CN105951676A - Interlocked wave-resistance protection slope precast block system and construction method - Google Patents
Interlocked wave-resistance protection slope precast block system and construction method Download PDFInfo
- Publication number
- CN105951676A CN105951676A CN201610450954.1A CN201610450954A CN105951676A CN 105951676 A CN105951676 A CN 105951676A CN 201610450954 A CN201610450954 A CN 201610450954A CN 105951676 A CN105951676 A CN 105951676A
- Authority
- CN
- China
- Prior art keywords
- slope
- prefabricated
- protection
- guarding
- wave
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/04—Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
- E02B3/12—Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
- E02B3/14—Preformed blocks or slabs for forming essentially continuous surfaces; Arrangements thereof
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Revetment (AREA)
Abstract
The invention discloses an interlocked wave-resistance protection slope precast block system and a construction method. The interlocked wave-resistance and protection slope precast block system comprises I-shaped precast protection slope blocks I (1) laid on a wave-resistance protection slope (3) with the gradient smaller than 1:2. The interlocked wave-resistance protection slope precast block system is characterized in that each precast protection slope block I (1) comprises flanges (1.1), a web (1.2), a groove section (1.3), flange inclined faces (1.4) and chamfers (1.5), wherein the flanges (1.1) are located at the upper end and the lower end of the precast protection slope block I (1), the web (1.2) is located in the middle of the precast protection slope block I (1), and the flange inclined faces (1.4) are located on transition sections between the flanges (1.1) and the web (1.2). The interlocked wave-resistance protection slope precast block system overcomes the defect that precast blocks are generally poured manually through a die in the prior art, and large gaps are liable to occur between the laid precast blocks. The interlocked wave-resistance protection slope precast block system has the beneficial effects that the small-size blocks are connected in a buckled manner, and other blocks cannot slide when a single block is damaged.
Description
Technical field
The invention belongs to the Hydraulic and Hydro-Power Engineering technical field such as dam and dyke, more specifically
It is a kind of chain the guarding wave slope protection prefabricated section system and construction method.
Background technology
In more than 90,000 reservoir dam of China, more than 95% is earth and rockfill dam, and earth and rockfill dam upstream is domatic to be subject to
Souring to wave must take effective safeguard procedures.Additionally, dyke building is too
Face bank protection protection problem.
The slope protection form conventional for above-mentioned engineering has: cast-in-place concrete bank protection, concrete are pre-
Clamp dog bank protection, stone masonry bank protection and dry stone pitching etc..Cast-in-place concrete bank protection and stone masonry protect
Slope, the problems such as the ability adapting to dam deformation is poor, the most cracking, dislocation destruction;Dry
Pitched work, mainly by manually building by laying bricks or stones, compares and takes a lot of work, and speed of application is relatively slow, and runs for many years
The easy air slaking of block stone, overall aesthetics is poor;Concrete precast block bank protection adapts to the energy of dam deformation
Power is strong, more attractive in appearance after laying, the most welcome.
For concrete precast block bank protection, difficulty of construction and construction quality are often pre-by bank protection
The impact of clamp dog monolithic weight is bigger.For normal hexagonal prefabricated section, because of its Parallel to the flow direction
Size is shorter, and in order to meet wave cut requirement, monolithic thickness is the biggest, affects engineering and throws
Money, its mutual gmatjpdumamics is the poorest, and prefabricated section typically uses mould manually to pour to form,
Bigger gap easily occurs between prefabricated section after laying, affects whole structure.
Summary of the invention
The first object of the present invention is to overcome the weak point of above-mentioned background technology, and proposes one
Plant chain the guarding wave slope protection prefabricated section system.
A kind of chain the guarding wave slope protection prefabricated section system of the present invention, it is included in the gradient less than 1:2's
The prefabricated slope-protection block I in I shape it is equipped with on the guarding wave slope protection;
It is characterized in that: described prefabricated slope-protection block I includes the edge of a wing, web, groove segment, the wing
Edge inclined-plane, chamfering;The described edge of a wing is positioned at the top and bottom of described prefabricated slope-protection block I,
Described web is positioned at the centre of described prefabricated slope-protection block I, and described inclined-plane, the edge of a wing is positioned at institute
Changeover portion between the edge of a wing and the web stated;Outside the upper surface of described prefabricated slope-protection block I
Sideline is provided with chamfering;The described inclined-plane, the edge of a wing at two ends is formed recessed with the side of described web
Groove section.
In technique scheme: the two of the length on a length of described edge of a wing of described web
Times.
In technique scheme: described prefabricated slope-protection block I join end to end be laid in described
On the guarding wave slope protection, and adjacent in left and right described in prefabricated slope-protection block I in, two of side are pre-
The edge of a wing of the top and bottom of slope-protection block I processed is stuck in the prefabricated slope-protection block I described in opposite side
On groove segment.
In technique scheme: a length of 80 centimetres of described prefabricated slope-protection block I, width
Being 30 centimetres, height is 20 centimetres;A length of 16 centimetres of the described edge of a wing, the edge of a wing is oblique
Face is 8 centimetres;Web is 32 centimetres.
In technique scheme: when the gradient is more than the guarding wave slope protection of 1:2, described is prefabricated
The lower surface of slope-protection block I is provided with groove segment region, and described groove segment region includes being positioned at institute
The web groove section at the web back side stated and excavating along the back side, the edge of a wing described in two ends, and extend to
The edge of a wing groove segment on described inclined-plane, the edge of a wing.
In technique scheme: the cutting depth in described groove segment region is super how described
/ 2nd of the height of prefabricated slope-protection block I;Described web groove section is long with described web
Degree, width are identical;Excavation starting point A of described edge of a wing groove segment is more than two points of edge of a wing length
One of.
The second object of the present invention is to overcome the weak point of above-mentioned background technology to propose one
Plant the construction method of chain the guarding wave slope protection prefabricated section system.
The construction method of a kind of chain the guarding wave slope protection prefabricated section system of the present invention, it is characterised in that:
Comprise the steps;
1., bank protection prefabricated section is made: rationally select coagulation according to prefabricated slope-protection block I strength grade
Soil match ratio, after match ratio job mix, will mix and stir material and import collecting bin, then will mix and stir
Material horizontal sliding, in steel form, is suppressed closely knit aftershaping by top hydraulic plate, is produced and design
The prefabricated slope-protection block I being consistent;
2., prefabricated section maintenance: prefabricated slope-protection block I, after machine pressing molding, is manually transported to put down
Whole solid prefabricated place, after the intensity of prefabricated slope-protection block I reaches 70%, can transport to
Dam facing;
3., dam facing finishing: clear up the guarding wave slope protection is domatic, remove weeds, tree root, broken
The foreign material such as stone, suitably finishing dam slope face.
4., laying Controling network is determined: utilize total powerstation and hydrolevelling device to measure location,
Checking the size of the guarding wave slope protection, measuring goes out to lay horizontal line and the datum line structure of prefabricated section
The Controling network become, and control point is done the most readily identified mark, determine the guarding wave slope protection
Construction surface size, in order to determine the quantity of the slope-protection block of laying;
5., on the guarding wave slope protection, be equipped with bed course in advance, bedding material select particle diameter D=1mm~
20mm and D50=10mm, < sand gravel of 5% fills on the guarding wave slope protection and presses clay content
Real, levelling the guarding wave slope protection, bed course thickness 10cm after compacting;
6., lay prefabricated section: during laying, the Controling network according to measured in advance is laid, lay
Time lay prefabricated slope-protection block I according to laying order from bottom to top is artificial;
7., locally vacancy casting concrete: the edge that the guarding wave slope protection is difficult to be laid use with
The concrete of prefabricated slope-protection block I equality strength is filled up, so that the guarding wave slope protection is domatic after Pu Sheing
Reach smooth aesthetic integrity requirement.
In technique scheme: step 6. in;Web in described prefabricated slope-protection block I
Lay towards with current flow to parallel, and the upper end of two prefabricated slope-protection block I of side and under
The edge of a wing of end is stuck on the groove segment in the prefabricated slope-protection block I described in opposite side.
In technique scheme: step 6. in;During the guarding wave slope protection described in laying;Described
The domatic 2m of meeting of the guarding wave slope protection in the range of irregularity degree control between-1 to 1cm.
The present invention has following technological merit: 1, the present invention is directed to earth and rockfill dam upstream dam slope wind-engaging
It is big, by parallel with water (flow) direction, due to prefabricated for the web laying direction of prefabricated section that wave washes away impact
The length in block web direction is much larger than width, can make full use of its features of shape, reduces stormy waves punching
Brush calculates the bank protection thickness required, cost saving;The most single prefabricated section weight reduces,
Reduce difficulty of construction.
2, the present invention is directed to domatic different gradient and be provided with two different form of I shape bank protection
Block, practical, applied widely.
3, the present invention uses the flexible connection mode that space articulating interlocks, and enhances protective slope structure
Stability in the large, it is possible to be effective against settlement deformation, frost heave, wave cut, earthquake
Destroy etc. external force.
4, present configuration is relatively easy, uses the compacting of machine scene, and not only work efficiency is high, can
Accelerating construction progress, and the prefabricated section consistent size of machine pressing, block quality is good, lays
Without jointing between rear block, smooth attractive in appearance.
5, the present invention uses the mutual snapping of small size block, will not because of the damage of single block,
Cause the slip of other block, it is simple to the maintenance of protective slope structure is changed.
Accompanying drawing explanation
Fig. 1 is that the gradient is less than the structural representation of prefabricated slope-protection block during 1:2.
Fig. 2 is the structural representation of the gradient prefabricated slope-protection block when being more than 1:2.
Fig. 3 is the structural representation side view of prefabricated slope-protection block.
Fig. 4 is the side view of the gradient prefabricated slope-protection block when being more than 1:2.
Fig. 5 is the rearview of the gradient prefabricated slope-protection block when being more than 1:2.
Fig. 6 is the mould schematic diagram of prefabricated slope-protection block.
Fig. 7 is the structural representation of existing prefabricated slope-protection block.
Fig. 8 be prefabricated slope-protection block specifically at the mounting structure schematic diagram of bank protection.
Fig. 9 is the concrete structure schematic diagram in Fig. 8 at B.
In figure: prefabricated slope-protection block I1, the edge of a wing 1.1, edge of a wing groove segment 1.1.1, web 1.2,
Web groove section 1.2.1, groove segment 1.3, inclined-plane, the edge of a wing 1.4, chamfering 1.5, groove segment region
2, the guarding wave slope protection 3.
Detailed description of the invention
Describe the performance of the present invention below in conjunction with the accompanying drawings in detail, but they are not intended that this
The restriction of invention, the most for example, will be become more by explanation advantages of the present invention simultaneously
Clear and easy to understand.
With reference to shown in Fig. 1-9: a kind of chain the guarding wave slope protection prefabricated section system of the present invention, it includes
The gradient the guarding wave slope protection 3 less than 1:2 is equipped with the prefabricated slope-protection block I1 in I shape;Its
Be characterised by: described prefabricated slope-protection block I1 include the edge of a wing 1.1, web 1.2, groove segment 1.3,
Inclined-plane, the edge of a wing 1.4, chamfering 1.5;The described edge of a wing 1.1 is positioned at described prefabricated slope-protection block I1
Top and bottom, described web 1.2 is positioned at the centre of described prefabricated slope-protection block I1, institute
The inclined-plane, the edge of a wing 1.4 stated changeover portion between the described edge of a wing 1.1 and web 1.2;?
The outer edge of the upper surface of described prefabricated slope-protection block I1 is provided with chamfering 1.5;Two ends described
The side of inclined-plane, the edge of a wing 1.4 and described web 1.2 form groove segment 1.3;Described web
The twice of the length on a length of described edge of a wing 1.1 of 1.2;Described prefabricated slope-protection block I1 is first
Tail is connected and is laid on described the guarding wave slope protection 3, and adjacent in left and right described in prefabricated bank protection
In block I1, the edge of a wing 1.1 of the top and bottom of two prefabricated slope-protection block I1 of side is stuck in separately
On the web 1.2 in prefabricated slope-protection block I1 described in side;Described prefabricated slope-protection block I length
Being 80 centimetres, width is 30 centimetres, and height is 20 centimetres;The length on the described edge of a wing 1.1
Degree is 16 centimetres, and inclined-plane, the edge of a wing 1.4 is 8 centimetres;Web 1.2 is 32 centimetres.
When the gradient is more than the guarding wave slope protection 3 of 1:2, the lower surface of described prefabricated slope-protection block I1
Being provided with groove segment region 2, described groove segment region 2 includes being positioned at described web 1.2
Web groove section 1.2.1 at the back side and excavating along the back side, the edge of a wing 1.1 described in two ends, and extend
Edge of a wing groove segment 1.1.1 to described inclined-plane, the edge of a wing 1.4.
The cutting depth in described groove segment region 2 is less than described prefabricated slope-protection block I1's
/ 2nd (H ≯ 1/2D) of height;Described web groove section 1.2.1 and described web
1.2 length, width are identical;Excavation starting point A of described edge of a wing groove segment 1.1.1 is more than the wing
/ 2nd (e ≮ 1/2a) of edge 1.1 length.
Present invention additionally comprises the construction method of a kind of chain the guarding wave slope protection prefabricated section system, including such as
Lower step;
1., bank protection prefabricated section is made: rationally select to mix according to prefabricated slope-protection block I1 strength grade
Solidifying soil match ratio, after match ratio job mix, will mix and stir material and import collecting bin, then will mix
With in material horizontal sliding to steel form, suppress closely knit aftershaping by top hydraulic plate, produce and set
The prefabricated slope-protection block I1 that meter is consistent;
2., prefabricated section maintenance: prefabricated slope-protection block I1, after machine pressing molding, is manually transported to
Smooth solid prefabricated place, after the intensity of prefabricated slope-protection block I1 reaches 70%, can transport
To dam facing;
3., dam facing finishing: clear up the guarding wave slope protection 3 is domatic, remove weeds, tree root,
The foreign material such as rubble, suitably finishing dam slope face.
4., laying Controling network is determined: utilize total powerstation and hydrolevelling device to measure location,
Checking the size of the guarding wave slope protection 3, measuring goes out to lay horizontal line and the datum line of prefabricated section
The Controling network constituted, and control point is done the most readily identified mark, determine the guarding wave slope protection
The construction surface size of 3, in order to determine the quantity of the slope-protection block of laying;
5., bedding material is laid: being equipped with bed course on the guarding wave slope protection 3 in advance, bedding material is selected
Particle diameter D=1mm~20mm and D50=10mm, < sand gravel of 5%, fills at wave resistance clay content
On bank protection 3 and be compacted, levelling the guarding wave slope protection 3, bed course thickness 10cm after compacting;
Compacting back pad layer thickness 10cm, the effect laying bed course is mainly the most levelling domatic 2. anti-filter
Effect, prevents soil particle in bank protection from being taken away by current;
6., lay prefabricated section: during laying, the Controling network according to measured in advance is laid, lay
Time lay prefabricated slope-protection block I1 according to laying order from bottom to top is artificial;
7., locally vacancy casting concrete: the edge being difficult to the guarding wave slope protection 3 lay uses
Fill up with the concrete of prefabricated slope-protection block I1 equality strength, so that the guarding wave slope protection 3 after Pu Sheing
Domatic reach smooth aesthetic integrity requirement.
Step 6. in;The laying of the web 1.2 in described prefabricated slope-protection block I1 towards with current
Flow to parallel, and the edge of a wing 1.1 of the top and bottom of two prefabricated slope-protection block I1 of side
It is stuck on the groove segment 1.3 in the prefabricated slope-protection block I1 described in opposite side.
Step 6. in;During the guarding wave slope protection 3 described in laying;Described the guarding wave slope protection 3 is domatic
In the range of meeting 2m, irregularity degree controls between-1 to 1cm.
Application example
According to " rolling earth-rock dam design specification " (SL274-2001), mix having outseam
Solidifying soil or armoured concrete slab bank protection, when dam slope gradient Coefficient m=2~5, plate is made at buoyancy
Can press with lower stable plate thickness
In formula: η coefficient, assembled protection slab is taken 1.1;
hPCumulative frequency is the wave height of 1%, m;
LmMean wavelength, m;
B is long to plate along dam slope, m;
ρcThe density of plate, t/m3,
ρwThe density of water, t/m3;
The gradient coefficient on the mono-slope of m, if toe is equal to α, i.e. equal to cot α.
According to modular formula, in same engineering, under identical design conditions, t ∝ b-1/3, i.e.
Concrete revetment block thickness t and slope-protection block along dam slope to the long b of plate1/3It is inversely proportional to, namely slope-protection block
The biggest to the long b of plate along dam slope, thickness t is the least for slope-protection block.
Note: for same engineering, hP、Lm、m、ρc、ρw, η be identical, t ∝ b-1/3。
According to above-mentioned formula, bank protection thickness is bigger by b (along dam slope to plate length) impact;Through surveying
Calculate, use I shape prefabricated section of the present invention, long to plate because increasing along dam slope, reduce along dam
Axis direction width, its thickness can reduce nearly 20% than traditional hexagon prefabricated section, reduce accordingly
Construction investment.
Certain large reservoir earth and rockfill dam runs for many years, and former dry stone pitching structural failure is serious, need to enter
Row consolidation process.By force and it is prone to construction, design in view of concrete precast block bank protection durability
Propose to use the bank protection mode of the chain concrete precast block of I shape, this engineering prefabricated slope-protection block chi
Very little for length L=80cm, width E=30cm, highly D=20cm, edge of a wing length a=16cm, abdomen
Plate length b=32cm, web width f=18cm, edge of a wing surface width c=8cm, chamfering deep
Degree h=1cm, after enforcement, dam facing is smooth attractive in appearance, achieves extraordinary protection effect.
The gradient of groove corresponding at inclined-plane, the edge of a wing 1.4 excavation is less than 1:1;
If taking the hexagon prefabricated section of identical weight, prefabricated section perspective view is (such as figure
7).According to " rolling earth-rock dam design rule " (SL274-2001) appendix A .2.3 concrete
It is the length of side that bank protection thickness equations can be calculated the size of the hexagon prefabricated section meeting condition
R=25cm, thickness J=24cm, and the I shape prefabricated section thickness under equal design conditions only needs
20cm, in the case of slope-protection block weight is identical, meets same anti-impact anti-floating effect, bank protection
Block thickness reduces 20%.Simultaneously compared to hexagon slope-protection block, I shape slope-protection block uses sky
Between be engaged the flexible connection mode of interlocking, enhance the stability in the large of protective slope structure, it is possible to have
The external force such as effect opposing settlement deformation, frost heave, wave cut, earthquake are destroyed.
I shape is added up with hexagonal laying quantity required
Slope-protection block form | Thickness (cm) | Surface area (m2) | Every 100m2Need slope-protection block quantity (block) |
I shape | 20 | 1920 | 521 |
Hexagonal | 24 | 1624 | 616 |
Wherein I shape prefabricated slope-protection block I needs cost about 10,000 yuan altogether, but six traditional limits
Shape slope-protection block needs about 10,000 5 thousand yuan, also demonstrates the economic valency of I shape prefabricated slope-protection block I
Value height, when the most large-area laying, has the prospect of well popularization.
Above-mentioned unspecified part is prior art.
Claims (9)
1. a chain the guarding wave slope protection prefabricated section system, it is included in the gradient and is equipped with the prefabricated slope-protection block I (1) in I shape less than on the guarding wave slope protection (3) of 1:2;
It is characterized in that: described prefabricated slope-protection block I (1) includes the edge of a wing (1.1), web (1.2), groove segment (1.3), inclined-plane, the edge of a wing (1.4), chamfering (1.5);The described edge of a wing (1.1) is positioned at the top and bottom of described prefabricated slope-protection block I (1), described web (1.2) is positioned at the centre of described prefabricated slope-protection block I (1), and described inclined-plane, the edge of a wing (1.4) is positioned at the changeover portion between the described edge of a wing (1.1) and web (1.2);Outer edge at the upper surface of described prefabricated slope-protection block I (1) is provided with chamfering (1.5);The described inclined-plane, the edge of a wing (1.4) at two ends forms groove segment (1.3) with the side of described web (1.2).
One the most according to claim 1 chain the guarding wave slope protection prefabricated section system, it is characterised in that: the twice of the length on a length of described edge of a wing (1.1) of described web (1.2).
One the most according to claim 1 chain the guarding wave slope protection prefabricated section system, it is characterized in that: described prefabricated slope-protection block I (1) joins end to end and is laid on described the guarding wave slope protection (3), and in the prefabricated slope-protection block I (1) described in adjacent in left and right, the edge of a wing (1.1) of the top and bottom of two prefabricated slope-protection block I (1) of side is stuck on the groove segment (1.3) in the prefabricated slope-protection block I (1) described in opposite side.
4. according to the chain the guarding wave slope protection prefabricated section system of the one described in any one in claim 1-3, it is characterised in that: a length of 80 centimetres of described prefabricated slope-protection block I, width is 30 centimetres, and height is 20 centimetres;A length of 16 centimetres of the described edge of a wing (1.1), inclined-plane, the edge of a wing (1.4) are 8 centimetres;Web (1.2) is 32 centimetres.
One the most according to claim 1 chain the guarding wave slope protection prefabricated section system, it is characterized in that: when the gradient is more than the guarding wave slope protection (3) of 1:2, the lower surface of described prefabricated slope-protection block I (1) is provided with groove segment region (2), described groove segment region (2) includes the web groove section (1.2.1) being positioned at described web (1.2) back side and excavates along the edge of a wing (1.1) back side described in two ends, and extends to the edge of a wing groove segment (1.1.1) on described inclined-plane, the edge of a wing (1.4).
One the most according to claim 5 chain the guarding wave slope protection prefabricated section system, it is characterised in that: the cutting depth in described groove segment region (2) is less than 1/2nd of described prefabricated slope-protection block I (1) height;Described web groove section (1.2.1) and described web (1.2) length, width are identical;Excavation starting point A of described edge of a wing groove segment (1.1.1) is more than 1/2nd of the edge of a wing (1.1) length.
The construction method of a kind of chain the guarding wave slope protection prefabricated section system the most as claimed in any of claims 1 to 6, it is characterised in that: comprise the steps;
1., bank protection prefabricated section is made: rationally select concrete mix according to prefabricated slope-protection block I (1) strength grade, after match ratio job mix, material will be mixed and stirred and import collecting bin, material horizontal sliding will be mixed and stirred again in steel form, suppress closely knit aftershaping by top hydraulic plate, produce and design the prefabricated slope-protection block I (1) being consistent;
2., prefabricated section maintenance: prefabricated slope-protection block I (1), after machine pressing molding, is manually transported to smooth solid prefabricated place, after the intensity of prefabricated slope-protection block I (1) reaches 70%, can transport to dam facing;
3., dam facing finishing: clear up the guarding wave slope protection (3) is domatic, remove the foreign material such as weeds, tree root, rubble, suitably finishing dam slope face.
4. laying Controling network, is determined: utilize total powerstation and hydrolevelling device to measure location, the size of the guarding wave slope protection (3) is checked, measuring goes out to lay horizontal line and the Controling network of datum line composition of prefabricated section, and control point is done the most readily identified mark, determine the construction surface size of the guarding wave slope protection (3), in order to determine the quantity of the slope-protection block of laying;
5., bedding material is laid: being equipped with bed course on the guarding wave slope protection (3) in advance, bedding material selects particle diameter D=1mm~20mm and D50=10mm, < sand gravel of 5% fills upper at the guarding wave slope protection (3) and is compacted, levelling the guarding wave slope protection (3), bed course thickness 10cm after compacting clay content;
6., lay prefabricated section: during laying, the Controling network according to measured in advance is laid, during laying, lay prefabricated slope-protection block I (1) according to laying order from bottom to top is artificial;
7., locally vacancy casting concrete: the edge that the guarding wave slope protection (3) is difficult to lay uses and the concrete of prefabricated slope-protection block I (1) equality strength is filled up, so that the guarding wave slope protection (3) is domatic after Pu Sheing reaches smooth aesthetic integrity requirement.
The construction method of a kind of chain the guarding wave slope protection prefabricated section system the most according to claim 7, it is characterised in that: step 6. in;Web (1.2) in described prefabricated slope-protection block I (1) lay towards with current flow to parallel, and the edge of a wing (1.1) of the top and bottom of two prefabricated slope-protection block I (1) of side is stuck on the groove segment (1.3) in the prefabricated slope-protection block I (1) described in opposite side.
The construction method of a kind of chain the guarding wave slope protection prefabricated section system the most according to claim 8, it is characterized in that: during the guarding wave slope protection (3) described in laying, in the range of described the guarding wave slope protection (3) the domatic 2m of meeting, irregularity degree controls between-1 to 1cm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610450954.1A CN105951676A (en) | 2016-06-21 | 2016-06-21 | Interlocked wave-resistance protection slope precast block system and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610450954.1A CN105951676A (en) | 2016-06-21 | 2016-06-21 | Interlocked wave-resistance protection slope precast block system and construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105951676A true CN105951676A (en) | 2016-09-21 |
Family
ID=56906920
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610450954.1A Pending CN105951676A (en) | 2016-06-21 | 2016-06-21 | Interlocked wave-resistance protection slope precast block system and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105951676A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108867551A (en) * | 2018-06-20 | 2018-11-23 | 广东水电二局股份有限公司 | A kind of the laying auxiliary device and laying method of the prefabricated hexagonal block of river levee slope protection |
CN109235365A (en) * | 2018-10-29 | 2019-01-18 | 中水电第十工程局(郑州)有限公司 | A kind of self-locking ecological revetment brick construction method |
CN112709191A (en) * | 2020-12-24 | 2021-04-27 | 黄河勘测规划设计研究院有限公司 | Prefabricated interlocking piece slope protection system suitable for check dam low reaches dam slope |
Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20000063592A (en) * | 2000-07-25 | 2000-11-06 | 김용태 | Metal mold making for concrete ornament block |
CN1572977A (en) * | 2003-06-24 | 2005-02-02 | 韩相姬 | Building blocks for bank protection |
KR100650501B1 (en) * | 2005-03-11 | 2006-11-29 | 주식회사 한길 | Environmental affinity type hydrophilic revetment block and construction method thereof |
CN201056702Y (en) * | 2007-05-24 | 2008-05-07 | 王保田 | Mutual embedded building blocks for slope protection and grass planting |
CN202157303U (en) * | 2011-05-19 | 2012-03-07 | 上海嘉洁生态型混凝土草坪有限公司 | Interlocking type composite ecologic concrete member |
CN202610766U (en) * | 2012-06-08 | 2012-12-19 | 金陵科技学院 | Hinged type ecological slope protection concrete block |
CN103758084A (en) * | 2014-01-27 | 2014-04-30 | 浙江水利水电学院 | Ecological river interlocking type building blocks and construction method for building protection ridge through building blocks |
CN103774617A (en) * | 2013-12-06 | 2014-05-07 | 浙江水利水电学院 | Mutually-embedded type slope protection building block and construction method thereof |
CN204456144U (en) * | 2015-01-07 | 2015-07-08 | 福建恒瑞新型建材有限公司 | A kind of comprehensive occlusal pattern slope vegetation protection brick |
CN205077446U (en) * | 2015-05-14 | 2016-03-09 | 交通运输部天津水运工程科学研究所 | A five pole type armor block that is used for seashore protection nature engineering |
CN105544465A (en) * | 2016-01-29 | 2016-05-04 | 俞向阳 | Bank protecting wall |
CN205776083U (en) * | 2016-06-21 | 2016-12-07 | 长江勘测规划设计研究有限责任公司 | A kind of chain the guarding wave slope protection prefabricated section system |
-
2016
- 2016-06-21 CN CN201610450954.1A patent/CN105951676A/en active Pending
Patent Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20000063592A (en) * | 2000-07-25 | 2000-11-06 | 김용태 | Metal mold making for concrete ornament block |
CN1572977A (en) * | 2003-06-24 | 2005-02-02 | 韩相姬 | Building blocks for bank protection |
KR100650501B1 (en) * | 2005-03-11 | 2006-11-29 | 주식회사 한길 | Environmental affinity type hydrophilic revetment block and construction method thereof |
CN201056702Y (en) * | 2007-05-24 | 2008-05-07 | 王保田 | Mutual embedded building blocks for slope protection and grass planting |
CN202157303U (en) * | 2011-05-19 | 2012-03-07 | 上海嘉洁生态型混凝土草坪有限公司 | Interlocking type composite ecologic concrete member |
CN202610766U (en) * | 2012-06-08 | 2012-12-19 | 金陵科技学院 | Hinged type ecological slope protection concrete block |
CN103774617A (en) * | 2013-12-06 | 2014-05-07 | 浙江水利水电学院 | Mutually-embedded type slope protection building block and construction method thereof |
CN103758084A (en) * | 2014-01-27 | 2014-04-30 | 浙江水利水电学院 | Ecological river interlocking type building blocks and construction method for building protection ridge through building blocks |
CN204456144U (en) * | 2015-01-07 | 2015-07-08 | 福建恒瑞新型建材有限公司 | A kind of comprehensive occlusal pattern slope vegetation protection brick |
CN205077446U (en) * | 2015-05-14 | 2016-03-09 | 交通运输部天津水运工程科学研究所 | A five pole type armor block that is used for seashore protection nature engineering |
CN105544465A (en) * | 2016-01-29 | 2016-05-04 | 俞向阳 | Bank protecting wall |
CN205776083U (en) * | 2016-06-21 | 2016-12-07 | 长江勘测规划设计研究有限责任公司 | A kind of chain the guarding wave slope protection prefabricated section system |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108867551A (en) * | 2018-06-20 | 2018-11-23 | 广东水电二局股份有限公司 | A kind of the laying auxiliary device and laying method of the prefabricated hexagonal block of river levee slope protection |
CN108867551B (en) * | 2018-06-20 | 2023-11-28 | 广东水电二局股份有限公司 | Auxiliary paving device and paving method for river levee slope protection prefabricated hexagonal blocks |
CN109235365A (en) * | 2018-10-29 | 2019-01-18 | 中水电第十工程局(郑州)有限公司 | A kind of self-locking ecological revetment brick construction method |
CN112709191A (en) * | 2020-12-24 | 2021-04-27 | 黄河勘测规划设计研究院有限公司 | Prefabricated interlocking piece slope protection system suitable for check dam low reaches dam slope |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100535254C (en) | Once forming construction technique for concrete panel rock fill dam bedding material and slope fixing mortar | |
CN103758084B (en) | A kind of ecological riverway interlocking type building block and construct the construction that protects bank | |
CN204530620U (en) | A kind of novel combination type Ecological Retaining Wall | |
CN104514216B (en) | A kind of canal on embankment frost heaving resistant leakage preventing structure and construction method | |
CN103774616A (en) | Construction method for ecological retaining wall built by self-embedded blocks | |
CN109653049B (en) | Construction method for processing bridge head filling road section on soft foundation | |
CN104846781A (en) | Ecological interlocking block and ecological interlocking block type slope protection construction method | |
CN113737747B (en) | Reservoir earth and rockfill dam upper reaches bank protection structure of breaking wave | |
CN111074844A (en) | Construction method of ecological interlocking revetment of river channel | |
CN107152012A (en) | Sluice construction technique | |
CN105951676A (en) | Interlocked wave-resistance protection slope precast block system and construction method | |
CN110306565A (en) | A kind of Road ecology slope protection system and construction method | |
CN104594297B (en) | A kind of double face slab rock-fill dams and construction method thereof | |
CN109487641A (en) | A kind of high-speed railway monoblock type cable slot structure and surface layer of subgrade bed construction method | |
CN211200281U (en) | Interlocking slope protection structure for river channel treatment | |
CN106702845B (en) | One kind preventing saline and alkaline permeable pavement structure | |
CN205776083U (en) | A kind of chain the guarding wave slope protection prefabricated section system | |
CN110747819A (en) | Concrete face rockfill dam with geotextile layer between bedding material and transition material | |
CN212272234U (en) | High-strength combined template for open groove section of large-section inclined shaft | |
CN103835310A (en) | Crib gravity retaining wall | |
CN207944429U (en) | Prefabricated interlock block for slope protection | |
CN108316237B (en) | Revetment retaining wall | |
CN109056762B (en) | Construction method of sea island beach dike | |
CN207878440U (en) | A kind of reinforcement composite foundation structure suitable for soft soil foundation | |
CN217710582U (en) | Rolling and pouring combined asphalt concrete straight core wall dam |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160921 |