CN110593200B - Anti-seepage structure for construction joint of rock-fill concrete dam and construction method thereof - Google Patents

Anti-seepage structure for construction joint of rock-fill concrete dam and construction method thereof Download PDF

Info

Publication number
CN110593200B
CN110593200B CN201910749742.7A CN201910749742A CN110593200B CN 110593200 B CN110593200 B CN 110593200B CN 201910749742 A CN201910749742 A CN 201910749742A CN 110593200 B CN110593200 B CN 110593200B
Authority
CN
China
Prior art keywords
layer
seepage
concrete
rock
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910749742.7A
Other languages
Chinese (zh)
Other versions
CN110593200A (en
Inventor
申林辉
宋思谕
魏彤彤
钟远福
陈建新
曾德军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201910749742.7A priority Critical patent/CN110593200B/en
Publication of CN110593200A publication Critical patent/CN110593200A/en
Application granted granted Critical
Publication of CN110593200B publication Critical patent/CN110593200B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/16Sealings or joints
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages
    • E02B7/04Dams across valleys
    • E02B7/06Earth-fill dams; Rock-fill dams

Abstract

The invention provides an impermeable structure for a construction joint of a rock-fill concrete dam, which comprises lower rock-fill concrete and a lower impermeable area arranged on one side of the lower rock-fill concrete. According to the invention, the water stop belt is arranged in the middle of the upstream seepage prevention area of each layer of construction joint surface of the rock-fill concrete dam, and is embedded in the lower layer of concrete and the upper layer of concrete, so that water seepage between the layers of construction joint surfaces of the rock-fill concrete dam can be effectively prevented, the influence on the durability and engineering appearance quality of dam concrete due to water seepage between the layers is avoided, a foundation is laid for building a water-tight dam, the phenomenon of water seepage between the layers on the downstream surface of the dam after water is stored in the reservoir is avoided, and the problem of water seepage of the construction joint surface is solved; on the premise of achieving the same effect, the invention has the advantages of simple structure, simple construction process, high construction speed, no need of special materials, low cost of galvanized iron sheet, light weight, energy conservation and environmental protection, and saves engineering investment compared with the traditional process.

Description

Anti-seepage structure for construction joint of rock-fill concrete dam and construction method thereof
Technical Field
The invention relates to an impermeable structure for a construction joint of a rock-fill concrete dam and a construction method thereof, and belongs to the technical field of rock-fill concrete dams.
Background
The rock-fill concrete is a novel concrete proposed by Qinghua university, and is a novel large-volume concrete construction mode developed on the basis of self-compacting concrete technology. The method comprises the steps of firstly directly putting large-grain-size rock piles into a bin to form rock piles with gaps, then pouring specially developed low-hydration-heat low-cost self-compacting concrete from the upper part of the rock piles, and filling the self-compacting concrete into the gaps of the rock piles by utilizing the high-flow segregation-resistant performance of the self-compacting concrete by virtue of self weight to form complete, compact, high-strength, low-hydration-heat and low-shrinkage-deformation mass concrete.
The rock-fill concrete adopts a construction mode of rock block layered stacking and self-compacting concrete layered filling, and the layered height is generally controlled to be 1.5-2 m, so that a horizontal construction joint exists. The quality of the joint surface combination treatment of the construction is related to the seepage prevention, stability, durability and the like of the dam after the reservoir is filled, and is the key point of the dam construction quality control.
In construction practice, rock-fill concrete layering rock-fill can't avoid rock block collision to smash stone dust and rubble to fall on horizontal construction joint face in the rock-fill process, smash stone dust and rubble to lie in the rock-fill bottom, can not clear up, causes the concrete placement back construction joint face to combine poorly. In addition, in the concrete pouring process, the concrete is forced to stop pouring due to other reasons, the treatment of the bin surface can only be carried out on the roughening or the scouring treatment of the concrete in the seepage-proofing areas on the upstream side and the downstream side, and the middle rockfill concrete area cannot be treated, so that the possibility of interlayer water seepage of the concrete construction joints is increased, and the phenomenon of interlayer water seepage on the downstream side of the dam after water storage of the reservoir sometimes occurs. The interlayer water seepage phenomenon after the dam is built is difficult to treat, so that the dam is difficult to treat at high cost, the ideal effect is difficult to achieve, and meanwhile, the durability of the concrete is reduced due to the interlayer water seepage, and the engineering appearance quality is seriously influenced. The traditional interlayer water seepage of the rockfill concrete dam treatment adopts a method of arranging an impermeable layer on the upstream and downstream surfaces of the dam body, wherein the impermeable layer is a polyurea elastomer impermeable layer obtained by adopting a spin-spray film construction method or other construction methods, however, the impermeable layer construction process is complex, the comprehensive cost is high, and the field quality control requirement is high, so that the impermeable layer is difficult to adopt in engineering construction.
Disclosure of Invention
In order to solve the technical problems, the invention provides the anti-seepage structure of the construction joint of the rock-fill concrete dam and the construction method thereof, and the anti-seepage structure of the construction joint of the rock-fill concrete dam and the construction method thereof have the advantages of simple structure, simple construction process, high construction speed, no need of special materials, low cost of galvanized iron sheet, light weight, energy conservation and environmental protection, and saving of engineering investment compared with the traditional process.
The invention is realized by the following technical scheme.
The invention provides an impermeable structure for a construction joint of a rock-fill concrete dam, which comprises lower rock-fill concrete and a lower impermeable area arranged on one side of the lower rock-fill concrete; the method is characterized in that: the upper end face of the lower-layer rock-fill concrete is provided with an upper-layer rock-fill concrete, one side of the upper-layer rock-fill concrete is provided with an upper-layer seepage-proofing area, and the positions of the upper-layer seepage-proofing area and the lower-layer seepage-proofing area correspond to each other; the same construction joint surface exists between the lower layer rock-fill concrete and the upper layer rock-fill concrete and between the lower layer seepage-proofing area and the upper layer seepage-proofing area; and a water stop belt is arranged on the vertical construction joint surface, one end of the water stop belt is arranged in the upper impermeable zone, and the other end of the water stop belt is arranged in the lower impermeable zone.
The water stop belt is horizontally arranged on the whole dam surface along the axial direction of the dam.
The lower impermeable zone is positioned on the upstream surface of the lower rockfill concrete, and the upper impermeable zone is positioned on the upstream surface of the upper rockfill concrete.
One end of the water stop belt is positioned in the middle of the lower impermeable zone, and the other end of the water stop belt is positioned in the middle of the upper impermeable zone.
The construction joint surface is provided with a plurality of layers, and the water stop belt is arranged on each layer of construction joint surface below the normal water storage level of the rock-fill concrete dam.
The construction method based on the seepage-proofing structure of the construction joint of the continuous rock-fill concrete dam comprises the following steps:
(1) constructing lower-layer rock-fill concrete, constructing a lower-layer seepage-proofing area on one side of the lower-layer rock-fill concrete, and forming a construction joint surface at the tops of the lower-layer rock-fill concrete and the lower-layer seepage-proofing area after construction is completed;
(2) after the self-compaction concrete pouring of the lower anti-seepage area is finished, before the initial setting of the concrete, horizontally arranging a water stop belt at the middle position in the lower anti-seepage area at the upstream of the construction joint surface along the axial direction of the dam, wherein one end of the water stop belt is embedded into the lower anti-seepage area at the upstream surface, and the other end of the water stop belt is exposed;
(3) manually finishing and trowelling concrete in the seepage-proofing area of the lower layer, and punching or roughening the construction joint surface;
(4) on the construction joint surface, constructing upper-layer rock-fill concrete corresponding to the position of the lower-layer rock-fill concrete and constructing an upper-layer seepage-proofing area corresponding to the position of the lower-layer seepage-proofing area;
(5) after the construction of the upper rock-fill concrete and the upper impermeable zone is completed, the exposed section of the water stop belt is embedded into the upper impermeable zone of the upstream surface.
In the step (2), the water stop is arranged on the whole dam face and is mutually perpendicular to the construction joint face.
The construction joint surface is provided with a plurality of layers, and the water stop belt is arranged on each layer of construction joint surface below the normal water storage level of the rock-fill concrete dam.
The invention has the beneficial effects that: arranging a water stop belt in the middle of an upstream seepage prevention area of each layer of construction joint surface of the rock-fill concrete dam, wherein the water stop belt is embedded in lower layer concrete and upper layer concrete, so that water seepage between the layers of construction joint surfaces of the rock-fill concrete dam can be effectively prevented, the influence on the durability and engineering appearance quality of dam concrete due to water seepage between the layers is avoided, a foundation is laid for building a water-tight dam, the phenomenon of water seepage between the layers on the downstream surface of the dam after water is stored in a reservoir is avoided, and the problem of water seepage of the construction joint surfaces is solved; on the premise of achieving the same effect, the invention has the advantages of simple structure, simple construction process, high construction speed, no need of special materials, low cost of galvanized iron sheet, light weight, energy conservation and environmental protection, and saves engineering investment compared with the traditional process.
Drawings
FIG. 1 is a schematic diagram of the structure of the present invention;
in the figure: 1-lower layer rock-fill concrete, 2-upper layer rock-fill concrete, 3-lower layer seepage-proofing area, 4-upper layer seepage-proofing area, 5-construction joint surface and 6-water stop.
Detailed Description
The technical solution of the present invention is further described below, but the scope of the claimed invention is not limited to the above.
As shown in fig. 1, the impermeable structure for the construction joint of the rockfill concrete dam comprises lower rockfill concrete 1 and a lower impermeable zone 3 arranged on one side of the lower rockfill concrete 1; the method is characterized in that: the upper end face of the lower-layer rock-fill concrete 1 is provided with an upper-layer rock-fill concrete 2, one side of the upper-layer rock-fill concrete 2 is provided with an upper-layer impermeable zone 4, and the upper-layer impermeable zone 4 corresponds to the lower-layer impermeable zone 3 in position; the same construction joint surface 5 exists between the lower layer rock-fill concrete 1 and the upper layer rock-fill concrete 2, and between the lower layer seepage-proofing area 3 and the upper layer seepage-proofing area 4; and a water stop belt 6 is arranged on the vertical construction joint surface 5, one end of the water stop belt 6 is arranged in the upper impermeable zone 4, and the other end is arranged in the lower impermeable zone 3.
The water stop belt 6 is horizontally arranged on the whole dam surface along the axial direction of the dam.
The lower impermeable zone 3 is positioned on the upstream surface of the lower rockfill concrete 1, and the upper impermeable zone 4 is positioned on the upstream surface of the upper rockfill concrete 2.
One end of the water stop 6 is positioned in the middle of the lower impermeable zone 3, and the other end is positioned in the middle of the upper impermeable zone 4.
The construction joint surface 5 is provided with a plurality of layers, and the water stop belt 6 is arranged on each layer of construction joint surface 5 below the normal water storage level of the rockfill concrete dam.
The construction method based on the seepage-proofing structure of the construction joint of the continuous rock-fill concrete dam comprises the following steps:
(1) constructing a lower-layer rock-fill concrete 1, constructing a lower-layer seepage-proofing area 3 on one side of the lower-layer rock-fill concrete 1, and forming a construction joint surface 5 at the tops of the lower-layer rock-fill concrete 1 and the lower-layer seepage-proofing area 3 after construction is completed;
(2) after the self-compaction concrete pouring of the lower anti-seepage area 3 is finished, before the initial setting of the concrete, horizontally arranging a water stop belt 6 along the axial direction of the dam at the middle position inside the lower anti-seepage area 3 at the upstream of the construction joint surface 5, wherein one end of the water stop belt 6 is embedded into the lower anti-seepage area 3 at the upstream surface, and the other end is exposed;
(3) manually finishing and trowelling the concrete of the lower impermeable zone 3, and punching or roughening the construction joint surface 5;
(4) on the construction joint surface 5, the upper layer rock-fill concrete 2 is constructed corresponding to the position of the lower layer rock-fill concrete 1, and the upper layer seepage-proofing area 4 is constructed corresponding to the position of the lower layer seepage-proofing area 3;
(5) after the construction of the upper layer rock-fill concrete 2 and the upper layer seepage-proofing area 4 is completed, the exposed section of the water stop 6 is embedded into the upper layer seepage-proofing area 4 on the upstream surface.
In the step (2), the water stop 6 is arranged on the whole dam surface and is mutually perpendicular to the construction joint surface 5.
The construction joint surface 5 is provided with a plurality of layers, and the water stop belt 6 is arranged on each layer of construction joint surface 5 below the normal water storage level of the rockfill concrete dam.
Preferably, the water stop 6 is disconnected when meeting the dam body structural joint and is respectively arranged in the lower impermeable zone 3 and the upper impermeable zone 4.
Preferably, the water stop 6 is made of galvanized iron sheet with the thickness of 0.5mm, the width of 40cm, and is embedded into the lower impermeable zone 3 for 20cm and the upper impermeable zone 4 for 20cm.
Examples
As described above, in the construction joint seepage-proofing structure of the rockfill concrete dam, the lower rockfill concrete 1 and the lower seepage-proofing area 3 on the upstream thereof are firstly constructed, the construction joint surface 5 is formed after construction is completed, the water stop belt 6 is horizontally arranged along the axial direction of the dam at the middle position inside the lower seepage-proofing area on the upstream of the construction joint surface 5 before initial setting of concrete after the self-compacting concrete pouring of the lower seepage-proofing area 3 is completed, and the water stop belt 6 is arranged on the whole dam surface and is perpendicular to the construction joint surface 5 and is disconnected when meeting the structural joint of the dam body.
Further, the water stop 6 is made of galvanized iron sheet with the thickness of 0.5mm, the width is 40cm, the water stop is embedded into the lower impermeable zone 3 for 20cm, and the water stop leaks out of the surface of the construction joint surface 5 for 20cm.
Secondly, after the water stop 6 is installed, the lower seepage-proofing area 3 of the upstream surface is smoothed by manually finishing the surface, and the construction joint surface 5 is punched or roughened according to a conventional construction joint surface treatment method.
Finally, after the construction of the upper-layer rockfill concrete 2 and the upper-layer seepage-proofing area 4 on the upper side of the upper-layer rockfill concrete 2 is completed, the water stop belt 6 is embedded into the upper-layer seepage-proofing area 4 of the upper-layer rockfill concrete 2 by 20cm, and finally, the seepage-proofing and water stop structure of the construction joint surface is formed.
Furthermore, the seepage prevention structure is arranged on each layer of construction joint surface 5 below the normal water storage level of the rock-fill concrete dam, namely, the seepage prevention structure can be arranged in a plurality of layers below the normal water storage level of the rock-fill concrete dam, and can effectively prevent water seepage between the construction joint surfaces of the rock-fill concrete dam.

Claims (6)

1. The construction method of the anti-seepage structure of the construction joint of the rockfill concrete dam comprises lower-layer rockfill concrete (1) and a lower-layer anti-seepage area (3) arranged on one side of the lower-layer rockfill concrete (1); the method is characterized in that: the upper end face of the lower-layer rock-fill concrete (1) is provided with an upper-layer rock-fill concrete (2), one side of the upper-layer rock-fill concrete (2) is provided with an upper-layer seepage-proofing area (4), and the positions of the upper-layer seepage-proofing area (4) and the lower-layer seepage-proofing area (3) correspond; the same construction joint surface (5) exists between the lower-layer rock-fill concrete (1) and the upper-layer rock-fill concrete (2) and between the lower-layer seepage-proofing area (3) and the upper-layer seepage-proofing area (4); a water stop belt (6) is arranged on the vertical construction joint surface (5), one end of the water stop belt (6) is arranged in the upper impermeable zone (4), and the other end is arranged in the lower impermeable zone (3);
the construction method comprises the following steps:
(1) constructing a lower-layer rock-fill concrete (1), constructing a lower-layer seepage-proofing area (3) on one side of the lower-layer rock-fill concrete (1), and forming a construction joint surface (5) at the tops of the lower-layer rock-fill concrete (1) and the lower-layer seepage-proofing area (3) after construction is completed;
(2) after the self-compaction concrete pouring of the lower anti-seepage area (3) is finished, before the initial setting of the concrete, a water stop belt (6) is horizontally arranged at the middle position inside the lower anti-seepage area (3) at the upstream of the construction joint surface (5) along the axial direction of the dam, one end of the water stop belt (6) is embedded into the lower anti-seepage area (3) at the upstream surface, and the other end of the water stop belt is exposed;
(3) manually finishing and trowelling the concrete of the lower impermeable zone (3), and punching or roughening the construction joint surface (5);
(4) on the construction joint surface (5), constructing an upper-layer rock-fill concrete (2) corresponding to the position of the lower-layer rock-fill concrete (1) and constructing an upper-layer seepage-proofing area (4) corresponding to the position of the lower-layer seepage-proofing area (3);
(5) after the construction of the upper rock-fill concrete (2) and the upper impermeable zone (4) is completed, the exposed section of the water stop belt (6) is embedded into the upper impermeable zone (4) on the upstream surface;
in the step (2), the water stop belt (6) is arranged on the whole dam surface and is mutually perpendicular to the construction joint surface (5).
2. The construction method of the rockfill concrete dam construction joint seepage-proofing structure according to claim 1, wherein the construction method comprises the following steps: the water stop belt (6) is horizontally arranged on the whole dam surface along the axial direction of the dam.
3. The construction method of the rockfill concrete dam construction joint seepage-proofing structure according to claim 1, wherein the construction method comprises the following steps: the lower impermeable area (3) is positioned on the upstream surface of the lower rockfill concrete (1), and the upper impermeable area (4) is positioned on the upstream surface of the upper rockfill concrete (2).
4. The construction method of the rockfill concrete dam construction joint seepage-proofing structure according to claim 1, wherein the construction method comprises the following steps: one end of the water stop belt (6) is positioned in the middle of the lower impermeable zone (3), and the other end of the water stop belt is positioned in the middle of the upper impermeable zone (4).
5. The construction method of the rockfill concrete dam construction joint seepage-proofing structure according to claim 1, wherein the construction method comprises the following steps: the construction joint surface (5) is provided with a plurality of layers, and the water stop belt (6) is arranged on each layer of construction joint surface (5) below the normal water storage level of the rock-fill concrete dam.
6. The construction method of the rockfill concrete dam construction joint seepage-proofing structure according to claim 1, wherein the construction method comprises the following steps: the construction joint surface (5) is provided with a plurality of layers, and the water stop belt (6) is arranged on each layer of construction joint surface (5) below the normal water storage level of the rock-fill concrete dam.
CN201910749742.7A 2019-08-14 2019-08-14 Anti-seepage structure for construction joint of rock-fill concrete dam and construction method thereof Active CN110593200B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910749742.7A CN110593200B (en) 2019-08-14 2019-08-14 Anti-seepage structure for construction joint of rock-fill concrete dam and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910749742.7A CN110593200B (en) 2019-08-14 2019-08-14 Anti-seepage structure for construction joint of rock-fill concrete dam and construction method thereof

Publications (2)

Publication Number Publication Date
CN110593200A CN110593200A (en) 2019-12-20
CN110593200B true CN110593200B (en) 2024-03-19

Family

ID=68854454

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910749742.7A Active CN110593200B (en) 2019-08-14 2019-08-14 Anti-seepage structure for construction joint of rock-fill concrete dam and construction method thereof

Country Status (1)

Country Link
CN (1) CN110593200B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112962536B (en) * 2021-02-09 2022-08-30 中国水电基础局有限公司 Seepage-proofing structure for construction joint of rockfill concrete dam and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2006026888A1 (en) * 2004-07-29 2006-03-16 Lichen Yang An incline bed and horizontal push method for constructing a dam with rolled concrete
CN103924554A (en) * 2014-04-17 2014-07-16 黄河勘测规划设计有限公司 Water stopping method of peripheral joint of concrete face rockfill dam built on deep covering layer
CN105297680A (en) * 2015-11-29 2016-02-03 中国水利水电科学研究院 Antiseismic design method of impervious body of 200 m high concrete face rockfill dam
CN207314284U (en) * 2017-09-11 2018-05-04 中国电建集团北京勘测设计研究院有限公司 Leakage preventing structure in a kind of dam of narrow steep river valley rockfill dam with asphalt concrete core
CN208219568U (en) * 2018-04-20 2018-12-11 中国电建集团贵阳勘测设计研究院有限公司 A kind of surface watertight seal structure for concrete face rockfill dam
CN110080172A (en) * 2019-05-13 2019-08-02 辽宁工程技术大学 A kind of core wall rockfill dam and its construction method with high barrier property energy
CN210827336U (en) * 2019-08-14 2020-06-23 中国电建集团贵阳勘测设计研究院有限公司 Rockfill concrete dam construction joint seepage prevention structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2006026888A1 (en) * 2004-07-29 2006-03-16 Lichen Yang An incline bed and horizontal push method for constructing a dam with rolled concrete
CN103924554A (en) * 2014-04-17 2014-07-16 黄河勘测规划设计有限公司 Water stopping method of peripheral joint of concrete face rockfill dam built on deep covering layer
CN105297680A (en) * 2015-11-29 2016-02-03 中国水利水电科学研究院 Antiseismic design method of impervious body of 200 m high concrete face rockfill dam
CN207314284U (en) * 2017-09-11 2018-05-04 中国电建集团北京勘测设计研究院有限公司 Leakage preventing structure in a kind of dam of narrow steep river valley rockfill dam with asphalt concrete core
CN208219568U (en) * 2018-04-20 2018-12-11 中国电建集团贵阳勘测设计研究院有限公司 A kind of surface watertight seal structure for concrete face rockfill dam
CN110080172A (en) * 2019-05-13 2019-08-02 辽宁工程技术大学 A kind of core wall rockfill dam and its construction method with high barrier property energy
CN210827336U (en) * 2019-08-14 2020-06-23 中国电建集团贵阳勘测设计研究院有限公司 Rockfill concrete dam construction joint seepage prevention structure

Also Published As

Publication number Publication date
CN110593200A (en) 2019-12-20

Similar Documents

Publication Publication Date Title
CN201865127U (en) Reinforced waterproof late poured band of basement bottom plate
CN204023501U (en) A kind of reinforcement Anti-seeping technology structure for earth and rockfill dam
CN207760804U (en) A kind of Multi-functional economy dike structure
CN202483588U (en) Self water-proof drainage system of tunnel lining
CN111395267A (en) Core wall rock-fill dam
CN105350511A (en) Border dike water bag strip, water storing border dike, and method for performing water bag strip pile-loading and prepressing
CN110593200B (en) Anti-seepage structure for construction joint of rock-fill concrete dam and construction method thereof
CN111472326A (en) Method and structure for building gravity dam on deep covering layer
CN212248108U (en) Core wall rock-fill dam
CN210827336U (en) Rockfill concrete dam construction joint seepage prevention structure
CN104060628B (en) The preparation method of free from flaw, leakproof overlarge area basement terrace and structure
CN105756100A (en) Basement post-pouring belt system and making method thereof
CN205369320U (en) Basement post -cast strip leakage protective system
CN110747819A (en) Concrete face rockfill dam with geotextile layer between bedding material and transition material
CN110331701A (en) Integral prefabricated type sluice chamber structure and its construction method on a kind of soft soil foundation
CN204849791U (en) Structure of earth rock cofferdam prevention of seepage system
CN213203978U (en) Ecological flood bank structure
CN212533930U (en) Slope protection for antiseep water conservancy flood control
CN206035047U (en) Prefabricated assembled underground granary of plastic cover
CN205421157U (en) Reinforced earth quaywall structure based on soft base of mud flat
CN205975937U (en) Underground tank of disconnect -type
CN104762924A (en) Upper storage reservoir basin seepage preventing method
CN201065524Y (en) Vertical dike
CN217870312U (en) Anti-seepage structure of roller compacted concrete dam
CN110512571A (en) A kind of RCC dam and its construction method containing rock-fill concrete core-wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant