US3402559A - Process of forming a large-diameter tubular pile foundation - Google Patents

Process of forming a large-diameter tubular pile foundation Download PDF

Info

Publication number
US3402559A
US3402559A US646116A US64611667A US3402559A US 3402559 A US3402559 A US 3402559A US 646116 A US646116 A US 646116A US 64611667 A US64611667 A US 64611667A US 3402559 A US3402559 A US 3402559A
Authority
US
United States
Prior art keywords
tubular
concrete
section
pipe piles
forming
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US646116A
Other languages
English (en)
Inventor
Fukushima Yoshikiyo
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Concrete Industries Co Ltd
Original Assignee
Nippon Concrete Industries Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Concrete Industries Co Ltd filed Critical Nippon Concrete Industries Co Ltd
Application granted granted Critical
Publication of US3402559A publication Critical patent/US3402559A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • E02D5/523Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments

Definitions

  • a number of tubular concrete sections are formed at the work site one on another in vertically aligned relation to form an integral tubular concrete pile structure, which is let down vertically through the water to reach the bottom ground.
  • Each of the tubular sections has a reinforcement including a set of vertical pipe piles, of concrete or steel, arranged in a circle. Such pipe piles in the sections are securely joined together to form multiplelength pipe piles extending from top to bottom of the pile structure.
  • the tubular sections may be precast.
  • This invention relates to the forming of pile foundation and has for its object to provide a novel foundation process by which foundations required to withstand heavy loads, for example, bridge piers set in a sea or a river, can be formed easily in short periods of time.
  • a tubular foundation is fabricated by vertically arranging a mumtude of hollow pie piles, for example, of concrete or steel in a circle, forming a tubular concrete section including the pipe piles as its core, joining with the top end of the piles another set of similar piles in the same circular arrangement, forming a second tubular concrete section including the second set of piles as its core, and repeating the procedure a required number of times to obtain a tubular foundation of a desired axial or vertical length.
  • FIGS. 1 and 1a illustrate two different forms of pipe pile usable in the process of the invention, FIG. 1 representing a vertical axial cross section of a concrete pipe pile reinforced wtih pretensioned tendons or wires while FIG. 1a representing a side elevation, partly in cross section, of a steel pipe pile;
  • FIG. 2 is a vertical axial cross section of a doublewalled tubular mold in which concrete is placed with the pipe piles vertically arranged in the annular space between the inner and outer walls of the mold;
  • FIG. 3 is a plan view of same, partly in transverse cross section, taken along the line III-III in FIG. 2;
  • FIG. 4 is a vertical axial cross section showing a second tubular concrete section formed integral with the first tubular concrete section of FIGS, 2 and 3 by welding the bottom ends of similar pipe piles together with the top ends of the respective pipe piles embedded in the first tubular concrete section and placing concrete in a similar double-walled tubular mold mounted on the first tubular concrete section;
  • FIGS. 5 and 6 illustrate the different stages of the step of letting down a tubular concrete structure formed to a predetermined length by the previous steps vertically through the water and the muddy deposit to the supporting ground;
  • FIG. 7 is a vertical axial cross section showing how the precast tubular concrete sections are joined at the work site to obtain a desired length of tubular structure
  • FIG. 8 is a side elevation, partly in section, showing how pressure water is led through the pipe piles to jet out from their bottom ends as the tubular concrete structure of the invention is let down through the underwater muddy deposit to the supporting ground.
  • FIG. 1 there is shown one form of pipe pile usable in the fabrication of foundations according to the present invention which is a prestressed concrete pipe pile including annular end plates of iron 11 and 12 having central openings 11a and 12a, respectively, and a multitude of pretensioned wires 13 extending between the end plates.
  • FIG. 1a Another form of pipe pile is shown in FIG. 1a, which is of steel.
  • a number of pipe piles in the form of FIG. 1 or FIG. 1a are vertically arranged in a circle, as shown in FIGS. 2 and 3.
  • tendons are applied to the circular arrangement of pipe piles in a spiral or circumferential fashion and joined together by connecting wires manually or by welding to form a tubular basket-like reinforcement structure including the pipe piles 1.
  • This reinforcement structure is placed in a double-walled tubular mold or form in the annular space between its inner and outer walls 4 and 40, As observed from FIG. 2, the pipe piles 1 in the reinforcement are of such length that their top ends extend above the top of the tubular mold 4-40.
  • concrete 5 is placed in the mold to form a first tubular section A.
  • a set of similar pipe piles 1 are arranged, as shown in FIG. 4, on the tubular section A in the same manner as those embedded therein with the bottom end plate 11 of each of the pipe piles placed in contact with the adjacent end plate 12 of the corresponding embedded pipe pile 1 in aligned relation to each other and such adjacent end plates 11 and 12 are Welded together.
  • Transverse and connecting tendons are applied to the second set of pipe piles 1, now integral with the first set, in the same manner as described above with the latter to form another tubular basket-like reinforcement structure.
  • a second tubular double-walled mold 4-40 is mounted on the tubular section A to surround the reinforcement structure and again concrete is placed in the mold to form a second tubular concrete section B integral with and similar to the first section A.
  • tubular pile structures can be fabricated on land which range in length from about 20 to 30 meters and in diameter from about 3 to 8 meters.
  • FIG. 5 One example of such tubular pile structure 6 is shown in FIG. 5, which includes three tubular sections A, B and C.
  • step 5 the tubular pile structure 6 is set on the supporting ground at the bottom of a sea or a river by letting down such structure vertically through the water.
  • step 6 when the structure 6 being let down reaches the surface H of the muddly deposit lying below the water surface S before reaching the bottom ground X, as shown in FIG, 5, the structure may be axially extended by substantially the same procedure described hereinbefore.
  • tubular sections D and E are the ones connected at the work site with the consecutive top section C or D of the pile structure 6 before the bottom section A of the structure 6 is set in the ground at an appropriate depth as a pile foundation to support a desired superstructure 8.
  • jacks can serve to help level the superstructure 8 as the tubular pile foundation 6 sinks secularly in the source of seasoning. In this case, when the secular sink has practically ceased, concrete is placed in the region of jacks 7 to complete the foundation work.
  • the letting down of the structure 6 can be facilitated by expelling the mud at its bottom.
  • the sets of pipe piles 1 of prestressed concrete or 1a of steel, embedded in the successive tubular sections A, B and C, are vertically aligned with each other, forming multiple-length pipe piles each defining a continuous hole 10 extending vertically through the tubular pile structure 6, as shown in FIG. 8.
  • jets of water can be formed to expel the neighboring mud at the bottom of the descending pile structure 6, as indicated by the arrows in FIG. 8, by feeding pressure water into the holes 10 at their top end.
  • tubular concrete structure for example, shown in FIG. 4, is fabricated at the work site by the procedure explained with reference to FIGS. 2, 3 and 4, it may also be fabricated by precasting individual tubular concrete sections A and B, each including for reinforcement a number of pipe piles 1 exposed at both top and bottom, as shown in FIG. 7.
  • precast sections they are placed one on another in vetrically alignment and the adjoining ends 11 and 12 of the vertically aligned pipe piles are interconnected as by welding.
  • an annular joint 30 of concrete is cast between the precast sections A and B, encircling the welded pipe joints, thereby to form an integral concrete structure.
  • a process of forming a large-diameter tubular pile foundation comprising a first step including the substeps of vertically arranging a set of pipe piles in a circle, applying tendons to the circular arrangement of pipe piles to form a basket-like reinforcement, inserting the reinforcement in the annular space in a double-walled tubular mold, and placing concrete in the mold to form a first tubular section; a second step including the substeps of securely connecting another set of pipe piles with the respective pipe piles embedded in said first tubular section at the top end thereof in aligned abutting relation with each other, applying tendons to the second set of pipe piles to form a basket-like reinforcement, setting up a double-walled tubular mold on the top of said first tubular section in aligned relation thereto and placing concrete in the annular space of the secondmentioned tubular mold to form a second tubular section integral with the first tubular section, and repeating such set of substeps to form further tubular sections to obtain an integral tubular structure of
  • a process of forming a large-diameter tubular pile foundation as set forth in claim 2 including a further step of arranging on the top end surface of the extended tubular structure a number of hydraulic jacks operable to keep the level of the superstructure built thereon in spite of any possible secular sink of the tubular structure under the load of the superstructure, and placing concrete about the jacks to set the level of the superstructure when the secular change has practically ceased.

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Piles And Underground Anchors (AREA)
  • Revetment (AREA)
  • Foundations (AREA)
US646116A 1966-09-26 1967-06-14 Process of forming a large-diameter tubular pile foundation Expired - Lifetime US3402559A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP41062991A JPS4834684B1 (enrdf_load_stackoverflow) 1966-09-26 1966-09-26

Publications (1)

Publication Number Publication Date
US3402559A true US3402559A (en) 1968-09-24

Family

ID=13216332

Family Applications (1)

Application Number Title Priority Date Filing Date
US646116A Expired - Lifetime US3402559A (en) 1966-09-26 1967-06-14 Process of forming a large-diameter tubular pile foundation

Country Status (4)

Country Link
US (1) US3402559A (enrdf_load_stackoverflow)
JP (1) JPS4834684B1 (enrdf_load_stackoverflow)
GB (1) GB1177970A (enrdf_load_stackoverflow)
MY (1) MY7100010A (enrdf_load_stackoverflow)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3537268A (en) * 1967-08-09 1970-11-03 Hans Christer Georgii Marine station and method for fabricating the same
US3958426A (en) * 1971-03-02 1976-05-25 Sigurd Heien Offshore harbor tank and installation
US3965688A (en) * 1973-07-25 1976-06-29 C. G. Doris Underwater structures, in particular for underwater drilling operations
US4273475A (en) * 1976-09-22 1981-06-16 Raymond International Inc. Load supporting structure
WO1984003528A1 (en) * 1983-03-01 1984-09-13 Finic Bv Method and apparatus for constructing reinforced concrete walls in the earth
US4824290A (en) * 1985-11-17 1989-04-25 Ahmad Masoudi Method of constructing a rigid structure upon the bottom of a water as well as lost casing for performing said method
AU601115B2 (en) * 1988-09-02 1990-08-30 Darya Paye Jetty Co. Ltd. Method and apparatus for placing a hollow column in the hard bottom of a body of water in particular in a rock bottom
US5487251A (en) * 1994-05-06 1996-01-30 Independent Concrete Pipe Apparatus and method for reinforcing cast structures
US20100170183A1 (en) * 2009-01-08 2010-07-08 Tarik Ali Abulaban Reinforced load bearing structure

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1665795A (en) * 1923-11-03 1928-04-10 George B Sipe Method of producing subaqueous foundations, piers, breakwaters, etc.
GB732494A (en) * 1952-12-30 1955-06-22 Gammon Malaya Ltd Improvements in or relating to concrete and the like piles

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1665795A (en) * 1923-11-03 1928-04-10 George B Sipe Method of producing subaqueous foundations, piers, breakwaters, etc.
GB732494A (en) * 1952-12-30 1955-06-22 Gammon Malaya Ltd Improvements in or relating to concrete and the like piles

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3537268A (en) * 1967-08-09 1970-11-03 Hans Christer Georgii Marine station and method for fabricating the same
US3958426A (en) * 1971-03-02 1976-05-25 Sigurd Heien Offshore harbor tank and installation
US3965688A (en) * 1973-07-25 1976-06-29 C. G. Doris Underwater structures, in particular for underwater drilling operations
US4273475A (en) * 1976-09-22 1981-06-16 Raymond International Inc. Load supporting structure
WO1984003528A1 (en) * 1983-03-01 1984-09-13 Finic Bv Method and apparatus for constructing reinforced concrete walls in the earth
US4496268A (en) * 1983-03-01 1985-01-29 Finic, B.V. Method and apparatus for constructing reinforced concrete walls in the earth
US4824290A (en) * 1985-11-17 1989-04-25 Ahmad Masoudi Method of constructing a rigid structure upon the bottom of a water as well as lost casing for performing said method
US4923334A (en) * 1985-11-17 1990-05-08 Ahmad Masoudi Lost casing for constructing a rigid structure upon the bottom of a body of water
AU601115B2 (en) * 1988-09-02 1990-08-30 Darya Paye Jetty Co. Ltd. Method and apparatus for placing a hollow column in the hard bottom of a body of water in particular in a rock bottom
US5487251A (en) * 1994-05-06 1996-01-30 Independent Concrete Pipe Apparatus and method for reinforcing cast structures
US20100170183A1 (en) * 2009-01-08 2010-07-08 Tarik Ali Abulaban Reinforced load bearing structure

Also Published As

Publication number Publication date
MY7100010A (en) 1971-12-31
JPS4834684B1 (enrdf_load_stackoverflow) 1973-10-23
DE1634505A1 (de) 1971-12-02
GB1177970A (en) 1970-01-14

Similar Documents

Publication Publication Date Title
US9739027B2 (en) Perimeter pile anchor foundation
US3431736A (en) Method of constructing underground concrete walls
US3402559A (en) Process of forming a large-diameter tubular pile foundation
US2933898A (en) Offshore platform structures
KR101777176B1 (ko) 서로 다른 형상을 가진 스틸관들을 이용한 cip 공법
US4293242A (en) Piles
US3389560A (en) Diffusion well construction
RU2123091C1 (ru) Фундамент под металлическую колонну, способ его сооружения и рихтования
CA1258185A (en) Method of constructing a rigid structure upon the bottom of a water as well as lost casing for performing said method
US3145540A (en) Prestressed composite pile
US2507259A (en) Pile
US4038795A (en) Concrete storage tank and method of making same
US1952380A (en) Wall structure
JP2757208B2 (ja) 連続地中壁工法
US1394571A (en) Subaqueous structure and method
CN113389197B (zh) 人工挖孔桩预制护壁及其施工方法
US1221067A (en) Tunnel and method of building same.
US3306049A (en) Excavating method using prestressed loop girders
JPH08326018A (ja) オールケーシング工法による橋脚造成工法
US1085600A (en) Method of underpinning buildings and other structures.
SU1177435A1 (ru) Способ сооружени буронабивной сваи
JPH0226014B2 (enrdf_load_stackoverflow)
CN210946788U (zh) 预制后注浆竹节桩
SU1186736A1 (ru) Сва
US1221068A (en) Method of building and placing piers.