TWI749673B - Hanging element and device of water surface grouting platform - Google Patents

Hanging element and device of water surface grouting platform Download PDF

Info

Publication number
TWI749673B
TWI749673B TW109126067A TW109126067A TWI749673B TW I749673 B TWI749673 B TW I749673B TW 109126067 A TW109126067 A TW 109126067A TW 109126067 A TW109126067 A TW 109126067A TW I749673 B TWI749673 B TW I749673B
Authority
TW
Taiwan
Prior art keywords
water surface
suspension element
grouting platform
surface grouting
hanging
Prior art date
Application number
TW109126067A
Other languages
Chinese (zh)
Other versions
TW202206683A (en
Inventor
盧湘凱
Original Assignee
盧湘凱
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 盧湘凱 filed Critical 盧湘凱
Priority to TW109126067A priority Critical patent/TWI749673B/en
Application granted granted Critical
Publication of TWI749673B publication Critical patent/TWI749673B/en
Publication of TW202206683A publication Critical patent/TW202206683A/en

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Foundations (AREA)

Abstract

A hanging element and device of water surface grouting platform are provided on foundation piles to facilitate grouting operations of buildings on the water. Each group of water surface grouting platform devices includes two foundation piles inserted and fixed in the water, The two hanging elements are respectively fixed on the two foundation piles through their respective assembly parts, the two hanging elements are respectively fixed to one end of a bearing column group, and the other end of the bearing column group is inserted into a supporting frame. At the left and right ends, the support frame is suspended under the water surface, and the grouting operation space is composed of multiple water surface grouting platform devices, and the laying of steel bars is more perfect through the penetration parts on the hanging elements.

Description

水面灌漿平台之吊掛元件及其裝置 Hanging element and device of water surface grouting platform

本發明是關於一種灌漿平台,尤指一種便於在水面上進行灌漿作業,且能改善鋼筋鋪設間距的水面灌漿平台之吊掛元件及其裝置。 The present invention relates to a grouting platform, in particular to a hanging element and device of a water surface grouting platform that is convenient for grouting operations on the water surface and can improve the spacing between steel bars.

按,一般鋼筋混凝土的建築手法,係於地基基礎完成後,將樁柱胸板或鋼板樁等作為暫設擋土牆進行構築,並組立柱子的鋼筋,在鋼筋外圍架設模板,再澆注混凝土,待柱子的混凝土凝固達到一定強度後,再組立梁和樓板的鋼筋,並架設模板灌注混凝土,之後逐層往上興建。 According to the general reinforced concrete construction method, after the foundation is completed, the pile chest plate or steel sheet pile is used as a temporary retaining wall to construct, and the reinforcement of the column is assembled, the formwork is erected on the periphery of the reinforcement, and the concrete is poured. After the concrete of the columns has solidified to a certain strength, the beams and the steel bars of the floor slab are assembled, and the formwork is installed to inject the concrete, and then the construction is built up layer by layer.

該等工法若要移至水面上進行,則需要先在水平面上架設平台,且工法中必須設置防水材,架設平台時為追求省時簡便,會利用懸掛裝置等作為輔助,以求加速灌漿作業的進行。 If these construction methods are to be moved to the surface of the water, a platform must be erected on the horizontal surface first, and waterproof materials must be installed in the construction method. In the pursuit of time-saving and simplicity when erecting the platform, suspension devices will be used as an aid to speed up the grouting operation. The progress.

進行灌漿作業期間,鋪設鋼筋的程序是確保建築物股價穩固的重要流程,不論是鋼筋的厚度、綁紮技巧、排列方式、間距等都是會影響整體建築結構的重要關鍵,且關於鋼筋排列的間距,建築法規甚至有嚴格規範,若是鋼筋排列過密而使水泥混凝土產生乾縮或剪力裂縫,鋼筋間的間距過小,不但影響綁紮的困難度,在灌漿過程中,水泥混凝土材料將極難以澆置至底部模板,除材料將對堆積於鋼筋上之外,鋼筋與模板之間 亦形成空洞及灌漿不實之施工瑕疵,使得混凝土的表面粗粒料之間形成較大孔隙,意即產生所謂的蜂窩現象,如此一來,容易造成水泥脆化剝落,這些瑕疵會嚴重影顯建築物的結構安全。 During the grouting operation, the procedure of laying steel bars is an important process to ensure the stability of the building’s stock price. Regardless of the thickness of the steel bars, tying techniques, arrangement methods, spacing, etc., they are all important keys that affect the overall building structure, and the spacing of the reinforcement arrangement , The building regulations even have strict specifications. If the steel bars are arranged too densely to cause dry shrinkage or shear cracks in the cement concrete, and the spacing between the steel bars is too small, it will not only affect the difficulty of binding, but also the cement concrete material will be extremely difficult to pour during the grouting process. To the bottom formwork, in addition to the material will be stacked on the reinforcement, between the reinforcement and the formwork Construction flaws such as cavities and false grouting are also formed, causing larger pores to be formed between the coarse particles on the surface of the concrete, which means the so-called honeycomb phenomenon occurs. As a result, it is easy to cause cement embrittlement and peeling, and these flaws will be seriously affected. The structure of the building is safe.

然而,使用在架設水面平台上的懸掛裝置,由於會凸出於作業空間中,鋼筋鋪設時一般係將長條狀的鋼筋以直向及橫向等距排列,在框設成矩形的作業空間中鋪設形成網狀結構,但凸出於作業空間的懸掛裝置會影響鋼筋排列的流暢度,排列鋼筋時如遇到凸出的懸掛裝置則須將鋼筋繞離,破壞了該區域的間距也影響鋼筋鋪設作業的流暢度。 However, the suspension device used on the erection of the water platform will protrude out of the working space. When laying steel bars, the long steel bars are generally arranged in a straight and horizontally equidistant arrangement in a rectangular working space. Laying to form a net-like structure, but the suspension device protruding from the work space will affect the smoothness of the steel bar arrangement. When the steel bar is arranged, if it encounters the protruding suspension device, the steel bar must be wound away, which destroys the spacing of the area and affects the steel bar. The smoothness of laying operations.

因此,如果解決在水面灌漿平台中鋪設鋼筋的的流暢度問題,及維持鋼筋間的間距,為目前業界所需。 Therefore, it is necessary for the industry to solve the problem of the smoothness of laying steel bars in the water surface grouting platform and maintain the spacing between the steel bars.

爰此,本發明的主要目的,在於提供一種能夠克服鋼筋在舖設時遇到懸掛裝置需要繞離影響鋪設流暢度問題的吊掛元及水面灌漿平台裝置。 In summary, the main purpose of the present invention is to provide a hanging element and water surface grouting platform device that can overcome the problem that the suspension device needs to be deviated from the suspension device during the laying of steel bars and affects the smoothness of the laying.

為達上述目的,本發明是關於一種水面灌漿平台之吊掛元件及其裝置,係供組設於基樁上,以便於在水上進行建築物之灌漿作業,每組水面灌漿平台裝置包括:二基樁,該二基樁插入並固定於水中;二吊掛元件,該二吊掛元件上各自設有一組設部及複數個穿設部,該二吊掛元件透過各自的該組設部分別固定在該二基樁上;二承力柱組,該二承力柱組分別以其中一端固定在該二吊掛元件上;及一支撐架,該二承力柱組的另一端分別與該支撐架的左右兩端組設,使該支撐架懸吊於水面下。 In order to achieve the above-mentioned object, the present invention relates to a suspension element and device of a surface grouting platform, which are installed on foundation piles to facilitate the grouting operation of buildings on the water. Each group of surface grouting platform devices includes: two Foundation piles, the two foundation piles are inserted and fixed in the water; two hanging elements, each of the two hanging elements is provided with a set of installation parts and a plurality of penetration parts, the two hanging elements respectively pass through the respective assembly parts Fixed on the two foundation piles; two load-bearing column groups, the two load-bearing column groups are respectively fixed on the two hanging elements with one end; and a support frame, the other end of the two load-bearing column groups are respectively connected to the The left and right ends of the support frame are assembled so that the support frame is suspended under the water surface.

在本申請的實施例中,透過設置至少二組水面灌漿平台裝置 以形成可灌漿的一作業空間。 In the embodiment of this application, by setting at least two sets of surface grouting platform devices To form a working space that can be grouted.

在本申請的實施例中,該些承力柱組係穿設並固定在該支撐架的左右兩端。 In the embodiment of the present application, the load-bearing column groups are penetrated and fixed on the left and right ends of the support frame.

在本申請的實施例中,該些穿設部係在該吊掛元件上開設的等距排列之穿孔。 In the embodiment of the present application, the perforation parts are equidistantly arranged perforations opened on the suspension element.

在本申請的實施例中,該些穿設部係在該吊掛元件上開設的不等距排列之穿孔。 In the embodiment of the present application, the piercing parts are unequal-spaced perforations arranged on the hanging element.

在本申請的實施例中,該些穿設部係在該吊掛元件的上、下兩側開設的對稱凹槽。 In the embodiment of the present application, the piercing parts are symmetrical grooves opened on the upper and lower sides of the hanging element.

在本申請的實施例中,該些穿設部係在該吊掛元件的上、下兩側開設的不對稱凹槽。 In the embodiment of the present application, the penetration parts are asymmetric grooves opened on the upper and lower sides of the hanging element.

在本申請的實施例中,該些穿設部係在該吊掛元件上開設的長型溝槽。 In the embodiment of the present application, the piercing parts are long grooves opened on the hanging element.

在本申請的實施例中,該二吊掛元件上對向平行設置的該些穿設部上插設有一支撐桿。 In the embodiment of the present application, a support rod is inserted into the penetration portions of the two hanging elements that are arranged oppositely and in parallel.

藉此,本發明的優點在於,透過吊掛元件上複數個等距離排列的穿設部,在鋪設鋼筋時,鋼筋能透過該些穿設部貫穿吊掛元件,無須再繞離吊掛元件,使得鋼筋鋪設作業能流暢進行,且在水面灌漿平台的架設期間,透過在穿設部中穿設支撐桿,能夠增加拉力及橫向承載力,在懸吊該支撐架時能避免該些承力柱組彎曲,及避免基樁損壞。 Thereby, the advantage of the present invention is that through a plurality of penetrating parts arranged at equal distances on the hanging element, when laying steel bars, the steel bars can penetrate the hanging element through the penetrating parts, and there is no need to go around and away from the hanging element. The steel bar laying operation can be carried out smoothly, and during the erection of the water surface grouting platform, by piercing the support rods in the penetration part, the tensile force and the lateral bearing capacity can be increased, and the load-bearing columns can be avoided when the support frame is suspended The group is bent, and to avoid damage to the foundation pile.

100:水面灌漿平台裝置 100: Water surface grouting platform device

101:作業空間 101: Work Space

110:基樁 110: foundation pile

120:吊掛元件 120: Hanging element

121:組設部 121: Assembly Department

122:穿設部 122: Wearing Department

1221:穿孔 1221: Piercing

1222:凹槽 1222: Groove

1223:溝槽 1223: groove

130:承力柱組 130: bearing column group

140:支撐架 140: support frame

200:鋼筋 200: Rebar

300:混凝土 300: Concrete

400:支撐桿 400: Support rod

圖1為本發明吊掛元件及承力柱組之示意圖。 Fig. 1 is a schematic diagram of the hanging element and load-bearing column set of the present invention.

圖2為本發明水面灌漿平台裝置之示意圖。 Figure 2 is a schematic diagram of the water surface grouting platform device of the present invention.

圖3為本發明水面灌漿平台裝置之實施示意圖。 Figure 3 is a schematic diagram of the implementation of the water surface grouting platform device of the present invention.

圖4為本發明水面灌漿平台裝置之鋼筋穿設示意圖。 Fig. 4 is a schematic diagram of steel bar penetration of the water surface grouting platform device of the present invention.

圖5為本發明開設穿孔之吊掛元件及承力柱組之示意圖。 Fig. 5 is a schematic diagram of a hanging element and a load-bearing pillar group with perforated holes in the present invention.

圖6為本發明開設凹槽之吊掛元件及承力柱組之示意圖一。 Fig. 6 is a schematic diagram 1 of the hanging element and load-bearing column group with grooves provided in the present invention.

圖7為本發明開設凹槽之吊掛元件及承力柱組之示意圖二。 Fig. 7 is the second schematic diagram of the hanging element and the load-bearing column group with grooves provided in the present invention.

圖8為本發明開設長型溝槽之吊掛元件及承力柱組之示意圖。 Fig. 8 is a schematic diagram of a hanging element and a load-bearing column group with a long groove provided in the present invention.

圖9為本發明支撐桿之使用示意圖。 Figure 9 is a schematic diagram of the use of the support rod of the present invention.

為了使本技術領域的人員更好地理解本發明方案,下面將結合本發明實施例中的附圖,對本發明實施例中的技術方案進行清楚、完整地描述,顯然,所描述的實施例僅僅是本發明一部分的實施例,而不是全部的實施例。基於本發明中的實施例,本領域普通技術人員所做的等效變化與修飾前提下所獲得的所有其他實施例,都應當屬於本發明保護的範圍。 In order to enable those skilled in the art to better understand the solutions of the present invention, the technical solutions in the embodiments of the present invention will be described clearly and completely in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only It is a part of the embodiments of the present invention, not all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained under the premise of equivalent changes and modifications made by persons of ordinary skill in the art shall fall within the protection scope of the present invention.

需要說明的是,本發明的說明書和權利要求書及上述附圖中的術語“上”、“下”、“裡”、“外”等是用於區別類似的物件,而不必用於描述特定的順序或先後次序。應該理解這樣使用的資料在適當情況下可以互換,以便這裡描述的本發明的實施例能夠以除了在這裡圖示或描述的那些以外的順序實施。此外,術語“包括”和“具有”以及他們的任何變形,意圖在於覆蓋不排他的包含。 It should be noted that the terms "upper", "lower", "in", "outer", etc. in the description and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe specific items. The order or precedence. It should be understood that the materials used in this way can be interchanged under appropriate circumstances so that the embodiments of the present invention described herein can be implemented in a sequence other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations of them are intended to cover non-exclusive inclusions.

請參閱圖1、圖2、圖3及圖4。本發明係關於一種水面灌漿平台之吊掛元件及其裝置,係供組設於基樁上,以便於在水上進行建築物之灌漿作業,每組水面灌漿平台裝置100包括:二基樁110,該二基樁110插入並固定於水中;二吊掛元件120,該二吊掛元件120上各自設有一組設部121及複數個穿設部122,該二吊掛元件120透過各自的該組設部121分別固定在該二基樁110上;二承力柱組130,該二承力柱組130分別以其中一端固定在該二吊掛元件120上;及一支撐架140,該二承力柱組130的另一端分別與該支撐架140的左右兩端組設,使該支撐架140懸吊於水面下。 Please refer to Figure 1, Figure 2, Figure 3 and Figure 4. The present invention relates to a suspension element and device of a water surface grouting platform, which are arranged on foundation piles to facilitate the grouting operation of buildings on the water. Each group of water surface grouting platform device 100 includes: two foundation piles 110, The two foundation piles 110 are inserted and fixed in the water; two hanging elements 120, each of which is provided with a set 121 and a plurality of penetrating portions 122, the two hanging elements 120 pass through each set The setting portion 121 is respectively fixed on the two foundation piles 110; two load-bearing column groups 130, the two load-bearing column groups 130 are respectively fixed on the two suspension elements 120 with one end; and a support frame 140, the two bearing The other end of the force column group 130 is respectively assembled with the left and right ends of the support frame 140 so that the support frame 140 is suspended under the water surface.

實施上,每一組承力柱組130的一端係事先固定於一吊掛元件120上,其固定方式可以是焊接、螺絲鎖固等任何能使承力柱組130穩定的與該吊掛元件120結合的方式,再將該吊掛元件120透過組設部121掛設並固定在該基樁110上,一個吊掛元件120掛設在一個基樁110上,將二個已掛有吊掛元件120的基樁110水平排列,並將支撐架140以承力柱組130懸掛於該吊掛元件120下方,其懸掛方式係為,以二承力柱組130的另一端穿設並焊接固定在該支撐架140的左右兩端,如此便形成一組水面灌漿平台裝置100。 In practice, one end of each load-bearing column group 130 is fixed to a hanging element 120 in advance, and the fixing method can be welding, screw locking, etc., which can make the load-bearing column group 130 stable with the hanging element. 120 combination, and then hang the hanging element 120 through the assembly part 121 and fix it on the foundation pile 110, one hanging element 120 is hung on one foundation pile 110, and the two hanging elements The foundation piles 110 of the element 120 are arranged horizontally, and the support frame 140 is suspended under the suspension element 120 by the bearing column group 130, and the suspension method is that the other end of the two bearing column group 130 is penetrated and fixed by welding At the left and right ends of the support frame 140, a set of surface grouting platform devices 100 are thus formed.

透過設置至少二組水面灌漿平台裝置100,以形成可灌漿的一作業空間101,透過在作業空間101中的底面及四周鋪設模板(圖未示)即可在該作業空間101中進行後續的灌漿以及鋼筋200鋪設作業。期作要流程主要是依序先鋪設網狀鋼筋200再倒入第一層混凝土300,待混凝土300乾後再往上繼續鋪設網狀鋼筋200,而後倒入第二層混凝土300,以此類推直至到建築物所需之高度。 By arranging at least two sets of water surface grouting platform devices 100 to form a working space 101 that can be grouted, and by laying a template (not shown) on the bottom surface and surroundings of the working space 101, subsequent grouting can be performed in the working space 101 And 200 laying operations of steel bars. The main plan is to lay the reticulated steel bars 200 in sequence, then pour the first layer of concrete 300, wait until the concrete 300 is dry, and then continue to lay the reticulated steel bars 200, and then pour the second layer of concrete 300, and so on. Until the height required by the building.

請再同時參閱圖1、圖5至圖8。當鋼筋200的鋪設作業已經達到該些吊掛元件120的高度時,直向的鋼筋200鋪設並不受該些吊掛元件120影響,而橫向的鋼筋200碰到該些吊掛元件120時可透過該些吊掛元件120上的該穿設部122貫穿該些吊掛元件120,而無須繞離。該些吊掛元件120上的該穿設部122排列方式根據使用需求可以為等距離排列,或不等距離排列。該些穿設部122的形式可以是在該吊掛元件120的平面上等距、不等距排列之穿孔1221(如圖1、圖5所示),或是在該吊掛元件120的上、下兩側開設的對稱、不對稱凹槽1222(如圖6、圖7所示)等任何能讓鋼筋200貫穿過該些吊掛元件120的孔隙。更進一步,該些穿設部122係在該吊掛元件120上開設的長型溝槽1223(如圖8所示),該長型溝槽1223直徑大於鋼筋200,因此當複數根鋼筋200要貫穿該吊掛元件120時,其鋼筋200的間距可以不受該穿設部122間的距離影響,可以任意調整貫穿該吊掛元件120的鋼筋200間距離。 Please refer to Figure 1, Figure 5 to Figure 8 at the same time. When the laying operation of the steel bars 200 has reached the height of the hanging elements 120, the laying of the vertical steel bars 200 is not affected by the hanging elements 120, while the horizontal steel bars 200 can touch the hanging elements 120. The suspending elements 120 are penetrated through the piercing parts 122 on the suspending elements 120 without winding away. The arrangement of the piercing parts 122 on the hanging elements 120 can be equidistant or unequal distance arrangement according to the use requirements. The form of the penetration portions 122 may be the perforations 1221 arranged at equal intervals and unequal distances on the plane of the suspension element 120 (as shown in FIGS. 1 and 5), or on the suspension element 120 , Symmetrical and asymmetrical grooves 1222 (as shown in FIG. 6 and FIG. 7) provided on the lower two sides, etc., allow the steel bar 200 to penetrate through the suspending elements 120. Furthermore, the penetration portions 122 are tied to the elongated grooves 1223 (as shown in FIG. 8) opened on the suspension element 120. The diameter of the elongated grooves 1223 is larger than the steel bar 200, so when a plurality of steel bars 200 require When penetrating the hanging element 120, the spacing of the steel bars 200 may not be affected by the distance between the penetration portions 122, and the distance between the steel bars 200 penetrating the hanging element 120 can be adjusted arbitrarily.

更進一步,請參閱圖9。在進行水面灌漿平台裝置100的架設作業期間,該吊掛元件120上的該些穿設部122上設有至少一支撐桿400,該支撐桿400被固定在該二吊掛元件120上對向平行設置的二穿設部122上,根據需求以及該吊掛元件120上所設置的該些穿設部122的數量,可設置二組以上的該支撐桿400,圖示以設置一支撐桿400為最佳實施例。在懸吊該支撐架140於水面下的過程中,由於初期尚未有模板及混凝土300支撐,該些基樁110及該些承力柱組130受到支撐架140的重量影響,容易產生彎曲變形,透過組設該支撐桿400,能夠在二吊掛元件120間提供橫向承載的支撐力,提升在支撐架140左、右兩側的該些承力柱組130拉力,能夠避免該些承力柱組130彎曲,及造成基樁110損壞。 To go further, please refer to Figure 9. During the erection operation of the surface grouting platform device 100, at least one support rod 400 is provided on the penetration portions 122 of the hanging element 120, and the support rod 400 is fixed on the two hanging elements 120 to face each other. Two or more sets of the supporting rods 400 can be provided on the two penetrating parts 122 arranged in parallel according to requirements and the number of the penetrating parts 122 provided on the hanging element 120, and a supporting rod 400 is provided as shown in the figure. It is the best embodiment. In the process of suspending the support frame 140 below the water surface, since there is no formwork and concrete 300 support at the initial stage, the foundation piles 110 and the bearing column groups 130 are affected by the weight of the support frame 140 and are prone to bending deformation. By assembling the support rod 400, it is possible to provide lateral load-bearing support between the two hanging elements 120, and to increase the tension of the load-bearing column groups 130 on the left and right sides of the support frame 140, which can avoid the load-bearing columns. The group 130 is bent and the foundation pile 110 is damaged.

而該支撐桿400在穿設該穿孔1221形式及該長型溝槽1223形式的該穿設部122時可以透過螺絲鎖固、扣環定位等固定方式使該支撐桿400暫時固定在該吊掛元件120的該穿設部122中;若是在該吊掛元件120的上、下兩側開設的凹槽1222中架設該支撐桿400,該支撐桿400可以透過螺絲鎖固方式進行固定,以利水面灌漿平台裝置100架設作業的進行。 When the support rod 400 is inserted through the perforation 1221 and the long groove 1223 through the penetration portion 122, the support rod 400 can be temporarily fixed to the suspension through fixing methods such as screw locking, buckle positioning, etc. In the penetration portion 122 of the element 120; if the support rod 400 is erected in the grooves 1222 opened on the upper and lower sides of the suspension element 120, the support rod 400 can be fixed by screw locking to facilitate The erection operation of the surface grouting platform device 100 is carried out.

如此一來,本發明透過在該吊掛元件120設置穿設部122,除了能在鋼筋200的鋪設作業上帶來更流暢的作業程序,以維持鋼筋200間距外,在水面灌漿平台裝置100的架設過程中還能透過加裝支撐桿400達到避免該些承力柱組130彎曲,及該些基樁110損壞的效果,達到更優良的平台架設品質及灌漿作業效果。 In this way, the present invention, through the provision of the penetration portion 122 on the suspension element 120, in addition to bringing a smoother operation procedure on the laying operation of the steel bars 200, and maintaining the spacing between the steel bars 200, the grouting platform device 100 is installed on the water surface. During the erection process, the support rod 400 can also be added to prevent the load-bearing column groups 130 from bending and the foundation piles 110 to be damaged, so as to achieve better platform erection quality and grouting operation effects.

以上所述,僅是本申請的具體實施例而已,並非對本申請作任何形式上的限制,雖然本申請已以具體實施例揭露如上,然而並非用以限定本申請,任何熟悉本專業的技術人員,在不脫離本申請技術方案範圍內,當可利用上述揭示的技術內容作出些許更動或修飾為等同變化的等效實施例,但凡是未脫離本申請技術方案的內容,依據本申請的技術實質對以上實施例所作的任何簡單修改、等同變化與修飾,均仍屬於本申請技術方案的範圍內。 The above are only specific embodiments of the application, and do not limit the application in any form. Although the application has been disclosed as above in specific embodiments, it is not intended to limit the application. Anyone who is familiar with the profession , Without departing from the scope of the technical solution of the application, when the technical content disclosed above can be used to make some changes or modification into equivalent embodiments with equivalent changes, but any content that does not deviate from the technical solution of the application is based on the technical essence of the application Any simple modifications, equivalent changes and modifications made to the above embodiments still fall within the scope of the technical solutions of the present application.

100:水面灌漿平台裝置 100: Water surface grouting platform device

110:基樁 110: foundation pile

120:吊掛元件 120: Hanging element

121:組設部 121: Assembly Department

122:穿設部 122: Wearing Department

1221:穿孔 1221: Piercing

130:承力柱組 130: bearing column group

140:支撐架 140: support frame

200:鋼筋 200: Rebar

Claims (8)

一種水面灌漿平台之吊掛元件及其裝置,係供組設於基樁上,以便於在水上進行建築物之灌漿作業,每組水面灌漿平台裝置包括:二基樁,該二基樁插入並固定於水中;二吊掛元件,該二吊掛元件上各自設有一組設部及複數個穿設部,該二吊掛元件透過各自的該組設部分別固定在該二基樁上,該二吊掛元件上對向平行設置的該些穿設部上插設有一支撐桿;二承力柱組,該二承力柱組分別以其中一端固定在該二吊掛元件上;及一支撐架,該二承力柱組的另一端分別與該支撐架的左右兩端組設,使該支撐架懸吊於水面下。 A hanging element and device of a water surface grouting platform are provided for assembly on foundation piles to facilitate the grouting operation of buildings on the water. Each group of water surface grouting platform device includes two foundation piles, which are inserted and combined. Fixed in the water; two hanging elements, the two hanging elements are each provided with a set of setting parts and a plurality of penetration parts, the two hanging elements are respectively fixed on the two foundation piles through the respective set of parts, the A support rod is inserted into the penetration portions of the two hanging elements that are arranged oppositely and in parallel; two load-bearing column groups, the two load-bearing column groups are respectively fixed on the two hanging elements with one end thereof; and a support The other ends of the two load-bearing column groups are respectively assembled with the left and right ends of the support frame, so that the support frame is suspended under the water surface. 如申請專利範圍第1項所述之水面灌漿平台之吊掛元件及其裝置,其中,透過設置至少二組水面灌漿平台裝置以形成可灌漿的一作業空間。 The suspension element and device of the surface grouting platform described in the first item of the scope of patent application, wherein at least two sets of surface grouting platform devices are provided to form a working space that can be grouted. 如申請專利範圍第1項所述之水面灌漿平台之吊掛元件及其裝置,其中,該些承力柱組係穿設並固定在該支撐架的左右兩端。 For the suspension element and device of the water surface grouting platform described in item 1 of the scope of patent application, the load-bearing column groups are penetrated and fixed on the left and right ends of the support frame. 如申請專利範圍第1項所述之水面灌漿平台之吊掛元件及其裝置,其中,該些穿設部係在該吊掛元件上開設的等距排列之穿孔。 The suspension element and device of the water surface grouting platform described in item 1 of the scope of patent application, wherein the perforation parts are equidistantly arranged perforations opened on the suspension element. 如申請專利範圍第1項所述之水面灌漿平台之吊掛元件及其裝置,其中,該些穿設部係在該吊掛元件上開設的不等距排列之穿孔。 For example, the suspension element and device of the water surface grouting platform described in item 1 of the scope of patent application, wherein the perforation parts are perforations arranged at unequal intervals on the suspension element. 如申請專利範圍第1項所述之水面灌漿平台之吊掛元件及其裝置,其中,該些穿設部係在該吊掛元件的上、下兩側開設的對稱凹槽。 For the suspension element and device of the water surface grouting platform described in item 1 of the scope of patent application, the penetration parts are symmetrical grooves opened on the upper and lower sides of the suspension element. 如申請專利範圍第1項所述之水面灌漿平台之吊掛元件及其裝置,其中,該些穿設部係在該吊掛元件的上、下兩側開設的不對稱凹槽。 For the suspension element and device of the water surface grouting platform described in item 1 of the scope of patent application, the penetration parts are asymmetric grooves opened on the upper and lower sides of the suspension element. 如申請專利範圍第1項所述之水面灌漿平台之吊掛元件及其裝置,其中,該些穿設部係在該吊掛元件上開設的長型溝槽。 The suspension element and device of the water surface grouting platform described in item 1 of the scope of patent application, wherein the penetration parts are long grooves opened on the suspension element.
TW109126067A 2020-07-31 2020-07-31 Hanging element and device of water surface grouting platform TWI749673B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW109126067A TWI749673B (en) 2020-07-31 2020-07-31 Hanging element and device of water surface grouting platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW109126067A TWI749673B (en) 2020-07-31 2020-07-31 Hanging element and device of water surface grouting platform

Publications (2)

Publication Number Publication Date
TWI749673B true TWI749673B (en) 2021-12-11
TW202206683A TW202206683A (en) 2022-02-16

Family

ID=80681217

Family Applications (1)

Application Number Title Priority Date Filing Date
TW109126067A TWI749673B (en) 2020-07-31 2020-07-31 Hanging element and device of water surface grouting platform

Country Status (1)

Country Link
TW (1) TWI749673B (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW201346106A (en) * 2012-05-04 2013-11-16 Chang Ho Machinery Engineering Co Ltd Pile reinforcement cage assembly construction method
CN106894544A (en) * 2016-12-30 2017-06-27 上海建工四建集团有限公司 Embedded individual layer steel plate concrete combined shear wall and its construction method
TWM568885U (en) * 2018-07-20 2018-10-21 樂鑫開發工程有限公司 Water surface grouting platform hanging device

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW201346106A (en) * 2012-05-04 2013-11-16 Chang Ho Machinery Engineering Co Ltd Pile reinforcement cage assembly construction method
CN106894544A (en) * 2016-12-30 2017-06-27 上海建工四建集团有限公司 Embedded individual layer steel plate concrete combined shear wall and its construction method
TWM568885U (en) * 2018-07-20 2018-10-21 樂鑫開發工程有限公司 Water surface grouting platform hanging device

Also Published As

Publication number Publication date
TW202206683A (en) 2022-02-16

Similar Documents

Publication Publication Date Title
US10094101B1 (en) Precast concrete system with rapid assembly formwork
CN103046645B (en) A kind of whole casting structure and construction method of Large-span Precast
WO2016077943A1 (en) Building supporting unit and building supporting structure employing same
CN107859206A (en) Pre-manufactured steel structure overlapped shear wall and its construction method
CN108625486A (en) A kind of across frame structure edge support node structure of steel bar girder plate
CN106703407A (en) Construction method of double-layered shape steel supporting rack of cantilever beam plate
CN104988984A (en) U-shaped steel and concrete combined orthogonal-diagonal spatial grid box type structure and manufacturing method
CN207812741U (en) Pre-manufactured steel structure overlapped shear wall
CN202202412U (en) Rectangular steel pipe concrete special-shaped column-steel beam framework middle node
CN203961281U (en) Steel bar girder beam form frame and H section steel beam-cast-in-place concrete floor formwork system
RU2552506C1 (en) Method for construction of monolithic structures of buildings and non-removable universal modular formwork system
CN208472973U (en) A kind of detachable reinforcing steel truss plate end support node structure
TWI749673B (en) Hanging element and device of water surface grouting platform
Babaev et al. Cast reinforced concrete frame of buildings and methods of its erection
CN107237428A (en) Precast concrete wall panel class component steel wire hook connects splicing construction and method
CN106013450A (en) Core tube skip-floor construction method
CN210067441U (en) Integrated cast-in-place concrete for elevator brick wall and door buttress
CN212773550U (en) Lifting and pulling device for steel bar truss floor support plate
CN108643388A (en) A kind of construction wall
CN213115585U (en) Stable form bearing structure that building engineering used
WO2021031860A1 (en) Beam lowering construction method of subsurface structure in top-down method
CN109610795B (en) Construction method of inverted cone-shaped building
CN106894631A (en) A kind of concrete partition combination tool
JP2009299346A (en) Construction method of building
CN106223459B (en) A kind of extrusion forming fibre cement house and its method of construction