US1208178A - Method of tunneling. - Google Patents

Method of tunneling. Download PDF

Info

Publication number
US1208178A
US1208178A US8752216A US8752216A US1208178A US 1208178 A US1208178 A US 1208178A US 8752216 A US8752216 A US 8752216A US 8752216 A US8752216 A US 8752216A US 1208178 A US1208178 A US 1208178A
Authority
US
United States
Prior art keywords
heading
stope
blasting
timbering
drift
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US8752216A
Inventor
Edward E Mccabe
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to US8752216A priority Critical patent/US1208178A/en
Application granted granted Critical
Publication of US1208178A publication Critical patent/US1208178A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C37/00Other methods or devices for dislodging with or without loading
    • E21C37/06Other methods or devices for dislodging with or without loading by making use of hydraulic or pneumatic pressure in a borehole
    • E21C37/12Other methods or devices for dislodging with or without loading by making use of hydraulic or pneumatic pressure in a borehole by injecting into the borehole a liquid, either initially at high pressure or subsequently subjected to high pressure, e.g. by pulses, by explosive cartridges acting on the liquid

Definitions

  • the invention relates t'o a new and useful method for tunneling in mines or wherever a horizontal tunnel is desired.
  • an object of the invention it is the aim to provide a system of tunneling wherein the manual handling such as shoveling of the broken rock or material is reduced to a minimum and also utilize the force of gravity to carry the broken material from the blasting point into cars.
  • a further object of the invention is to provided a system wherein the drift heading and the stope heading can be simultaneously worked without interference.
  • the stope heading is worked from the top angularly downwardly, thereby allowing the broken rock or other material to gravitate along the inclined bottom of the stope heading onto the lagging of the timbering, where it further gravitates through a suitable opening in the lagging to cars, said space in the lagging being advanced as the stope heading is advanced.
  • a further object is to obviate collection of the broken rock on top of the lagging of the timbering and the subsequent manual shoveling of the broken material into cars through chutes, which is the case in the systems now in use, where stope headings are blasted up from the bottom. Also in the methods now in use the timbering catches the full shock of the explosion and the broken rock, which iscast downwardly upon the timbering, thereby damaging it to a great extent.
  • a further object is to provide a system wherein all chutes are eliminated and at the same time provide a construction of timbering so that the lagging may be taken up as the stope heading is advanced, thereby advancing the opening as the stope heading is advanced and in this manner allow the cars to ll at any point under the timbering and also so constructing the timbering that it may be advanced as the tunnel is advanced.
  • a further object is to provide a system wherein the side walls of headings may be blasted on either stope or drift or both sides of the drift heading according to the width of tunnel desined and the broken matter gravitated to receptacles.
  • Figure 1 is a vertical longitudinal central view illustrating the construction of the tunnel.
  • Fig. 2 is a front elevation looking into the tunnel.
  • Fig. 3 is a sectional view on line 33 of Fig. 1.
  • 1 designates a drift heading or passageway, which is run in on the bottom or track level 2 of the tunnel.
  • a timbering construction 3 which consists of the side uprights 1 and 5, said uprights being held in spaced relation to each other by the transverse bars 6, which are secured at 7 to the uprights 4; and 5.
  • Resting upon the upper ends of the corresponding oppositely disposed uprights are a series of transverse beams 8, the purpose of which will presently appear.
  • the uprights t and 5 are held in spaced relation in the drift heading by the bars 9, which are spiked or otherwise secured to the uprights as at 10 which in connection with the bars 6 prevents collapsing of the frame of the timber-ing.
  • a lagging 11 is placed upon the beams 8, which laggings consists of a series of beams 12 longitudinally disposed, these beams may be of any length, but should be long enough to span from one transverse beam 8 to the next transverse beam 8, however in practice the beams and uprights are of such lengths that they may be easily handled by one man.
  • Several of the centrally disposed beams 12 are omitted longitudinally throughout the entire length of the timbering so as to form a longitudinal opening 13.
  • a second lagging 15 formed by a series of beams 14, which are placed at right angles to the beams 12 of the lagging 11.
  • the beams forming the laggings 11 and 15 are not secured to each other or to the beams 8, the reason for which will presently appear.
  • Secured at 16, to one of the crossbeams 8 and extending downwardly and rearwardly from the timbering 3 are braces 17 and 18, which serve to prevent the collapsing of the timbering, the ends 19 of the braces 17 and 1S are embedded in the floor of the tunnel.
  • the timbering is further braced by wedges la and 5a which are driven in between the uprights and the side walls of the drift; heading thereby additionally bracing and preventing the collapsing of the timbering.
  • the track is centrally disposed under the timbering and in alinement with the longitudinal opening 13 in theI lagging 11 and upon said track a car 22 is placed for the reception of the broken material.
  • the stope heading 23 is blasted in from the top, of the tunnel l21 until the incline 24 is formed, after which the blasting is continued so that the incline 2l at all stages of subsequent blasting will be maintained at an acute angle to the roof of the drift heading 1.
  • the broken material 211L gravitates down the incline 24 of the stope heading on to the lagging 15, thence through the opening 15a in said lagging 15 and through the uncovered portion of the longitudinal opening 13 in the'hgging 11 and into the car 22 which is lunder and in registration with the opening 15a. lhen a car is full it is hauled away and another car placed under the opening 15a thereby7 catching the broken rock after each blast.
  • the opening 152l is also advanced, by removing, as required, the beams 14 forming the upper lagging 15. Also as the drift and stope headings are advanced the various parts of the timbering, as needed, may be removed from the rear end and joined to the forward end of the timbering thereby providing a continuous advancement of the timboring as the headings are advanced.
  • the side walls 25 and 26 are blasted away at the same time as the stope heading and in the same manner except that below the level of the top lagging the broken rock will gravitate to the iiooring of the tunnel.
  • l. rlhe method of excavating tunnels comprising first constructing a drift heading, then removing the roof by blasting in a stope heading, blasting away the material from the lower surface of the stope heading and maintaining said stope heading in adyance of the tunnel during subsequent blasting.
  • the method of excavating rock tunnels comprising first constructing a drift heading then removing the roof by blasting in a stope heading, blasting away the material. from the lower surface of the stope heading, allowing the broken material to gravitate to receptacles and maintaining said stope heading in advance of the tunnel during subsequent blasting.
  • the method of excavating tunnels which comprises constructing a drift heading, erecting a. staging in the drift heading, providing this staging with an opening, blasting in a stope heading, blasting away the material from the lower surface of the stope heading, allowing the broken material to gravitate through the opening in the staging into receptacles, maintaining said stope heading in advance of the tunnel during subsequent blasting and advancing the opening in the staging as the rear end of the stope heading is advanced.
  • the method of excavating rock tunnels which comprises constructing a drift heading, erecting a. staging in the drift heading, providing this staging with an opening, blasting in a stope heading, blasting away the material from the lower surface of the stope heading, allowing the broken material to gravitate through the opening in the staging into a. receptacle, maintaining said stope heading in advance of the tunnel during subsequent blasting and advancing the opening in the staging and the receptacle so that the opening and receptacle will at all times be in vertical alinement with the rear end of the stope heading as said rear end is advanced.
  • the method of excavating tunnels comprising first constructing a drift heading ⁇ then removing the roof by blasting in a stope heading, blasting away the material from the lower surface of the stope heading so that the walls of the stope heading will break the momentum of the broken material, then allowing the broken material to gravitate to receptacles and maintaining said stope heading in advance of the tunnel during subsequent blasting.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Description

EDWARD E. MCCABE, 0F BENTON, WISCONSIN.
METHOD OF TUNNELING.
Specicaton of Letters Patent.
Patented Dec. 12, 1916.
Application led March 29, 1916. Serial No. 87,522.
To all 'whom t may concern:
Be it known that I, EDWARD E. MCCABE, citizen of the United States, residing at Benton, in the county of Lafayette and State of Wisconsin, have invented certain new and useful Improvements in Methods of Tunneling, of which the following is a specification.
The invention relates t'o a new and useful method for tunneling in mines or wherever a horizontal tunnel is desired.
As an object of the invention it is the aim to provide a system of tunneling wherein the manual handling such as shoveling of the broken rock or material is reduced to a minimum and also utilize the force of gravity to carry the broken material from the blasting point into cars.
A further object of the invention is to provided a system wherein the drift heading and the stope heading can be simultaneously worked without interference. To accomplish this result the stope heading is worked from the top angularly downwardly, thereby allowing the broken rock or other material to gravitate along the inclined bottom of the stope heading onto the lagging of the timbering, where it further gravitates through a suitable opening in the lagging to cars, said space in the lagging being advanced as the stope heading is advanced.
A further object is to obviate collection of the broken rock on top of the lagging of the timbering and the subsequent manual shoveling of the broken material into cars through chutes, which is the case in the systems now in use, where stope headings are blasted up from the bottom. Also in the methods now in use the timbering catches the full shock of the explosion and the broken rock, which iscast downwardly upon the timbering, thereby damaging it to a great extent. t
A further object is to provide a system wherein all chutes are eliminated and at the same time provide a construction of timbering so that the lagging may be taken up as the stope heading is advanced, thereby advancing the opening as the stope heading is advanced and in this manner allow the cars to ll at any point under the timbering and also so constructing the timbering that it may be advanced as the tunnel is advanced.
A further object is to provide a system wherein the side walls of headings may be blasted on either stope or drift or both sides of the drift heading according to the width of tunnel desined and the broken matter gravitated to receptacles.
The invention consists in the matters herein described, and more fully defined in the appended claims:
In the drawings: Figure 1 is a vertical longitudinal central view illustrating the construction of the tunnel. Fig. 2 is a front elevation looking into the tunnel. Fig. 3 is a sectional view on line 33 of Fig. 1.
Referring more especially to the drawings, 1 designates a drift heading or passageway, which is run in on the bottom or track level 2 of the tunnel. In the drift heading a timbering construction 3 is placed, which consists of the side uprights 1 and 5, said uprights being held in spaced relation to each other by the transverse bars 6, which are secured at 7 to the uprights 4; and 5. Resting upon the upper ends of the corresponding oppositely disposed uprights are a series of transverse beams 8, the purpose of which will presently appear. The uprights t and 5 are held in spaced relation in the drift heading by the bars 9, which are spiked or otherwise secured to the uprights as at 10 which in connection with the bars 6 prevents collapsing of the frame of the timber-ing. A lagging 11 is placed upon the beams 8, which laggings consists of a series of beams 12 longitudinally disposed, these beams may be of any length, but should be long enough to span from one transverse beam 8 to the next transverse beam 8, however in practice the beams and uprights are of such lengths that they may be easily handled by one man. Several of the centrally disposed beams 12 are omitted longitudinally throughout the entire length of the timbering so as to form a longitudinal opening 13. Upon the top of the lagging 11 is a second lagging 15, formed by a series of beams 14, which are placed at right angles to the beams 12 of the lagging 11. The beams forming the laggings 11 and 15 are not secured to each other or to the beams 8, the reason for which will presently appear. Secured at 16, to one of the crossbeams 8 and extending downwardly and rearwardly from the timbering 3 are braces 17 and 18, which serve to prevent the collapsing of the timbering, the ends 19 of the braces 17 and 1S are embedded in the floor of the tunnel. The timbering is further braced by wedges la and 5a which are driven in between the uprights and the side walls of the drift; heading thereby additionally bracing and preventing the collapsing of the timbering.
A track 20, consisting of rails 20, which are mounted upon cross ties 2l, extends along the floor of the tunnel and the drift heading. The track is centrally disposed under the timbering and in alinement with the longitudinal opening 13 in theI lagging 11 and upon said track a car 22 is placed for the reception of the broken material.
The stope heading 23 is blasted in from the top, of the tunnel l21 until the incline 24 is formed, after which the blasting is continued so that the incline 2l at all stages of subsequent blasting will be maintained at an acute angle to the roof of the drift heading 1. As the rock or other material is blasted the broken material 211L gravitates down the incline 24 of the stope heading on to the lagging 15, thence through the opening 15a in said lagging 15 and through the uncovered portion of the longitudinal opening 13 in the'hgging 11 and into the car 22 which is lunder and in registration with the opening 15a. lhen a car is full it is hauled away and another car placed under the opening 15a thereby7 catching the broken rock after each blast.
It will be seen that by this method of tunneling the broken rock will gravitate to the car immediately after being broken by the blast and that the timbering will not be damaged by the blast for the reason that the broken rock cannot come in contact with it. It will also be seen that blasting can be continued without stopping to clear away the debris for the reason that the broken rock or other material gravitates down the incline 24: and into the car 22 immediately after each blast, therefore the incline immediately clears so that blasting is practically a continuous operation.
As the blasting of the stope heading is advanced, the opening 152l is also advanced, by removing, as required, the beams 14 forming the upper lagging 15. Also as the drift and stope headings are advanced the various parts of the timbering, as needed, may be removed from the rear end and joined to the forward end of the timbering thereby providing a continuous advancement of the timboring as the headings are advanced.
The side walls 25 and 26 are blasted away at the same time as the stope heading and in the same manner except that below the level of the top lagging the broken rock will gravitate to the iiooring of the tunnel.
Having thus described my invention what I claim and desire to secure by Letters Patent is:
l. rlhe method of excavating tunnels comprising first constructing a drift heading, then removing the roof by blasting in a stope heading, blasting away the material from the lower surface of the stope heading and maintaining said stope heading in adyance of the tunnel during subsequent blasting.
2. The method of excavating rock tunnels comprising first constructing a drift heading then removing the roof by blasting in a stope heading, blasting away the material. from the lower surface of the stope heading, allowing the broken material to gravitate to receptacles and maintaining said stope heading in advance of the tunnel during subsequent blasting.
8. The method of excavating tunnels which comprises constructing a drift heading, erecting a. staging in the drift heading, providing this staging with an opening, blasting in a stope heading, blasting away the material from the lower surface of the stope heading, allowing the broken material to gravitate through the opening in the staging into receptacles, maintaining said stope heading in advance of the tunnel during subsequent blasting and advancing the opening in the staging as the rear end of the stope heading is advanced.
4L. The method of excavating rock tunnels which comprises constructing a drift heading, erecting a. staging in the drift heading, providing this staging with an opening, blasting in a stope heading, blasting away the material from the lower surface of the stope heading, allowing the broken material to gravitate through the opening in the staging into a. receptacle, maintaining said stope heading in advance of the tunnel during subsequent blasting and advancing the opening in the staging and the receptacle so that the opening and receptacle will at all times be in vertical alinement with the rear end of the stope heading as said rear end is advanced.
The method of excavating tunnels comprising first constructing a drift heading` then removing the roof by blasting in a stope heading, blasting away the material from the lower surface of the stope heading so that the walls of the stope heading will break the momentum of the broken material, then allowing the broken material to gravitate to receptacles and maintaining said stope heading in advance of the tunnel during subsequent blasting.
6. The method of excavating tunnels comprising first constructing a drift heading, then removing the roof and widening the tunnel by blasting in a stope heading of a In testimony whereof I affix my signature greater width than the'tunnel, blasting away in the presence of two witnesses. the material from the lower surface of the stope heading, allowing the broken material EDWARD E' MCCABE to gravitate to receptacles and maintaining Witnesses:
said stope heading in advance of the tunnel FRANK T. SHEEAN,
during subsequent blasting. A. O. AUSTERMANN.
Copies of this patent may be obtained for ve cents each, by addressing the Commissioner of Yatents, Washington, D. C.
US8752216A 1916-03-29 1916-03-29 Method of tunneling. Expired - Lifetime US1208178A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US8752216A US1208178A (en) 1916-03-29 1916-03-29 Method of tunneling.

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US8752216A US1208178A (en) 1916-03-29 1916-03-29 Method of tunneling.

Publications (1)

Publication Number Publication Date
US1208178A true US1208178A (en) 1916-12-12

Family

ID=3276092

Family Applications (1)

Application Number Title Priority Date Filing Date
US8752216A Expired - Lifetime US1208178A (en) 1916-03-29 1916-03-29 Method of tunneling.

Country Status (1)

Country Link
US (1) US1208178A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2952411A (en) * 1955-07-12 1960-09-13 William M Hand Mine track assembly
US3792906A (en) * 1972-07-24 1974-02-19 D Kuck Excavation or earth removal by landsliding same on a fluid lubricant
US20020070600A1 (en) * 1999-08-06 2002-06-13 Dong-Young Ro Three dimensional multi-phase tunneling method and equipments thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2952411A (en) * 1955-07-12 1960-09-13 William M Hand Mine track assembly
US3792906A (en) * 1972-07-24 1974-02-19 D Kuck Excavation or earth removal by landsliding same on a fluid lubricant
US20020070600A1 (en) * 1999-08-06 2002-06-13 Dong-Young Ro Three dimensional multi-phase tunneling method and equipments thereof

Similar Documents

Publication Publication Date Title
WO2019051569A1 (en) Method for underground mining of minerals
US4445723A (en) Method of circle mining of ore
US8899692B2 (en) Method and apparatus for mining a material in an underground environment
US1208178A (en) Method of tunneling.
DE2307413C2 (en) Device for the extraction of a floz-like deposit in longwall mining
EP3259223B1 (en) Conveying system for open-cast mining
RU2248448C1 (en) Method for extraction of steep-falling deposits of weak ores
US1004418A (en) Method of mining.
US20040245845A1 (en) Shield system for coal mining
US3111306A (en) Method of mining trona using a continuous miner
RU2103507C1 (en) Method and cutter-loader machine for development of seam deposits of minerals
JPH0626297A (en) Tunnel drilling method
DE3729140A1 (en) System for the underground mining of minerals
US796499A (en) Art of mining coal.
SU1011861A1 (en) Method of working rich deposits of minerals
US1106863A (en) Process for moving material.
EP0273441B1 (en) Process for discharging spoils
DE3634195A1 (en) METHOD AND EQUIPMENT FOR CARRYING OUT A ROPE ANCHOR
US877779A (en) Method of tunneling in rock.
US1999931A (en) Coextensive room system with mechanical conveyers
US2622403A (en) Method for driving rock tunnels
RU2193660C1 (en) Method of underground mining of steeply dipping vein deposits
US2896929A (en) Method of driving rock excavations
US1583075A (en) Method and apparatus for supporting timbering in tunnels
US1100142A (en) Shield for excavating tunnels and shafts.