US3548432A - Suspension bridge cable anchorage - Google Patents

Suspension bridge cable anchorage Download PDF

Info

Publication number
US3548432A
US3548432A US614651A US3548432DA US3548432A US 3548432 A US3548432 A US 3548432A US 614651 A US614651 A US 614651A US 3548432D A US3548432D A US 3548432DA US 3548432 A US3548432 A US 3548432A
Authority
US
United States
Prior art keywords
anchorage
bearing
strands
bridge
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US614651A
Inventor
Jackson L Durkee
Frank W Neeld Jr
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Bethlehem Steel Corp
Original Assignee
Bethlehem Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Bethlehem Steel Corp filed Critical Bethlehem Steel Corp
Application granted granted Critical
Publication of US3548432A publication Critical patent/US3548432A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/14Towers; Anchors ; Connection of cables to bridge parts; Saddle supports

Definitions

  • This invention is directed to simplified, more efficient and economical anchorages for prefabricated strands in suspension bridge cables.
  • suspension bridge anchorages for prefabricated strands have generally involved structural members partially embedded in concrete, to the protruding portions of which structural members the strands are secured in various manners.
  • Typical of such anchorages are those shown in Pats. 1,852,683 to Sunderland and 2,178,147 to Moisseiif. While these anchorages have been found to adequately anchor the cable, they have certain disadvantages.
  • the metal anchor bars stretch under load and there is a tendency for a progressive breaking of the bond with the concrete beginning at the point of entry of the bar into the concrete at the forward face and working towards the rear of the anchorage. This causes cracking of the concrete, and such cracks at the front face of the anchorage create points of water entry.
  • the prestressed type of anchorage has been developed and used.
  • a rigid prefabricated assembly comprising a plurality of hollow cylindrical members secured at their lower ends to a heavy bearing slab having openings therethrough in registry with the cylindrical mem- ICC bers, embedding the said assembly in a concrete anchorage block, passing the ends of the strands to be anchored through the orifices in the anchorage block provided by the hollow cylindrical members, and seating the strand end fittings against the bearing slab adjacent the lower end of each cylindrical member by any suitable means so that the tension in the strand is taken against the bearing slab and transferred uniformly in compression into the anchorage concrete.
  • FIG. 1 is a sectional elevation of a bridge anchorage according to the present invention.
  • FIG. 2 is a detailed longitudinal section through the embedded portion of the anchorage shown in FIG. 1.
  • FIG. 3 is an end view of the embedded section along line 3-3 of FIG. 2.
  • FIGS. 4 and 5 are respectively elevations of an upper and a lower section of an anchorage assembly before embedment.
  • FIGS. 6 and 7 are respectively transverse sections along lines 6-6 and '77 of FIGS. 4 and 5.
  • FIG. 8 is a detail of the bearing end of a portion of the anchorage assembly.
  • FIG. 9 is a section of the bearing assembly of the anchorage of the present invention, along line 99 of FIG. 8.
  • FIG. 10 is a detail of the splay end of a section of the anchorage assembly.
  • FIG. 11 is a detailed longitudinal section through the embedded portion of an anchorage having diverging anchorage cylinders.
  • FIG. 12 is an end view of the embedded section of FIG. 11 along line 1212 of FIG. 11.
  • FIG. 13 is a detail of the bearing end of a portion of the anchorage of FIG. 11.
  • a suspension bridge cable 11 formed from a plurality of prefabricated strands, which strands may be either the wellknown helical-wire strands or the more modern shopfabricated parallel-wire strands, passes through an anchorage saddle 13 supported on a portion 15 of the bridge structure, from which saddle 13 the individual component strands 17 diverge from each other at predetermined splay angles to anchorage block 19.
  • Anchorage block 19 may be part of anchorage foundation 21 of the bridge.
  • Hollow anchorage cylinders 23 are embedded in anchorage block 19 to provide tubular orifices passing from one end of anchorage block 19 to the other.
  • Strands 17 pass through anchorage cylinders 23, and sockets 25 on the ends of the strands are abutted against a heavy bearing slab 27 firmly secured to the rear of anchorage cylinders 23 and partially embedded in anchorage block 19.
  • tension on strands 17 is taken in compression through shims 29 and bearing assembly 31 into bearing slab 27, and also into anchorage cylinders 23, which components then transfer the strand forces into the concrete of anchorage block 19.
  • Anchorage cylinders 23 are secured not only to bearing slab 27 but also to an intermediate embedded diaphragm plate 56 and a front diaphragm plate 53 which together with the bearing slab 27 tie the entire fabricated assembly together into a rigid structural unit. (Refer to FIGS. 3, 4 and 5). Other suitable structural members may be secured to the anchorage cylinders as may be necessary to tie them together in a unit, either in addition to or in place of plates 53 and 56. It is important that bearing slab 27 be present, however, to transfer the initial bearing of the strands uniformly into the rear face of the anchorage concrete as well as into anchorage cylinders 23. Various concrete engaging means may be welded as may be necessary to the anchorage cylinders or provided as an integral part of the outer surfaces thereof in order to increase the interlocking of the cylinders and the assembly as a Whole with the concrete of the anchorage.
  • FIG. 2 which shows a detail of the anchorage as sembly
  • end fittings or sockets are spaced from hearing slab 27 by slotted shims 29 which seat on bearing assembly 31 shown in detail in FIGS. 8 and 9.
  • Bearing assembly 31 is made in two halves 33 and 35 each comprising a flat plate 39 each with a cutout section defining, when placed around strand 17 as shown in FIG. 9, a tight fitting round hole 40 through which the strand passes.
  • To each plate is attached a half section of a tubular element 37 concentric with hole 40.
  • Strands 17 will normally have end fittings 25, of any suitable kind such as poured-zinc-type sockets, already secured on the ends before they are transported to the bridge site.
  • end fittings 25 of any suitable kind such as poured-zinc-type sockets
  • the ends with fittings 25 are pulled through anchorage cylinders 23, the two halves 33 and 35 of bearing assembly 31 are placed around each strand 17, and each assembly is placed against bearing slab 27 with the small tubular elements 37 positioned inside the slab orifice.
  • a fairlead 43 of nylon, zinc, or other suitable material is inserted in the opposite or upper end of the anchorage cylinder 23 and adjusted radially to support and direct strands 17 toward the splay point at anchorage saddle 13.
  • a stopper plug 45 of a suitable caulking material such as rubber may be cast or placed near the upper end of anchorage cylinder 23, and a filling 47 of a moisture excluding material such as chloride-free cement grout or plastic foam forced into anchorage cylinders 23 through access pipes 48 and taps 48B to provide a seal around the strands 17. Stopper 45 limits the flow of filling 47 near the upper end of anchorage cylinder 23.
  • special sealing plug 41 of rubber of other suitable dense material may be cast-in-place at the upper end of the anchorage cylinder as a means of preventing any water entry.
  • FIGS. 4 through 7 show an anchorage assembly before it is embedded in anchorage block 19.
  • This assembly may be fabricated in portions such as two halves 49 and 51 for convenience in shipping and erection.
  • Anchorage cylinders 23 in both sections are welded to heavy bearing slab sections 27A or 27B at one end by means of welds 28, and to diaphragm plate sections 53A and 53B at the other end by welds 54 with a small section of anchorage cylinders 23 protruding through plates 53A and 53B so that any moisture that may subsequently run down the front face of the anchorage housing will be deflected away from the strands in the completed anchorage.
  • Stiffening webs 55 are welded between anchorage cylinders 23 to provide additional rigidity to the entire assembly.
  • One or more intermediate diaphragm plate sections 56A and 56B secured by welds 52 to cylinders 23 may be used to give the assembly portions additional rigidity.
  • Assembly half 51 has three I-beams or support members 57 secured to it to provide attachment means for supporting it on supporting frameworks 59, as shown in FIG. 1, prior to the time that the concrete of anchorage block 19 is placed.
  • Holes 60 for lifting the assemblies are supplied in plates 27A and 27B, and 53A and 53B, reinforced with plates 58 as may be required.
  • Bearing slabs 27A and 27B and diaphragm plates 53A and 53B conveniently serve as partial concrete forms for the anchorage block 19 during its formation.
  • Splice plates 62 attached to the upper portion of hearing slab section 27B provide attachment means between slab sections 27A and 27B following assembly at the bridge site.
  • Stiffened bearing and connecting angles 63 and 64 provide a bearing surface and attachment means between diaphragm plates 53A and 53B. Aligned bolt holes, not shown, through angles 63 and 64 facilitate connection of the assemblies.
  • a small bearing bar 65 at the top of intermediate diaphragm plate 56B provides support for matching diaphragm plate 56A following erection at the bridge site. It may be desirable at times to securely Weld the two halves 49 and 51 of the anchorage assembly together at the bridge site in order to provide a rigid unitary whole.
  • the entire anchorage is customarily enclosed in a weather structure 61 as shown in dotted outline in FIG. 1, with a sealing hood 66 provided to prevent water access into the achorage.
  • the anchorage members 23 instead of being assembled in parallel relationship to each other may be assembled in diverging relationship, at the same angle as the splay angles of the respective strands 17 which pass therethrough. In this manner fairleads 43 to direct a change in direction of the strand may be eliminated and the strands 17 directed in a straight line from the splay point or anchorage saddle to a curved or stepped bearing surface at the rear of the anchorage, which surface would have to be suitably equipped with bearing slab means to transfer the stress into the concrete.
  • FIGS. 11, 12 and 13 show such a diverging anchorage assembly.
  • the parts are designated by the same numerals as used in FIGS. 1 through 10.
  • a stepped bearing surface is provided at the rear of the anchorage by the use of beveled bearing assemblies 31 composed of half sections 33 and 35 which bearing assemblies 31 are, as seen in FIG. 12, arranged so that the bevel of each assembly compensates for the various diverging angles of the anchorage cylinders 23 with respect to the flat bearing plate or slab 27.
  • the ends of the anchorage cylinders 23 are cut off square and welded at an angle within the orifices in bearing plate or slab 27.
  • the anchorage cylinders could also be cut on a bevel and butted directly against the bearing slab 27 as shown in FIG. 8.
  • An anchorage for bridge strand in a suspension bridge comprising:
  • An anchorage for bridge strand in a suspension bridge comprising:
  • (f) means secured to the ends of said bridge strands and bearing against said bearing plate.
  • a prefabricated anchorage assembly for embedment 15 in a concrete anchorage block of a bridge comprising:

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Description

Dec. 22, 1970 DURKEE El AL 3,548,432
SUSPENSION BRIDGE CABLE ANCHORAGE Filed Feb. 8, 1967 4 Sheets-Sheet 1 INVENTQRS Jae/(son L. Our/fee Fran/f H4 lVee/o Jr.
Dec. 22, 1970 L. DURKEE A 3,548,432
SUSPENSION BRIDGE CABLE ANCHORAGE Filed Feb. 8, 1967 4 Sheets-Sheet 2 INVENTO/IS Jae/(son L. Dar/fee flan/r M lVee/a L/r.
Dec. 22, 1970 DURKEE ETAL 3,548,432
SUSPENSION BRIDGE CABLE ANCHORAGE Filed Feb. 8, 1967 4 Sheets-Sheet 5 Jackson L. Our/fee Fran/f M A/ce/a Jr.
INVENTORS Dec. 22-, 1970 ,DURKEE EIAL 3,548,432
SUSPENSION BRIDGE CABLE ANCHORAGE Filed Feb. 8, 1967 4 Sheets-Sheet 4.
. INVENTORS Jae/(son L. Dl/r/(ce Han/f M4 A ee/o L/r.
United States Patent O 3,548,432 SUSPENSION BRIDGE CABLE ANCHORAGE Jackson L. Durkee, Bethlehem, and Frank W. Neeld,
In, Riegelsville, Pa, assignors to Bethlehem Steel Corporation, a corporation of Delaware Filed Feb. 8, 1967, Ser. No. 614,651. Int. Cl. E0111 11/00 US. Cl. 1421 3 Claims ABSTRACT OF THE DISCLOSURE An anchorage for prefabricated strands of suspension bridge cables wherein a series of adjacent hollow cylindrical members are integrally attached to a heavy backing plate to form a unitary anchorage means which is then embedded in a concrete anchorage block. Individual strands of the suspension cable are passed through the cylindrical members and secured against the backing plate so that the tension of the strands is uniformly transferred throughout the anchorage block by the backing plate and the cylindrical members.
BACKGROUND OF THE INVENTION This invention is directed to simplified, more efficient and economical anchorages for prefabricated strands in suspension bridge cables.
In the past, suspension bridge anchorages for prefabricated strands have generally involved structural members partially embedded in concrete, to the protruding portions of which structural members the strands are secured in various manners. Typical of such anchorages are those shown in Pats. 1,852,683 to Sunderland and 2,178,147 to Moisseiif. While these anchorages have been found to adequately anchor the cable, they have certain disadvantages. The metal anchor bars stretch under load and there is a tendency for a progressive breaking of the bond with the concrete beginning at the point of entry of the bar into the concrete at the forward face and working towards the rear of the anchorage. This causes cracking of the concrete, and such cracks at the front face of the anchorage create points of water entry. In order to overcome these objections the prestressed type of anchorage has been developed and used. These anchorages, while effective, are considerably more expensive because of the complicated prestressing components and procedures, the complicated tension linkages at the front of the anchorage, and for other significant reasons.
Attempts have been made to provide a simpler anchorage for structural cables by passing the cable through an opening in an anchorage block and securing the cable at the rear of the block. A specialized form of such an anchorage arrangement is shown in Pat. 2,914,783 to Hoyden et a1. Such anchorages are not completely satisfactory, however, as they do not uniformly distribute the load throughout the anchorage concrete, and, depending upon the particular design, may also experience difficulty due to poor bond of metalwork with concrete.
SUMMARY OF THE INVENTION It is an object of this invention to provide a simplified bridge cable anchorage which distributes the load uniformly throughout the anchorage and preserves the integrity of the concrete, and which is, at the same time, cheaper, simpler, and faster to construct than anchorages heretofore known.
We have discovered that the foregoing object can be attained by providing a rigid prefabricated assembly comprising a plurality of hollow cylindrical members secured at their lower ends to a heavy bearing slab having openings therethrough in registry with the cylindrical mem- ICC bers, embedding the said assembly in a concrete anchorage block, passing the ends of the strands to be anchored through the orifices in the anchorage block provided by the hollow cylindrical members, and seating the strand end fittings against the bearing slab adjacent the lower end of each cylindrical member by any suitable means so that the tension in the strand is taken against the bearing slab and transferred uniformly in compression into the anchorage concrete.
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a sectional elevation of a bridge anchorage according to the present invention.
FIG. 2 is a detailed longitudinal section through the embedded portion of the anchorage shown in FIG. 1.
FIG. 3 is an end view of the embedded section along line 3-3 of FIG. 2.
FIGS. 4 and 5 are respectively elevations of an upper and a lower section of an anchorage assembly before embedment.
FIGS. 6 and 7 are respectively transverse sections along lines 6-6 and '77 of FIGS. 4 and 5.
FIG. 8 is a detail of the bearing end of a portion of the anchorage assembly.
FIG. 9 is a section of the bearing assembly of the anchorage of the present invention, along line 99 of FIG. 8.
FIG. 10 is a detail of the splay end of a section of the anchorage assembly.
FIG. 11 is a detailed longitudinal section through the embedded portion of an anchorage having diverging anchorage cylinders.
FIG. 12 is an end view of the embedded section of FIG. 11 along line 1212 of FIG. 11.
FIG. 13 is a detail of the bearing end of a portion of the anchorage of FIG. 11.
DESCRIPTION OF THE PREFERRED EMBODIMENT Referring to the draings, as shown in FIG. 1 a suspension bridge cable 11 formed from a plurality of prefabricated strands, which strands may be either the wellknown helical-wire strands or the more modern shopfabricated parallel-wire strands, passes through an anchorage saddle 13 supported on a portion 15 of the bridge structure, from which saddle 13 the individual component strands 17 diverge from each other at predetermined splay angles to anchorage block 19. Anchorage block 19 may be part of anchorage foundation 21 of the bridge. Hollow anchorage cylinders 23 are embedded in anchorage block 19 to provide tubular orifices passing from one end of anchorage block 19 to the other. Strands 17 pass through anchorage cylinders 23, and sockets 25 on the ends of the strands are abutted against a heavy bearing slab 27 firmly secured to the rear of anchorage cylinders 23 and partially embedded in anchorage block 19. Referring to FIG. 2, tension on strands 17 is taken in compression through shims 29 and bearing assembly 31 into bearing slab 27, and also into anchorage cylinders 23, which components then transfer the strand forces into the concrete of anchorage block 19.
Anchorage cylinders 23 are secured not only to bearing slab 27 but also to an intermediate embedded diaphragm plate 56 and a front diaphragm plate 53 which together with the bearing slab 27 tie the entire fabricated assembly together into a rigid structural unit. (Refer to FIGS. 3, 4 and 5). Other suitable structural members may be secured to the anchorage cylinders as may be necessary to tie them together in a unit, either in addition to or in place of plates 53 and 56. It is important that bearing slab 27 be present, however, to transfer the initial bearing of the strands uniformly into the rear face of the anchorage concrete as well as into anchorage cylinders 23. Various concrete engaging means may be welded as may be necessary to the anchorage cylinders or provided as an integral part of the outer surfaces thereof in order to increase the interlocking of the cylinders and the assembly as a Whole with the concrete of the anchorage.
In FIG. 2, which shows a detail of the anchorage as sembly, it is seen that end fittings or sockets are spaced from hearing slab 27 by slotted shims 29 which seat on bearing assembly 31 shown in detail in FIGS. 8 and 9. Bearing assembly 31 is made in two halves 33 and 35 each comprising a flat plate 39 each with a cutout section defining, when placed around strand 17 as shown in FIG. 9, a tight fitting round hole 40 through which the strand passes. To each plate is attached a half section of a tubular element 37 concentric with hole 40.
Strands 17 will normally have end fittings 25, of any suitable kind such as poured-zinc-type sockets, already secured on the ends before they are transported to the bridge site. When the strands 17 are erected the ends with fittings 25 are pulled through anchorage cylinders 23, the two halves 33 and 35 of bearing assembly 31 are placed around each strand 17, and each assembly is placed against bearing slab 27 with the small tubular elements 37 positioned inside the slab orifice. A fairlead 43 of nylon, zinc, or other suitable material is inserted in the opposite or upper end of the anchorage cylinder 23 and adjusted radially to support and direct strands 17 toward the splay point at anchorage saddle 13.
After the full dead load of the bridge is in place and the strands are fully tensioned, a stopper plug 45 of a suitable caulking material such as rubber may be cast or placed near the upper end of anchorage cylinder 23, and a filling 47 of a moisture excluding material such as chloride-free cement grout or plastic foam forced into anchorage cylinders 23 through access pipes 48 and taps 48B to provide a seal around the strands 17. Stopper 45 limits the flow of filling 47 near the upper end of anchorage cylinder 23. Lastly, special sealing plug 41 of rubber of other suitable dense material may be cast-in-place at the upper end of the anchorage cylinder as a means of preventing any water entry.
FIGS. 4 through 7 show an anchorage assembly before it is embedded in anchorage block 19. This assembly may be fabricated in portions such as two halves 49 and 51 for convenience in shipping and erection. Anchorage cylinders 23 in both sections are welded to heavy bearing slab sections 27A or 27B at one end by means of welds 28, and to diaphragm plate sections 53A and 53B at the other end by welds 54 with a small section of anchorage cylinders 23 protruding through plates 53A and 53B so that any moisture that may subsequently run down the front face of the anchorage housing will be deflected away from the strands in the completed anchorage. Stiffening webs 55 are welded between anchorage cylinders 23 to provide additional rigidity to the entire assembly. One or more intermediate diaphragm plate sections 56A and 56B secured by welds 52 to cylinders 23 may be used to give the assembly portions additional rigidity.
Assembly half 51 has three I-beams or support members 57 secured to it to provide attachment means for supporting it on supporting frameworks 59, as shown in FIG. 1, prior to the time that the concrete of anchorage block 19 is placed. Holes 60 for lifting the assemblies are supplied in plates 27A and 27B, and 53A and 53B, reinforced with plates 58 as may be required. Bearing slabs 27A and 27B and diaphragm plates 53A and 53B conveniently serve as partial concrete forms for the anchorage block 19 during its formation.
Splice plates 62 attached to the upper portion of hearing slab section 27B provide attachment means between slab sections 27A and 27B following assembly at the bridge site. Stiffened bearing and connecting angles 63 and 64 provide a bearing surface and attachment means between diaphragm plates 53A and 53B. Aligned bolt holes, not shown, through angles 63 and 64 facilitate connection of the assemblies. A small bearing bar 65 at the top of intermediate diaphragm plate 56B provides support for matching diaphragm plate 56A following erection at the bridge site. It may be desirable at times to securely Weld the two halves 49 and 51 of the anchorage assembly together at the bridge site in order to provide a rigid unitary whole.
The entire anchorage is customarily enclosed in a weather structure 61 as shown in dotted outline in FIG. 1, with a sealing hood 66 provided to prevent water access into the achorage.
If a larger anchorage block 19 and anchorage assemblies 49 and 51 are not detrimental, the anchorage members 23 instead of being assembled in parallel relationship to each other may be assembled in diverging relationship, at the same angle as the splay angles of the respective strands 17 which pass therethrough. In this manner fairleads 43 to direct a change in direction of the strand may be eliminated and the strands 17 directed in a straight line from the splay point or anchorage saddle to a curved or stepped bearing surface at the rear of the anchorage, which surface would have to be suitably equipped with bearing slab means to transfer the stress into the concrete.
FIGS. 11, 12 and 13 show such a diverging anchorage assembly. The parts are designated by the same numerals as used in FIGS. 1 through 10. A stepped bearing surface is provided at the rear of the anchorage by the use of beveled bearing assemblies 31 composed of half sections 33 and 35 which bearing assemblies 31 are, as seen in FIG. 12, arranged so that the bevel of each assembly compensates for the various diverging angles of the anchorage cylinders 23 with respect to the flat bearing plate or slab 27. For convenience of fabrication the ends of the anchorage cylinders 23 are cut off square and welded at an angle within the orifices in bearing plate or slab 27. As an alternative the anchorage cylinders could also be cut on a bevel and butted directly against the bearing slab 27 as shown in FIG. 8.
By the arrangement of this invention there is provided an economic and convenient bridge anchorage wherein the tension of the suspension strands is taken in direct compression on the rear surface of the anchorage and is dispersed uniformly throughout the anchorage block to secure the strength and safety of a prestressed embedded type anchorage without the expense and complications of such anchorages.
We claim:
1. An anchorage for bridge strand in a suspension bridge comprising:
(a) a concrete anchorage block at one end of the bridge span,
(b) a plurality of hollow cylindrical members arranged in a pattern adjacent to each other in a substantially parallel relationship embedded in said anchorage block,
(c) a perforated bearing slab mounted against one end of said concrete anchorage block,
(d) the end portions of said cylindrical members being secured to said bearing slab in registry with the perforations in said bearing slab,
(e) a plurality of bridge strands extending through said cylindrical members,
(f) means secured to the ends of said bridge strands and bearing against said bearing slab, and
(g) a fairlead at the upper end of each hollow cylindrical member on the inside of any curvature of the strand leaving the hollow member to direct the strand to a splay point where the strands are brought together to form a bridge suspension cable comprised of the said strands.
2. An anchorage for bridge strand in a suspension bridge comprising:
(a) a concrete anchorage block at one end of the bridge span, said block having a lower face,
(b) a perforated metal bearing plate bearing against the lower face of the anchorage block,
(c) a perforated metal support plate spaced from said bearing plate,
(d) a plurality of rigid hollow metal cylindrical members arranged in a pattern adjacent to each other, embedded in said anchorage block, and fixedly secured at their outer ends to the bearing plate and the support plate in registry with the perforations therein;
(e) a plurality of bridge strands extending through said cylindrical members, and
(f) means secured to the ends of said bridge strands and bearing against said bearing plate.
3. A prefabricated anchorage assembly for embedment 15 in a concrete anchorage block of a bridge comprising:
(a) a perforated metal bearing plated adapted to bear against a lower face of said anchorage block, (b) a perforated metal support plate spaced from said bearing plate,
(c) a plurality of rigid hollow metal cylindrical members arranged in a pattern adjacent to each other and fixed secured at their outer ends to the bearing plate and the support plate in registry with the perforations 5 therein.
References Cited UNITED STATES PATENTS 2,914,783 12/1959 Hoyden et a1 1421 3,156,169 11/1964 Finsterwalder 948 10 3,225,499 12/1965 Kourkene 52-230 FOREIGN PATENTS 892,046 1/1944 France 14-21 906,940 3/1954 Germany 14-21 JACOB L. NACKENOFF, Primary Examiner US. Cl. X.R. 52-230.
US614651A 1967-02-08 1967-02-08 Suspension bridge cable anchorage Expired - Lifetime US3548432A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US61465167A 1967-02-08 1967-02-08

Publications (1)

Publication Number Publication Date
US3548432A true US3548432A (en) 1970-12-22

Family

ID=24462172

Family Applications (1)

Application Number Title Priority Date Filing Date
US614651A Expired - Lifetime US3548432A (en) 1967-02-08 1967-02-08 Suspension bridge cable anchorage

Country Status (3)

Country Link
US (1) US3548432A (en)
FR (1) FR1553466A (en)
GB (1) GB1216708A (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3864776A (en) * 1973-11-15 1975-02-11 Parson Brinckerhoff Quade & Do Prestressed post tension suspension bridge cable anchorage
US4473915A (en) * 1981-09-30 1984-10-02 Dyckerhoff & Widmann Aktiengesellschaft Tension member and a method of assembling and installing the tension member
US4484425A (en) * 1982-07-21 1984-11-27 Figg And Muller Engineers, Inc. Anchorage of cables
US6560807B1 (en) * 1999-09-15 2003-05-13 Freyssinet International (Stup) Cable with parallel wires for building work structure, anchoring for said cable, and anchoring method
US20030182739A1 (en) * 2002-04-02 2003-10-02 Figg Eugene C. Cable-stay cradle system
US20120255272A1 (en) * 2011-04-07 2012-10-11 Soletanche Freyssinet Method and device for protecting the end of an anchored cable
US20150275462A1 (en) * 2012-02-02 2015-10-01 Empire Technology Development Llc Modular concrete reinforcement
US20150300452A1 (en) * 2014-04-22 2015-10-22 Richard V. Campbell Advanced Stranded Cable Termination Methods and Designs
US20160168855A1 (en) * 2013-08-01 2016-06-16 Dywidag-Systems International Gmbh Corrosion-protected tension member and plastically deformable disc of corrosion protection material for such a tension member
CN107245948A (en) * 2017-07-27 2017-10-13 德阳天元重工股份有限公司 A kind of multi-functional cable saddle
US9850630B2 (en) * 2013-05-31 2017-12-26 Vsl International Ag Cable anchorage with bedding material
CN109505260A (en) * 2018-12-25 2019-03-22 中铁大桥局第七工程有限公司 A kind of positioning device and localization method of finished main cable shape of self-anchored suspension anchor tube
CN110886218A (en) * 2019-12-02 2020-03-17 湖北省路桥集团有限公司 Main cable profile steel anchoring system of large-span suspension bridge and construction method
CN112411388A (en) * 2020-11-26 2021-02-26 西南交通大学 Alignment erection method for main cable strand marks of suspension bridge based on multi-reference cable strands

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH662595A5 (en) * 1983-08-22 1987-10-15 Losinger Ag ANCHORING OF FREELY SWINGING STEEL ELEMENTS OF A DYNAMICALLY STRESSED COMPONENT.
GB8410253D0 (en) * 1984-04-19 1984-05-31 Manuf Aceros Caucho Sa Deflector element in cable anchorages
US4663907A (en) * 1985-06-26 1987-05-12 Manufacturas De Acero Y Caucho S.A. Anchorage for stressed reinforcing tendon
CN105155413B (en) * 2015-08-14 2017-01-11 山东大学 Partial non-bonded tunnel type compound anchorage system and method
CN105937208B (en) * 2016-06-21 2017-06-23 中国水利水电第五工程局有限公司 A kind of laser trimming equipment that positioning is installed for anchorage pre-stressed steel pipe
CN107059617A (en) * 2016-12-24 2017-08-18 中铁十八局集团有限公司 A kind of interim anchorage of combined type
CN113235426A (en) * 2021-05-17 2021-08-10 中建桥梁有限公司 Anchorage anchoring system positioning device and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR892046A (en) * 1943-03-09 1944-03-27 Anchoring mass for suspension bridges
DE906940C (en) * 1952-08-07 1954-03-18 Dyckerhoff & Widmann Ag Anchoring the suspension cables of a suspension bridge
US2914783A (en) * 1953-04-10 1959-12-01 Gutehoffnungshuette Sterkrade Bridge construction
US3156169A (en) * 1964-11-10 Finsterwalder
US3225499A (en) * 1962-07-02 1965-12-28 Jack P Kourkene Post tensioning concrete reinforcing wires

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3156169A (en) * 1964-11-10 Finsterwalder
FR892046A (en) * 1943-03-09 1944-03-27 Anchoring mass for suspension bridges
DE906940C (en) * 1952-08-07 1954-03-18 Dyckerhoff & Widmann Ag Anchoring the suspension cables of a suspension bridge
US2914783A (en) * 1953-04-10 1959-12-01 Gutehoffnungshuette Sterkrade Bridge construction
US3225499A (en) * 1962-07-02 1965-12-28 Jack P Kourkene Post tensioning concrete reinforcing wires

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3864776A (en) * 1973-11-15 1975-02-11 Parson Brinckerhoff Quade & Do Prestressed post tension suspension bridge cable anchorage
US4473915A (en) * 1981-09-30 1984-10-02 Dyckerhoff & Widmann Aktiengesellschaft Tension member and a method of assembling and installing the tension member
US4484425A (en) * 1982-07-21 1984-11-27 Figg And Muller Engineers, Inc. Anchorage of cables
US6560807B1 (en) * 1999-09-15 2003-05-13 Freyssinet International (Stup) Cable with parallel wires for building work structure, anchoring for said cable, and anchoring method
US6658684B2 (en) 1999-09-15 2003-12-09 Freyssinet International (Stup) Cable with parallel wires for building work structure, anchoring for said cable and anchoring method
US20030182739A1 (en) * 2002-04-02 2003-10-02 Figg Eugene C. Cable-stay cradle system
US6880193B2 (en) * 2002-04-02 2005-04-19 Figg Bridge Engineers, Inc. Cable-stay cradle system
US20050086751A1 (en) * 2002-04-02 2005-04-28 Figg Eugene C.Jr. Cable-stay cradle system
US7003835B2 (en) * 2002-04-02 2006-02-28 Figg Bridge Engineers, Inc. Cable-stay cradle system
US8769921B2 (en) * 2011-04-07 2014-07-08 Soletanche Freyssinet Method and device for protecting the end of an anchored cable
US20120255272A1 (en) * 2011-04-07 2012-10-11 Soletanche Freyssinet Method and device for protecting the end of an anchored cable
US20150275462A1 (en) * 2012-02-02 2015-10-01 Empire Technology Development Llc Modular concrete reinforcement
US9725867B2 (en) * 2012-02-02 2017-08-08 Empire Technology Development Llc Modular concrete reinforcement
US9850630B2 (en) * 2013-05-31 2017-12-26 Vsl International Ag Cable anchorage with bedding material
US20160168855A1 (en) * 2013-08-01 2016-06-16 Dywidag-Systems International Gmbh Corrosion-protected tension member and plastically deformable disc of corrosion protection material for such a tension member
US10889988B2 (en) 2013-08-01 2021-01-12 Dywidag-Systems International Gmbh Corrosion-protected tension member and plastically deformable disc of corrosion protection material for such a tension member
US20150300452A1 (en) * 2014-04-22 2015-10-22 Richard V. Campbell Advanced Stranded Cable Termination Methods and Designs
US10578191B2 (en) * 2014-04-22 2020-03-03 Bright Technologies, Llc Advanced stranded cable termination methods and designs
CN107245948A (en) * 2017-07-27 2017-10-13 德阳天元重工股份有限公司 A kind of multi-functional cable saddle
CN109505260A (en) * 2018-12-25 2019-03-22 中铁大桥局第七工程有限公司 A kind of positioning device and localization method of finished main cable shape of self-anchored suspension anchor tube
CN110886218A (en) * 2019-12-02 2020-03-17 湖北省路桥集团有限公司 Main cable profile steel anchoring system of large-span suspension bridge and construction method
CN112411388A (en) * 2020-11-26 2021-02-26 西南交通大学 Alignment erection method for main cable strand marks of suspension bridge based on multi-reference cable strands

Also Published As

Publication number Publication date
FR1553466A (en) 1969-01-10
GB1216708A (en) 1970-12-23

Similar Documents

Publication Publication Date Title
US3548432A (en) Suspension bridge cable anchorage
US4972537A (en) Orthogonally composite prefabricated structural slabs
US3585771A (en) Connecting precast concrete structural members
US4587684A (en) Precast concrete bridge
JP6375195B2 (en) Widened PC slab structure and widening method of existing PC slab
US5457839A (en) Bridge deck system
CN109281436A (en) Pretensioned prestressing laminated frame is set a roof beam in place and its construction method
KR101913069B1 (en) Prestressed Steel-Concrete Composite Girder and Method for Fabricating thereof
US3501881A (en) Reinforcement of concrete structures
KR101705002B1 (en) Prefabricated double composite plate girder bridge and its construction method
KR100388078B1 (en) Apparatus to repair and reinforce bridge and thereof method
CN110117931A (en) Prefabricated PC combined box beam
US2208814A (en) Building construction
US2685194A (en) Precast concrete framing construction
KR20180126939A (en) composite girder which uses a filled steel pipe as a web member and ties and connects with a steel wire
KR102159429B1 (en) Cross section stiffnesses enhanced saddle sttached temporary bridge and method of structure using the same
KR102140167B1 (en) Strengthening method of concrete structures by pretensioning
CN114045750B (en) Construction method of high pier column tie beam
KR200184684Y1 (en) Apparatus to prevent the negative moment of a bridge
JPH08312061A (en) Steel column member and leg part fixing structure thereof
KR102072655B1 (en) Method for producing steel tube partially filled with concrete and steel tube partially filled with concrete produced thereby
KR100596072B1 (en) Composite Beam Stiffened with Prestressed Concrete Panel Having Embedded Lower Flange and Constructing Method thereof
US2132269A (en) Cable anchor
KR101357637B1 (en) Horizontal shear connector for precast concrete bridge pier
KR102598284B1 (en) Tendon buried concrete structure for external pre-tensioning reinforcement, and construction method for the same