US300469A - De witt c - Google Patents

De witt c Download PDF

Info

Publication number
US300469A
US300469A US300469DA US300469A US 300469 A US300469 A US 300469A US 300469D A US300469D A US 300469DA US 300469 A US300469 A US 300469A
Authority
US
United States
Prior art keywords
plates
tunnel
section
earth
hood
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
Publication date
Application granted granted Critical
Publication of US300469A publication Critical patent/US300469A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/005Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by forcing prefabricated elements through the ground, e.g. by pushing lining from an access pit

Definitions

  • This invention relates to the construction of underground tunnels and other excavations, including tunnels under the beds of rivers and other waters, both when the work is done under ordinary atmospheric pressure and under a forced pressure of air in the section be ing worked.
  • the invention consists in excavating a small portion of earth in the crown of the heading and inserting therein one or more iron plates and securing the same to the upper part of a completed section of the tunnel, thereby forming a partial hood projecting in front of said section, then excavating the heading in advance of said hood and inserting anotherplate or plates and attaching the same to the partial hood, afterward excavating the earth under the first-named partial hood sufficiently for the insertion of one or more plates at the sides thereof, and attaching said side plates to the completed section of tunnel and to said hoodplates, and continuing the operation till each circle of plates in succession is completed,and the whole earth is excavated in a step-like manner from within them; and it also consists in forming in the excavation a tube or shell composed of plates having facial flanges, the said plates being supported by compressed air while being bolted together, all as hereinafter fully described.
  • Figure 1 represents a longitudinal sectional elevation of an underground tunnel in part, such as may be used under the bed of a river, and which may be made in sections divided by bulk-heads, with an air-lock connecting the sections :for working with compressed air to keep out the water and to partially hold up the earth, said view representing such tunnel as in the course of being constructed in accordance with my invention; and Fi 2 rep resents a transverse sect-ion of a finished portion of the tunnel.
  • a in the drawings indicates a finished portion or section of the tunnel,divided by a bulkhead, B, from an unfinished section, A, thereof, and with an air-lock, G, in between them, for making the excavation subject to a compressed condition of the atmosphere within the section of the tunnel in the course of being excavated.
  • the tunnel when completed, is-formed with an exterior tube or shell, of iron or other suitable material, lined with brick, concrete, stone, or other material.
  • the exterior shell is made of a series of plates, D, of boiler-iron, and of curvilinear contour in direction of their length corresponding with the transverse shape of the tunnel to be made.
  • the flanges or projections I) on the plates D also serve to anchor this lining E to its place, and when arranged on or along each margin of the several plates form a most effectual anchor.
  • Said lining may be constructed of good hard-burned brick laid in hydraulic cement.
  • the tunnel is here shown as of circular form in its transverse section, it may deviate more or less from such shape. Thus it may be of greater height than width, or otherwise. WVhen the excavation is made subject to a compressed, condition of the atmosphere within the section of the tunnel in the course of being excavated, the plates used to form the exterior shell will be quickly forced to their positions and partly held to their places, as if by suction applied to their exterior, by the atmospheric compression from within, so soon as said plates come in contact with the earthen exterior of the tunnel-section,

Description

(No Model.)
DE WITT U. HASKIN.
ART OF UGNSTRUGTING TUNNELS.
Patented June 17, 1884.
WITNESSES f aw/w BY Maw/ M ATTORNEYS.
UNrrnD STATES PATENT @rrrcn.
DE XVITT G. HASKIN, OF NEXV YORK, N. Y.
ART OF CONSTRUCTING TUNNELS.
SPECIFICATION forming part of Letters Patent NO. 300,469, dated June 17, 1884.
(X0 model.)
To ctZZ whom it may concern.-
Be it known that I, DE Wrrr U. HASKI'N, of the city, county, and State of New York, have invented certain new and useful Improvements in the Art of Constructing Tunnels, of which the following is a full, clear, and exact description.
This invention relates to the construction of underground tunnels and other excavations, including tunnels under the beds of rivers and other waters, both when the work is done under ordinary atmospheric pressure and under a forced pressure of air in the section be ing worked.
The invention consists in excavating a small portion of earth in the crown of the heading and inserting therein one or more iron plates and securing the same to the upper part of a completed section of the tunnel, thereby forming a partial hood projecting in front of said section, then excavating the heading in advance of said hood and inserting anotherplate or plates and attaching the same to the partial hood, afterward excavating the earth under the first-named partial hood sufficiently for the insertion of one or more plates at the sides thereof, and attaching said side plates to the completed section of tunnel and to said hoodplates, and continuing the operation till each circle of plates in succession is completed,and the whole earth is excavated in a step-like manner from within them; and it also consists in forming in the excavation a tube or shell composed of plates having facial flanges, the said plates being supported by compressed air while being bolted together, all as hereinafter fully described.
Reference is to be had to the accompanying drawings, forming part of this specification, in which similar letters of reference indicate corresponding parts in all the figures.
Figure 1 represents a longitudinal sectional elevation of an underground tunnel in part, such as may be used under the bed of a river, and which may be made in sections divided by bulk-heads, with an air-lock connecting the sections :for working with compressed air to keep out the water and to partially hold up the earth, said view representing such tunnel as in the course of being constructed in accordance with my invention; and Fi 2 rep resents a transverse sect-ion of a finished portion of the tunnel.
A in the drawings indicates a finished portion or section of the tunnel,divided by a bulkhead, B, from an unfinished section, A, thereof, and with an air-lock, G, in between them, for making the excavation subject to a compressed condition of the atmosphere within the section of the tunnel in the course of being excavated. The tunnel, when completed, is-formed with an exterior tube or shell, of iron or other suitable material, lined with brick, concrete, stone, or other material. Thus the exterior shell is made of a series of plates, D, of boiler-iron, and of curvilinear contour in direction of their length corresponding with the transverse shape of the tunnel to be made. These plates are rapidly put into their places, commencing at the roof or upper portion of the excavation, so that workmen at the heading will always be protected by an iron ceiling, and the earth above the tunnel furnished with. a support almost as soon as an excavation is made. To thus put in the plates D the men at the heading first dig or spade forward a thin partially-circular opening, leaving the core or main portion untouched, and only excavating suiiiciently to allow the top plates to be placed in position, where they are bolted and braced to each other before the earth beneath is removed, the most advanced plates being extended out like a hood, well braced up until all the earth in the core beneath is removechand the plates are put in position on all sides around the excavation. This method of proceeding is clearly shown at the right hand of Fig. 1 of the drawings. These plates D, which form the shell of the tunnel, have inner facial flanges, b, on each of their sides or margins, which admit of each plate being bolted, as at c, all around it to the next one. Said plates are so arranged in relation with each other that they break joints, as clearly shown in Fig. 1. After thesecticn of atunnel has been thus fitted with an exterior shell, as described, or as portions of said shell in direction of its length are completed, abrick, concrete, stone, or other mason-work lining, E, of considerably greater thickness than the plates D, is
built up within or applied to said plates, and,
being formed as an arch on all sides, resists all outside pressure both vertically and laterally. The flanges or projections I) on the plates D also serve to anchor this lining E to its place, and when arranged on or along each margin of the several plates form a most effectual anchor. Said lining may be constructed of good hard-burned brick laid in hydraulic cement.
Although. the tunnel is here shown as of circular form in its transverse section, it may deviate more or less from such shape. Thus it may be of greater height than width, or otherwise. WVhen the excavation is made subject to a compressed, condition of the atmosphere within the section of the tunnel in the course of being excavated, the plates used to form the exterior shell will be quickly forced to their positions and partly held to their places, as if by suction applied to their exterior, by the atmospheric compression from within, so soon as said plates come in contact with the earthen exterior of the tunnel-section,
I and thus said plates will assist in retaining the air, and serve to better uphold the roof and sides from caving in.
The above-described method permits the ready change of shape and form of the plates while putting them in to suit the variable nature of the soil that may be encountered;
Having thus fully described niyinvention, I claim as new and desire to secure by Letters Patent- 1. The herein-described method of constructing tunnels, which consists in excavating a small portion of the earth in the crown of the heading and inserting therein one or more iron plates and securing the same to they upper part of a completed section of the tunnel, thereby forming a partial hood projecting in front of said section, then excavating the heading in advance of said hood and inserting another plate or plates and attaching the same to the partial hood, afterward excavating the earth under the first-named partial hood sufficiently for the insertion of one or more plates at the sides thereof, and attaching said side plates to the completed section of tunnel and to said'hood-plates, and continuing the operation till each circle of plates in succession is completed and the whole earth is excavated in a step-like manner from within them, as shown and set forth.
2. The herein-described methodof constructing tunnels,consis'ting in forming in the excavation a tube or shell composed of plates having facial flanges, the said plates being supported in position while being bolted to-- gether by compressed air, as set forth.
DE wirr o. H-ASKIN.
XVitnesses:
EDGAR TATE, ALFRED HOLOOMBE DAVIS.
US300469D De witt c Expired - Lifetime US300469A (en)

Publications (1)

Publication Number Publication Date
US300469A true US300469A (en) 1884-06-17

Family

ID=2369647

Family Applications (1)

Application Number Title Priority Date Filing Date
US300469D Expired - Lifetime US300469A (en) De witt c

Country Status (1)

Country Link
US (1) US300469A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3260054A (en) * 1962-04-12 1966-07-12 Entpr S Leon Chagnaud & Fils Process for producing excavations in water-bearing ground
US20150075664A1 (en) * 2013-09-19 2015-03-19 Timothy J. Cormier Corrugated metal plate assembly system and method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3260054A (en) * 1962-04-12 1966-07-12 Entpr S Leon Chagnaud & Fils Process for producing excavations in water-bearing ground
US20150075664A1 (en) * 2013-09-19 2015-03-19 Timothy J. Cormier Corrugated metal plate assembly system and method
US9290895B2 (en) * 2013-09-19 2016-03-22 Contech Engineered Solutions LLC Corrugated metal plate assembly system and method

Similar Documents

Publication Publication Date Title
US300469A (en) De witt c
US786382A (en) Method of subway construction.
US1026412A (en) Tunneling-machine.
JP3135188B2 (en) Construction method of underground cavity
US960940A (en) Art of constructing tunnels in the earth.
US413384A (en) Tunneling-ram
US745453A (en) Pilot-sheeting.
US413383A (en) Method of constructing tunnels
US1009312A (en) Lining-wall for shafts.
Copperthwaite Tunnel shields and the use of compressed air in subaqueous works
US755956A (en) Method of constructing tunnels, shafts, or other excavations.
US933776A (en) Sinking shafts and the like.
US440576A (en) Robert d
US286789A (en) Metal shield for tunnel-working
US1088152A (en) Tunnel and method of constructing same.
US960941A (en) Constructing concrete and like walls in the earth.
US466046A (en) Method of and apparatus for constructing tunnels
US2179429A (en) Cofferdam construction
US713519A (en) Method of building tunnels, shafts, &c.
US932717A (en) Method of constructing foundations.
US958592A (en) Tunnel.
US1272479A (en) Method of building foundations for subaqueous tunnels.
US817657A (en) Art or process of lowering river-tunnels.
US427728A (en) Well-lining
US918100A (en) Method of underpinning and supporting walls.