WO1992000425A2 - Improved methods for providing foundations for building structures - Google Patents
Improved methods for providing foundations for building structures Download PDFInfo
- Publication number
- WO1992000425A2 WO1992000425A2 PCT/GB1991/001011 GB9101011W WO9200425A2 WO 1992000425 A2 WO1992000425 A2 WO 1992000425A2 GB 9101011 W GB9101011 W GB 9101011W WO 9200425 A2 WO9200425 A2 WO 9200425A2
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- trench
- ground
- assembly
- foundation
- pile
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/12—Pile foundations
- E02D27/14—Pile framings, i.e. piles assembled to form the substructure
Definitions
- the present invention concerns an improved method for providing a foundation for a building structure.
- the most commonly employed method of providing a foundation for a building structure is to excavate a flat bottomed and vertical sided trench in the bottom of which is formed a foundation or footing by pouring concrete therein.
- this method is relatively simple it has a number of drawbacks. For example, it employs a relatively large volume of concrete. As a result of the use of a trench and the situation of the footing substantially below ground level it requires excavation of soil considerably in excess of the volume of concrete and this often gives rise to difficulties if water is present as the trench must be free of water when the concrete is poured.
- the construction of the trench depends to a large extent on the condition of the ground in which it is excavated. For example, if the ground is poor the trench walls will collapse unless shuttering is employed, this being time consuming and expensive. If the ground in which the trench is provided is subjected to heave eg., it is clay, special provisions must be employed.
- a stepped trench must be dug, that is, a trench comprising a plurality of horizontal sections each stepped relative to its neighbouring section to take account of the rise and fall in the ground level.
- a further disadvantage of existing foundation forming techniques is that as the foundation is being formed it is subject to inspection by a Local Authority Building Inspector. This is often inconvenient and can cause unnecessary delays to the overall working schedule.
- An object of the present invention is to obviate or mitigate these disadvantages.
- a method of forming a foundation for a building structure comprising providing from below the level of the ground in which the foundation is to be formed a trench which is of substantially the same depth as the depth of a foundation beam to be formed therein, forming piles at spaced intervals in said trench leading from the base of the trench, placing reinforcement in said trench and filling the trench with a settable material to form said foundation beam with the tops of said pile cast therein.
- the sides of the trench converge downwardly.
- the cross-section of the trench is substantially triangular.
- the cross-section of the trench is substantially trapezoidal.
- the reinforcement is a steel assembly of substantially V-shaped cross-section.
- the tops of the piles may be connected to the reinforcing steel prior to the pouring of the settable material.
- the steel assembly preferably includes two longitudinally extending reinforcing members and a plurality of mutually spaced link members.
- the limbs of the V-shaped link members diverge upwardly in their in use position.
- Each limb may be provided at its end with an outwardly directed extension.
- Each extension is preferably provided with an end cap for locating the link against the trench side.
- At least one spacer member is preferably provided for the reinforcement assembly to maintain a correct spacing between the base of the assembly and the trench base.
- each of two upper longitudinally extending reinforcing members is fixed to a limb at its junction with its extension.
- the fixing is by means of welding.
- the lowermost longitudinally extending reinforcing member is not positioned on the assembly until after the remaining link members and longitudinal members have been positioned in the trench. Additional link members may be provided for the steel assembly and are positioned after the assembly without the bottom longitudinal member, has been placed in the trench.
- the trench is lined with an impervious sheet member.
- the impervious member may be polythene.
- the surfaces of the trench are lined with a compressable material so as to enable the foundation to withstand movement of the ground therearound.
- the compressable material may be polystyrene or compressed paper, as a proprietory clayboard product. In ground which is not sufficiently stable a more rigid lining material may be employed.
- a low friction coat is applied to at least the upper end of the pile to permit movement of the ground relative to the pile.
- an inflatable tube is inserted into a pre-formed hole in the ground in which a pile may be cast in situ, and inflated to maintain the hole open until the pile is formed by pouring a settable material into the hole.
- steel as precased piles may be driven or augered piled used.
- the settable material is concrete.
- the depth of the trench is between 12" and 24" (300 mm to 600 mm).
- the trench is formed in sloping ground its depth is increased such that the upper surface of the foundation beam cast therein comprises a plurality of mutually stepped horizontal sections, the depth of a step being an integral of 3" (77 mm) for brickwork, and as otherwise required for blockwork and the minimum depth of the beam not reduced.
- a second layer of foundation is then formed on top of the foundation beam comprising a plurality of mutually stepped horizontal sections, the depth of each step being an integral of 3" (77 mm).
- the ground is levelled by conventional techniques and the trench is formed from the level of the excavated ground.
- a trench forming machine comprising a chassis having ground engaging means and a vibratory assembly mounted thereon, a trench forming wheel having a cross-section corresponding to the cross-section of the trench to be formed being rotatably mounted on said vibrating assembly, means being provided to select amplitude, frequency and applied direction of vibratory force such that the wheel is caused to penetrate the ground on which it rests to form a trench.
- the trench forming assembly can be self propelled.
- it may be provided with means for moving it along the trench,
- Preferably means are provided for raising or lowering the trench forming wheel relative to the chassis.
- a trench forming machine including a former having a cross-section corresponding to the cross-section of the trench, driving means for forcing the former into the ground to form a section of trench and means for moving said former and replacing it with a pile forming means whereby said driving means may drive said pile.
- said driving means comprises an impact assing said former/pile into the ground.
- FIG. 1 shows a diagrammatic cross-section through a foundation for a building structure
- Fig. 2 shows a diagrammatic cross-sectional elevation of a section of foundation formed in sloping ground
- Fig. 3 shows a diagrammatic cross-sectional elevation similar to Fig. 2 but illustrating a modification
- Fig. 4 shows a diagrammatic elevation of a trench forming apparatus
- Fig. 5 shows a diagrammatic cross-section of the apparatus of Fig. 4,
- Fig. 6 shows a diagrammatic elevation of a further trench forming apparatus.
- a foundation for a building structure is formed using an excavator which, from ground level 10, excavates a substantially triangular cross-section trench 12, of depth 15" (380 mm) and opening with 15" (380 mm) with a V-shaped bucket the dimensions of which correspond exactly to the dimensions of the trench. That is the bucket requires no overcutter as normally called for in excavator buckets.
- This ability of the bucket to cut a correctly shaped and sized trench is due, in part, to the "wedge" action provided by the bucket shape and provides a trench which itself performs the task normally performed by additional shuttering. Figs.
- the trench follows the inclination of the ground in which it is formed and it will be realised that this trench forming operation, as it is at ground level excavates the minimum amount of soil and can be performed with the minimum of difficulty.
- the trench may be formed by rolling or hammering the ground with suitable forming machinery to be described later.
- a plurality of piles 14 are driven at approximately 10 feet (3 metres) intervals, the pile heads 15 extending into the trench.
- Any pile driving technique suitable to the circumstances may be employed, for example, hammering, vibrating or augering, and the depth to which the piles are driven is predetermined in accordance with the load bearing qualities required and the soil conditions into which they are driven.
- a low friction slip coating 14 may be provided about at least the upper third of each pile when the ground in which the foundations are being formed is succeptible to movement or heave. This low t friction coating 14 allows the ground to move about the pile without significantly affecting the position or stability of the pile. It is possible for the piles to be driven prior to the excavation of the trench but this is likely to make the trench constructions marginally more complicated as a result of the protrusion of the pile heads into the trench.
- piles formed in situ As well as driving pre-formed piles, it is possible to use piles formed in situ.
- the holes in which these piles are to be formed are produced by driving a tube into the ground by any convenient method as described above. The tube is then removed to leave the hole in which the pile is to be formed. It is often found that there is a substantial interval between the formation of the hole and the insertion of the pile forming material, often concrete, therein. To prevent the hole collapsing during this interval an inflatable tube is inserted into the hole and inflated to a pressure sufficient to maintain the hole open. When the pile hole is to be filled, the tube is deflated and removed from the hole and the concrete is poured.
- the trench Prior to or after the pile placing operation the trench is lined by a polythene sheet which extends beyond the upper edges of the trench.
- the polythene sheet lining may be substituted by any suitable compressible material for example, compressed paper or polystyrene.
- the polythene sheet In loose ground the polythene sheet may be replaced by a more rigid lining to support the surrounding ground.
- This lining will take up any slight movement of the ground substantially about the trench, thereby helping prevent the foundations from moving and possibly cracking.
- a generally V-shaped cross-section reinforced steel assembly 16 comprising three longitudinally extending reinforcing rods 18 and surrounding transverse link members 20 is positioned within the trench spaced from the trench walls and bottom, optionally with the pile heads 15 connected to the reinforcement.
- Concrete 22 is then poured into the trench around the reinforcement following normal concrete pouring techniques with the upper surface 24 of the concrete being at a near ground level 10 when the ground is level.
- the reinforced steel assembly is of particular significance. It comprises three longitudinal members 18, two being positioned in use near to the surface 24 of the concrete and one 18 being positioned, in use, close to the base of the trench.
- the members are held in position by transversely extending link members 20 but contrary to normal construction techniques the link members 20 do not form a continuous loop but are of substantially 'V' shaped configuration with the open end of the V uppermost and its side limbs 17 diverging upwardly.
- the upper ends of the side limbs 17 have outwardly directed extension 19 which, in use, are substantially horizontal.
- Plastics as concrete material end spacer caps 21 are fitted to these extensions .
- Normal reinforcement construction techniques call for the fabrication of the reinforcing assembly on site by bending straight reinforcing bars into shape to form a link. Each link is then attached to the longitudinal members normally by wiring. This is a time-consuming technique which is not particularly suitable to the present invention, especially when it is applied on undulating ground as a reinforcement assembly produced by conventional techniques exhibits a considerable rigidity which would prevent it from complying substantially with the contour of the trench base. Additionally, in view of the inherent inaccuracies in in situ bar fixing, a normally constructed reinforcement assembly may not conform exactly to the profile of the trench so that the more important longitudinal members would not be correctly positioned at their optimum operational location.
- the open top nature of the reinforcing assembly 16 of the present invention obviates these disadvantages, not only because it lends itself to prefabrication in a factory environment rather than in situ but also because it provides on site a relatively flexible assembly which will conform substantially to the profile of the base of the trench and which also, owing to its open top nature can be readily manipulated on site to achieve optimum positioning of the reinforcing bars.
- the reinforcing assembly is manufactured in standard or occasionally special lengths in an orientation which is inverted compared with that shown in the drawing by bending links 20 on a former from precut lengths of reinforcing bar or automatically from a coil and placing them at predetermined spaced intervals on an assembly jig.
- a pair of longitudinal reinforcing members 18 of predetermined length is then laid on the links, each at the junction between a limb and its extension 19, and permenantly fixed thereto by, for example, spot welding.
- Reinforcing assemblies of this nature can be made up in a plurality of different lengths and once assembled one can be nested one within another for transportation, occupying the minimum storage and transportation space.
- Bundles of different length assemblies are delivered to site and on site it is a simple matter to select an assembly of suitable length for the conditions in which it is to operate and place it in the trench after having positioned in the trench bottom suitable spacer blocks 23 of plastics or other suitable material.
- the spacer blocks 23, together with the end caps 21 thus ensure the correct positioning of the longitudinal members 18 relative to the trench walls.
- the design of the foundation beam of the present invention normally calls for the placement of additional link members 20 at and near the piles 14 and this can readily be achieved on site by utilising additional link members which have not been preconnected to longitudinal members 18, simply placing them in the trench at the desired spacing over the prepositioned longitudinal members 18.
- the final stage in the construction of the reinforcing assembly is the lowering of the bottom longitudinal reinforcing member 18 to the base of the reinforcing links 20.
- the entire reinforcing system is then in position and concrete can be poured thereon in the normal manner.
- the upper surface 24 of the concrete is formed with a plurality of 3" (80 mm) deep steps 26 by the use of simple transverse shuttering boards, the viscosity of the concrete being such that with steps of this depth a continuous stepped beam can be cast without employing shuttering of greater depth than the steps, that is, shuttering to the depth of the trench.
- the concrete 22 is poured into the trench around the reinforcement such that the upper surface 24 of the concrete conforms substantially with contours of the ground.
- a second layer of concrete 25 is then poured onto the layer 24 and is formed with a plurality of 3" (80 mm) deep steps 26 as described above.
- steps of a depth of integrals of 3" may be formed with the employment of suitable shuttering. This is a convenient step depth when bricks have to be laid on the foundation. If alternative building elements have to be laid, for example concrete blocks, the dimension of the step is varied appropriately.
- the ground is first levelled in the normal manner and the trench is formed from the new ground level.
- a more conventional reinforcing system can be utilized.
- the reinforcing assembly is constructed in situ and the links 20 take the normal closed triangular form.
- the disadvantages of such a system have been described above but in certain instances it may be applicable. It has been mentioned earlier that in addition to forming the trench by soil removal using an excavator provided with a V shaped bucket it is possible to form the trench by rolling or hammering.
- Figs. 4 and 5 show diagrammatically an elevation and end view of a suitable apparatus.
- the apparatus comprises a chasis 40 which may be mounted on wheels or crawler track 42.
- the chasis supports a vibrating assembly 44 which in turn rotatably mounts the trench forming wheel 46 which, has a substantially V shaped cross-section.
- Steering means may be provided to control the direction of movement of the wheel assembly.
- the vibrator In operation once the assembly has been positioned at the starting point of the trench to be dug the vibrator is set in motion, the amplitude, frequency and direction of the vibration being so chosen that the wheel penetrates into the ground.
- the direction of applied force may be further chosen such that the vibration also causes movement of the wheel assembly in the direction of the trench to be dug.
- the wheel assembly may be provided with separate means for moving it in the desired direction.
- the assembly includes height adjustment means so that trenches of different depths can be formed .
- FIG. 6 An alternative trench forming machine is illustrated diagrammatically in Fig. 6 and comprises a wheeled or tracked vehicle 50 having at one end an assembly 52 to removably position a former 54 in the path of an impact hammer 56 which is also mounted on the vehicle.
- the former 54 has a cross-section corresponding to the cross-section of the trench, that is triangular, and can be hammered into the ground to form a short length of trench. It is then lifted out of the trench and moved along to a position above the next section of trench to be formed with the former just overlapping the previously formed section. The operation is then repeated.
- the former mounting assembly 52 is actuated to remove the former 54 from its operating position below the hammer 56 and to bring a pile driving assembly 58 into this position.
- a pile 60 can then be driven into the bottom of the trench 62 by the same machine.
- the present invention provides a reinforced concrete foundation beam the strength of which equals a conventional rectangular cross-section non-reinforced beam which utilises only 60? ⁇ of the concrete of the standard beam and which, even with its reinforcing steel, costs no more than a standard non-reinforced cross-section beam.
- the trench 12 in which the beam is formed is formed at ground level it is easy to form and does not suffer from water filling problems.
- the foundation formation is systemized it need not be inspected by Local Authority Inspectors at all stages throughout its construction.
- the inclined sides of the trench can readily accommodate ground which is subjected to heave, all that is necessary being for the pile to be constructed, according to known techniques, for ground which is subjected to heave, and the sides of the trench to be lined with a compressible material, for example, plastics material sheets or clayboard as described above.
- the substantially triangular cross-section of the beam is replaced by a more trapezoidal cross-section, that is a beam having downwardly converging sides but a substantially horizontal base.
- a rectangular cross-section beam can be provided.
- the trench is not of considerable depth and normally has downwardly converging sides it is self-supporting and readily constructable even in bad ground.
- shuttering for a triangular section cast in situ reinforced concrete beam which is formed at ground level.
- the shuttering may be permanent and sacrificial or removable and re-usable. After the beam has been cast the ground it encloses or which surrounds it may be in filled.
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Foundations (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
Claims
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB909014040A GB9014040D0 (en) | 1990-06-23 | 1990-06-23 | Improved methods for providing foundations for building structures |
GB9223376A GB2259315B (en) | 1990-06-23 | 1992-11-05 | Improved methods for providing foundations for building structures |
Applications Claiming Priority (6)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB9014040.1 | 1990-06-23 | ||
GB909014040A GB9014040D0 (en) | 1990-06-23 | 1990-06-23 | Improved methods for providing foundations for building structures |
GB909017028A GB9017028D0 (en) | 1990-08-03 | 1990-08-03 | Improved methods for providing foundations for building structures |
GB9017028.3 | 1990-08-03 | ||
GB9023945.0 | 1990-11-03 | ||
GB909023945A GB9023945D0 (en) | 1990-11-03 | 1990-11-03 | Improved methods for providing foundations for building structures |
Publications (2)
Publication Number | Publication Date |
---|---|
WO1992000425A2 true WO1992000425A2 (en) | 1992-01-09 |
WO1992000425A3 WO1992000425A3 (en) | 1992-03-19 |
Family
ID=27265155
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/GB1991/001011 WO1992000425A2 (en) | 1990-06-23 | 1991-06-21 | Improved methods for providing foundations for building structures |
Country Status (3)
Country | Link |
---|---|
AU (1) | AU8058091A (en) |
GB (2) | GB9014040D0 (en) |
WO (1) | WO1992000425A2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2010088929A1 (en) * | 2009-02-06 | 2010-08-12 | Soiltec Gmbh | Foundation for buildings |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1115381A (en) * | 1964-06-01 | 1968-05-29 | John Grosvenor De Jacobi Du Va | Improvements in and relating to lifting or positioning apparatus |
FR2576938A1 (en) * | 1985-02-01 | 1986-08-08 | Bloch Christian | Method, which may be made industrial, for building foundations and substructures for constructions with a ground floor and one storey |
US4754588A (en) * | 1987-06-26 | 1988-07-05 | Gregory Steven D | Foundation piling system |
GB2216153A (en) * | 1988-03-25 | 1989-10-04 | Roydon John Chute Thompson | Permanent shuttered in situ beam foundation system |
-
1990
- 1990-06-23 GB GB909014040A patent/GB9014040D0/en active Pending
-
1991
- 1991-06-21 WO PCT/GB1991/001011 patent/WO1992000425A2/en active Application Filing
- 1991-06-21 AU AU80580/91A patent/AU8058091A/en not_active Abandoned
-
1992
- 1992-11-05 GB GB9223376A patent/GB2259315B/en not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1115381A (en) * | 1964-06-01 | 1968-05-29 | John Grosvenor De Jacobi Du Va | Improvements in and relating to lifting or positioning apparatus |
FR2576938A1 (en) * | 1985-02-01 | 1986-08-08 | Bloch Christian | Method, which may be made industrial, for building foundations and substructures for constructions with a ground floor and one storey |
US4754588A (en) * | 1987-06-26 | 1988-07-05 | Gregory Steven D | Foundation piling system |
GB2216153A (en) * | 1988-03-25 | 1989-10-04 | Roydon John Chute Thompson | Permanent shuttered in situ beam foundation system |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2010088929A1 (en) * | 2009-02-06 | 2010-08-12 | Soiltec Gmbh | Foundation for buildings |
US8790043B2 (en) | 2009-02-06 | 2014-07-29 | Soiltec Gmbh | Foundation for buildings |
Also Published As
Publication number | Publication date |
---|---|
GB2259315A (en) | 1993-03-10 |
GB9223376D0 (en) | 1993-01-06 |
WO1992000425A3 (en) | 1992-03-19 |
GB9014040D0 (en) | 1990-08-15 |
GB2259315B (en) | 1994-05-11 |
AU8058091A (en) | 1992-01-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4697955A (en) | Method of constructing reinforced concrete works such as underground galleries, road tunnels, et cetera; pre-fabricated contrete elements for constructing such works | |
KR100713787B1 (en) | The underground structure assembly and the underground structure building method which it uses | |
JP2837128B2 (en) | Construction method of cast-in-place concrete pile | |
CN110387886B (en) | Civil air defense engineering foundation pit supporting structure and construction method thereof | |
JPH06306854A (en) | Earth retaining wall body | |
KR100289256B1 (en) | Tunnel construction method in shallow toffee area | |
KR101296857B1 (en) | Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same | |
CN106759486A (en) | A kind of underground structure being made up of stake and wall and its construction method | |
KR100784201B1 (en) | Method for construction of tunnel | |
KR20030065963A (en) | A method of constrution method for tunnel of structure pipe | |
GB2205121A (en) | Underpinning buildings by using, in situ, cast piles | |
WO1992000425A2 (en) | Improved methods for providing foundations for building structures | |
KR102289576B1 (en) | Top-down type underground structure construction method using earth support plate | |
JP6938198B2 (en) | Construction method | |
GB2255990A (en) | Underpinning buildings | |
JP3380301B2 (en) | Viaduct construction method | |
EP3783154A1 (en) | Quay wall and method for building a quay wall | |
JP5960786B2 (en) | Shield machine collection method in open shield method | |
JP2996113B2 (en) | How to build a shaft | |
JP7437336B2 (en) | Temporary cofferdam method, temporary cofferdam structure | |
JP3511145B2 (en) | How to build underground structures | |
KR102610909B1 (en) | Method and structure of steel pipe propulsion using anchor installation inside steel pipe to prevent sinking | |
NL1013267C2 (en) | Tunnel construction method for waterlogged urban area provides tunnel for underground railway and surface roadway | |
KR102149709B1 (en) | Deformation prevention method of files for retaining wall of underground | |
JP3228199U (en) | Construction structure of earth retaining support |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
AK | Designated states |
Kind code of ref document: A2 Designated state(s): AT AU BB BG BR CA CH CS DE DK ES FI GB HU JP KP KR LK LU MC MG MN MW NL NO PL RO SD SE SU US |
|
AL | Designated countries for regional patents |
Kind code of ref document: A2 Designated state(s): AT BE BF BJ CF CG CH CI CM DE DK ES FR GA GB GN GR IT LU ML MR NL SE SN TD TG |
|
AK | Designated states |
Kind code of ref document: A3 Designated state(s): AT AU BB BG BR CA CH CS DE DK ES FI GB HU JP KP KR LK LU MC MG MN MW NL NO PL RO SD SE SU US |
|
AL | Designated countries for regional patents |
Kind code of ref document: A3 Designated state(s): AT BE BF BJ CF CG CH CI CM DE DK ES FR GA GB GN GR IT LU ML MR NL SE SN TD TG |
|
WWE | Wipo information: entry into national phase |
Ref document number: 9223376.6 Country of ref document: GB |
|
REG | Reference to national code |
Ref country code: DE Ref legal event code: 8642 |
|
NENP | Non-entry into the national phase in: |
Ref country code: CA |