US20050226713A1 - Process for handling cargo and cargo handling facility - Google Patents
Process for handling cargo and cargo handling facility Download PDFInfo
- Publication number
- US20050226713A1 US20050226713A1 US10/957,100 US95710004A US2005226713A1 US 20050226713 A1 US20050226713 A1 US 20050226713A1 US 95710004 A US95710004 A US 95710004A US 2005226713 A1 US2005226713 A1 US 2005226713A1
- Authority
- US
- United States
- Prior art keywords
- cargo
- warehouse
- wharf
- transport
- handling facility
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65G—TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
- B65G67/00—Loading or unloading vehicles
- B65G67/60—Loading or unloading ships
- B65G67/603—Loading or unloading ships using devices specially adapted for articles
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65G—TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
- B65G63/00—Transferring or trans-shipping at storage areas, railway yards or harbours or in opening mining cuts; Marshalling yard installations
- B65G63/002—Transferring or trans-shipping at storage areas, railway yards or harbours or in opening mining cuts; Marshalling yard installations for articles
Definitions
- the present invention relates to the field of material handling, and more specifically, to a process for handling cargo and a cargo handling facility for use in such process.
- Containerization pemits substantial improvements in the speed by which cargo is loaded and unloaded, and in the shipping industry, profits are made by maximizing the amount of time that vessels are in production, namely, transporting goods, and minimizing the amount of time that vessels are in port.
- standard containers are typically engineered for loads up to 20 tons, whereas many discrete loads, such as steel coils, are in excess of that mass.
- lakers which carry the bulk of the cargo within the Great Lakes, are of a size and configuration which is not amenable to the large scale cartage of containers.
- the process for handling cargo comprises the step of providing a cargo handling facility.
- the cargo handling facility includes a wharf defining a marine berth of sufficient length to accommodate the docking of a marine vessel in substantially parallel relation to a sidewall of the wharf; a shelter having a roof structure overlying the marine berth and an adjacent portion of the wharf; one or more overhead lifting means, such as overhead cranes, are mounted beneath the roof structure for movement over the marine berth and over the adjacent portion of the wharf in both transverse and parallel directions relative to the sidewall of the wharf.
- This provides for movement of the cargo by the overhead lifting means between the marine vessel and one or more exterior transport positions located on the wharf, which exterior transport positions are also preferably located under the roof structure.
- the cargo handling facility preferably further includes a waterside wall extending upwardly, from the bed of water on which the wharf sits, to the roof structure, so that the marine berth is sheltered on the water side by the waterside wall.
- the cargo handling facility preferably also further includes a warehouse having an access wall in which one or more cargo doorways opening onto the wharf are provided.
- the warehouse structure is preferably oriented with its access wall positioned towards and arranged substantially parallel to the waterside edge of the wharf, such that the marine berth is sheltered on the land side by the access wall.
- the one or more exterior transport positions are preferably located one each on the wharf outside a respective one of the one or more cargo doorways.
- One or more cargo conveyance means are preferably associated one each with said one or more cargo doorways, and each of said one or more cargo conveyance means is adapted to convey cargo between a respective exterior transport position on the wharf outside its associated cargo doorway to a respective interior transport position in the warehouse inside its associated cargo doorway.
- the transport means is for moving cargo between the interior transport positions and the interior of the warehouse.
- the location and the structure of the facility provides for an efficient and advantageous deployment of stevedore and warehouse labour, thereby to permit handling of cargo, including breakbulk cargo, in a manner that is relatively inexpensive as compared to conventional breakbulk cargo handling processes.
- FIG. 1 is a plan view of a cargo handling facility provided in a preferred embodiment of the process of the present invention
- FIG. 2 is an enlarged plan view of the structure of FIG. 1 ;
- FIG. 2A is an enlarged view of encircled area 2 A of FIG. 2 ;
- FIG. 3 is a front, right perspective view of the structure of FIG. 1 , with a marine vessel shown approaching the marine berth;
- FIG. 4 is a view similar to FIG. 3 , with the marine vessel berthed and shown in phantom outline;
- FIG. 5 is a right side interior perspective, view of the structure of FIG. 4 , with the cargo-doors of the marine vessel shown in their closed, sealed positions;
- FIG. 5A is an enlarged view of encircled area 5 A of FIG. 5 ;
- FIG. 6 is a view similar to FIG. 5 , with a pair of cargo doors to the cargo hold shown open, and with the hoist of a first overhead crane disposed above the hold;
- FIG. 7 is a view similar to FIG. 6 , with cargo (in this particular case, a coil of steel), shown being withdrawn from the hold by the hoist of the first overhead crane;
- cargo in this particular case, a coil of steel
- FIG. 8 is a view similar to FIG. 7 , with the first overhead crane shown depositing the cargo at an exterior transport position on a respective cargo conveyance means;
- FIG. 9 is a view similar to FIG. 7 , with the first overhead crane shown depositing the cargo onto a transport truck;
- FIG. 10 is a view of the structure of FIG. 8 , from the interior of the warehouse, with the cargo conveyance means repositioned such that the cargo is presented at the interior transport position of the cargo, and with a second overhead crane shown in the process of picking up the cargo;
- FIG. 11 is a view similar to FIG. 10 , with the second overhead crane shown depositing the cargo at a position on the warehouse floor;
- FIG. 12 is a view similar to FIG. 10 , with the second overhead crane shown depositing the cargo on a transport truck.
- the process comprises the step of providing a cargo handling facility which is designated with general reference numeral 20 in FIG. 3 , and will be understood to include, in the preferred embodiment illustrated: a wharf 22 , a warehouse 24 , a staging structure 26 and one or more cargo conveyance means 28 , all as indicated in FIG. 2 ; a shelter 30 , as indicated in FIG. 4 ; one or more overhead lifting means 32 , as indicated in FIG. 5 ; and transport means 34 , as indicated in FIG. 11 .
- a cargo handling facility which is designated with general reference numeral 20 in FIG. 3 , and will be understood to include, in the preferred embodiment illustrated: a wharf 22 , a warehouse 24 , a staging structure 26 and one or more cargo conveyance means 28 , all as indicated in FIG. 2 ; a shelter 30 , as indicated in FIG. 4 ; one or more overhead lifting means 32 , as indicated in FIG. 5 ; and transport means 34 , as indicated in FIG. 11 .
- the wharf 22 defines a marine berth of sufficient length to accommodate the docking of a marine vessel 42 , said marine berth being shown in phantom outline in FIG. 1 and designated with general reference numeral 36 .
- the wharf 22 preferably has defined thereon, substantially parallel to its waterside edge 38 , as shown in FIG. 5 , a first delivery alley 40 which transport trucks may traverse.
- the marine vessel 42 is shown, inter alia, in FIG. 3 , and a transport truck 44 as shown, inter alia, in FIG. 5 , but it should expressly be understood that neither form part of the invention.
- the warehouse 24 of the preferred embodiment is not essential to the broadest conception of the invention, but where present preferably is a climate-controlled structure having an access wall 46 , a back wall 48 opposed to the access wall 46 , and end walls 50 extending between the access wall 46 and the back wall 48 , all as indicated in FIG. 2 , and is orientated with the access wall 46 thereof positioned towards and arranged substantially parallel to the waterside edge 38 of the wharf 22 , such that the marine berth 36 is sheltered on the land side by the access wall 46 , as indicated in FIG. 4 .
- the access wall 46 is provided with one or more cargo doorways 52 , numbering five in the preferred embodiment illustrated, opening onto said wharf 22 , and one or more cargo doors 54 , associated one each with said one or more cargo doorways 53 , are also provided, as illustrated in FIG. 2 .
- Each cargo door 54 is operatively mounted to the access wall 46 for movement between an open position, whereat it is disposed apart from its associated cargo doorway 52 as shown in FIG. 11 , and a closed position, whereat it substantially occludes and seals said cargo doorway against the ambient air outside, as shown in FIG. 12 .
- second 56 , third 58 ad fourth 60 delivery alleys Located within the warehouse 24 , and specifically, defined on the storage floor thereof, are second 56 , third 58 ad fourth 60 delivery alleys, adapted to permit the traverse of delivery vehicles as set forth hereinafter, and provided in the exterior wall structure 62 of the warehouse 24 (as shown generally in FIG. 3 ) are overhead doors 64 , disposed in pairs for each of said delivery alleys 56 , 58 , 60 , at respective ends thereof and adapted to permit ingress and egress of said delivery vehicles, as best indicated in FIG. 2 .
- the second delivery alley 56 is located proximate and substantially parallel to the access wall 46 , and is adapted to permit the traverse of loaded transport trucks 44 ;
- the third delivery alley 58 is located proximate to the back wall 48 of the warehouse 24 , and is adapted to permit traverse by a pair of loaded transport trucks 44 in side-by-side relation;
- the fourth deliver valley 60 is located adjacent to and parallel the third delivery alley 58 , and is adapted to permit the traverse of loaded rail cars (not shown).
- the staging structure 26 is connected exteriorly to warehouse 24 and forms a heated airlock 66 in combination therewith, said airlock 66 having located therein extensions of the third delivery alley and fourth delivery alley, numbered 68 , 70 respectively in FIG. 2 , in which loaded transport trucks and rail cars can be acclimatized prior to ingress to the warehouse, to limit moisture infiltration into the warehouse.
- the one or more cargo conveyance means 28 are associated one each with said one or more cargo doorways 52 , with each of said one or more cargo conveyance means 28 being adapted to convey cargo between a respective exterior transport position 72 on the wharf 22 outside its associated cargo doorway 52 to a respective interior transport position 74 in the warehouse 24 inside its associated cargo doorway 52 .
- the exterior transport positions 72 are shown in phantom outline in FIG. 5 ; interior transport positions 74 are shown in phantom outline in FIG. 11 .
- the cargo conveyance means 28 are shown as tandem steel coil conveyors, each including a pair of cart rails 76 ; a wheeled cart 78 mounted for rolling movement on said rails and load-rated for 50 tons; and a cable and pulley system (not shown) operatively connected to said wheeled cart 78 to selectively propel same between the wharf 22 and the interior 79 of the warehouse 24 .
- conveyor belts could be readily substituted for the steel coil conveyors, if the process were to be employed for handling bulk cargo or relatively less massive cargo.
- the shelter 30 preferably includes a roof structure 80 ; a waterside wall 82 ; and a pair of shelter end walls 84 .
- the roof structure 80 overlies the wharf 22 and the marine berth 36 , thereby to overly the one or more overhead lifting means 32 , the marine berth 36 , and the exterior transport positions 74 .
- Lights (not shown) are preferably suspended beneath the roof structure 80 to illuminate the sheltered area.
- the waterside wall 82 extends upwardly, from the bed of the water body on which the wharf sits, to the roof structure 80 , such that the marine berth 36 is sheltered on the water side by the waterside wall 82 , and in the preferred embodiment, is arranged substantially parallel to the access wall 46 .
- the shelter end walls 84 substantially enclose the ends of said wharf 22 , said end walls 84 each having an overhead door 64 located therein to permit ingress and egress of transport trucks to and from the first delivery alley 40 .
- the one or more overhead lifting means 32 are provided to move cargo between a berthed vessel, as illustrated in FIG. 5 , and the exterior transport positions 72 , and in the preferred embodiment comprises a first overhead crane 86 .
- the first overhead crane 86 is arranged such that its rails 88 are disposed adjacent and parallel to the access wall 46 and the waterside wall 82 , respectively, and is provided with, for example, three bridges 90 , each having at least one trolley hoist 92 .
- the transport means 34 is for moving cargo between the interior transport positions 74 and the interior 79 of the warehouse 24 and, as illustrated in FIG. 11 , in the preferred embodiment comprises, for each cargo conveyance means 28 , a second overhead crane 94 having a pair of rails 96 extending, on opposite sides of said each conveyor 28 , from the access wall 46 , and in substantially normal relation thereto, to the back wall 48 of the warehouse 24 , and provided with two bridges 98 , each having a single trolley hoist 100 rated for 50 tons.
- a vessel to be unloaded will be maneuvered into the marine berth, as indicated by the sequence of FIG. 3 and FIG. 4 , and secured to the wharf 22 in a conventional manner (not shown).
- such cargo will be breakbulk cargo, such as coils of steels, stowed in the hold, as well as sundry containers secured topside to the vessel.
- Unloading involves opening the doors to the hold of the vessel, as indicated by the sequence of FIGS. 5, 6 ; withdrawing a piece of cargo from the hold, as indicated by the sequence of FIGS. 6,7 ; and depositing the cargo on a respective wheeled cart 28 , as shown in FIG. 8 , or on the bed of a transport truck 44 , as shown in FIG. 9 .
- the choice of transport truck, and among the wheeled carts 28 will be calculated by the stevedores, having regard to the intended destination of the goods using conventional logistics techniques which accordingly are not detailed herein.
- All three hoists 92 on the first overhead crane 86 will be utilized by the stevedores, to expedite unloading of the vessel, and because the wharf 22 and the marine berth 36 are sheltered and illuminated, unloading can be carried on continuously, night and day, and in inclement weather conditions.
- the associated cargo doorway 54 is opened, the wheeled carts 78 are urged into the warehouse interior 79 ; and the cargo doorway 54 is closed, as indicated by the sequence of FIG. 11 and FIG. 12 .
- This limits moisture infiltration into the warehouse interior 79 and thus, minimizes corrosion or other moisture-related spoilage of the cargo, as well as loading on the warehouse HVAC system.
- Warehousing/logistics of the cargo occurs contemporaneously with unloading.
- warehouse labour utilizing the associated second overhead cranes 94 empty the wheeled cart 78 and deposit the cargo thereon either onto a delivery vehicle 101 located on the delivery alleys 56 , 58 or 60 , as indicated by the sequence of FIG. 10 and FIG. 12 , or into the warehouse, as indicated by the sequence of FIG. 10 and FIG. 11 .
- the cargo doorway 54 is reopened, and the wheeled cart 78 is returned to the exterior transport position 72 , to receive further cargo, until such time as the vessel is unloaded.
- the warehouse interior 79 is illuminated and climate controlled, such that operation can be carried on in darkness and inclement weather, so as not to impede the progress of the stevedores.
- the three bridges 98 and the associated hoists 100 of the second overhead cranes 96 are utilized simultaneously, to expedite unloading, with the bridge 98 disposed nearest the interior transport positions 74 being deployed largely to move cargo off the wheeled carts 78 a short distance within the warehouse 24 , to speed cycle time, and the second overhead cranes 96 more distant being deployed for more time-consuming warehousing/logistics functions.
- Transport trucks, rail cars/rail car movers and/or tow motors may also be utilized to move cargo within the warehouse, so as to be within the reach of a given second overhead crane 96 , or to bring said cargo into the airlock 66 , to shed excess moisture prior to warehousing, as desired.
- the consolidation of equipment combined with the ability to readily operate in darkness, and inclement weather conditions, permits permanent staffing of the facility, both in terms of warehouse workers and stevedores, in a shift work environment, which heretofore has been out of reach.
- the economies of scale inherent in the process and facility disclosed provide significant advantages in efficiencies and costs, particularly in relation to, for example, operating costs, all to the benefit of shippers, port authorities, warehousers and stevedores.
- the process provides for an efficient allocation of labour between stevedores and warehouse labour, such that the involvement of stevedores in warehouse/logistic efforts is minimized, and such that the involvement of warehouse/logistics employees in stevedoring functions is minimized, with resultant cost benefits flowing therefrom.
Landscapes
- Engineering & Computer Science (AREA)
- Ocean & Marine Engineering (AREA)
- Aviation & Aerospace Engineering (AREA)
- Mechanical Engineering (AREA)
- Ship Loading And Unloading (AREA)
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CA2,444,612 | 2003-10-02 | ||
CA002444612A CA2444612A1 (fr) | 2003-10-02 | 2003-10-02 | Methode de manutention de cargaisons et installation de manutention de cargaisons |
Publications (1)
Publication Number | Publication Date |
---|---|
US20050226713A1 true US20050226713A1 (en) | 2005-10-13 |
Family
ID=34398303
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US10/957,100 Abandoned US20050226713A1 (en) | 2003-10-02 | 2004-10-01 | Process for handling cargo and cargo handling facility |
Country Status (2)
Country | Link |
---|---|
US (1) | US20050226713A1 (fr) |
CA (1) | CA2444612A1 (fr) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7987017B2 (en) | 2005-02-25 | 2011-07-26 | Apm Terminals North America, Inc. | System and process for improving container flow in a port facility |
WO2014066989A1 (fr) * | 2012-11-02 | 2014-05-08 | Carego Innovative Solutions, Inc. | Installation et procédé relatifs à un entrepôt |
US9828193B2 (en) | 2014-05-15 | 2017-11-28 | Carego Innovative Solutions, Inc. | Method for stacking welded tube |
CN108861637A (zh) * | 2018-07-16 | 2018-11-23 | 上海振华重工(集团)股份有限公司 | 集装箱运输系统 |
US10160598B2 (en) | 2012-11-02 | 2018-12-25 | Carego Innovative Solutions, Inc. | Method for arranging coils in a warehouse |
CN114524371A (zh) * | 2022-04-24 | 2022-05-24 | 中国建筑第五工程局有限公司 | 一种门式起重机及其吊装方法 |
CN114852734A (zh) * | 2022-06-20 | 2022-08-05 | 成都市技师学院(成都工贸职业技术学院) | 一种基于物流用快速卸货装置 |
US11429916B2 (en) | 2018-02-27 | 2022-08-30 | Carego Tek Inc. | Facility for processing steel |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4353188A (en) * | 1977-02-25 | 1982-10-12 | Seago Marvin E | Food storage building |
US5421688A (en) * | 1991-06-25 | 1995-06-06 | Krupp Industrietechnik Gesellschaft Mit Beschrankter Haftung | Installation for the load transfer of piece goods in the form of load units such as containers, returnable containers, semi-trailers or the like |
US5931625A (en) * | 1993-03-08 | 1999-08-03 | Tax Ingeniewigesellschaft M.B.H. | Freight loading/unloading crane |
US20020197135A1 (en) * | 1998-03-10 | 2002-12-26 | Arntzen John O. | Container transfer terminal system and method |
US6698990B1 (en) * | 1999-05-20 | 2004-03-02 | Gottwald Port Technology Gmbh | Loading and unloading installation for general cargo, especially for ISO containers |
-
2003
- 2003-10-02 CA CA002444612A patent/CA2444612A1/fr not_active Abandoned
-
2004
- 2004-10-01 US US10/957,100 patent/US20050226713A1/en not_active Abandoned
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4353188A (en) * | 1977-02-25 | 1982-10-12 | Seago Marvin E | Food storage building |
US5421688A (en) * | 1991-06-25 | 1995-06-06 | Krupp Industrietechnik Gesellschaft Mit Beschrankter Haftung | Installation for the load transfer of piece goods in the form of load units such as containers, returnable containers, semi-trailers or the like |
US5931625A (en) * | 1993-03-08 | 1999-08-03 | Tax Ingeniewigesellschaft M.B.H. | Freight loading/unloading crane |
US20020197135A1 (en) * | 1998-03-10 | 2002-12-26 | Arntzen John O. | Container transfer terminal system and method |
US6698990B1 (en) * | 1999-05-20 | 2004-03-02 | Gottwald Port Technology Gmbh | Loading and unloading installation for general cargo, especially for ISO containers |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7987017B2 (en) | 2005-02-25 | 2011-07-26 | Apm Terminals North America, Inc. | System and process for improving container flow in a port facility |
US8306649B2 (en) | 2005-02-25 | 2012-11-06 | Apm Terminals North America, Inc. | System and process for improving container flow in a port facility |
WO2014066989A1 (fr) * | 2012-11-02 | 2014-05-08 | Carego Innovative Solutions, Inc. | Installation et procédé relatifs à un entrepôt |
US20150298907A1 (en) * | 2012-11-02 | 2015-10-22 | Carego Innovative Solutions, Inc. | Warehouse-related method and facility |
US9522783B2 (en) * | 2012-11-02 | 2016-12-20 | Carego Innovative Solutions, Inc. | Warehouse-related method and facility |
US10160598B2 (en) | 2012-11-02 | 2018-12-25 | Carego Innovative Solutions, Inc. | Method for arranging coils in a warehouse |
US9828193B2 (en) | 2014-05-15 | 2017-11-28 | Carego Innovative Solutions, Inc. | Method for stacking welded tube |
US11429916B2 (en) | 2018-02-27 | 2022-08-30 | Carego Tek Inc. | Facility for processing steel |
CN108861637A (zh) * | 2018-07-16 | 2018-11-23 | 上海振华重工(集团)股份有限公司 | 集装箱运输系统 |
CN114524371A (zh) * | 2022-04-24 | 2022-05-24 | 中国建筑第五工程局有限公司 | 一种门式起重机及其吊装方法 |
CN114852734A (zh) * | 2022-06-20 | 2022-08-05 | 成都市技师学院(成都工贸职业技术学院) | 一种基于物流用快速卸货装置 |
Also Published As
Publication number | Publication date |
---|---|
CA2444612A1 (fr) | 2005-04-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP2146894B1 (fr) | Systeme d'entreposage et de distribution portuaire pour conteneurs de transport international | |
AU2017281303B2 (en) | Robotic cargo handling system and method | |
US5511923A (en) | Container terminal apparatus and method | |
JP5834078B2 (ja) | 貨物を取り扱うシステム | |
US6715977B2 (en) | Loading device for ISO containers | |
US20030198539A1 (en) | Cargo-transfer apparatus and method | |
WO2012133278A1 (fr) | Terminal à conteneurs et procédé de commande pour celui-ci | |
KR20130058001A (ko) | 인터모달 콘테이너들의 운송, 보관 및 인도 시스템 | |
CN107381083B (zh) | 一种港口冷链运输系统 | |
FI71908C (fi) | Fartyg och system foer lastning och lossning av detsamma. | |
US20050226713A1 (en) | Process for handling cargo and cargo handling facility | |
US20030198544A1 (en) | Centralized cargo transfer system using a movable transfer dock | |
KR20000023671A (ko) | 상품 출하 시스템 | |
US20020102150A1 (en) | Container terminal apparatus and method | |
CN207645377U (zh) | 一种港口冷链运输系统 | |
EP1843940B1 (fr) | Dispositif de manipulation de chargement d un bateau de marchandises et systeme sur un bateau de marchandises | |
US20040213652A1 (en) | Cargo transfer system using a palletized container | |
US11377313B2 (en) | Shipping container handling systems and methods | |
FI111157B (fi) | Menetelmä ja sovitelma paperi-, kartonki- ja sellurullien lastaamiseksi kuljetusvälineeseen | |
CN207129684U (zh) | 船岸输送系统 | |
CN103523679B (zh) | 带有双层跨海栈桥的集装箱装卸系统 | |
JP4564398B2 (ja) | コンテナターミナル | |
JPS628890A (ja) | 客船内の集配装置 | |
BE1008880A6 (nl) | Binnenvaartvrachtschip. | |
AU2022240814A1 (en) | Container terminal |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
AS | Assignment |
Owner name: STEELCARE INCORPORATED, CANADA Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:TSAFARIDIS, DEMETRIUS;REEL/FRAME:015618/0605 Effective date: 20041026 |
|
STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |