US413383A - Method of constructing tunnels - Google Patents

Method of constructing tunnels Download PDF

Info

Publication number
US413383A
US413383A US413383DA US413383A US 413383 A US413383 A US 413383A US 413383D A US413383D A US 413383DA US 413383 A US413383 A US 413383A
Authority
US
United States
Prior art keywords
ram
tunneling
tunnel
casing
plates
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
Publication date
Application granted granted Critical
Publication of US413383A publication Critical patent/US413383A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/063Tunnels submerged into, or built in, open water
    • E02D29/077Tunnels at least partially built beneath the water-bed characterised by being made by methods involving disturbance thereof all along the location line, e.g. by cut-and-cover or caisson methods
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling

Definitions

  • Pcf-1 WilhESEE lnx/anim@ Lum@ BEEEhEf /QMV//y/f/ By "f muy.
  • This invention relates to new and useful improvements in the art of constructing subaqueous tunnels under rivers, lakes, harbors,
  • vention consists in the improved method of construction, whereby I am not only enabled to advance the tunnel without resorting to the necessity of excavating, boring, or removing the earth, as is the case with the methods in present use, but whereby the earth, instead of being removed, becomes in my construetion an element of ⁇ strength and protection to the. tunnel, all as'more fully hereinafter described, and set forth in the accompanying drawings, in which-- Figure l is avertical crossfsection through a river, illustrating the method of building my tunnel.
  • Fig. 2 is an enlarged cross-section of the tunnel as completed.
  • Fig. 3 is an enlarged longitudinal central section through a portion of the completed tunnel, with the tunneling-ram in position as in the act of operation.
  • FIG. 4 is a perspective view of one of the platesv of which I preferably construct the casing of the tunnel.
  • Fig. 5 is a diagram plan view of the tunneling-ram, illustrating the devices for steering it.
  • Fig. 6 is a crosssection on line X X in Fig. 3.
  • Fig. 7 is a cross-section on line Y Y in Fig. 3.
  • Fig. 8 is a detail cross -section through two plates, showing the construction of the joint.
  • A is the main casing of the tunnel. It may be of any desired cross-section, and is .constructed of metal plat-es, preferably of rectangular cast-iron plates B, smooth upon the outside, and provided with inwardly-projecting flanges C, for securing the plates together on their edges by bolts.
  • These plates are of suitable curvature to form, when secured together, the desired crosssection of the tunnel, and of a size not too large and heavy to be brought in through the completed portion of the tunnel-casing and to be readily secured from the inside.
  • the plates are preferably made of even length and secured together to lap at the sides. To form water-tight joints, the plates are provided upon their edges with corresponding tongues and grooves, and gaskets are placed between the joints.
  • tunneling-ram C' which is of similar con: struction and cross-section as the tunnel, but suitably larger to form a sleeve on the casing of the tunnel.
  • the forward end of this tunheling-ram is provided with a strong watertight bulk-head.D, the front face E of which is inclined from front to rear, substantially as shown. contracted or tapering, and is built smooth on the inside and forms an annular space for the packing F;
  • the nose or pointK of the tunneling-ram is hinged in any. suitable manner, and is provided with suitable steering-gear to raise or depress it, and hinged wings L are secured to the sides of the tunnelingrarn in recesses formed therein, and provided with actuatinggear to be opened outwardly to any desired degree or secured in their recesses to be flush. with the sides of the ram.
  • the pistons are retracted and a new set of plates with new packing are secured to the end of the casing.
  • the hydraulic pressure from the cylinders may be individually applied to force each plate into position, and the plates are preferably only temporarily secured together until the joint hydraulic pressure from all the cylinders and the outside pressure have forced the plates into a permanent relation to each other.
  • My method of tunneling contemplates constructing the tunnel a few feet (more or less) below the bottom of the river, lake, or other body of water, to enable the ram to displace the earth in an upward direction into the water, and should abrupt change in the grade require it other known methods of tunneling may be temporarily applied to meet exceptional conditions.
  • suitable provision may be made in the construction of the tunneling-ram to permit of boring, drilling, excavating, or otherwise removing the earth, as may be determined in advance.
  • buoyancy of the tunnel and the tunneling-ram is counteracted by the use of castiron or other metal in the construction of all the parts, and, if need be, ballast inside ap plied as a lining to the tunnel-casing, or by IOO IIO
  • An important adjunct of my improvement is the operation of exploring the ground in advance of the tunneling-ram.
  • This operation is intended for the purpose of discovering bowlders, rock, or other obstructions of a nature liable to form an obstacle to the tunneling, and also for the purpose of loosening and preparing the ground in advance of the head of the tunneling-ram, so that it will offer less resistance to displacement by the tunneling-ram and become of a more plastic nature, so as topack around the tunnel.
  • clayey soil it is of especial value to loosen the soil, as it is well known that by a certain amount of working or socalled puddling it becomes quite plastic, and then forms an excellent covering or packing around the tunnel, which of itself is water-tight.
  • This exploring lor working of the lground is easily produced or effected by the use of a suitable.

Description

(No Model.) 3 Sheets-Sheet 1. L. BEBCHER.
METHOD 0F CONSTRUGTING T'UNNBLS. No. 413.383. Patented 00.11. 22, 1889.
Pcf-1 WilhESEE: lnx/anim@ Lum@ BEEEhEf /QMV//y/f/ By "f muy.
N.' PETERSUmtolUMnphw, wzuhlmm. D, C.
(No Model.) 3 Sheets-Sheet l L. BJ-JGHER` METHOD 0F GONSTRUGTING TNNELS. No. 413,383.- Patented Oct. 22, 1889.
A i lhVEHmg-; A A Luther lnaugrj'iErfa 5M @L By @f4/W@ LBBBGHER.
- 'METHOD 0F GONSTRUCTING kTUNNELS. No. 413.383'. Patented Oct. 22, 1889.
|| It il l wh/@SEEE I A l lhJE/ILDT;
LGL'LMHEV/ B55121151" nog :Evy j f 1 NW NA PETERS. PhowLilhusgphur. "mingle". D c.
UNITED STATES APATENT OEEICE.-
LUTHER EEEcrIER, on DETROIT, MICHIGAN.
METHOD OF CONSTRUGTING TUNNELS.
SPECIFICATION forming part of Letters Patent No. 413,383, dated October 22, 1889.
Application iled January 31, 1889. Serial No. 298,183. (No model.)
.To all. whom t may concern:
Be it known that I, LUTHER BEECHER, a citizen of the United States, residing at Detroit, in the county of Wayne and State of Michigan, have invented certain new and useful Improvements in the Method of Constructing Tunnels, of which the following is a specification, reference being had therein to the accompanying drawings.
This invention relates to new and useful improvements in the art of constructing subaqueous tunnels under rivers, lakes, harbors,
inlets, marshes, and lowlands; and the in.
vention consists in the improved method of construction, whereby I am not only enabled to advance the tunnel without resorting to the necessity of excavating, boring, or removing the earth, as is the case with the methods in present use, but whereby the earth, instead of being removed, becomes in my construetion an element of`strength and protection to the. tunnel, all as'more fully hereinafter described, and set forth in the accompanying drawings, in which-- Figure l is avertical crossfsection through a river, illustrating the method of building my tunnel. Fig. 2 is an enlarged cross-section of the tunnel as completed. Fig. 3 is an enlarged longitudinal central section through a portion of the completed tunnel, with the tunneling-ram in position as in the act of operation. Fig. 4 is a perspective view of one of the platesv of which I preferably construct the casing of the tunnel. Fig. 5 is a diagram plan view of the tunneling-ram, illustrating the devices for steering it. Fig. 6 is a crosssection on line X X in Fig. 3. Fig. 7 is a cross-section on line Y Y in Fig. 3. Fig. 8 is a detail cross -section through two plates, showing the construction of the joint.
A is the main casing of the tunnel. It may be of any desired cross-section, and is .constructed of metal plat-es, preferably of rectangular cast-iron plates B, smooth upon the outside, and provided with inwardly-projecting flanges C, for securing the plates together on their edges by bolts. These plates are of suitable curvature to form, when secured together, the desired crosssection of the tunnel, and of a size not too large and heavy to be brought in through the completed portion of the tunnel-casing and to be readily secured from the inside. The plates are preferably made of even length and secured together to lap at the sides. To form water-tight joints, the plates are provided upon their edges with corresponding tongues and grooves, and gaskets are placed between the joints. For gaskets I choose lead plates perforated after the plates are jointed and ready to be bolted together by a pointed tool, which gradually enlarges a passage large enough for the bolt to pass through, whereby the lead displaced is crowded into the joint around the bolt-hole and prevents leakage.
On the construction end of the tunnel I use the tunneling-ram C', which is of similar con: struction and cross-section as the tunnel, but suitably larger to form a sleeve on the casing of the tunnel. .I The forward end of this tunheling-ram is provided with a strong watertight bulk-head.D, the front face E of which is inclined from front to rear, substantially as shown. contracted or tapering, and is built smooth on the inside and forms an annular space for the packing F;
Within the tunneling-rain and abutting The rear end of the ram is slightly against the bulk-head are disposed a series of hydraulic cylinders G, the pistons H of which reciprocate in the axial line of the tunnelingram, `and these hydraulic cylinders are connected by pipes I with a suitable force-pump .I or head, preferably located on the shoreV side of the tunnel in such manner as to operate the cylinders by hydraulic pressure in the well-known application of hydraulic jacks.
The nose or pointK of the tunneling-ram is hinged in any. suitable manner, and is provided with suitable steering-gear to raise or depress it, and hinged wings L are secured to the sides of the tunnelingrarn in recesses formed therein, and provided with actuatinggear to be opened outwardly to any desired degree or secured in their recesses to be flush. with the sides of the ram.
Having now described the elements of m improvement, I will proceed to describe the construction of a subaqueous tunnel in ac-r` IOO and projecting with its front portion through the wall of the shaft into a coifer formed bya temporary coffer-dam, I then construct the tunneling-ram at such a depth that when pushed ahead the tunnelinguain advances in solid ground. NVithin the rear end of the tunneling ram, which projects inside the shaft, I then construct a section of the casing and firmly brace the same against the opposite wall of the shaft, providing ample space for unobstructed access into the tunnel. After securing a suitable packing in the annular space between the tapering rear end of the tunneling-ram and the casing, preferably as hereinafter described, and abutting the ends of the pistons against the edge of the casing by the use of suitable blocking, sufficient hydraulic pressure is applied to the cylinders to push the tunneling-ram forward the necessary distance for adding new plates to the tunnel-casing. The travel of the pistons is made, preferably, equal to the length of the plates, and proper means are provided to withdraw the pistons into the cylinders after the operation of driving the tunneling-ram ahead is completed.
Itis obvious that for subaqueous tunneling great care has to be taken to provide a reliable water-tight joint between the tunneling-ram and the casing of the tunnel. To this end I have devised a novel way of packing, which consists in stuffing into the annular space between the casing and the rear end of the tunnelingsram a plastic packing adapted to form a water-proof joint. Compositions of this kind are well known and used for various engineering purposes and may be readily adapted for my purpose. A very suitable packing may be obtained with a plastic composition formed of asphalt or coal-tar made to harden by mixing it with cement and having incorporated with it some stringy or fibrous matter, such as tow, old rope, or equivalent materials. This is stuffed into the annular space for the whole length of the joint, and when the tunnelingram is driven forward the tapering portion thereof compresses it firmly around the casing and into the joints thereof, and after a time it hardens and forms a protective covering for the main casing, which firmly adheres to it and makes it A water-proof, besides strengthening it and protecting it from rusting on the outside.
After the tunneling-ram is advanced bythe application of sufficient hydraulic pressure into all the cylinders the pistons are retracted and a new set of plates with new packing are secured to the end of the casing. In this operation the hydraulic pressure from the cylinders may be individually applied to force each plate into position, and the plates are preferably only temporarily secured together until the joint hydraulic pressure from all the cylinders and the outside pressure have forced the plates into a permanent relation to each other.
, The various details connected with these operations and not alluded to herein may be easily carried out by ordinary engineering skill, and obvious modifications of carrying out my method under different contingencies may be devised without departing from the spirit of my invention.
The best conditions for the application of my method of tunneling are found in ground reasonably free from rocks and obstructions and where the ground is for the most part so regular that the tun neling-ram can follow the same without producing too many or abrupt changes in the grade. By nia-king preliminary surveys, as required for the construction of any tunnel,no matter by what method, it will be generally found easy to select a suitable profile, especially7 by crossing under navigable rivers or bays.
My method of tunneling contemplates constructing the tunnel a few feet (more or less) below the bottom of the river, lake, or other body of water, to enable the ram to displace the earth in an upward direction into the water, and should abrupt change in the grade require it other known methods of tunneling may be temporarily applied to meet exceptional conditions. To this end suitable provision may be made in the construction of the tunneling-ram to permit of boring, drilling, excavating, or otherwise removing the earth, as may be determined in advance.
The conditions under which my method is applicable are those ordinarily found in crossing under rivers or lakes, in which there are generally a few inches or feet of loose sand, gravel, or silt on the bottom, with a solid bed of clay or clayey soil underneath. By advancing with the tunneling-ram in the solid bed the lighter particles are lifted above the bottom and gradually washed away, while the clay or heavy soil is compacted all around the tunnel and the portion displaced upwardly is left over the top of the tunnel to form a covering, which may be rammed down from above, and which, if of a elayey nature, may become of itself a water-tight medium around the tunnel. If desired or necessary on account of insufcient covering, suitable ballast may be thrown over the tunnel from the outside.
By using the steering-gear of the ram in a proper manner it will not be found difficult to follow the rise and fall of the bottom within the allowable limits; but if the means for steering should be inadaptable orinadequate piles P may be driven at suitable intervals into the bed, preferably in pairs, far enough apart to let the tunneling-ram pass between and serve as guides. By connecting the upper end of each pair of piles with the yoke R the casing may be irmlykanchored in place, if necessary, to prevent possible displacement.
The buoyancy of the tunnel and the tunneling-ram is counteracted by the use of castiron or other metal in the construction of all the parts, and, if need be, ballast inside ap plied as a lining to the tunnel-casing, or by IOO IIO
securing cast-iron blocks into the panels formed between the iianges of the plates of.
the casing.
An important adjunct of my improvement is the operation of exploring the ground in advance of the tunneling-ram. This operation is intended for the purpose of discovering bowlders, rock, or other obstructions of a nature liable to form an obstacle to the tunneling, and also for the purpose of loosening and preparing the ground in advance of the head of the tunneling-ram, so that it will offer less resistance to displacement by the tunneling-ram and become of a more plastic nature, so as topack around the tunnel. In clayey soil it is of especial value to loosen the soil, as it is well known that by a certain amount of working or socalled puddling it becomes quite plastic, and then forms an excellent covering or packing around the tunnel, which of itself is water-tight. This exploring lor working of the lground is easily produced or effected by the use of a suitable.
vesselsuch as a large scow-anchored in front of the tunneling-ram, and operating in the ground with suitable tools-such as heavy spuds-working up and down in the necessary manner to find all rocks and bowlders or other obstructions, which are removed in any suitable manner.
Instead or loosening the ground with tools, the more modern way of using explosives may be made use of, which would also dispose of rocks or other obstructions.4 The` manner of using dynamite or other explosives for similar purposes is so well known that a further description thereof may properly be omitted and left to the practical engineer.
It is obvious that although the material may be thoroughly loosened and worked up in advance of the tunneling-ram, and that it may be lifted up by the wedge-shaped end of the' sides of the tunnelcasing by the applicationV of mechanical means.
As the presence of quicksands in the strata or in pockets does not in the ,leastin-terfere with the successful operation of my method, the latter presents the most economical solu-v tion, not only of one of the most difficultengineering problems in tunneling, but in all subsequent tunnel constructions in which my method is applicable on general conditions.
The construction of my tunneling-ram in respect to the hinged nose or point and the a lateral deflection of the tunneling-ram to one side or the other, as desired, and as a further means of guiding the tunneling-ram in the intended direction a judicious use of the hydraulic jacks in the tunneling-ram forms another means of accomplishing this end.
I attach importance to the fact that the forward end of the ram be upon an incline, as
shown, in contradistinction to being concaved or tapered from the longitudinal center to the sides, as heretofore, so that the earth is displaced upward and compressed above the casing instead of being thrown mostly tothe ,r
sides and there compressed.
No claim is-here made to the apparatus shown herein, as it forms the subj ect-matter of my application, Serial No. 302,026, filed March', 1889.
What I claim as my invention is l. The herein-described improvement in the art of subaqueous tunnel construction, which consists in slidingly operating the tunnelingramon the construction end of the tunnel-yI casing, and displacing the earth upward and A extending the tunnel-casing stepv by step as the tunneling advances, and loosening or preparing the ground in advance of the ram by mechanical means removed from the ram, as
set forth. Y
2. The herein-described improvement in the art of subaqueous tunnel construction, .which consists in slidingly operating the tunneling- IOO ram on the construction end of `the tunnelcasing and in compressing in a tapering space j between the ram and the casing an outer covering 1n the advancing movement of the ram as set forth. f
3. Theherein-described improvementin the art of subaqueous tunnel construction, which consists in extending the casing step by step within the tunnelinguam moving over said casing and compressing suitable packingin a tapering space between the casing and the .ram and into the joints of the casing by the advancing 'movement of the-ram, as set forth.
In testimony whereof I affix my signature, in presence of two witnesses,-this 22d day of December, .1888. Y
Witnesses:
J. PAUL MAYER, P. M. HULBERT.
IIO
LUTHER BEECHER.;`
US413383D Method of constructing tunnels Expired - Lifetime US413383A (en)

Publications (1)

Publication Number Publication Date
US413383A true US413383A (en) 1889-10-22

Family

ID=2482314

Family Applications (1)

Application Number Title Priority Date Filing Date
US413383D Expired - Lifetime US413383A (en) Method of constructing tunnels

Country Status (1)

Country Link
US (1) US413383A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3223025A1 (en) * 1982-06-19 1983-12-22 Bilfinger + Berger Bauaktiengesellschaft, 6800 Mannheim Method and device for controlling the lateral advance direction of a straight or continuously curved part of a concrete structure with rectangular cross-section during the through-press process
US20070248416A1 (en) * 2004-05-12 2007-10-25 Pierre Aristaghes Process and Device for Building a Tunnel Immersed on a Sub-Sea Soil
US20140219725A1 (en) * 2011-06-01 2014-08-07 Vermeer Manufacturing Company Tunneling apparatus
US9255476B2 (en) 2012-08-17 2016-02-09 Ric-Man Construction, Inc. Shaft construction in the earth and method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3223025A1 (en) * 1982-06-19 1983-12-22 Bilfinger + Berger Bauaktiengesellschaft, 6800 Mannheim Method and device for controlling the lateral advance direction of a straight or continuously curved part of a concrete structure with rectangular cross-section during the through-press process
US20070248416A1 (en) * 2004-05-12 2007-10-25 Pierre Aristaghes Process and Device for Building a Tunnel Immersed on a Sub-Sea Soil
US7766579B2 (en) * 2004-05-12 2010-08-03 Bouygues Travaux Publics Process and device for building a tunnel immersed on a sub-sea soil
US20140219725A1 (en) * 2011-06-01 2014-08-07 Vermeer Manufacturing Company Tunneling apparatus
US9506344B2 (en) * 2011-06-01 2016-11-29 Vermeer Manufacturing Company Tunneling apparatus
US9255476B2 (en) 2012-08-17 2016-02-09 Ric-Man Construction, Inc. Shaft construction in the earth and method thereof

Similar Documents

Publication Publication Date Title
US5542782A (en) Method and apparatus for in situ installation of underground containment barriers under contaminated lands
DE2108591C3 (en) Device and method for implementing the shield construction method for the construction of tunnels and galleries
US413383A (en) Method of constructing tunnels
US3570253A (en) Constructional works
US413384A (en) Tunneling-ram
JPH02200917A (en) Landslide suppressing well cylinder and its building method
Haswell Thames Cable Tunnel.
JP2007132186A (en) Non-excavation constructing technique for underground structure
US563106A (en) Method of and apparatus foe sinkinc caissons fob
Meem The bracing of trenches and tunnels, with practical formulas for earth pressures
US933776A (en) Sinking shafts and the like.
Proctor Tunneling Detroit River
US851532A (en) Coffer-dam and caisson construction.
Halcrow A Century of Tunnelling
RU2101502C1 (en) Method of formation of haulage ramp
US761658A (en) Method of constructing tunnels.
JPH0860650A (en) Excavation method
JPH01244016A (en) Reflux spiral foundation work
Mayo Development of Nonpneumatic Caisson Engineering
EP0974634A1 (en) Ground improvement process and structure
JPH0617590A (en) Excavating method for tunnel
Sherman et al. Discussion on Steel Sheeting and Sheet-Piling
John et al. 4 The construction of large diameter bored piles with particular reference to London Clay
BRUCE et al. CORRESPONDENCE. THE ROTHERHITHE TUNNEL.
Galbraith Reinforced Concrete Piling.