表迷。 根据混凝土生产、 供应能 力、 坝体尺寸和细部结构等因素来确定施工进占方向。 举例如在常温条件下, 混凝土生产能力 250m3/h,对碾压混凝土拱坝或百米以内的重力坝, 最佳施工方 案是采取纵向, 即自混凝土供应进坝的始点对面坝肩开仓而至始点坝肩收仓。 坝段间不立模板, 用振动切缝机造缝。 百米以上高重力坝, 坝宽尺寸较大, 可 采用纵向下、上游平分, 自下游斜向上游分别采取自岸坡一端进占的方法施工。 The inclined layer flat push paving method is used for RCC construction, separate bin stage, normal pouring stage and closing correction page (fine ^Article 91) At the stage, as shown in Figure 4, Figure 3, and Figure 5, the fans of the rationale have been clarified. The construction occupation direction is determined according to factors such as concrete production, supply capacity, dam size and detail structure. For example, under normal temperature conditions, the concrete production capacity is 250m 3 /h. For RCC arch dams or gravity dams up to 100 meters, the best construction plan is to take the longitudinal direction, that is, to open the dam shoulder from the starting point of concrete supply into the dam. And at the beginning of the dam shoulder to close the warehouse. There is no formwork between the dam sections, and the seam is made by a vibrating slitting machine. For high-gravity dams over 100 meters, the dam width is large, and it can be divided vertically and vertically. From the downstream to the upstream, the construction is carried out from one end of the bank slope.
斜层坡度 1: 8-1: 25变化幅度可供选择,选择的依据是以供应混凝土供应的 强度(mVh )大而坡度緩; 斜坡 2. 3。 ~ 7 . 1。的仰角余弦函数都〉 0. 99;这表明在 斜层层面上振动碾压功能的衰减是轻微的;也不会给混凝土拌和物抗分离性带 来损害。  Inclined slope 1: 8-1: 25 variation range is available, based on the strength of the supplied concrete supply (mVh) and the slope is slow; slope 2. 3. ~ 7. 1. The cosine function of the elevation angle is > 99. This indicates that the attenuation of the vibratory rolling function on the level of the inclined layer is slight; it does not damage the concrete mixture against separation.
众所周知, 筑坝施工层面缝新、 老混凝土胶结质量如图 3. 18,是最为关键 的部位。  As we all know, the quality of new and old concrete cement joints on the dam construction level is shown in Figure 3.18, which is the most critical part.
为此, 本发明特别强调: 其一, 应用高压(40MPa 左右)喷射水冲毛处理 如图 3. 18 层面,只要连续浇筑的时间允许,可在碾压混凝土达到设计龄期强度 的 20%时开始冲毛,冲毛使混凝土表面粘结牢固的好的碳酸钙结晶薄膜露出而 不要求骨料凸出;因为胶结强度取决于水泥颗粒而不是使粗骨料凸出;其二,在 浇筑混凝土摊铺砂浆垫层之前,清除因浇筑施工的污染物至洁净,而成为半"干 燥,,状态(如遇雨水可用压缩风吹拂或用负压机具吸除表面水);其三,在处理合 格的仓面上立即摊铺砂浆 (砂浆强度标号要大于碾压混凝土强度 1 ~ 2 级)随即 覆盖碾压混凝土, 并立刻振动碾压致密; 其四, 当纵向施工时, 坝体碾压混凝 土和上游自身防渗碾压混凝土, 进占应先后错开半个水平条带的宽度, 以防止 因故施工停顿, 薄弱层集中而极少可能带来的渗漏危害; 其五, 斜坡底脚水平 条带宽度应小于 1个斜层的水平宽度, 即图 3, 16<12 , 目的是水平条带碾压混 凝土的施工周期时间少于 1个斜层的浇筑时间周期。 一一以上这些措施, 有利 于碾压混凝土层面缝胶结牢固而与碾压混凝土本体力学性能相近。  To this end, the present invention particularly emphasizes: First, the application of high pressure (about 40 MPa) spray water blistering treatment as shown in Figure 3.18, as long as the continuous casting time allows, when the roller compacted concrete reaches 20% of the design age strength Beginning to blister, the blistering exposes a good calcium carbonate crystalline film with a firm surface to the concrete without requiring the bulging of the aggregate; because the cementation strength depends on the cement granules rather than the coarse aggregates; second, the concrete is poured Before paving the mortar mat, remove the contaminants from the pouring construction to clean, and become semi-dry, state (if the rain can be blown by compressed air or negative pressure machine to absorb surface water); third, in the treatment Immediately spread the mortar on the surface of the warehouse (the strength of the mortar is greater than the strength of the roller compacted concrete 1 ~ 2), then cover the RCC, and immediately vibrate and compact; Fourth, when the longitudinal construction, the dam body compacted concrete and The upstream self-seepage anti-seepage RCC shall occupy the width of half of the horizontal strips in order to prevent the construction from stalling for a reason, and the weak layers are concentrated and there is little possibility of seepage. Hazard; Fifth, the horizontal strip width of the slope foot should be less than the horizontal width of one inclined layer, that is, Figure 3, 16<12, the purpose is to construct the horizontal strip RCC with less than one inclined layer. Time period. One or more of these measures are beneficial to the compaction of the laminated concrete layer and the mechanical properties of the RCC body.
斜层平推铺筑法要求碾压混凝土运输、 摊铺消除拌和物理骨料的分离的工 艺技巧, 以及切缝碾压后的核子密度计检测等均与水平铺筑法的碾压: ¾凝土作 业技艺是相同的, 而斜层平推铺筑法能直观方便无干扰地进行施工层面缝的施 工作业, 能保证碾压层面在塑性状态下碾压致密, 实践已表明碾压致密的层面 从坝体钻芯样中极少能够察觉到。  The inclined layer flat-pushing method requires the process technology of RCC transportation, paving to eliminate the separation of the physical aggregate, and the nuclear density meter detection after the slitting and rolling, and the horizontal paving method: 3⁄4 condensation The earthwork skill is the same, and the inclined layer flat push paving method can intuitively and conveniently carry out the construction work of the construction layer joint without interference, and can ensure that the crushed layer is compacted in a plastic state, and the practice has shown that the compacted layer is compacted. Very little can be detected from the core of the dam.
近年来, 中国最先采用富浆振实的碾压混凝土为大坝全断面碾压> '昆凝土施 工, 创造了十分便当的条件。 富浆振实碾压混凝土是用约 7%的胶凝材斜浆液掺 更正页(细则第 9 1条) 入 93%量的碾压混凝土拌和物中用插入式振动器振实; 胶凝材料浆液掺入特殊 性能(緩凝, 耐久, 防渗, 微膨胀)外加剂, 其配比经试验确定, 并用高速搅 拌制成, 高速搅拌机 ( >900rpm )能充分激散水泥颗粒,可减緩沉淀和凝聚;管路 泵运供坝上富浆振实碾压混凝土施工,碾压混凝土摊铺后人工分底、中二层布洒 约 2L/ m2 (碾压层厚 0. 3m ) 的浆液量,应用混凝土平仓振捣致密,富浆振实碾压 混凝土利于碾压混凝土与坝体构造物(邻近坝上、下游模板,分仓浇筑的分缝模 板, 岩面; 廊道, 井洞, 钢筋混凝土等)同步浇筑升程施工: 先振实富浆振实碾 压混凝土再与碾压混凝土同时振动碾压, 碾轮要求搭接已振实的富浆振实碾压 混凝土上 10- 20cm。 因此富浆振实碾压混凝土邻近坝下游模板处只要求铺筑宽 30 cm; 坝体上游按设计的防渗结构要求确定。这样就构成了任一形状的全断面 碾压混凝土建筑物。 In recent years, China has first used the solidified compacted concrete for the dam full-section rolling >'Kun concrete construction, which created a very convenient condition. The slurry-grinding RCC is mixed with a correction sheet of about 7% of the cement material (Article 9 1) 93% of the RCC mixture is vibrated with a plug-in vibrator; the cementitious material slurry is mixed with special properties (retardation, durability, anti-seepage, micro-expansion) admixture, the ratio of which is determined by experiment and used High-speed mixing, high-speed mixer (>900rpm) can fully pulverize cement particles, which can slow down sedimentation and coagulation; pipeline pumping for reinforced concrete on the dam, roller compacted concrete construction, roller compacted concrete paving after artificial bottoming The middle and second layers are sprayed with a slurry volume of about 2L/m 2 (rolling layer thickness of 0.3m). The concrete is closed and the vibrating compact is dense. The slurry-rich compacted roller compacted concrete is beneficial to the RCC and the dam structure. Upper and lower dam formwork, split joint formwork for splitting, rock face; corridor, well hole, reinforced concrete, etc.) Synchronous pouring lift construction: first vibrating and solidifying compacted RCC and vibrating simultaneously with RCC Rolling, the roller requires 10-20 cm on the tapped and solidified roller compacted concrete. Therefore, the slurry-rich compacted RCC is only required to be paved to a width of 30 cm adjacent to the downstream of the dam; the upstream of the dam is determined according to the designed anti-seepage structure requirements. This constitutes a full-faced RCC building of any shape.
碾压混凝土筑坝属于机械化施工, 需用为数不多的人工从事协调, 动态地 质量管理及其关键的技术部位的工艺要求作业。本发明实践对照 ISO9004: 2000 附录 A自我评定指南运作成熟水平: "5最好的运作级别;最强的综合改进过程; 证实达到了水平对比的最好结果"。 因此,推行斜层平推铺筑法及其相匹配的碾 压混凝土筑坝施工法', 保证了施工层缝面胶结质量, 保证了.坝面无裂缝发生; 使碾压混凝土施工速率更提高、 施工经济更节省, 碾压混凝土筑坝优点:(投资 · 少、 工期短)得以充分发挥, 取代传统的混凝土筑坝 ( 1936年美国 , Hoover坝 筑坝的一套方法)将成为可能。 这就是本发明的重大意义与作用所在。  Roller compacted concrete dams are mechanized construction, requiring a small number of manuals to coordinate, dynamic quality management and process requirements for key technical parts. Practice of the Invention ISO9004: 2000 Appendix A Self-Assessment Guide Operational maturity level: "5 best operational level; the strongest comprehensive improvement process; confirm the best results of horizontal comparison." Therefore, the implementation of the inclined layer flat-pushing method and its matching RCC dam construction method guarantees the cementing quality of the seam surface of the construction layer, ensuring that no cracks occur on the dam surface; The construction economy is more economical. The advantages of RCC dam construction: (investment and short construction period) can be fully utilized to replace the traditional concrete dam (1936 US, Hoover dam dam construction method) will become possible. This is the significance and role of the present invention.
实施例 1  Example 1
斜层平推铺筑法用于江垭坝的实绩中,如果浇筑仓面 60m X 200m = UOOOm2, 浇筑层厚度 3m,混凝土入仓浇筑强度 q = 200m3 -h-1,则水平层和不同的斜层坡比, 每碾压层厚度 0. 3m, 斜层坡度 1: 8—1: 25, 所需层间间隔时间比较见表 1。 The inclined layer flat push paving method is used in the performance of Jiangyaoba. If the pouring warehouse surface is 60m X 200m = UOOOm 2 , the pouring layer thickness is 3m, and the concrete pouring pouring strength q = 200m 3 -h -1 , the horizontal layer and For different slope ratios, the thickness of each layer is 0.3 m, and the slope of the slope is 1: 8 - 1: 25. See Table 1 for the comparison of interlayer intervals.
表 1 各种铺筑坡比的层间间隔时间比较表  Table 1 Comparison of interlayer interval time of various paving slope ratios
坡比 1: m, m 25 20 15 10 8  Slope 1: m, m 25 20 15 10 8
α (° ) 0 (通仓平层) 2. 29 2. 86 3. 81 5. 71 7. 13  α (° ) 0 (opening level) 2. 29 2. 86 3. 81 5. 71 7. 13
铺筑层数 10 26 34 45 67 84  Number of paving layers 10 26 34 45 67 84
每层 4ί &筑所需时间 18: 00 6: 55 5: 24 4: 03 2: 42 2: 10  4 ί & Build Time per Floor 18: 00 6: 55 5: 24 4: 03 2: 42 2: 10
层间间隔时间比较 8. 33 3. 20 2. 50 1. 88 1. 12 1. 00  Inter-layer spacing time comparison 8. 33 3. 20 2. 50 1. 88 1. 12 1. 00
表 1中所列斜层坡比, 由于仰角 ^[艮小, 余弦值都在 0. 99以上, 层面的倾斜 对机械操作性能和混凝土性状均无影响。  The slope ratios listed in Table 1 have no effect on the mechanical operation performance and concrete properties because the elevation angle ^[艮 is small and the cosine values are above 0.99.
更正页(细贝 !f第 91条) 工业施工应用 '|~生 Correction page (fine shell! f section 91) Industrial construction application '|~生
1、 由于顺浇筑仓面长边向进占, '、为满足混 土入仓速度为前提':确定调 整斜层坡度, 使碾压仓面浇筑机械流水作业, 工序集中, 高速连续进行, 大幅 度地提高了综合生产率。 1. Due to the long side of the pouring and pouring face, ', in order to meet the speed of mixing the soil into the warehouse': to determine the slope of the inclined layer, to make the mechanical flow of the rolling warehouse surface, the process is concentrated, high-speed continuous, large The land has increased overall productivity.
2、碾压混凝土的质量与几个时间参数存在着密不可分的关系,斜层平推铺 筑法是唯一可能满足这个时间要求的方法, 例如美国混凝土学会曾提出要求: a. 碾压混凝土拌和物从出机至碾压完毕的时间不超过 40min。  2. The quality of RCC is inextricably linked with several time parameters. The inclined layer paving method is the only method that may meet this time requirement. For example, the American Concrete Institute has requested: a. Roller compacted concrete The time from the exit to the completion of the crushing does not exceed 40 minutes.
b.碾压混凝土拌和物从入仓至开碾时间不超过 10min。  b. The time from rolling into the grouting concrete mixture does not exceed 10 minutes.
c. 层面及缝面的垫层料, 从铺筑到覆盖不超过 15min。  c. The layering material of the layer and the seam surface shall not exceed 15 minutes from paving to covering.
3、 该法既可以横向, 又可以纵向施工进占, 这样, 它的碾压层面或施工缝 面都可作到倾向上游, 有利大坝的抗滑稳定。  3. The method can be used both horizontally and vertically. Therefore, its rolling layer or construction joint can be inclined to the upstream, which is beneficial to the stability of the dam.
4、 改变了即往的水平层铺筑法施工的空间约束条件, 施工准备、养护和质 量监察直观有序, 管理简化, 形成全坝大规模流水作业局面, 浇筑作业干扰小, 提高了施工安全度, 加大了施工机械利用率, 施工流畅和更趋向合理化。  4. The spatial constraints of the construction of the horizontal layer paving method have been changed. The construction preparation, maintenance and quality supervision are intuitive and orderly, and the management is simplified. The large-scale flow operation of the dam is formed, the disturbance of the pouring operation is small, and the construction safety is improved. Degree, increased utilization rate of construction machinery, smooth construction and more rationalization.
. 5、 简化了混凝土入仓道路的布设, 省去了垂直运输部件安设的麻烦, 消除 了狭窄部位的施工难度及盾量的隐患。 - ■· ^ . .  5. Simplified the layout of concrete warehousing roads, eliminating the trouble of installing vertical transportation parts, eliminating the construction difficulty and hidden danger of the stencil. - ■· ^ .
6、 减少了层间停歇时间, 新老混凝土结合缝是质量关键的部位, 约占斜层 碾压仓面面积的 1 / 10以内的坡脚平铺面积, 用该法就很容易保证施工缝面垫 层砂桨的新鲜度, 在不受施工机械踏轧的情况下, 极短的时间内覆盖混凝土, 并碾压致密, 获得最为可靠的缝面防渗性能与胶结的牢固性。  6. The interval between floors is reduced. The new and old concrete joints are the key parts of the quality. They account for about the area of the slopes within 1 / 10 of the area of the inclined layer. It is easy to ensure the construction joints with this method. The freshness of the surface pad sand pad is covered with concrete in a very short time without being subjected to the rolling of the construction machine, and compacted and compacted to obtain the most reliable seam surface impermeability and cementing firmness.
7、 该法更适应特殊条件下的施工, 如雨天, 高温日照或低温季节施工。  7. The method is more suitable for construction under special conditions, such as rainy days, high temperature sunshine or low temperature season construction.
8、 大坝上、 下游富浆振实碾压和坝体碾压混凝土的收仓面(即升程终止的 水平仓面), 因振捣、 碾压致密的过程, 水分上升空气上浮至表层的残留; 碾压 轮的压陷凹凸形成的发状裂隙, 表层混凝土细石与振动碾振频产生共振而 "跳 动", 消弱了与周边混凝土拌和物的紧密结合等原因, 致使表层大约厚 30-50麵 的混凝土的耐久性(抗渗、 抗冻)、 力学性能(尤其抗拉强度)都很差, 是危及 大坝寿命(即无需维护的最长年限) 的关键部位, 本发明为了解决这一课题, 特提出:  8. On the dam, the downstream rich slurry compaction and the ram body compacted concrete closing surface (ie the horizontal warehouse surface where the lift is terminated), due to the process of vibrating and compacting, the water rises and the air floats to the surface. Residues; the hair-like cracks formed by the indentation of the rolling wheel, the surface concrete fine stone and the vibration grinding frequency resonate and "jump", weakening the close combination with the surrounding concrete mixture, etc., causing the surface layer to be thick The durability of 30-50 face concrete (impregnancy, frost resistance) and mechanical properties (especially tensile strength) are very poor, and it is a key part that jeopardizes the life of the dam (ie, the longest period of maintenance without maintenance). To solve this problem, I propose:
a.富浆振实碾压混凝土, 第一次振捣致密之后 90-120min, 混凝土 "硬化" 达到 "重塑" 状态时(注: "重塑" 状态, 用振捣棒振动插入 10cm深, 振 30 秒, 周围 10cm内仍能泛浆, 且不留孔洞者)再应用 1. lkw曲波板振动器(波形 更正页(细 ¾第91条) 25. 4^25. 4mm, 500 c400麵铁板)纵向 (垂直水流方向)振动至充分泛浆为止。 b、 在坝体碾压混凝土的收仓面上, 至第一次振动碾压完成后 6G- 90rain, 采用无振碾压 1-2遍(慢速〈0. 3m/s行走, 1-2往返)。 a. Rich slurry compacted RCC, 90-120min after the first vibrating compaction, when the concrete "hardens" to reach the state of "remodeling" (Note: "Remolded" state, vibrate into the 10cm depth with vibrating rod, Vibration for 30 seconds, still can be slurryed within 10cm, and no holes are left.) 1. Apply lkw curve plate vibrator (waveform correction page (fine 3⁄4, 91) 25. 4^25. 4mm, 500 c400 iron plate) vibrate in the longitudinal direction (vertical flow direction) until it is fully flooded. b. On the receiving surface of the roller compacted concrete of the dam, 6G-90rain after the completion of the first vibration rolling, using 1-2 times of vibrationless rolling (slow speed <0.3m/s walking, 1-2 round trip).
9、为了防止大坝防渗体区域发生竖向劈头裂缝,坝段分块长度宜 10m (温 和地区 15πι )为了避免因坝块小, 影响碾压施工的顺畅, 则在上一坝体浇筑升 程施工之先后按次序用手风钻诱导孔直径 38腿; 终止设应力释放孔直径  9. In order to prevent the vertical boring crack in the dam anti-seepage area, the length of the dam section should be 10m (15πι in the mild area). In order to avoid the smoothness of the roller compaction due to the small dam block, the dam is poured in the upper dam. The construction process is followed by hand-drilling to induce the diameter of the hole 38 legs; terminate the stress relief hole diameter
150-200mm, 使其上、 下连贯通兼有排水功能, 至坝内排水廊道排出,对于坝体 分块长度在 20m以上, 这对辗压混凝土筑坝施工十分有利, 但实践表明, 长坝 块分缝数年后常引发竖向裂缝, 本发明利用在收仓面上的养生停歇时间, 在大
Figure imgf000008_0001
3m以上, 诱导缝的、构成是紧临迎水坝面设置铜止水部件 1' 道或 1道以上, 钻诱导孔直径为 38亳米, 间距 10公分, 钻深为 0. 7倍混凝土 浇^升程厚度; 钻应力释放孔直径 150 mm, 诱导孔用钻渣或干砂回填, 应力释 放孔用木板封堵孔口, 测量记录、 施钻、 使上、 下贯通, 底部与排水廊道连通, 以排除大坝渗流水。 满足 "碾压混凝土坝的渗流控制和防渗结构" 自身稳定, 防渗效果可靠, 适应变形能力, 施工方便无干扰等特点。
150-200mm, so that the upper and lower joints have a drainage function, and discharge to the drainage corridor in the dam. For the dam body length of 20m or more, this is very beneficial for the construction of the tamping concrete, but the practice shows that The dam block often causes vertical cracks after several years of slitting. The present invention utilizes the health stop time on the receiving surface, in the large
Figure imgf000008_0001
The slabs of the concrete are poured. The depth of the drill is 0. 7 times the concrete pouring. The diameter of the drilled hole is 38 mm, the spacing is 10 cm, and the drilling depth is 0. 7 times the concrete pouring. Lifting thickness; The diameter of the drilling stress relief hole is 150 mm, the inducing hole is backfilled with drilling slag or dry sand, the stress relief hole is blocked with wooden board, measuring and recording, drilling, connecting the upper and lower, and the bottom is connected with the drainage gallery. To exclude dam seepage water. It satisfies the "seepage control and anti-seepage structure of RCC dam" itself, stable anti-seepage effect, adaptability to deformation, convenient construction and no interference.
10、 ·综合技术经济效益:  10. Comprehensive technical and economic benefits:
a.斜层平推铺筑涤与水平层铺筑法的施工比较, 如表 2所示 ,(以江垭筑坝 实绩为例) 的施工综合效率:  a. Comparison of the construction of the inclined layer flattening and the horizontal layer paving method, as shown in Table 2, (taking the performance of Jiangyan dam as an example) the comprehensive construction efficiency:
两种碾压混凝土铺筑法施工速度效益比较表  Comparison of construction speed efficiency of two kinds of roller compacted concrete paving method
Figure imgf000008_0002
Figure imgf000008_0002
*数字上行为统计的平均值; 下行为两种铺筑法相对比数。  * The average of the behavioral statistics on the number; the behavior is the relative ratio of the two paving methods.
从表 2所列数值表明, 斜层平推铺筑最适合于同一升程高度上的大仓面施 工, 水平层铺筑法效率为 100, 则斜层平推铺筑法为 143。 表 3, 通仓平层铺筑法与斜层平推铺筑法与优越性比较。
Figure imgf000009_0001
The values listed in Table 2 indicate that the inclined layer flat push paving is most suitable for the large warehouse surface at the same lift height. The efficiency of the horizontal layer paving method is 100, and the inclined layer paving method is 143. Table 3, comparison of the flat layer paving method and the inclined layer flat paving method and superiority.
Figure imgf000009_0001
更正页《细则第 91条) b.经济效益 Correction page "Rules 91" b. Economic benefits
以江垭坝的坝体碾压混凝土实绩为例,斜层平推铺筑法比水平层铺筑法的工效 提高 30 % ,提高经济效益 RMB26. 40元 / m3,省去隔缝模板及其两侧富浆胶凝浆 液的经济效益 RMB2. 30元 / m3Jiangya dam to dam RCC performance, for example, the swash layer placing method than the 30% efficiency level layer paving method, improving economic efficiency RMB26. 40 membered / m 3, eliminating the need for templates and Gap The economic benefit of the slurry-rich slurry on both sides is RMB 2.30/m 3 .
c.社会效益  c. Social benefits
建设拦河大坝水利枢纽工程,是防洪减灾,发掘水利电力资源的社会基础产业, 应用本专利技术,使施工过程简化,质量保证,进度加快,提早发挥工程功效,必 将产生显著的社会效益。  The construction of the river dam water conservancy project is a social basic industry for flood control and disaster mitigation, and the discovery of water conservancy and power resources. The application of this patented technology simplifies the construction process, ensures quality, speeds up the progress, and early exerts the project efficiency, which will certainly produce significant social benefits. .
d. 通仓平层铺筑法与斜层平推铺筑法优越性比较归纳如表 3。  d. The superiority of the flat-level paving method and the inclined layer flat-pushing method is summarized in Table 3.
更正页 细^第 91条)  Correction page Details ^Article 91)

Claims

权利 要 求 Rights request
1 . 一种用于碾压混凝土筑坝施工的斜层平推铺筑法, 它是由碾压混凝土 拌和, 运输, 切缝、 核子密度检测, 同时在邻近才莫板, 坝体内构造物和传统混 凝土交接部位应用富浆振实的碾压混凝土, 养生, 低温防护, 进行下一个浇筑 升程所组成的工艺 , 其特征是在斜层平推铺筑的施工进占方向与仓面的长度方 向一致, 浇筑升程 3 - 15个碾压层, 浇筑层厚度 0. 9 - 4. 5m,每个升程浇筑的混 凝土方量 2000 - 90000m3,斜层坡度 1 : 8 - 1 : 25进行放样, 在大坝岸坡基础岩 面上、 混凝土浇筑的起始和终了的端部与施工方向一致的侧向模板、 构造物、 经测绘标定出每个编号斜层碾压的确定位置; 铺筑砂桨之前的 "老" 混凝土层 面分两次处理, 第一次, 在计划浇筑施工和混凝土浇筑之前, 用 40MPa高压喷 射水沖刷, 笫二次, 在临近浇筑施工进占之前, 沿坡脚水平条带的区域, 清除 表面附着的由浇筑施工带来的污染物; 斜层摊铺, 在斜层摊铺碾压, 其中斜层 坡脚的水平条带, 前缘留出 30 - 50cni作为 "侧限", 不予碾压, 斜层碾压与水 平条带碾压面搭接 0. 5— lm,斜层平推铺筑施工前沿坡脚的水平条带的宽度小 于斜层铺筑的进占宽度, 使施工缝的间隔时间少于碾压混凝土斜层铺筑周期的 时间;碾压混凝土浇筑施工的收仓面, 第一次振捣致密之后 90- 120?nin, 混凝土 硬化达到重塑状态时, 富浆振实混凝土用曲波板振动, 坝体碾压混凝土用无振 樣压直至泛浆, 使大坝混凝土浇筑的施工缝结合更为致密。 1. A method for inclined layer paving of RCC dam construction, which is composed of roller compacted concrete mixing, transportation, slitting, nuclear density detection, and at the same time in the vicinity of the board, the structure of the dam body and The traditional concrete transfer site uses a slurry-grinding RCC, a health-care, low-temperature protection, and a process of the next pouring lift, which is characterized by the construction occupation direction of the inclined layer and the length direction of the storage surface. Consistently, pouring 3 - 15 rolling layers, pouring layer thickness 0. 9 - 4. 5m, concrete weight of each lift pouring 2000 - 90000m 3 , slope grade 1: 8 - 1: 25 for stakeout , on the foundation rock face of the dam bank slope, the starting and ending end of the concrete pouring, the lateral formwork and structure in the same direction as the construction direction, and the determined position of each numbered inclined layer rolling is marked by the surveying; The "old" concrete layer before the sand paddle is treated twice. For the first time, before the planned pouring construction and concrete pouring, it is washed with 40MPa high-pressure jet water, twice, before the pouring construction, the horizontal bar along the slope band The area, which removes the surface-attached contaminants caused by the pouring construction; the inclined layer paving, paving and rolling in the inclined layer, wherein the horizontal strip of the inclined slope foot, the front edge leaves 30 - 50cni as the "limit"", not rolling, the inclined layer rolling and the horizontal strip rolling surface overlap 0. 5 - lm, the width of the horizontal strip along the slope before the inclined layer paving construction is less than the width of the oblique layer paving , the interval between the construction joints is less than the time of the paving cycle of the roller compacted concrete; the closing surface of the roller compacted concrete pouring construction, 90-120?nin after the first vibrating compaction, when the concrete hardens to reach the remodeling state The rich pulp vibrating concrete is vibrated by the curved wave plate, and the dam body compacted concrete is pressed with no vibration to the slurry, so that the construction joint of the dam concrete pouring is more compact.
2、 根据权利要求 1所述的一种用于碾压混凝土筑坝施工的斜层平推铺筑法, 其特征在于利用在收仓面上的养生停歇时间, 在大坝横缝设计间距的 1/2处用 人工钻孔方法形成防止大坝上游面裂缝发生的诱导缝。  2. The inclined layer flat-pushing method for roller compacted concrete dam construction according to claim 1, characterized in that the health care stop time on the collection surface is used, and the spacing between the dam transverse joints is designed. At 1/2, an artificial drilling method is used to form an induced joint that prevents cracks from occurring on the upstream surface of the dam.
3、 根据权利要求 2所述的一种用于碾压混凝土筑坝施工的斜 J:平推铺筑法, 其特征在于诱导缝长度为 3米以上, 诱导缝的构成是紧临迎水坝面设置铜止水 部件 1道或 1道以上, 钻诱导孔直径为 38毫米, 间距 10公分, 钻深为 0. 7倍 混凝土浇筑升程厚度; 钻应力释放孔直径大于 150 mm, 诱导孔用钻渣或干砂回 填, 应力释放孔用木板封堵孔, 测量记录、 施钻、 使上、 下贯通, 底部与排水 廊道连通, 以排除大坝渗流水。  3. The inclined J: flat push paving method for roller compacted concrete dam construction according to claim 2, characterized in that the length of the induced joint is more than 3 meters, and the formation of the induced joint is close to the dam surface. Set the copper water stop parts 1 or more, the drill induction hole diameter is 38 mm, the spacing is 10 cm, the drilling depth is 0.7 times the concrete pouring lift thickness; the drilling stress relief hole diameter is greater than 150 mm, the induction hole is drilled The slag or dry sand is backfilled, and the stress relief hole is sealed with a wooden board to measure the record, drill, make the upper and lower through, and the bottom is connected with the drainage gallery to exclude the dam seepage water.
更正页(细则第 91条) Correction page (Article 91)
PCT/CN2004/000880 2004-07-29 2004-07-29 An incline bed and horizontal push method for constructing a dam with rolled concrete WO2006026888A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
PCT/CN2004/000880 WO2006026888A1 (en) 2004-07-29 2004-07-29 An incline bed and horizontal push method for constructing a dam with rolled concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/CN2004/000880 WO2006026888A1 (en) 2004-07-29 2004-07-29 An incline bed and horizontal push method for constructing a dam with rolled concrete

Publications (1)

Publication Number Publication Date
WO2006026888A1 true WO2006026888A1 (en) 2006-03-16

Family

ID=36036053

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2004/000880 WO2006026888A1 (en) 2004-07-29 2004-07-29 An incline bed and horizontal push method for constructing a dam with rolled concrete

Country Status (1)

Country Link
WO (1) WO2006026888A1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109750637A (en) * 2019-03-12 2019-05-14 中国电建集团中南勘测设计研究院有限公司 A kind of RCC dam structure
CN110396992A (en) * 2019-07-23 2019-11-01 中国电建集团贵阳勘测设计研究院有限公司 A kind of Face Slab of Concrete-faced Rockfill anti-crack construction technique
CN110593200A (en) * 2019-08-14 2019-12-20 中国电建集团贵阳勘测设计研究院有限公司 Seepage-proofing structure for construction joint of rockfill concrete dam and construction method thereof
CN112759315A (en) * 2020-12-21 2021-05-07 中国水利水电第九工程局有限公司 Construction method for dynamically controlling VC value of roller compacted concrete under complex weather condition
CN115012362A (en) * 2022-06-14 2022-09-06 中交上海航道局有限公司 Construction process of flood drainage channel for deep silt layer in intertidal zone

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0711618A (en) * 1993-01-14 1995-01-13 Shimizu Corp Dam concrete placing method and device
JPH07300842A (en) * 1994-05-02 1995-11-14 Shimizu Corp Construction method of dam
CN1232111A (en) * 1999-04-20 1999-10-20 姜长全 Inclined bed horizontal push spreading method for concrete rolling damming construction
JP2002069980A (en) * 2000-08-25 2002-03-08 Hazama Gumi Ltd Planar placing method of dam concrete

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0711618A (en) * 1993-01-14 1995-01-13 Shimizu Corp Dam concrete placing method and device
JPH07300842A (en) * 1994-05-02 1995-11-14 Shimizu Corp Construction method of dam
CN1232111A (en) * 1999-04-20 1999-10-20 姜长全 Inclined bed horizontal push spreading method for concrete rolling damming construction
JP2002069980A (en) * 2000-08-25 2002-03-08 Hazama Gumi Ltd Planar placing method of dam concrete

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109750637A (en) * 2019-03-12 2019-05-14 中国电建集团中南勘测设计研究院有限公司 A kind of RCC dam structure
CN110396992A (en) * 2019-07-23 2019-11-01 中国电建集团贵阳勘测设计研究院有限公司 A kind of Face Slab of Concrete-faced Rockfill anti-crack construction technique
CN110396992B (en) * 2019-07-23 2024-03-19 中国电建集团贵阳勘测设计研究院有限公司 Concrete face rockfill dam face anti-cracking construction process
CN110593200A (en) * 2019-08-14 2019-12-20 中国电建集团贵阳勘测设计研究院有限公司 Seepage-proofing structure for construction joint of rockfill concrete dam and construction method thereof
CN110593200B (en) * 2019-08-14 2024-03-19 中国电建集团贵阳勘测设计研究院有限公司 Anti-seepage structure for construction joint of rock-fill concrete dam and construction method thereof
CN112759315A (en) * 2020-12-21 2021-05-07 中国水利水电第九工程局有限公司 Construction method for dynamically controlling VC value of roller compacted concrete under complex weather condition
CN115012362A (en) * 2022-06-14 2022-09-06 中交上海航道局有限公司 Construction process of flood drainage channel for deep silt layer in intertidal zone
CN115012362B (en) * 2022-06-14 2023-07-21 中交上海航道局有限公司 Construction process of flood drainage canal of deep silt layer of intertidal zone

Similar Documents

Publication Publication Date Title
CN101906768B (en) Panel construction method of concrete faced rock-fill dam
CN106192907B (en) Add the construction method of 150m~300m grade high concrete panel rock-fill dams of cement sand and gravel structure sheaf
CN103556831B (en) Huge area is without muscle abrasion-proof concrete method for constructing terrace
CN107354917B (en) A kind of gravity rock and its construction method
CN110130278A (en) A kind of cementing rock-fill dams and its construction method
CN108914753A (en) A kind of airport asphalt concrete pavement preventive maintenance method
CN108797249A (en) The construction method of soft soil roadbed high roadbed steep slope road section Foam lightweight soil
WO2019007176A1 (en) Foam light soil railway subgrade structure and construction method
CN104652371B (en) The glue of crossing set up based on old dam coagulates rock-fill dams and construction method thereof
CN104514216A (en) Fill channel anti-frost heaving and anti-seepage structure and construction method
CN102943455A (en) Construction method for underwater mold bag concrete slope protection of river bank
CN206346075U (en) Side broad way based structures based on existing railway roadbed
CN209324375U (en) A kind of reparation structure of the poor highway tunnel lining cavity of pair of country rock
CN206245730U (en) A kind of cast-in-place pitched roof double template structure
WO2006026888A1 (en) An incline bed and horizontal push method for constructing a dam with rolled concrete
CN110004787A (en) Pier storage yard road concrete surface construction method
CN107142902A (en) High head and large flow tunneling boring damming method
CN105951676A (en) Interlocked wave-resistance protection slope precast block system and construction method
CN207567570U (en) A kind of Foam lightweight soil railway bed transition section structure
CN110055845A (en) A kind of construction method that highway bridge and culvert two sides are soft soil roadbed
CN205776083U (en) A kind of chain the guarding wave slope protection prefabricated section system
CN108867225A (en) The processing method of sinkhole within the scope of karst landform road foundation
CN111535323B (en) Full-section quasi-tertiary matching long-age roller compacted concrete construction method
CN104746507B (en) A kind of construction refuse regenerated draining CFG pile foundation and construction method thereof
CN114319875A (en) Seamless construction process for super-large-area concrete ground

Legal Events

Date Code Title Description
AK Designated states

Kind code of ref document: A1

Designated state(s): AE AG AL AM AT AU AZ BA BB BG BR BW BY BZ CA CH CN CO CR CU CZ DE DK DM DZ EC EE EG ES FI GB GD GE GH GM HR HU ID IL IN IS JP KE KG KP KR KZ LC LK LR LS LT LU LV MA MD MG MK MN MW MX MZ NA NI NO NZ OM PG PH PL PT RO RU SC SD SE SG SK SL SY TJ TM TN TR TT TZ UA UG US UZ VC VN YU ZA ZM ZW

AL Designated countries for regional patents

Kind code of ref document: A1

Designated state(s): BW GH GM KE LS MW MZ NA SD SL SZ TZ UG ZM ZW AM AZ BY KG KZ MD RU TJ TM AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IT LU MC NL PL PT RO SE SI SK TR BF BJ CF CG CI CM GA GN GQ GW ML MR NE SN TD TG

121 Ep: the epo has been informed by wipo that ep was designated in this application
NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase