US20100054859A1 - Hydraulic Sliding Insertion Panel and Its Using Method - Google Patents

Hydraulic Sliding Insertion Panel and Its Using Method Download PDF

Info

Publication number
US20100054859A1
US20100054859A1 US12/516,200 US51620007A US2010054859A1 US 20100054859 A1 US20100054859 A1 US 20100054859A1 US 51620007 A US51620007 A US 51620007A US 2010054859 A1 US2010054859 A1 US 2010054859A1
Authority
US
United States
Prior art keywords
board
poling
reinforced concrete
sliding insertion
stratum
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US12/516,200
Inventor
Fu Rong He
Wanjun Ji
Jing Lu
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of US20100054859A1 publication Critical patent/US20100054859A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/14Sealing joints between adjacent sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • E02D5/185Bulkheads or similar walls made solely of concrete in situ with flexible joint members between sections
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/24Placing by using fluid jets

Definitions

  • the present invention relates to water engineering and reinforced concrete poling board integrated underground engineering, such as embankment, harbor waterway, artificial island, roadway bridge, sluice, culvert and water channel, and particularly to a hydraulic sliding insertion panel and its using method.
  • the conventional hydraulic insertion of reinforced concrete poling board generally has the following shortcomings: 1. Hydraulic thrusting is the only means, so that sinking is slow and hard to bypass and eliminate the underground obstacles; 2. it is hard to form an integrated structure in the connection portion that has high strength and tightness.
  • Chinese patent ZL200420040430.8 SLIDEWAY AND SLIDE PLATE OF A HYDRAULIC SLIDING INSERTION PANEL provides a connection technique, no inner cavity is formed in the connection portion of two panels that cannot be sealed by the water isolation path. Thus grout injected into the bottom of the connection portion of two panels cannot normally return to the top of the board due to leakage, thus the expected tightness of the connection portion cannot be achieved. 3.
  • Each pile board and existing hydraulic sliding insertion panel has to be provided thereon with a flow guide tube, a sprinkler pipe and a sprinkler head, which substantially increases the cost in fabrication and steel consumption.
  • the high pressure water supply pipe needs to be connected once for each poling board during construction, thus extending the period spent for construction and increasing cost.
  • the object of the invention is to provide a hydraulic sliding insertion panel that can be quickly sunk into the stratum and effectively remove underground obstacles and the method of using the same.
  • the prior art disadvantages and shortcomings may be effectively overcome by employing the connecting technique in which a connection between two boards which has a strength and tightness fully meeting the performance index of the board body and employing the constructing technique in which the engineering boards with no flow guide tube and water jetting pipe can in combination with a tool board sink into the stratum.
  • the board sinking speed is increased, the capability of eliminating the underground obstacles is enhanced, the amount of steel consumed is reduced, time spent for loading and unloading of water supply pipe for each board is shortened, and the high strength integral connection between boards is achieved, so as to achieve the object of speeding up construction, reducing the engineering cost, enhancing safety and stability, and altering the constructing pattern of existing engineering construction.
  • the hydraulic sliding insertion panel comprises a reinforced concrete poling board, a flow guide tube vertically set in the poling board, a water distributing pipe communicating with the flow guide tube horizontally set in the bottom of the poling board, a slideway provided on the one side and a slide plate provided on the other side of the poling board respectively, and erection loops and inbuilt preset steel bars on the top of the poling board.
  • the hydraulic sliding insertion panel further comprises vertical water isolation paths set in the reinforced concrete poling board on the two sides of the slide way and the slide plate.
  • the lower end of the reinforced concrete poling board has a level, tapered or unilaterally tapered shape.
  • the water distributing pipe has an upper half embedded in the reinforced concrete poling board and a lower half provided with a plurality of sprinkler holes arrayed in an uniformly spaced jigsaw pattern, each of the sprinkler holes having a diameter of 2 to 8 mm, with a dispensing area of 9 to 36 cm 2 on the cross section of the reinforced concrete poling board.
  • Each of the water isolation paths is a groove vertically set on the side surfaces of the reinforced concrete poling board and having a cross section of semicircle, a semi-square, a semi-rectangle, a semi-rhombus or a semi-ellipse, and after two adjacent poling boards are sunk in the stratum, the two corresponding water isolation paths of the two adjacent poling boards will present a complete circle, square, rectangle, rhombus or ellipse shape.
  • the slideway is a finished steel product having a perpendicular recess, such as square steel, channel steel, angle steel and steel slab.
  • the slide plate is an I-steel or T-steel, one half in the slideway and slide plate and another half exposed outside, which slides in the slideway while the reinforced concrete poling board is being sunk.
  • the reinforced concrete poling board is designed to comprise a tool board structure having a metal cutting blade set in the bottom of and in parallel with the water distributing pipe.
  • the reinforced concrete poling board is designed to comprise a simplified engineering board structure only comprising a slideway, a slide plate and water isolation paths thereon.
  • the reinforced concrete poling board is designed to have an inverted T-shaped structure that is slim in the upper portion and thick in the lower portion.
  • a hydraulic sliding insertion panel and its using method comprises: (A) hoisting the reinforced concrete poling board by a lifting apparatus and sinking the reinforced concrete poling board into the stratum by hydraulic jet via the flow guide tube and the distributing pipe, then sinking another reinforced concrete poling board into the stratum by inserting the slide plate of another reinforced concrete poling board through the recessed hollow square steel slideway of the poling board that has already been sunk in the stratum, characterized by further comprising: (B) integrated connection between various boards, first flushing the water isolation paths by flushing pipes, then setting down a strip bag and infusing grout so as to form an inner cavity between the boards completely isolated from the exterior; (C) lowering a grout pipe into the hollow square steel in the inner cavity, and filling the inner cavity with grout from bottom to top so that an integrated structure of steel bar reinforced concrete with sandwiched steel sheet is formed in the connection portion; (D) casting the top crossbeam on site or not, when casting, casting after bonding together with the preset steel
  • the step (A) may be performed as follows: cutting the stratum with a tool board having a metal cutting blade, removing the tool board, and sinking a simplified engineering board in the stratum cut by the tool board, wherein cutting and sinking is alternately carried out, with other steps being the same as (B), (C) and (D), so as to finally form the simplified engineering board integral structure in the stratum.
  • step (A) is implemented entirely by the tool board, with other steps being the same as (B), (C) and (D), so as to finally form the simplified engineering board integral structure in the stratum.
  • the hydraulic sliding insertion panel has the functions of hydraulic cutting, integrated connection, on-site crossbeam casting and vertical lifting, may have the pile board form a firm integrated structure underground. And the connection between two boards may have a strength and tightness reaching or surpassing the performance of the board itself. So the problems, such as seepage, leakage and poor connection, generally involved in various existing piling engineering projects are avoided.
  • the water distributing pipe is used to properly distribute water flow in high pressure.
  • the sinking speed in a normal condition is substantially increased.
  • the tool board is capable of effectively removing or bypassing the underground obstacles such as tree stems and stones.
  • the conventional underground integrated structure is for the present built by digging earth, bonding steel bars and casting in position.
  • the present construction technique allows a number of poling boards to be precast on the ground for implementing the integrated underground engineering, which are sequentially sunk into the stratum in a constructing manner similar to that of building toy bricks, and formed into an integrated structure by implementing integrated connection technique therebetween.
  • engineering projects like underground culverts and transportation tunnels may be carried out in this way.
  • top preset steel bars are bonded together with additional horizontal steel bars, and then cast into a crossbeam, so as to strengthen the connection.
  • the portion of the poling board to be sunk into the stratum may be precast into an inverted T-shaped structure.
  • the gap between the board and stratum is filled by grout injected by the flow guide tube within the board, immediately after that portion has been sunk into the stratum, so as to form an integrated concrete structure to substantially increase the bearing capacity of each board thus reducing the cost.
  • FIG. 1 is a schematic view illustrating the structure according to the present invention
  • FIG. 2 is a schematic top view of the structure shown in FIG. 1 ;
  • FIG. 3 is a schematic side view of the structure shown in FIG. 1 ;
  • FIG. 4 is a schematic view of the water jet sprayed by the water distributing pipe of the structure shown in FIG. 1 ;
  • FIG. 5 is a schematic view of the sprinkler holes of the water distributing pipe as shown in FIG. 4 ;
  • FIG. 6 is a schematic view of a tool board structure as shown in FIG. 1 ;
  • FIG. 7 is a schematic view of an engineering board structure as shown in FIG. 1 ;
  • FIG. 8 is a schematic view according to the present invention under construction
  • FIG. 9 is a schematic top view of the connection portion of the reinforced concrete poling boards as shown in FIG. 8 ;
  • FIG. 10 is a schematic view of the inner cavity formed by the connection portion of the reinforced concrete poling boards
  • FIG. 11 is a schematic view of the integrated structure with sandwiched steel sheet formed by the reinforced concrete poling boards;
  • FIG. 12 is a schematic view of the operation of filling grout in the inner cavity as shown in FIG. 10 ;
  • FIG. 13 is a schematic view of the bonding of the crosswise steel bars with the top preset steel bars
  • FIG. 14 is a schematic view of casting the crossbeam on site
  • FIG. 15 is a schematic view of the revetment formed on both sides of the reinforced concrete poling boards
  • FIG. 16 is a schematic view of the inverted T-shaped poling board as shown in FIG. 1 ;
  • FIG. 17 is a cross-section of the structure as shown in FIG. 16 taken along A-A;
  • FIG. 18 is a cross-section of the structure as shown in FIG. 16 taken along B-B.
  • a hydraulic sliding insertion panel comprises a reinforced concrete poling board 1 , a flow guide tube 2 vertically set in the poling board, a water distributing pipe 3 communicating with the flow guide tube horizontally set in the bottom of the poling board, a slideway 5 provided on the one side and a slide plate 6 provided on the other side of the poling board respectively, and erection loops 8 and inbuilt preset steel bars 9 on the top of the poling board 1 .
  • the hydraulic sliding insertion panel further comprises vertical water isolation paths 7 set in the reinforced concrete poling board on the two sides of the slide way and the slide plate.
  • the lower end of the reinforced concrete poling board 1 has a level, tapered or unilaterally tapered shape.
  • the water distributing pipe 3 has an upper half embedded in the reinforced concrete poling board and a lower half provided with a plurality of sprinkler holes 10 arrayed in an uniformly spaced jigsaw pattern, each of the sprinkler holes having a diameter of 2 to 8 mm, with a dispensing area of 9 to 36 cm 2 on the cross section of the reinforced concrete poling board.
  • Each of the water isolation paths 7 is a groove vertically set on the side surfaces of the reinforced concrete poling board and having a cross section of semicircle, a semi-square, a semi-rectangle, a semi-rhombus or a semi-ellipse.
  • the two corresponding water isolation paths of the two adjacent poling boards will present a complete circle, square, rectangle, rhombus or ellipse shape.
  • the slideway is a finished steel product having a perpendicular recess, such as square steel, channel steel, angle steel and steel slab.
  • the slide plate is an I-steel or T-steel, one half in the slideway and slide plate and another half exposed outside, which slides in the slideway while the reinforced concrete poling board is being sunk.
  • the reinforced concrete poling board is further designed to comprise a tool board structure having a metal cutting blade 4 set in the bottom of and in parallel with the water distributing pipe.
  • the reinforced concrete poling board is further designed to comprise a simplified engineering board structure only comprising a slideway, a slide plate and water isolation paths thereon. Whether there is a water isolation path or not depends on the specific project.
  • the reinforced concrete poling board may have an inverted T-shaped structure that is slim in the upper portion and thick in the lower portion, when it is designed to support a heavy weight, such as when building bridge poles.
  • a hydraulic sliding insertion panel and its using method according to the invention comprises: (A) hoisting the reinforced concrete poling board by a lifting apparatus and sinking the reinforced concrete poling board into the stratum by hydraulic jet via the flow guide tube and the distributing pipe, then sinking another reinforced concrete poling board into the stratum by inserting the slide plate of another reinforced concrete poling board through the recessed hollow square steel slideway of the poling board that has already been sunk in the stratum.
  • the method further comprises: (B) integrated connection between various boards, first flushing the water isolation paths by flushing pipes, then setting down a strip bag and infusing grout so as to form an inner cavity 14 between the boards completely isolated from the exterior; (C) lowering a grout pipe 15 into the hollow square steel in the inner cavity, and filling the inner cavity with grout from bottom to top so that an integrated structure of steel bar reinforced concrete with sandwiched steel sheet is formed in the connection portion; (D) casting the top crossbeam 16 on site or not as required by the engineering.
  • step (D) When casting on site, casting is performed after bonding together with the preset steel bars 9 and the newly added crosswise steel bars to form a crosswise entity, and step (D) may be omitted depending on the specific project, in which case no steel bar is preset on the reinforced concrete poling board.
  • the step (A) may be performed as follows: cutting the stratum with a tool board having a metal cutting blade, removing the tool board, and sinking a simplified engineering board in the stratum cut by the tool board. Cutting and the sinking is alternately carried out, with other steps being the same as (B), (C) and (D), so as to finally form the simplified engineering board integral structure in the stratum.
  • a further step may be added depending on the specific project, which is carried out by throwing rubbles on both sides of the hydraulic sliding insertion panel, so as to form a revetment 17 of a certain height for further increasing the stability and anti-fracture strength thereof.
  • the hydraulic sliding insertion panel is used as a supporting structure, e.g. a bridge or pier pile
  • the portion to be sunk underground is spread out bilaterally to form an inverted T-shaped structure through bonding the steels bars and on site casting concrete.
  • a board after being sunk into the stratum has a side friction area and terminal bearing area far greater than that of a conventional board.
  • the gap between the board and stratum is wholly filled with grout to form an integrated concrete structure to substantially increase the bearing capacity of each board.
  • the base of the board is shortened, and the construction cost is lowered.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Revetment (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

A hydraulic sliding insertion panel comprises a reinforced concrete poling board (1), a flow guide tube (2) is set in the poling board (1) and a water distributing pipe (3) communicated with the flow guide tube (2) is set in the bottom of the poling board; moreover, a slideway (5) and a slide plate (6) are set on the two sides of the poling board (1) respectively, and an erection loop (8) is set on the top of the poling board. The using method comprises steps as follows: (A) firstly, hoisting the reinforced concrete poling board by a lifting appliance and sinking it into the stratum by hydraulic jet via the flow guide tube and the distributing pipe, then inserting the slide plate of the other reinforced concrete poling board into the stratum in the hollow square steel slideway with a gap of the poling board sunk in the stratum; (B) flushing the isolated watercourse firstly, then setting down the strip bag and infusing the grout, so forming an inner cavity isolated from the exterior between the boards; (C) putting a grout pipe into the hollow square steel in the inner cavity, and filling the grout subsequently; (D) casting the top crossbeam in position after seizing the preset steel bars and the added cross steel bars. In addition, step (D) can be omitted according to the requirements of the engineering.

Description

    FIELD OF THE INVENTION
  • The present invention relates to water engineering and reinforced concrete poling board integrated underground engineering, such as embankment, harbor waterway, artificial island, roadway bridge, sluice, culvert and water channel, and particularly to a hydraulic sliding insertion panel and its using method.
  • DESCRIPTION OF THE RELATED ART
  • The conventional hydraulic insertion of reinforced concrete poling board generally has the following shortcomings: 1. Hydraulic thrusting is the only means, so that sinking is slow and hard to bypass and eliminate the underground obstacles; 2. it is hard to form an integrated structure in the connection portion that has high strength and tightness. Although Chinese patent ZL200420040430.8 SLIDEWAY AND SLIDE PLATE OF A HYDRAULIC SLIDING INSERTION PANEL provides a connection technique, no inner cavity is formed in the connection portion of two panels that cannot be sealed by the water isolation path. Thus grout injected into the bottom of the connection portion of two panels cannot normally return to the top of the board due to leakage, thus the expected tightness of the connection portion cannot be achieved. 3. Each pile board and existing hydraulic sliding insertion panel has to be provided thereon with a flow guide tube, a sprinkler pipe and a sprinkler head, which substantially increases the cost in fabrication and steel consumption. And the high pressure water supply pipe needs to be connected once for each poling board during construction, thus extending the period spent for construction and increasing cost.
  • SUMMARY OF THE INVENTION
  • The object of the invention is to provide a hydraulic sliding insertion panel that can be quickly sunk into the stratum and effectively remove underground obstacles and the method of using the same. The prior art disadvantages and shortcomings may be effectively overcome by employing the connecting technique in which a connection between two boards which has a strength and tightness fully meeting the performance index of the board body and employing the constructing technique in which the engineering boards with no flow guide tube and water jetting pipe can in combination with a tool board sink into the stratum. In this way, the board sinking speed is increased, the capability of eliminating the underground obstacles is enhanced, the amount of steel consumed is reduced, time spent for loading and unloading of water supply pipe for each board is shortened, and the high strength integral connection between boards is achieved, so as to achieve the object of speeding up construction, reducing the engineering cost, enhancing safety and stability, and altering the constructing pattern of existing engineering construction.
  • The hydraulic sliding insertion panel according to one aspect of the invention comprises a reinforced concrete poling board, a flow guide tube vertically set in the poling board, a water distributing pipe communicating with the flow guide tube horizontally set in the bottom of the poling board, a slideway provided on the one side and a slide plate provided on the other side of the poling board respectively, and erection loops and inbuilt preset steel bars on the top of the poling board. The hydraulic sliding insertion panel further comprises vertical water isolation paths set in the reinforced concrete poling board on the two sides of the slide way and the slide plate.
  • In one aspect, the lower end of the reinforced concrete poling board has a level, tapered or unilaterally tapered shape. The water distributing pipe has an upper half embedded in the reinforced concrete poling board and a lower half provided with a plurality of sprinkler holes arrayed in an uniformly spaced jigsaw pattern, each of the sprinkler holes having a diameter of 2 to 8 mm, with a dispensing area of 9 to 36 cm2 on the cross section of the reinforced concrete poling board. Each of the water isolation paths is a groove vertically set on the side surfaces of the reinforced concrete poling board and having a cross section of semicircle, a semi-square, a semi-rectangle, a semi-rhombus or a semi-ellipse, and after two adjacent poling boards are sunk in the stratum, the two corresponding water isolation paths of the two adjacent poling boards will present a complete circle, square, rectangle, rhombus or ellipse shape. There may be one water isolation path on each side of the slideway and slide plate or one water isolation paths on either side of the slideway and slide plate, or no water isolation path is provided. The slideway is a finished steel product having a perpendicular recess, such as square steel, channel steel, angle steel and steel slab. The slide plate is an I-steel or T-steel, one half in the slideway and slide plate and another half exposed outside, which slides in the slideway while the reinforced concrete poling board is being sunk. In another aspect, the reinforced concrete poling board is designed to comprise a tool board structure having a metal cutting blade set in the bottom of and in parallel with the water distributing pipe. In still another aspect, the reinforced concrete poling board is designed to comprise a simplified engineering board structure only comprising a slideway, a slide plate and water isolation paths thereon. In still another aspect, the reinforced concrete poling board is designed to have an inverted T-shaped structure that is slim in the upper portion and thick in the lower portion.
  • A hydraulic sliding insertion panel and its using method according to the present invention comprises: (A) hoisting the reinforced concrete poling board by a lifting apparatus and sinking the reinforced concrete poling board into the stratum by hydraulic jet via the flow guide tube and the distributing pipe, then sinking another reinforced concrete poling board into the stratum by inserting the slide plate of another reinforced concrete poling board through the recessed hollow square steel slideway of the poling board that has already been sunk in the stratum, characterized by further comprising: (B) integrated connection between various boards, first flushing the water isolation paths by flushing pipes, then setting down a strip bag and infusing grout so as to form an inner cavity between the boards completely isolated from the exterior; (C) lowering a grout pipe into the hollow square steel in the inner cavity, and filling the inner cavity with grout from bottom to top so that an integrated structure of steel bar reinforced concrete with sandwiched steel sheet is formed in the connection portion; (D) casting the top crossbeam on site or not, when casting, casting after bonding together with the preset steel bars and the newly added crosswise steel bars to form a crosswise entity, and step (D) may be omitted depending on the specific project, in which case no steel bar is preset on the reinforced concrete poling board.
  • In another aspect, the step (A) may be performed as follows: cutting the stratum with a tool board having a metal cutting blade, removing the tool board, and sinking a simplified engineering board in the stratum cut by the tool board, wherein cutting and sinking is alternately carried out, with other steps being the same as (B), (C) and (D), so as to finally form the simplified engineering board integral structure in the stratum.
  • In still another aspect, the step (A) is implemented entirely by the tool board, with other steps being the same as (B), (C) and (D), so as to finally form the simplified engineering board integral structure in the stratum.
  • The present invention provides the following advantages over the prior art:
  • 1. The hydraulic sliding insertion panel has the functions of hydraulic cutting, integrated connection, on-site crossbeam casting and vertical lifting, may have the pile board form a firm integrated structure underground. And the connection between two boards may have a strength and tightness reaching or surpassing the performance of the board itself. So the problems, such as seepage, leakage and poor connection, generally involved in various existing piling engineering projects are avoided.
  • 2. The water distributing pipe is used to properly distribute water flow in high pressure. Thus the sinking speed in a normal condition is substantially increased. And the tool board is capable of effectively removing or bypassing the underground obstacles such as tree stems and stones.
  • 3. The conventional underground integrated structure is for the present built by digging earth, bonding steel bars and casting in position. Owing to the development of an unique underground poling boards connection technique and the special advantage of providing for the strength and tightness in the inter-board connection portion reaching or surpassing the performance of the board itself, the present construction technique allows a number of poling boards to be precast on the ground for implementing the integrated underground engineering, which are sequentially sunk into the stratum in a constructing manner similar to that of building toy bricks, and formed into an integrated structure by implementing integrated connection technique therebetween. For example, engineering projects like underground culverts and transportation tunnels may be carried out in this way. By replacing the conventional construction mode with the present invention, the construction speed is greatly increased, the engineering cost is lowered, and the safety and stability thereof is assured so as to provide a new way for reinforced concrete poling board underground integrated construction.
  • 4. No more need to install the flow guide tube, sprinkler head and sprinkler pipe on each poling board. So cost in fabrication and steel consumption is reduced.
  • 5. No more need to connect the water supply pipe once for each poling board during construction. So time and cost are saved.
  • 6. The top preset steel bars are bonded together with additional horizontal steel bars, and then cast into a crossbeam, so as to strengthen the connection.
  • 7. In the case when the hydraulic sliding insertion panel is used as supporting structures, e.g. bridge or pier piles, the portion of the poling board to be sunk into the stratum may be precast into an inverted T-shaped structure. Besides, the gap between the board and stratum is filled by grout injected by the flow guide tube within the board, immediately after that portion has been sunk into the stratum, so as to form an integrated concrete structure to substantially increase the bearing capacity of each board thus reducing the cost.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • FIG. 1 is a schematic view illustrating the structure according to the present invention;
  • FIG. 2 is a schematic top view of the structure shown in FIG. 1;
  • FIG. 3 is a schematic side view of the structure shown in FIG. 1;
  • FIG. 4 is a schematic view of the water jet sprayed by the water distributing pipe of the structure shown in FIG. 1;
  • FIG. 5 is a schematic view of the sprinkler holes of the water distributing pipe as shown in FIG. 4;
  • FIG. 6 is a schematic view of a tool board structure as shown in FIG. 1;
  • FIG. 7 is a schematic view of an engineering board structure as shown in FIG. 1;
  • FIG. 8 is a schematic view according to the present invention under construction;
  • FIG. 9 is a schematic top view of the connection portion of the reinforced concrete poling boards as shown in FIG. 8;
  • FIG. 10 is a schematic view of the inner cavity formed by the connection portion of the reinforced concrete poling boards;
  • FIG. 11 is a schematic view of the integrated structure with sandwiched steel sheet formed by the reinforced concrete poling boards;
  • FIG. 12 is a schematic view of the operation of filling grout in the inner cavity as shown in FIG. 10;
  • FIG. 13 is a schematic view of the bonding of the crosswise steel bars with the top preset steel bars;
  • FIG. 14 is a schematic view of casting the crossbeam on site;
  • FIG. 15 is a schematic view of the revetment formed on both sides of the reinforced concrete poling boards;
  • FIG. 16 is a schematic view of the inverted T-shaped poling board as shown in FIG. 1;
  • FIG. 17 is a cross-section of the structure as shown in FIG. 16 taken along A-A;
  • FIG. 18 is a cross-section of the structure as shown in FIG. 16 taken along B-B.
  • DETAILED DESCRIPTION OF THE EMBODIMENTS
  • With reference to FIGS. 1 to 18, a hydraulic sliding insertion panel comprises a reinforced concrete poling board 1, a flow guide tube 2 vertically set in the poling board, a water distributing pipe 3 communicating with the flow guide tube horizontally set in the bottom of the poling board, a slideway 5 provided on the one side and a slide plate 6 provided on the other side of the poling board respectively, and erection loops 8 and inbuilt preset steel bars 9 on the top of the poling board 1. The hydraulic sliding insertion panel further comprises vertical water isolation paths 7 set in the reinforced concrete poling board on the two sides of the slide way and the slide plate.
  • The lower end of the reinforced concrete poling board 1 has a level, tapered or unilaterally tapered shape. The water distributing pipe 3 has an upper half embedded in the reinforced concrete poling board and a lower half provided with a plurality of sprinkler holes 10 arrayed in an uniformly spaced jigsaw pattern, each of the sprinkler holes having a diameter of 2 to 8 mm, with a dispensing area of 9 to 36 cm2 on the cross section of the reinforced concrete poling board. Each of the water isolation paths 7 is a groove vertically set on the side surfaces of the reinforced concrete poling board and having a cross section of semicircle, a semi-square, a semi-rectangle, a semi-rhombus or a semi-ellipse. After two adjacent poling boards are sunk in the stratum, the two corresponding water isolation paths of the two adjacent poling boards will present a complete circle, square, rectangle, rhombus or ellipse shape. There may be one water isolation paths 7 on each side of the slideway 5 and slide plate 6, or one water isolation paths on either side of the slideway and slide plate, or no water isolation path is provided. The slideway is a finished steel product having a perpendicular recess, such as square steel, channel steel, angle steel and steel slab. The slide plate is an I-steel or T-steel, one half in the slideway and slide plate and another half exposed outside, which slides in the slideway while the reinforced concrete poling board is being sunk. The reinforced concrete poling board is further designed to comprise a tool board structure having a metal cutting blade 4 set in the bottom of and in parallel with the water distributing pipe. In still another embodiment, the reinforced concrete poling board is further designed to comprise a simplified engineering board structure only comprising a slideway, a slide plate and water isolation paths thereon. Whether there is a water isolation path or not depends on the specific project. The reinforced concrete poling board may have an inverted T-shaped structure that is slim in the upper portion and thick in the lower portion, when it is designed to support a heavy weight, such as when building bridge poles.
  • A hydraulic sliding insertion panel and its using method according to the invention comprises: (A) hoisting the reinforced concrete poling board by a lifting apparatus and sinking the reinforced concrete poling board into the stratum by hydraulic jet via the flow guide tube and the distributing pipe, then sinking another reinforced concrete poling board into the stratum by inserting the slide plate of another reinforced concrete poling board through the recessed hollow square steel slideway of the poling board that has already been sunk in the stratum. The method further comprises: (B) integrated connection between various boards, first flushing the water isolation paths by flushing pipes, then setting down a strip bag and infusing grout so as to form an inner cavity 14 between the boards completely isolated from the exterior; (C) lowering a grout pipe 15 into the hollow square steel in the inner cavity, and filling the inner cavity with grout from bottom to top so that an integrated structure of steel bar reinforced concrete with sandwiched steel sheet is formed in the connection portion; (D) casting the top crossbeam 16 on site or not as required by the engineering. When casting on site, casting is performed after bonding together with the preset steel bars 9 and the newly added crosswise steel bars to form a crosswise entity, and step (D) may be omitted depending on the specific project, in which case no steel bar is preset on the reinforced concrete poling board.
  • In another embodiment, the step (A) may be performed as follows: cutting the stratum with a tool board having a metal cutting blade, removing the tool board, and sinking a simplified engineering board in the stratum cut by the tool board. Cutting and the sinking is alternately carried out, with other steps being the same as (B), (C) and (D), so as to finally form the simplified engineering board integral structure in the stratum.
  • When the construction of the hydraulic sliding insertion panel is performed in water, particularly under sea, after the above steps (A) to (D), a further step may be added depending on the specific project, which is carried out by throwing rubbles on both sides of the hydraulic sliding insertion panel, so as to form a revetment 17 of a certain height for further increasing the stability and anti-fracture strength thereof.
  • In case the hydraulic sliding insertion panel is used as a supporting structure, e.g. a bridge or pier pile, when the poling board is precast on the ground, the portion to be sunk underground is spread out bilaterally to form an inverted T-shaped structure through bonding the steels bars and on site casting concrete. As a result, such a board after being sunk into the stratum has a side friction area and terminal bearing area far greater than that of a conventional board. Besides, the gap between the board and stratum is wholly filled with grout to form an integrated concrete structure to substantially increase the bearing capacity of each board. Thus the base of the board is shortened, and the construction cost is lowered.

Claims (14)

1. A hydraulic sliding insertion panel, comprising a reinforced concrete poling board, a flow guide tube vertically set in the poling board, a water distributing pipe communicating with the flow guide tube horizontally set in the bottom of the poling board, a slideway provided on the one side and a slide plate provided on the other side of the poling board respectively, and erection loops and inbuilt preset steel bars on the top of the poling board, wherein the hydraulic sliding insertion panel further comprises vertical water isolation paths set in the reinforced concrete poling board on the two sides of the slide way and the slide plate.
2. The hydraulic sliding insertion panel according to claim 1, wherein the lower end of the reinforced concrete poling board has a level, tapered or unilaterally tapered shape.
3. The hydraulic sliding insertion panel according to claim 1, characterized by a water distributing pipe, which has an upper half embedded in the reinforced concrete poling board and a lower half provided with a plurality of sprinkler holes arrayed in an uniformly spaced jigsaw pattern, each of the sprinkler holes having a diameter of 2 to 8 mm, with a dispensing area of 9 to 36 cm2 on the cross section of the reinforced concrete poling board.
4. The hydraulic sliding insertion panel according to claim 1, wherein each of the water isolation paths is a groove vertically set on the side surfaces of the reinforced concrete poling board and having a cross section of semicircle, a semi-square, a semi-rectangle, a semi-rhombus or a semi-ellipse, and after two adjacent poling boards are sunk in the stratum, the two corresponding water isolation paths of the two adjacent poling boards will present a complete circle, square, rectangle, rhombus or ellipse shape.
5. The hydraulic sliding insertion panel according to claim 1, wherein one water isolation path on each side of the slideway and slide plate or one water isolation paths on either side of the slideway and slide plate, or no water isolation path is provided.
6. The hydraulic sliding insertion panel according to claim 1, wherein the slideway is a finished steel product having a perpendicular recess, such as square steel, channel steel, angle steel and steel slab.
7. The hydraulic sliding insertion panel according to claim 1, wherein the slide plate is an I-steel or T-steel, one half in the slideway and slide plate and another half exposed outside, which slides in the slideway while the reinforced concrete poling board is being sunk.
8. The hydraulic sliding insertion panel according to claim 1, wherein the reinforced concrete poling board is further designed to comprise a tool board structure having a metal cutting blade set in the bottom of and in parallel with the water distributing pipe.
9. The hydraulic sliding insertion panel according to claim 1, wherein the reinforced concrete poling board is further designed to comprise a simplified engineering board structure only comprising a slideway, a slide plate and water isolation paths thereon.
10. The hydraulic sliding insertion panel according to claim 1, wherein the reinforced concrete poling board is further designed to have an inverted T-shaped structure that is slim in the upper portion and thick in the lower portion.
11. A hydraulic sliding insertion panel and its using method, comprising (A) hoisting the reinforced concrete poling board by a lifting apparatus and sinking the reinforced concrete poling board into the stratum by hydraulic jet via the flow guide tube and the distributing pipe, then sinking another reinforced concrete poling board into the stratum by inserting the slide plate of another reinforced concrete poling board through the recessed hollow square steel slideway of the poling board that has already been sunk in the stratum, wherein the method further comprises: (B) integrated connection between various boards, first flushing the water isolation paths by flushing pipes, then setting down a strip bag and infusing grout so as to form an inner cavity between the boards completely isolated from the exterior; (C) lowering a grout pipe into the hollow square steel in the inner cavity, and filling in the inner cavity with grout from bottom to top so that an integrated structure of steel bar reinforced concrete with sandwiched steel sheet is formed in the connection portion; (D) casting the top crossbeam on site or not, when casting, casting after bonding together with the preset steel bars and the newly added crosswise steel bars to form a crosswise entity, and step (D) may be omitted depending on the specific project, in which case no steel bar is preset on the reinforced concrete poling board.
12. The hydraulic sliding insertion panel and its using method according to claim 11, wherein the step (A) is performed as follows: cutting the stratum with a tool board having a metal cutting blade, removing the tool board, and sinking a simplified engineering board in the stratum cut by the tool board, wherein cutting and sinking is alternately carried out, with other steps being the same as (B), (C) and (D), so as to finally form the simplified engineering board integral structure in the stratum.
13. The hydraulic sliding insertion panel and its using method according to claim 11, wherein the step (A) is implemented entirely by the tool board, with other steps being the same as (B), (C) and (D), so as to finally form the simplified engineering board integral structure in the stratum.
14. The hydraulic sliding insertion panel and its using method according to claim 12, wherein the step (A) is implemented entirely by the tool board, with other steps being the same as (B), (C) and (D), so as to finally form the simplified engineering board integral structure in the stratum.
US12/516,200 2006-11-24 2007-06-28 Hydraulic Sliding Insertion Panel and Its Using Method Abandoned US20100054859A1 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
CNB2006100704024A CN100387785C (en) 2006-11-24 2006-11-24 Hydraulic sheeting and use method thereof
CN200610070402.4 2006-11-24
PCT/CN2007/002015 WO2008061415A1 (en) 2006-11-24 2007-06-28 A hydraulic sliding insertion panel and its using method

Publications (1)

Publication Number Publication Date
US20100054859A1 true US20100054859A1 (en) 2010-03-04

Family

ID=38082257

Family Applications (1)

Application Number Title Priority Date Filing Date
US12/516,200 Abandoned US20100054859A1 (en) 2006-11-24 2007-06-28 Hydraulic Sliding Insertion Panel and Its Using Method

Country Status (3)

Country Link
US (1) US20100054859A1 (en)
CN (1) CN100387785C (en)
WO (1) WO2008061415A1 (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015169005A (en) * 2014-03-07 2015-09-28 新日鐵住金株式会社 Wall body having concrete sheet pile and steel member
US20150275499A1 (en) * 2012-10-17 2015-10-01 Matthew John Lubberts Building systems and methods
JP2015187356A (en) * 2014-03-27 2015-10-29 株式会社不動テトラ Construction method of multilayer impervious structure
JP2015229843A (en) * 2014-06-04 2015-12-21 新日鐵住金株式会社 Tip-processed steel sheet pile and installation method therefor
US20170107713A1 (en) * 2016-12-30 2017-04-20 Edvard Amirian Method for constructing building through gravity and weight of the building structure
US20170175408A1 (en) * 2012-10-17 2017-06-22 Matthew John Lubberts Building systems and methods
US20180106006A1 (en) * 2016-10-18 2018-04-19 3HX Tech LLC Discharge jet and pile-plank applying the same
US10077539B1 (en) * 2015-05-01 2018-09-18 Southern Jetwall LLC Wall and retaining members and fluidizing installation of retaining members
CN108868822A (en) * 2018-06-29 2018-11-23 平顶山平煤机煤矿机械装备有限公司 The intelligent slip casting aperture apparatus of tunnel lining trolley
JP2018204273A (en) * 2017-06-02 2018-12-27 ジオスター株式会社 Concrete pile sheet member, earth retaining wall, construction method of earth retaining wall
US10407858B2 (en) * 2015-07-23 2019-09-10 Qingdao Jingli Engineering Co., Ltd. End point closing wall forming device of extrusion type underground diaphragm wall and method for operating same
JP2020007829A (en) * 2018-07-10 2020-01-16 株式会社技研製作所 Pile press-in machine and pile press-in method
CN114319314A (en) * 2022-01-24 2022-04-12 信息产业部电子综合勘察研究院 Construction method for constructing large-thickness collapsible loess foundation by utilizing profile steel cement soil mixing wall

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103088820B (en) * 2013-01-15 2015-07-08 东营石大海辰科技有限责任公司 Waterpower self-excited oscillation jet flow vibratory pile sinking device and pile sinking technology
CN104727302B (en) * 2015-03-30 2016-06-29 中铁七局集团第三工程有限公司 Board wall cast-in-place construction technique between a kind of friction pile stake
CN106284309A (en) * 2016-10-18 2017-01-04 山东宏旭建设有限公司 Discharge jet, the peg board applying this discharge jet and peg board enter the method on stratum
CN106759343A (en) * 2016-12-13 2017-05-31 中铁十九局集团第二工程有限公司 Ring cutting pile tube under water under high pressure
CN107366287A (en) * 2017-07-05 2017-11-21 浙江宏力阳生态建设股份有限公司 A kind of fluidic architecture for waterpower pile sinking
CN109778786A (en) * 2019-03-02 2019-05-21 何富荣 A kind of no bank of stone dam and the dam construction building method
CN116770813B (en) * 2023-06-19 2024-01-26 中铁一局集团(广州)建设工程有限公司 Perpendicularity adjusting structure for prefabricated underground continuous wall installation process and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US969343A (en) * 1909-04-16 1910-09-06 Lackawanna Steel Co Composite piling.
US1366029A (en) * 1918-04-03 1921-01-18 Lloyd M Seaman Concrete construction
US6328503B1 (en) * 1997-02-19 2001-12-11 Yuy Architects And Engineers Co., Ltd. Method for constructing an underground structure
US6568881B2 (en) * 2001-10-15 2003-05-27 Walter Daniel Long Jet head device for sinking pilings
US6786675B1 (en) * 1999-10-25 2004-09-07 Carl T. Detiveaux Erosion control and bulkhead apparatus

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1429312A (en) * 1972-06-22 1976-03-24 Hollandsche Betongroep Nv Pile driving apparatus and method
CN85202494U (en) * 1985-05-21 1986-06-11 陆祖荫 Interlocked reinforced concrete sheet pile
CN1260424A (en) * 1999-11-25 2000-07-19 孟宪民 Vibratory pipe sinking dug-hole pile
JP3591778B2 (en) * 2002-02-14 2004-11-24 東日本旅客鉄道株式会社 Pile driving method
CN1380469A (en) * 2002-05-29 2002-11-20 东营科华水力插板技术中心 Combined plate-inserting dam and its construction process
CN2642831Y (en) * 2003-08-18 2004-09-22 何富荣 Flashboard dyke
CN2709518Y (en) * 2004-05-12 2005-07-13 东营桩建水力插板技术有限公司 Slidway, slide board of hydraulic timer lagging
CN2709522Y (en) * 2004-06-11 2005-07-13 岳毅 Hydraulic spile pile device of water-resisting, concrete placing and seam sealing
CN2825744Y (en) * 2005-06-15 2006-10-11 张振华 Hydraulic inserting sheet pile

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US969343A (en) * 1909-04-16 1910-09-06 Lackawanna Steel Co Composite piling.
US1366029A (en) * 1918-04-03 1921-01-18 Lloyd M Seaman Concrete construction
US6328503B1 (en) * 1997-02-19 2001-12-11 Yuy Architects And Engineers Co., Ltd. Method for constructing an underground structure
US6786675B1 (en) * 1999-10-25 2004-09-07 Carl T. Detiveaux Erosion control and bulkhead apparatus
US6568881B2 (en) * 2001-10-15 2003-05-27 Walter Daniel Long Jet head device for sinking pilings

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150275499A1 (en) * 2012-10-17 2015-10-01 Matthew John Lubberts Building systems and methods
US9617724B2 (en) * 2012-10-17 2017-04-11 Matthew John Lubberts Building systems and methods
US10087643B2 (en) * 2012-10-17 2018-10-02 Matthew John Lubberts Building systems and methods
US20170175408A1 (en) * 2012-10-17 2017-06-22 Matthew John Lubberts Building systems and methods
JP2015169005A (en) * 2014-03-07 2015-09-28 新日鐵住金株式会社 Wall body having concrete sheet pile and steel member
JP2015187356A (en) * 2014-03-27 2015-10-29 株式会社不動テトラ Construction method of multilayer impervious structure
JP2015229843A (en) * 2014-06-04 2015-12-21 新日鐵住金株式会社 Tip-processed steel sheet pile and installation method therefor
US10077539B1 (en) * 2015-05-01 2018-09-18 Southern Jetwall LLC Wall and retaining members and fluidizing installation of retaining members
US10407858B2 (en) * 2015-07-23 2019-09-10 Qingdao Jingli Engineering Co., Ltd. End point closing wall forming device of extrusion type underground diaphragm wall and method for operating same
US20180106006A1 (en) * 2016-10-18 2018-04-19 3HX Tech LLC Discharge jet and pile-plank applying the same
US10081925B2 (en) * 2016-12-30 2018-09-25 Edvard Amirian Method for constructing building through gravity and weight of the building structure
US20170107713A1 (en) * 2016-12-30 2017-04-20 Edvard Amirian Method for constructing building through gravity and weight of the building structure
JP2018204273A (en) * 2017-06-02 2018-12-27 ジオスター株式会社 Concrete pile sheet member, earth retaining wall, construction method of earth retaining wall
CN108868822A (en) * 2018-06-29 2018-11-23 平顶山平煤机煤矿机械装备有限公司 The intelligent slip casting aperture apparatus of tunnel lining trolley
JP2020007829A (en) * 2018-07-10 2020-01-16 株式会社技研製作所 Pile press-in machine and pile press-in method
JP7154051B2 (en) 2018-07-10 2022-10-17 株式会社技研製作所 Pile press-in machine and pile press-in method
CN114319314A (en) * 2022-01-24 2022-04-12 信息产业部电子综合勘察研究院 Construction method for constructing large-thickness collapsible loess foundation by utilizing profile steel cement soil mixing wall

Also Published As

Publication number Publication date
WO2008061415A1 (en) 2008-05-29
CN100387785C (en) 2008-05-14
CN1963042A (en) 2007-05-16

Similar Documents

Publication Publication Date Title
US20100054859A1 (en) Hydraulic Sliding Insertion Panel and Its Using Method
US9567720B2 (en) Offshore platform for a marine environment
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN102124163B (en) Method for constructing a chair-type, self-supported earth retaining wall
CN106930321B (en) The construction method of underground structure is built in a kind of stake of pipe-jacking with large diameter combination hole
CN208844415U (en) For changing the aqueduct of the flow direction in the river above piping lane to be onstructed
CN211340827U (en) Structure for newly building bridge by passing through existing bridge piles in subway tunnel
CN111119128B (en) Danger-removing, reinforcing and seepage-proofing method for natural rock-fill dam of barrier lake
CN111042053A (en) Permanent temporary combined retaining wall structure in urban hydraulic engineering and construction method thereof
CN110593308B (en) Open excavation back pressure construction method for foundation pit of overhead operation subway underground comprehensive pipe gallery
CN110700280A (en) Narrow zone foundation pit supporting construction flow guide device and construction method
CN108374663B (en) Twice-molding construction method for sandy gravel geological tunnel
CN107489106B (en) A kind of rocky bed subaqueous bearing platform construction method
CN106498957A (en) Steel sheet pile cofferdam construction platform and integral construction method
CN114575355B (en) Soil protection construction method
CN107642101B (en) Rock riverbed steel cofferdam bottom sealing and water drainage preventing construction method
CN101338567B (en) Construction method for underground buildings by rotary-spray shaft digging method cooperating with semi-inverse method
CN110295573B (en) River bank protection engineering slope protection structure capable of adapting to severe hydrological meteorological conditions in construction period
CN104164871B (en) The constructional method of the two recessed occlusion water-seal pile of supporting
CN214116461U (en) Embankment ballast
CN210975839U (en) Narrow and small area underground structure supporting construction guiding device
CN109653193B (en) Reverse construction method for underground continuous wall
CN113123358A (en) Ship pool deformation prevention structure under coal mining differential settlement effect and construction method
CN113373865A (en) Frame type dyke structure
CN112962534A (en) Large-area dredging dredger fill foundation structure and treatment method thereof

Legal Events

Date Code Title Description
STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION