WO2002052105A1 - Ballast removal method and apparatus - Google Patents

Ballast removal method and apparatus Download PDF

Info

Publication number
WO2002052105A1
WO2002052105A1 PCT/GB2001/005796 GB0105796W WO02052105A1 WO 2002052105 A1 WO2002052105 A1 WO 2002052105A1 GB 0105796 W GB0105796 W GB 0105796W WO 02052105 A1 WO02052105 A1 WO 02052105A1
Authority
WO
WIPO (PCT)
Prior art keywords
ballast
bed
excavation
boom
conveyor belt
Prior art date
Application number
PCT/GB2001/005796
Other languages
French (fr)
Inventor
Allan Law Steel
William Richard Davies
Original Assignee
Dbt Gb Limited
Jarvis Fastline Limited
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dbt Gb Limited, Jarvis Fastline Limited filed Critical Dbt Gb Limited
Priority to DE60130254T priority Critical patent/DE60130254T2/en
Priority to EP01272123A priority patent/EP1348057B1/en
Publication of WO2002052105A1 publication Critical patent/WO2002052105A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F7/00Equipment for conveying or separating excavated material
    • E02F7/02Conveying equipment mounted on a dredger
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B27/00Placing, renewing, working, cleaning, or taking-up the ballast, with or without concurrent work on the track; Devices therefor; Packing sleepers
    • E01B27/04Removing the ballast; Machines therefor, whether or not additionally adapted for taking-up ballast
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/18Dredgers; Soil-shifting machines mechanically-driven with digging wheels turning round an axis, e.g. bucket-type wheels
    • E02F3/20Dredgers; Soil-shifting machines mechanically-driven with digging wheels turning round an axis, e.g. bucket-type wheels with tools that only loosen the material, i.e. mill-type wheels
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F5/00Dredgers or soil-shifting machines for special purposes
    • E02F5/22Dredgers or soil-shifting machines for special purposes for making embankments; for back-filling
    • E02F5/223Dredgers or soil-shifting machines for special purposes for making embankments; for back-filling for back-filling
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2203/00Devices for working the railway-superstructure
    • E01B2203/01Devices for working the railway-superstructure with track
    • E01B2203/017Devices for working the railway-superstructure with track removed or not present yet
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2203/00Devices for working the railway-superstructure
    • E01B2203/02Removing or re-contouring ballast
    • E01B2203/028Alternative ways
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2203/00Devices for working the railway-superstructure
    • E01B2203/03Displacing or storing ballast
    • E01B2203/032Displacing or storing ballast with special use or configuration of conveyor belts
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2203/00Devices for working the railway-superstructure
    • E01B2203/03Displacing or storing ballast
    • E01B2203/034Displacing or storing ballast using storing containers
    • E01B2203/038Displacing or storing ballast using storing containers detachable from the vehicle

Definitions

  • This invention relates to a method and an apparatus for removing ballast from a road bed and, more particularly, to an improved method and apparatus for removing ballast from a rail road bed, which apparatus can be controlled by a sole operator using a single vehicle to lift and remove ballast.
  • ballast material When preparing an area of ground for the laying of a road or railroad, the designated area is excavated and ballast material is laid along the route.
  • the ballast material generally takes the form of gravel or broken stone and, in the case of a railroad, is placed on the excavated bed to provide a firm surface upon which the track is supported.
  • the ballast also functions to hold the track in position when laid.
  • the ballast material facilitates drainage of surface water from the rail bed to avoid flooding in bad weather.
  • the ballast may become dislodged from the rail bed or, in some cases where safety checks or rail maintenance operations must be carried out, the ballast may require removal either for replacement or cleaning operations to be carried out. This is particularly important if the ballast becomes clogged with dirt and debris as the proper drainage function will be impaired which could lead to flooding in low lying areas thereby requiring further safety operations to be carried out on the same stretch of track.
  • ballast Traditional methods of removing ballast require the removal of the rails, which are stored at a location perhaps adjacent to the railway line. A fleet of vehicles is then transported to the site to handle the removal operation. It is not unusual for at least 4 separate vehicles to be required, with personnel required for each vehicle .
  • Ballast is dug up from the rail bed for example using suitable earth moving equipment and the recovered ballast is then loaded into wagons to be removed from the site. Often the area in which the operation is taking place is difficult to access from road networks and this can add further time delays caused by the removal operation itself.
  • the present invention aims to provide a method and apparatus for removing ballast from a road way and particularly from a railway line, which overcomes or at least mitigates some of the above mentioned disadvantages which are associated with traditional methods and apparatus used for removing ballast from such locations.
  • a continuous method of removing ballast material particularly from a railway line bed comprising the steps positioning an excavation apparatus at the work site, advancing the apparatus along the bed, introducing ballast into the apparatus at one end thereof, conveying ballast from the excavation site through the apparatus to a selectively positionable delivery means at the other end of the apparatus remote from the excavation site, from which the ballast is fed to a containment means for collection.
  • an apparatus for the continual excavation and collection of ballast particularly from a railway bed comprising means for excavating ballast from the bed, conveying means for moving the ballast from the excavating means through the apparatus and selectively positionable delivery means for delivering ballast from the conveying means to a point of collection.
  • the above apparatus can be controlled by a sole operator.
  • the operator does not need to carry out the removal operation in stages but can drive the apparatus the length of the rail bed within which the ballast is to be removed and excavate and collect the ballast in a single operation.
  • the selectively positionable means comprises a boom mounted on the rear of the apparatus.
  • the boom is provided with conveyor means for moving the ballast along the length of the boom.
  • the conveying means passing through the apparatus comprises a conveyor belt from which ballast can fall onto the conveyor means of the boom.
  • the excavation means comprises means for lifting ballast from the bed and means for feeding the lifted ballast onto the conveyor belt.
  • the feeding means comprises a pair of contra rotating rotors provided with blades which direct the excavated ballast therebetween and deposit it onto the conveyor belt .
  • the apparatus may be provided with caterpillar tracks to allow the apparatus to be driven over rough or uneven ground as well as normal road surfaces .
  • Figure 2 is a schematic front view of the apparatus of Figure 1 in operation adjacent a wagon for collecting ballast;
  • Figure 3 is a schematic overhead view of the apparatus of Figure 1 in operation.
  • FIG. 1-3 an apparatus for removing ballast from a road way, particularly from a rail road bed.
  • the apparatus is incorporated into a vehicle 1 which is intended to be driven and controlled by a single operator thereby overcoming the labour intensive problems associated with the prior art methods and apparatus used.
  • the apparatus further comprises means for excavating and lifting ballast from the rail bed.
  • the excavation means 5 is mounted on the front of the main frame 3 of the vehicle (as determined by the direction of operation of the vehicle) and comprises a loading apron 6 which may be formed of a wear resistant material .
  • the loading apron comprises a generally C-shaped member which is mounted to the main frame at the closed end thereof.
  • Means are provided on the mainframe 3 for raising and lowering the loading apron 6 towards and away from the rail bed and also for altering the transverse relationship with the main frame. This allows the position of the loading apron to be adjusted in order to ensure that the loading apron maintains the optimum position during operation.
  • Feeding means are provided within the loading apron 6 to encourage ballast excavated and lifted by the loading apron to pass through it back towards the main frame 3 of the vehicle .
  • the feedings means in the illustrated embodiment comprise a pair of rotors 8 which are mounted side by side within the loading apron and a set of spill plates 7.
  • the rotors are each provided with a plurality of blades 9 which may be formed of a wear resistant material.
  • the blades are of a sufficient length as to advance ballast towards the centre of the loading apron.
  • Means are provided within the loading apron of the vehicle for rotating the rotors 8 in opposite directions to facilitate advancement of the ballast .
  • Conveyor means are provided within the main frame 3 of the vehicle for conveying ballast from the loading apron 6 to the rear of the vehicle .
  • the conveyor means may be in the form of a conveyor belt 10.
  • the height of the conveyor belt increases as it passes through the vehicle 1.
  • Means (not shown) may be provided on the main frame to adjust the height of the conveyor belt 10 if required. It is envisaged that the conveyor belt will be driven by hydraulic means provided on the main frame. Additionally, tensioning means may be provided in order to adjust the tensioning of the conveyor belt to achieve optimum operation of the apparatus.
  • a selectively positionable feeding means is mounted to the rear of the vehicle.
  • the feeding means takes the form of a boom member 11 mounted onto the main frame 3 by suitable fixings which allow the position of the boom 11 to be adjusted as required.
  • the boom member is provided with a further conveyor belt 12 which extends along the entire length of the boom.
  • this secondary conveyor belt may be provided with tensioning means to adjust the operational characteristics of the belt.
  • a control cab 13 is mounted on the main frame 3 of the vehicle and in the illustrated embodiment is shown as being located behind the loading apron 6 and above the primary conveyor belt 10. It is envisaged that the cab will be fully glazed in order to provide maximum visibility for the operator during use. Furthermore, the position of the cab allows the operator to oversee the operation of the apparatus in order that he can make any adjustments necessary during the excavation process. Control means (not shown) are provided within the cab, as will be described further below, for operating the vehicle.
  • control means may, for example, comprise amongst other things, means for operating and controlling the speed of the primary and secondary conveyor belts 10,12, control means for raising and lowering the loading apron 6, control means for advancing, retracting and tilting the loading apron and control means for adjusting the position of the boom 11.
  • control means for raising and lowering the loading apron 6
  • control means for advancing, retracting and tilting the loading apron and control means for adjusting the position of the boom 11.
  • standard vehicle control means will also be provided within the cab which will allow the vehicle to be driven along standard roads to any particular location where it may be required.
  • a wagon 14 is illustrated in the figures for collecting ballast excavated from the rail bed by the apparatus described above.
  • the wagon is shown as being provided on an adjacent rail to the rail bed being cleared, although the wagon could of course be replaced with a skip or truck which can be moved along the rail bed together with the excavation apparatus in order to facilitate continuous operation of the apparatus.
  • Additional control means for the various components of the apparatus may also be mounted on the mainframe 3 of the vehicle. This may include for example, power packs, fuel tank, electric and hydraulic equipment, service jacks and other associated means.
  • the rails of the railroad bed from which the ballast is to be excavate are removed and stored at a suitable location such as adjacent to the rail bed.
  • the removal apparatus as described above is then moved into position on the rail bed.
  • the vehicle 1 upon which the apparatus is located may be driven to the required location or may alternatively be transported to the required location via the existing rail network prior to removal of the rails .
  • Wagons 14 or other suitable collection means is then provided adjacent to the collection apparatus and it is intended that the collection apparatus should be advanced together with the apparatus. It is therefore preferable that a wagon or wagon train be positioned on adjacent tracks to the rail bed to be removed to allow the apparatus to deposit collected ballast into the successive wagons.
  • the position of the boom 11 is adjusted so that the free end of the boom and the conveyor belt 12 provided thereon is located above the wagon 14 or truck into which the excavated ballast is to be loaded.
  • the position of the loading apron 6 of the apparatus can be adjusted, grading down into the ballast in order to bring the front of the loading apron into engagement beneath ballast to be removed.
  • the loading apron 6 and primary and secondary conveyor belts 10,12 are activated by the operator of the apparatus. As the vehicle 1 is advanced forwards along the rail bed, ballast is lifted into the loading apron.
  • Contra rotation of the two rotors 8 directs excavated ballast between the blades 9 and moves the ballast through the loading apron 6 onto the end of the primary conveyor belt 10 which is located within the loading apron.
  • the excavated ballast is then carried along the primary conveyor belt until it reaches the end of the belt at the rear of the main frame 3. It then falls from the end of the primary conveyor belt and drops onto the secondary conveyor belt 12 provided on the boom member 11 at the rear of the main frame.
  • the ballast is carried along the secondary conveyor belt and falls from the free end of the conveyor belt into the wagon 14 or other collection means provided adjacent to the rail bed.
  • any inconsistencies in the distance between the vehicle and the adjacent collection means can be compensated for by suitable movement of the boom member.
  • Indicator means may be provided within the cab 13 of the vehicle to allow the operator to monitor the position of the boom and to allow him to make suitable adjustments without interrupting the operation of the apparatus. This enables the apparatus o be operated more efficiently and facilitates the one- pass operation of the apparatus as previously described.
  • a wagon train is provided adjacent to the rail bed from which ballast is to be removed.
  • the apparatus can be driven along the rail bed excavating ballast as it advances.
  • the ballast falling from the secondary conveyor belt fills each successive wagon as the apparatus advances along the bed. Once all of the wagons are filled they can be simply transported along the rail track to a suitable location for unloading.
  • the method and apparatus allows for the continuous excavation of ballast from a road or railroad bed by a sole operator in a single vehicle with a single pass along the bed by the vehicle. This provides a significant advantage over prior art excavation methods and apparatus used therein.

Abstract

A continuous method of removing ballast material particularly from a railway line bed comprising the steps of positioning an excavation apparatus (1) at the work site, advancing the apparatus along the bed to lift ballast from the bed, introducing the lifted ballast into the apparatus at one end thereof, conveying ballast from the excavation site through the apparatus to a selectively positionable delivery means (11) at the other end of the apparatus remote from the excavation site, from which the ballast is fed to a containment means for collection (14).

Description

BALLAST REMOVAL METHOD AND APPARATUS
This invention relates to a method and an apparatus for removing ballast from a road bed and, more particularly, to an improved method and apparatus for removing ballast from a rail road bed, which apparatus can be controlled by a sole operator using a single vehicle to lift and remove ballast.
When preparing an area of ground for the laying of a road or railroad, the designated area is excavated and ballast material is laid along the route. The ballast material generally takes the form of gravel or broken stone and, in the case of a railroad, is placed on the excavated bed to provide a firm surface upon which the track is supported. The ballast also functions to hold the track in position when laid. Furthermore, the ballast material facilitates drainage of surface water from the rail bed to avoid flooding in bad weather.
Under some conditions, the ballast may become dislodged from the rail bed or, in some cases where safety checks or rail maintenance operations must be carried out, the ballast may require removal either for replacement or cleaning operations to be carried out. This is particularly important if the ballast becomes clogged with dirt and debris as the proper drainage function will be impaired which could lead to flooding in low lying areas thereby requiring further safety operations to be carried out on the same stretch of track.
Traditional methods of removing ballast require the removal of the rails, which are stored at a location perhaps adjacent to the railway line. A fleet of vehicles is then transported to the site to handle the removal operation. It is not unusual for at least 4 separate vehicles to be required, with personnel required for each vehicle .
Ballast is dug up from the rail bed for example using suitable earth moving equipment and the recovered ballast is then loaded into wagons to be removed from the site. Often the area in which the operation is taking place is difficult to access from road networks and this can add further time delays caused by the removal operation itself.
These traditional methods are both labour intensive in requiring different personnel to operate the various pieces of equipment and also time consuming in requiring equipment to be brought to the site and removed therefrom as required. For example, the earth moving equipment may have to be moved to and from the work site several times in order to fill a wagon with sufficient ballast. Furthermore, the earth moving equipment may have to be removed from the work site to allow the wagon access to the work site for loading. This leads to a situation where either the work is progressed in stages to allow for the required equipment to be on hand at the appropriate times, or alternatively in a labour intensive operation which relies on a fleet of vehicles and a work force to operate the vehicles as and when required.
The present invention aims to provide a method and apparatus for removing ballast from a road way and particularly from a railway line, which overcomes or at least mitigates some of the above mentioned disadvantages which are associated with traditional methods and apparatus used for removing ballast from such locations.
According to one aspect of the present invention there is provided a continuous method of removing ballast material particularly from a railway line bed comprising the steps positioning an excavation apparatus at the work site, advancing the apparatus along the bed, introducing ballast into the apparatus at one end thereof, conveying ballast from the excavation site through the apparatus to a selectively positionable delivery means at the other end of the apparatus remote from the excavation site, from which the ballast is fed to a containment means for collection.
According to a further aspect of the present invention there is provided an apparatus for the continual excavation and collection of ballast particularly from a railway bed, said apparatus comprising means for excavating ballast from the bed, conveying means for moving the ballast from the excavating means through the apparatus and selectively positionable delivery means for delivering ballast from the conveying means to a point of collection.
Advantageously, the above apparatus can be controlled by a sole operator. As the operation of the apparatus is continuous, the operator does not need to carry out the removal operation in stages but can drive the apparatus the length of the rail bed within which the ballast is to be removed and excavate and collect the ballast in a single operation. Preferably, the selectively positionable means comprises a boom mounted on the rear of the apparatus.
Advantageously, the boom is provided with conveyor means for moving the ballast along the length of the boom.
Conveniently, the conveying means passing through the apparatus comprises a conveyor belt from which ballast can fall onto the conveyor means of the boom.
Preferably, the excavation means comprises means for lifting ballast from the bed and means for feeding the lifted ballast onto the conveyor belt.
Preferably also, the feeding means comprises a pair of contra rotating rotors provided with blades which direct the excavated ballast therebetween and deposit it onto the conveyor belt .
Advantageously, the apparatus is provided with means for transporting the apparatus to and from the rail bed.
Conveniently, the apparatus may be provided with caterpillar tracks to allow the apparatus to be driven over rough or uneven ground as well as normal road surfaces .
An embodiment of the present invention will now be described with reference to the accompanying drawings in which: Figure 1 is a schematic side view of an apparatus for removing ballast from a road way in accordance with one aspect of the present invention;
Figure 2 is a schematic front view of the apparatus of Figure 1 in operation adjacent a wagon for collecting ballast; and
Figure 3 is a schematic overhead view of the apparatus of Figure 1 in operation.
Turning now to the Figures there is shown in Figures 1-3 an apparatus for removing ballast from a road way, particularly from a rail road bed. The apparatus is incorporated into a vehicle 1 which is intended to be driven and controlled by a single operator thereby overcoming the labour intensive problems associated with the prior art methods and apparatus used.
As shown in Figure 1, an apparatus for removing ballast comprises a vehicle 1 provided with suitable transport means 2. In the illustrated embodiment, the vehicle comprises a main frame 3 to which the transport means 2 for advancing the vehicle along a road bed are connected in a conventional manner. Advantageously, transport means 2 includes caterpillar tracks 4 mounted on either side of the vehicle and this provides adhesion to the ground for the apparatus to penetrate the ballast and these also allow the vehicle to be driven directly over rough or uneven ground in order to gain access to the road way to be worked on.
The apparatus further comprises means for excavating and lifting ballast from the rail bed. The excavation means 5 is mounted on the front of the main frame 3 of the vehicle (as determined by the direction of operation of the vehicle) and comprises a loading apron 6 which may be formed of a wear resistant material . The loading apron comprises a generally C-shaped member which is mounted to the main frame at the closed end thereof.
Means (not shown) are provided on the mainframe 3 for raising and lowering the loading apron 6 towards and away from the rail bed and also for altering the transverse relationship with the main frame. This allows the position of the loading apron to be adjusted in order to ensure that the loading apron maintains the optimum position during operation.
Feeding means are provided within the loading apron 6 to encourage ballast excavated and lifted by the loading apron to pass through it back towards the main frame 3 of the vehicle . The feedings means in the illustrated embodiment comprise a pair of rotors 8 which are mounted side by side within the loading apron and a set of spill plates 7. The rotors are each provided with a plurality of blades 9 which may be formed of a wear resistant material. The blades are of a sufficient length as to advance ballast towards the centre of the loading apron. Means are provided within the loading apron of the vehicle for rotating the rotors 8 in opposite directions to facilitate advancement of the ballast .
Conveyor means are provided within the main frame 3 of the vehicle for conveying ballast from the loading apron 6 to the rear of the vehicle . The conveyor means may be in the form of a conveyor belt 10. In the illustrated embodiment, the height of the conveyor belt increases as it passes through the vehicle 1. Means (not shown) may be provided on the main frame to adjust the height of the conveyor belt 10 if required. It is envisaged that the conveyor belt will be driven by hydraulic means provided on the main frame. Additionally, tensioning means may be provided in order to adjust the tensioning of the conveyor belt to achieve optimum operation of the apparatus.
At the other end of the conveyor belt 10, remote from the loading apron 6, a selectively positionable feeding means is mounted to the rear of the vehicle. The feeding means takes the form of a boom member 11 mounted onto the main frame 3 by suitable fixings which allow the position of the boom 11 to be adjusted as required.
The boom member is provided with a further conveyor belt 12 which extends along the entire length of the boom. As with the primary conveyor belt 10, this secondary conveyor belt may be provided with tensioning means to adjust the operational characteristics of the belt.
A control cab 13 is mounted on the main frame 3 of the vehicle and in the illustrated embodiment is shown as being located behind the loading apron 6 and above the primary conveyor belt 10. It is envisaged that the cab will be fully glazed in order to provide maximum visibility for the operator during use. Furthermore, the position of the cab allows the operator to oversee the operation of the apparatus in order that he can make any adjustments necessary during the excavation process. Control means (not shown) are provided within the cab, as will be described further below, for operating the vehicle. Such control means may, for example, comprise amongst other things, means for operating and controlling the speed of the primary and secondary conveyor belts 10,12, control means for raising and lowering the loading apron 6, control means for advancing, retracting and tilting the loading apron and control means for adjusting the position of the boom 11. Additionally, standard vehicle control means will also be provided within the cab which will allow the vehicle to be driven along standard roads to any particular location where it may be required.
A wagon 14 is illustrated in the figures for collecting ballast excavated from the rail bed by the apparatus described above. The wagon is shown as being provided on an adjacent rail to the rail bed being cleared, although the wagon could of course be replaced with a skip or truck which can be moved along the rail bed together with the excavation apparatus in order to facilitate continuous operation of the apparatus.
This enables the apparatus to remove ballast in a single pass along the rail bed rather than a series of backwards and forwards operations to remove ballast and then return to a collection device to load recovered ballast onto a suitable means to allow for removal from the work site.
Additional control means (not shown) for the various components of the apparatus may also be mounted on the mainframe 3 of the vehicle. This may include for example, power packs, fuel tank, electric and hydraulic equipment, service jacks and other associated means.
The operation of the apparatus will now be described with reference to the Figures. Firstly, the rails of the railroad bed from which the ballast is to be excavate are removed and stored at a suitable location such as adjacent to the rail bed. The removal apparatus as described above is then moved into position on the rail bed. The vehicle 1 upon which the apparatus is located may be driven to the required location or may alternatively be transported to the required location via the existing rail network prior to removal of the rails .
Wagons 14 or other suitable collection means is then provided adjacent to the collection apparatus and it is intended that the collection apparatus should be advanced together with the apparatus. It is therefore preferable that a wagon or wagon train be positioned on adjacent tracks to the rail bed to be removed to allow the apparatus to deposit collected ballast into the successive wagons.
Prior to use of the apparatus, the position of the boom 11 is adjusted so that the free end of the boom and the conveyor belt 12 provided thereon is located above the wagon 14 or truck into which the excavated ballast is to be loaded.
As shown in Figures 2 and 3, the position of the loading apron 6 of the apparatus can be adjusted, grading down into the ballast in order to bring the front of the loading apron into engagement beneath ballast to be removed. The loading apron 6 and primary and secondary conveyor belts 10,12 are activated by the operator of the apparatus. As the vehicle 1 is advanced forwards along the rail bed, ballast is lifted into the loading apron.
Contra rotation of the two rotors 8 directs excavated ballast between the blades 9 and moves the ballast through the loading apron 6 onto the end of the primary conveyor belt 10 which is located within the loading apron.
The excavated ballast is then carried along the primary conveyor belt until it reaches the end of the belt at the rear of the main frame 3. It then falls from the end of the primary conveyor belt and drops onto the secondary conveyor belt 12 provided on the boom member 11 at the rear of the main frame. The ballast is carried along the secondary conveyor belt and falls from the free end of the conveyor belt into the wagon 14 or other collection means provided adjacent to the rail bed.
As the position of the boom member 11 and therefore the end of the secondary conveyor belt 12 can be controlled by the operator from within the cab, any inconsistencies in the distance between the vehicle and the adjacent collection means can be compensated for by suitable movement of the boom member.
Indicator means (not shown) may be provided within the cab 13 of the vehicle to allow the operator to monitor the position of the boom and to allow him to make suitable adjustments without interrupting the operation of the apparatus. This enables the apparatus o be operated more efficiently and facilitates the one- pass operation of the apparatus as previously described.
In the embodiment shown in Figure 2 , a wagon train is provided adjacent to the rail bed from which ballast is to be removed. In this embodiment, the apparatus can be driven along the rail bed excavating ballast as it advances. The ballast falling from the secondary conveyor belt fills each successive wagon as the apparatus advances along the bed. Once all of the wagons are filled they can be simply transported along the rail track to a suitable location for unloading.
It is to be understood that although the above description has been particularly directed towards the excavation of ballast from a rail way bed, the apparatus and method described could equally be used for the excavation of ballast from a road bed.
As has been described above, the method and apparatus allows for the continuous excavation of ballast from a road or railroad bed by a sole operator in a single vehicle with a single pass along the bed by the vehicle. This provides a significant advantage over prior art excavation methods and apparatus used therein.

Claims

1. A continuous method of removing ballast material particularly from a railway line bed comprising the steps of positioning an excavation apparatus at the work site, advancing the apparatus along the bed to lift ballast from the bed, introducing the lifted ballast into the apparatus at one end thereof, conveying ballast from the excavation site through the apparatus to a selectively positionable delivery means at the other end of the apparatus remote from the excavation site, from which the ballast is fed to a containment means for collection.
2. A continuous method of removing ballast material particularly from a railway line bed substantially as hereinbefore described.
3. An apparatus for the continual excavation and collection of ballast particularly from a railway bed, said apparatus comprising means for excavating ballast from the bed, conveying means for moving the ballast from the excavating means through the apparatus and selectively positionable delivery means for delivering ballast from the conveying means to a point of collection.
4. An apparatus according to claim 3 , wherein the selectively positionable means comprises a boom mounted on the rear of the apparatus.
5. An apparatus according to claim 4 , wherein the boom is provided with conveyor means for moving the ballast along the length of the boom.
6. An apparatus according to claim 5, wherein the conveying means passing through the apparatus comprises a conveyor belt from which ballast can fall onto the conveyor means of the boom.
7. An apparatus according to claim 6, wherein the excavation means comprises means for lifting ballast from the bed and means for feeding the lifted ballast onto the conveyor belt .
8. An apparatus according to claim 7, wherein the feeding means comprises a pair of contra rotating rotors provided with blades which direct the excavated ballast therebetween and deposit it onto the conveyor belt .
9. An apparatus according to any one of claims 3-8, wherein the apparatus is provided with means for transporting the apparatus to and from the rail bed.
10. An apparatus according to claim 9, wherein the apparatus may be provided with caterpillar tracks to allow the apparatus to be driven over rough or uneven ground as well as normal road surfaces.
11. An apparatus for the continual excavation and collection of ballast particularly from a railway bed substantially as hereinbefore described with reference to and as shown in the accompanying drawings .
PCT/GB2001/005796 2000-12-22 2001-12-24 Ballast removal method and apparatus WO2002052105A1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
DE60130254T DE60130254T2 (en) 2000-12-22 2001-12-24 DEVICE AND METHOD FOR REMOVING SCRATCH BEDING
EP01272123A EP1348057B1 (en) 2000-12-22 2001-12-24 Ballast removal method and apparatus

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
GB0031480.7 2000-12-22
GBGB0031480.7A GB0031480D0 (en) 2000-12-22 2000-12-22 Ballast removal method and apparatus

Publications (1)

Publication Number Publication Date
WO2002052105A1 true WO2002052105A1 (en) 2002-07-04

Family

ID=9905762

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/GB2001/005796 WO2002052105A1 (en) 2000-12-22 2001-12-24 Ballast removal method and apparatus

Country Status (5)

Country Link
EP (1) EP1348057B1 (en)
AT (1) ATE371770T1 (en)
DE (1) DE60130254T2 (en)
GB (1) GB0031480D0 (en)
WO (1) WO2002052105A1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1650347A1 (en) 2004-06-01 2006-04-26 Fastline Limited Ballast removal method and apparatus
GB2431682A (en) * 2005-10-27 2007-05-02 Ps Rail Ltd Ballast removing device and method
WO2007116249A2 (en) * 2006-04-10 2007-10-18 Matisa Materiel Industriel Sa Storage car
WO2009132745A1 (en) * 2008-04-28 2009-11-05 Franz Plasser Bahnbaumaschinen- Industriegesellschaft Mbh Method for the removal of ballast from a track
FR2960006A1 (en) * 2010-05-17 2011-11-18 Delcourt Ferroviaire Dfc Method for replacing e.g. ballast such as rail, involves performing clearing operation of ballast by ballast clearing vehicle that evacuates dirt extracted from dirt transport wagons circulating on side track along work track

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL2001478C2 (en) * 2008-04-14 2009-10-19 Konink Bam Groep Nv Device and method for removing ballast material from a ballast bed.

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1752714A (en) * 1927-06-06 1930-04-01 Albert C Wilcox Coal-loading machine
FR1387729A (en) * 1964-04-07 1965-01-29 Mobile machine for cleaning railroad ballast
FR2588023A1 (en) * 1985-10-02 1987-04-03 Drouard Freres Ets Method and machine for clearing the ballast from a railway track
US5228552A (en) * 1990-01-12 1993-07-20 Voest-Alpine Berftechnik Gesellschaft M.B.H. Loading device for mining
EP0626483A2 (en) * 1993-05-28 1994-11-30 Inc. Ozzie's Pipeline Padder Pipeline padding apparatus with rotary feeder

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1752714A (en) * 1927-06-06 1930-04-01 Albert C Wilcox Coal-loading machine
FR1387729A (en) * 1964-04-07 1965-01-29 Mobile machine for cleaning railroad ballast
FR2588023A1 (en) * 1985-10-02 1987-04-03 Drouard Freres Ets Method and machine for clearing the ballast from a railway track
US5228552A (en) * 1990-01-12 1993-07-20 Voest-Alpine Berftechnik Gesellschaft M.B.H. Loading device for mining
EP0626483A2 (en) * 1993-05-28 1994-11-30 Inc. Ozzie's Pipeline Padder Pipeline padding apparatus with rotary feeder

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1650347A1 (en) 2004-06-01 2006-04-26 Fastline Limited Ballast removal method and apparatus
GB2431682A (en) * 2005-10-27 2007-05-02 Ps Rail Ltd Ballast removing device and method
EP1783276A2 (en) * 2005-10-27 2007-05-09 PS Rail Limited Ballast removing device
EP1783276A3 (en) * 2005-10-27 2007-05-23 PS Rail Limited Ballast removing device
WO2007116249A2 (en) * 2006-04-10 2007-10-18 Matisa Materiel Industriel Sa Storage car
WO2007116249A3 (en) * 2006-04-10 2008-01-17 Matisa Materiel Ind Sa Storage car
WO2009132745A1 (en) * 2008-04-28 2009-11-05 Franz Plasser Bahnbaumaschinen- Industriegesellschaft Mbh Method for the removal of ballast from a track
FR2960006A1 (en) * 2010-05-17 2011-11-18 Delcourt Ferroviaire Dfc Method for replacing e.g. ballast such as rail, involves performing clearing operation of ballast by ballast clearing vehicle that evacuates dirt extracted from dirt transport wagons circulating on side track along work track

Also Published As

Publication number Publication date
EP1348057A1 (en) 2003-10-01
EP1348057B1 (en) 2007-08-29
DE60130254T2 (en) 2008-05-29
GB0031480D0 (en) 2001-02-07
ATE371770T1 (en) 2007-09-15
DE60130254D1 (en) 2007-10-11

Similar Documents

Publication Publication Date Title
US5479725A (en) Method of and arrangement for rehabilitating a ballast bed of a track
US4307667A (en) Railroad track relaying train
US4479439A (en) Mobile arrangement and method for improving a track bed
US4108076A (en) Method for removing ballast from railroad tracks
CA1177694A (en) Track work train
US4357874A (en) Mobile arrangement and method for improving a track bed
CZ279331B6 (en) maintenance mechanized machine
EP0712961B1 (en) Method and arrangement for the subgrade-rehabilitation of the ballast of a railway track
CA2383161C (en) A cleaning machine and method of cleaning ballast
PL199479B1 (en) Railway track renovating machine
USRE35788E (en) Method of and arrangement for rehabilitating a ballast bed of a track
EP1348057B1 (en) Ballast removal method and apparatus
PL201968B1 (en) Railway track renovating machine
US4400897A (en) Method and railway train for draining a railway track
US4440088A (en) Fabric insertion system
US4119154A (en) Method and apparatus for treating ballast
EP1650347A1 (en) Ballast removal method and apparatus
JPS626002A (en) Apparatus for re-laying gravel for tunnel
CN117468284B (en) Railway screening backfill equipment and method
EP2067898A2 (en) Method and equipment for track renewal
JP2829834B2 (en) Ballast ballast collection device
CA1201937A (en) Railway track renewal train
EP2122056A1 (en) Apparatus for removing and loading track ballast
RU2078868C1 (en) Ballast cleaner
WO2014019021A1 (en) Ballast undercutter

Legal Events

Date Code Title Description
AK Designated states

Kind code of ref document: A1

Designated state(s): AE AG AL AM AT AU AZ BA BB BG BR BY BZ CA CH CN CO CR CU CZ DE DK DM DZ EC EE ES FI GB GD GE GH GM HR HU ID IL IN IS JP KE KG KP KR KZ LC LK LR LS LT LU LV MA MD MG MK MN MW MX MZ NO NZ OM PH PL PT RO RU SD SE SG SI SK SL TJ TM TN TR TT TZ UA UG US UZ VN YU ZA ZM ZW

AL Designated countries for regional patents

Kind code of ref document: A1

Designated state(s): GH GM KE LS MW MZ SD SL SZ TZ UG ZM ZW AM AZ BY KG KZ MD RU TJ TM AT BE CH CY DE DK ES FI FR GB GR IE IT LU MC NL PT SE TR BF BJ CF CG CI CM GA GN GQ GW ML MR NE SN TD TG

DFPE Request for preliminary examination filed prior to expiration of 19th month from priority date (pct application filed before 20040101)
121 Ep: the epo has been informed by wipo that ep was designated in this application
WWE Wipo information: entry into national phase

Ref document number: 2001272123

Country of ref document: EP

WWP Wipo information: published in national office

Ref document number: 2001272123

Country of ref document: EP

REG Reference to national code

Ref country code: DE

Ref legal event code: 8642

NENP Non-entry into the national phase

Ref country code: JP

WWW Wipo information: withdrawn in national office

Country of ref document: JP

WWG Wipo information: grant in national office

Ref document number: 2001272123

Country of ref document: EP