TWI558480B - A method of hot forging press for shaping metal rods - Google Patents

A method of hot forging press for shaping metal rods Download PDF

Info

Publication number
TWI558480B
TWI558480B TW103128809A TW103128809A TWI558480B TW I558480 B TWI558480 B TW I558480B TW 103128809 A TW103128809 A TW 103128809A TW 103128809 A TW103128809 A TW 103128809A TW I558480 B TWI558480 B TW I558480B
Authority
TW
Taiwan
Prior art keywords
metal bar
die
stamping
mold
metal
Prior art date
Application number
TW103128809A
Other languages
Chinese (zh)
Other versions
TW201607636A (en
Inventor
廖茂智
王啓聖
Original Assignee
智品精密機械有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 智品精密機械有限公司 filed Critical 智品精密機械有限公司
Priority to TW103128809A priority Critical patent/TWI558480B/en
Publication of TW201607636A publication Critical patent/TW201607636A/en
Application granted granted Critical
Publication of TWI558480B publication Critical patent/TWI558480B/en

Links

Description

金屬棒材熱鍛衝壓成型方法 Metal bar hot forging stamping forming method

本發明係關於一種成型方法,特別是指一種金屬棒材熱鍛衝壓成型方法。 The present invention relates to a molding method, and more particularly to a method of hot forging stamping of a metal bar.

按,一般零件(即指螺帽、華司、與其他機械所需之零件等等),其主要是備具有一較大體積之金屬塊體,而後進行車修加工程序,即一一漸進的切削、研磨該金屬塊體,以使該金屬塊體外型形成所需使用之零件;然而,使用車修加工方式,其所需備具之金屬塊體必須是大於該零件體積外,並且車修加工過程中除加工緩慢外,同時也會產生許多廢料,造成材料成本、製造時間的增加外,並且使用車修加工方式所形成之零件,由於該金屬塊體加工過程中,並非使用擠壓之方式,故加工後之零件其硬度也較差。 Press, general parts (referred to as nuts, washers, and other mechanical parts, etc.), which are mainly equipped with a large volume of metal blocks, and then the vehicle repair process, that is, one by one Cutting and grinding the metal block so that the metal block is externally formed to form a part to be used; however, using the vehicle repair method, the required metal block must be larger than the part volume, and the vehicle repair is performed. In addition to slow processing during processing, many waste materials are also generated, resulting in an increase in material cost and manufacturing time, and the use of parts formed by the car repair process, because the metal block processing process is not using extrusion In the way, the hardness of the parts after processing is also poor.

因此,有部分業者進而使用衝壓成型方式進行製造,而該衝壓成型,係指在室溫下,係將該金屬材料放置於鍛造機之模具上,以利用該鍛造機上之衝模,加以對該模具上之金屬材料經由衝擊而施加壓力,使該金屬材料產生塑性變形或分離,從而獲得所需零件的一種壓力加工方法。 Therefore, some manufacturers further use a stamping method, which is to place the metal material on a die of a forging machine at room temperature to utilize the die on the forging machine. A pressure processing method in which a metal material on a mold is subjected to pressure by impact to plastically deform or separate the metal material to obtain a desired part.

而現行衝壓成型方法僅侷限於使用於體積較小之金屬材料,如螺絲成型機中必須先將金屬材料拉成桿徑較小之金屬線材,而後該鍛造機方有足夠之衝擊力能使該金屬線材衝壓成型,然而,若遇到所需零件體積較大時,其受限金屬線材本身之膨脹比因素、該鍛造機之模具、衝模與動力大小,雖然理論上可採取增加該鍛造機之整體體積與噸數,以因應所需製造之零件體積,但實際上是非常的不符合經濟效益,因此現行若遇大體積之零件時,仍是以車修方式進行加工;故,如何在不增加該鍛造機之體積與動力下,就可針對體積較大之金屬材料進行衝壓加工,並且能確保該鍛造機仍可正常的進行作業,乃為業界大家所努力之目標。 The current stamping forming method is limited to the use of a small metal material. For example, in a screw forming machine, the metal material must first be drawn into a metal wire having a small diameter, and then the forging machine has sufficient impact force to enable the Metal wire stamping, however, if the required part volume is large, the expansion ratio of the metal wire itself, the die, the die and the power of the forging machine, although theoretically, the forging machine can be added. The overall volume and tonnage, in order to meet the required volume of parts, but in fact is very inconsistent with economic benefits, so in the current large-volume parts, it is still processed in the way of repair; therefore, how to not By increasing the volume and power of the forging machine, it is possible to perform stamping processing on a large-sized metal material, and to ensure that the forging machine can still operate normally, which is an objective of the industry.

因此,本發明之目的,是在提供一種金屬棒材熱鍛衝壓成型方法,其使體積較大之金屬棒材更易加工,以降低鍛造機所需衝壓動力外,更可避免該衝模與模具之損耗。 Therefore, the object of the present invention is to provide a metal bar hot forging stamping forming method, which makes the metal bar of larger volume easier to process, so as to reduce the punching power required by the forging machine, and avoid the die and the die. loss.

於是,本發明金屬棒材熱鍛衝壓成型方法,其依序包含有一備料步驟、加熱步驟及衝壓成型步驟;其中,該加熱步驟,備具有一加熱器,並且將該金屬棒材輸入至該加熱器進行加熱,以使該金屬棒材形成一高溫狀態,以使該金屬棒材形成一高膨脹比之易加工性;另,該衝壓成型步驟中備具有一鍛造機,以便將該高溫狀態之金屬棒材由該進料裝置輸入至該模衝裝置上,藉以增加該金屬棒材之易加工性, 進而降低該衝模所需之衝壓動力,以及該衝模與模具之損耗外,即可快速的將該金屬材料衝壓成型出一物件,同時該冷卻裝置之冷卻液循環冷卻該模具,有效避免該模具因該金屬棒材之高溫而損壞,促使該鍛造機可正常的進行加工作業。 Therefore, the metal bar hot forging stamping forming method of the present invention comprises a preparation step, a heating step and a press forming step in sequence; wherein the heating step is provided with a heater, and the metal bar is input to the heating The device is heated to form the metal bar to a high temperature state, so that the metal bar forms a high expansion ratio for easy processing; and the press forming step has a forging machine for the high temperature state a metal bar is input to the die punching device by the feeding device, thereby increasing the ease of processing of the metal bar. Further, in addition to reducing the punching power required for the die, and the loss of the die and the die, the metal material can be quickly formed into an object, and the coolant of the cooling device is circulated to cool the die, thereby effectively avoiding the die. The high temperature of the metal bar is damaged, which causes the forging machine to perform normal processing operations.

〔本發明〕 〔this invention〕

3‧‧‧金屬棒材熱鍛衝壓成型方法 3‧‧‧Metal bar hot forging stamping forming method

31‧‧‧備料步驟 31‧‧‧Material preparation steps

32‧‧‧加熱步驟 32‧‧‧heating steps

33‧‧‧衝壓成型步驟 33‧‧‧ Stamping step

4‧‧‧鍛造機 4‧‧‧Forging machine

41‧‧‧加熱器 41‧‧‧heater

42‧‧‧衝模 42‧‧‧ die

43‧‧‧模具 43‧‧‧Mold

44‧‧‧夾料器 44‧‧‧Clamps

45‧‧‧冷卻裝置 45‧‧‧Cooling device

A‧‧‧金屬棒材 A‧‧‧Metal Bar

451‧‧‧管路 451‧‧‧pipe

452‧‧‧噴水器 452‧‧‧ sprinkler

圖1 是本發明一較佳實施例之方塊圖。 1 is a block diagram of a preferred embodiment of the present invention.

圖2、圖3是本發明一較佳實施例之動作示意圖。 2 and 3 are schematic views showing the operation of a preferred embodiment of the present invention.

有關本發明之前述及其他技術內容、特點與功效,在以下配合參考圖式之較佳實施例的詳細說明中,將可清楚的明白。 The above and other technical contents, features, and advantages of the present invention will become apparent from the Detailed Description of the <RTIgt;

參閱圖1、圖2,本發明一較佳實施例,本實施例金屬棒材熱鍛衝壓成型方法3,該金屬棒材熱鍛衝壓成型方法3包含有一備料步驟31、一加熱步驟32及一衝壓成型步驟33;其中,該備料步驟31係備具有金屬棒材A;另,該加熱步驟32其主要在於一鍛造機4上設有一加熱器41,且該加熱器41恰可供該金屬棒材A輸入,同時該金屬棒材A輸入過程中受到該加熱器41加熱,以使該金屬棒材A呈現出高溫軟化狀態,而形成一具高膨脹比之加工特性。 Referring to FIG. 1 and FIG. 2, a preferred embodiment of the present invention, a metal bar hot forging stamping forming method 3, the metal bar hot forging stamping forming method 3 includes a preparation step 31, a heating step 32 and a a stamping forming step 33; wherein the preparing step 31 is provided with a metal bar A; and the heating step 32 is mainly characterized in that a forging machine 4 is provided with a heater 41, and the heater 41 is just for the metal bar The material A is input while the metal bar A is heated by the heater 41 during the input process, so that the metal bar A exhibits a high temperature softening state to form a processing characteristic with a high expansion ratio.

該加熱步驟32其備具有一加熱器4,並且將該金屬棒材A輸入至該加熱器4進行加熱,以使該金屬棒材A形成一 高溫狀態,而該高溫狀態可依據不同材料做一設定,以使該金屬棒材A形成易加工之型態。 The heating step 32 is provided with a heater 4, and the metal bar A is input to the heater 4 for heating to form the metal bar A. The high temperature state, and the high temperature state can be set according to different materials, so that the metal bar A forms a form that is easy to process.

仍續前述,配合參閱圖3,其在鍛造機4上作業,該鍛造機4具有複數設於該鍛造機4上之衝模42,複數與該衝模42相對應之模具43,分設於該等模具43間之夾料器44,以及一設於該模具43上之冷卻裝置45,其中,該冷卻裝置45具有多數環繞於該等模具43周圍之管路451,以及流動於該等管路451內之冷卻液,以便該裁切後之該金屬棒材A經過該等衝模衝壓,再配合該等夾料器44夾持位移,以使該金屬棒材A漸進式衝壓成型出一零件外觀,此時該金屬棒材A於該模具43中被該衝模42所予以衝壓,該等模具43所吸收的熱量可受到該冷卻裝置45加以冷卻。 Still referring to FIG. 3, which is operated on a forging machine 4, the forging machine 4 has a plurality of dies 42 disposed on the forging machine 4, and a plurality of dies 43 corresponding to the dies 42 are disposed at the same a cutter 44 between the molds 43 and a cooling device 45 disposed on the mold 43, wherein the cooling device 45 has a plurality of tubes 451 surrounding the molds 43 and flows through the tubes 451. a cooling liquid inside, so that the cut metal bar A is punched by the punches, and then clamped and displaced by the clamps 44, so that the metal bar A is progressively stamped to form a part appearance. At this time, the metal bar A is pressed by the die 42 in the mold 43, and the heat absorbed by the molds 43 can be cooled by the cooling device 45.

仍續前述,故該衝壓成型步驟33執行時,先將前述經過該加熱步驟32中之金屬棒材A直接輸送到該鍛造機4上,即該加熱器41將該金屬棒材A進行加熱,而後再經由該夾料器44之夾持下,得以將該金屬棒材A輸送至該模具43上,而該衝模42衝擊過程中,由於該金屬棒材A之高溫狀態,使該金屬棒材A變得質軟,除可減少該衝模42、模具43所需之撞擊受力,同時更增加該金屬棒材A之延展性,使得該金屬棒材A更易進行加工,因此該衝模42所需之衝壓動力也可以降低,促使該衝模42、模具43能輕易地將該金屬棒材A衝壓成型。 Continuing the foregoing, when the press forming step 33 is performed, the metal bar A passing through the heating step 32 is directly transported to the forging machine 4, that is, the heater 41 heats the metal bar A. Then, the metal bar A is conveyed to the mold 43 by the clamping of the clamper 44, and the metal bar is made due to the high temperature state of the metal bar A during the impact of the die 42. A becomes soft, in addition to reducing the impact force required for the die 42 and the mold 43, and at the same time increasing the ductility of the metal bar A, making the metal bar A easier to process, so the die 42 is required The punching power can also be lowered, so that the die 42 and the mold 43 can easily press-form the metal bar A.

再者,同時於衝壓過程中,由於該金屬棒材A本 身具備高溫,衝擊的瞬間其熱能將傳導至該模具43上,而透過該冷卻裝置45之冷卻液持續的流動於該等模具43間,將可避免該模具43在連續作業中,防止溫度過高而使得該模具43也變得相對質軟之情況,有效防止該模具43變形損壞之情事,進而使該模具43與衝模42之壽命更加延長;此外,為使該衝模42與模具43能夠穩定的進行降溫,亦可適時透過該衝模42與模具43間設有一噴水器452,以針對該衝模42進行噴水冷卻作業。 Furthermore, at the same time in the stamping process, due to the metal bar A When the body is provided with a high temperature, the thermal energy will be transmitted to the mold 43 at the moment of impact, and the coolant passing through the cooling device 45 continuously flows between the molds 43 to prevent the mold 43 from being prevented from being in a continuous operation. When the mold 43 is relatively high, the mold 43 is also relatively soft, and the mold 43 is effectively prevented from being deformed and damaged, thereby further prolonging the life of the mold 43 and the die 42. Further, in order to stabilize the die 42 and the mold 43 In order to cool down, a water sprayer 452 may be disposed between the die 42 and the mold 43 in time to perform a water spray cooling operation on the die 42.

是以,透過該金屬棒材熱鍛衝壓成型方法3之加熱步驟32,將可使該金屬棒材A變得質軟,而增加該金屬棒材A之易加工性外,進而降低該衝模42所需之衝壓動力,以及減少該衝模42與模具43之損耗,即可快速的將該金屬材料A衝壓成型出一半成品或成品之零件,以供後續進行使用。 Therefore, the heating step 32 of the hot bar forming method 3 of the metal bar can make the metal bar A soft, and increase the ease of processing of the metal bar A, thereby reducing the die 42. The required punching power, as well as reducing the loss of the die 42 and the mold 43, can quickly form the metal material A into a half finished or finished part for subsequent use.

歸納前述,本發明金屬棒材熱鍛衝壓成型方法,其依序藉由該備料步驟、加熱步驟及衝壓成型步驟等程序,以透過該加熱步驟係先將該金屬棒材形成一高溫狀態後,促使該金屬棒材能經由加熱至高熱狀態下,以便該金屬棒材形成一高膨脹比之易加工性,進而降低該衝模所需之衝壓動力及減少該衝模與模具之損耗,於該衝壓成型步驟中再將該金屬棒材輸入至鍛造機之模具上,以便該鍛造機之衝模即可快速的將該金屬材料衝壓成型出一物件,同時該模具之穿孔兩端係連接該鍛造機之冷卻裝置,以供該冷卻裝置之冷卻液循 環冷卻該模具,有效避免該模具因該金屬棒材之高溫而損壞。 In the above, the metal bar hot forging press forming method of the present invention sequentially forms the metal bar into a high temperature state by the steps of the preparing step, the heating step, and the press forming step, etc., through the heating step. Promoting the metal bar to be heated to a high heat state, so that the metal bar forms a high expansion ratio and easy to process, thereby reducing the punching power required for the die and reducing the loss of the die and the die. In the step, the metal bar is further input into the die of the forging machine, so that the die of the forging machine can quickly press the metal material into an object, and the perforated ends of the die are connected to the cooling of the forging machine. a device for the cooling liquid of the cooling device The ring cools the mold, effectively preventing the mold from being damaged by the high temperature of the metal bar.

惟以上所述者,僅為說明本發明之較佳實施例而已,當不能以此限定本發明實施之範圍,即大凡依本發明申請專利範圍及發明說明書內容所作之簡單的等效變化與修飾,皆應仍屬本發明專利涵蓋之範圍內。 The above is only the preferred embodiment of the present invention, and the scope of the present invention is not limited thereto, that is, the simple equivalent changes and modifications made in accordance with the scope of the present invention and the contents of the description of the invention. All should remain within the scope of the invention patent.

3‧‧‧金屬棒材熱鍛衝壓成型方法 3‧‧‧Metal bar hot forging stamping forming method

31‧‧‧備料步驟 31‧‧‧Material preparation steps

32‧‧‧加熱步驟 32‧‧‧heating steps

33‧‧‧衝壓成型步驟 33‧‧‧ Stamping step

41‧‧‧加熱器 41‧‧‧heater

4‧‧‧鍛造機 4‧‧‧Forging machine

Claims (2)

一種金屬棒材熱鍛衝壓成型方法,其係將該金屬棒材在鍛造機上衝壓成形,該金屬棒材熱鍛衝壓成型方法包含有:一備料步驟,其備具有一金屬棒材;一加熱步驟,其在該鍛造機上設有一加熱器,且該加熱器恰可供該金屬棒材輸入,同時該金屬棒材輸入過程中受到該加熱器加熱,以使該金屬棒材呈現出高溫軟化狀態;及一衝壓成型步驟,其在鍛造機上作業,該鍛造機具有複數設於該鍛造機上之衝模,複數與該衝模相對應之模具,分設於該等模具間之夾料器,以及一設於該模具上之冷卻裝置,其中,該冷卻裝置具有多數環繞於該等模具周圍之管路,以及流動於該等管路內之冷卻液,以便該裁切後之該金屬棒材經過該等衝模衝壓,再配合該等夾料器夾持依序位移至各個模具上,以使該金屬棒材漸進式衝壓成型出一零件外觀,此時該金屬棒材於該模具中被該衝模予以衝壓,該等模具所吸收的熱量可受到該冷卻裝置加以冷卻。 A metal bar hot forging stamping forming method, which is formed by stamping a metal bar on a forging machine, the metal bar hot forging stamping forming method comprising: a preparing step, which is provided with a metal bar; a step of providing a heater on the forging machine, and the heater is just for inputting the metal bar, and the metal bar is heated by the heater during the input process, so that the metal bar exhibits high temperature softening. And a stamping forming step of operating on a forging machine having a plurality of dies disposed on the forging machine, a plurality of dies corresponding to the dies, and a splicer disposed between the dies And a cooling device disposed on the mold, wherein the cooling device has a plurality of pipes surrounding the molds, and a coolant flowing in the pipes, so that the cut metal bars After the stamping, the clamps are sequentially displaced to the respective molds, so that the metal bar is progressively stamped and formed into a part appearance, and the metal bar is in the mold at this time. The stamping die to be heat absorbed by such a mold may be cooled by the cooling means. 根據申請專利範圍第1項所述金屬棒材熱鍛衝壓成型方法,其中,該衝模與模具間設有一噴水器,以針對該衝模進行噴水冷卻作業。 The hot-bar stamping forming method for a metal bar according to the first aspect of the invention, wherein a water sprinkler is disposed between the die and the die to perform a water spray cooling operation for the die.
TW103128809A 2014-08-21 2014-08-21 A method of hot forging press for shaping metal rods TWI558480B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW103128809A TWI558480B (en) 2014-08-21 2014-08-21 A method of hot forging press for shaping metal rods

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW103128809A TWI558480B (en) 2014-08-21 2014-08-21 A method of hot forging press for shaping metal rods

Publications (2)

Publication Number Publication Date
TW201607636A TW201607636A (en) 2016-03-01
TWI558480B true TWI558480B (en) 2016-11-21

Family

ID=56084577

Family Applications (1)

Application Number Title Priority Date Filing Date
TW103128809A TWI558480B (en) 2014-08-21 2014-08-21 A method of hot forging press for shaping metal rods

Country Status (1)

Country Link
TW (1) TWI558480B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI817735B (en) * 2022-09-22 2023-10-01 勝惟工具工業股份有限公司 Long sleeve forming method with multi-strokes

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWM250730U (en) * 2003-12-02 2004-11-21 Shiue-Jr Liau Punching mold
TW201006971A (en) * 2008-06-28 2010-02-16 Japan Super Quartz Corp Water-cooled mold
TWM414281U (en) * 2011-05-20 2011-10-21 Chyan Tay Iron Factory Co Ltd Material feeding structure for forging furnace

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWM250730U (en) * 2003-12-02 2004-11-21 Shiue-Jr Liau Punching mold
TW201006971A (en) * 2008-06-28 2010-02-16 Japan Super Quartz Corp Water-cooled mold
TWM414281U (en) * 2011-05-20 2011-10-21 Chyan Tay Iron Factory Co Ltd Material feeding structure for forging furnace

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI817735B (en) * 2022-09-22 2023-10-01 勝惟工具工業股份有限公司 Long sleeve forming method with multi-strokes

Also Published As

Publication number Publication date
TW201607636A (en) 2016-03-01

Similar Documents

Publication Publication Date Title
TWI537075B (en) A method for making a spanner
KR100971219B1 (en) Yoke manufacturing method
JP5437730B2 (en) Hot bulge forming apparatus, hot bulge forming method, and hot bulge formed product
JP6240564B2 (en) Molding apparatus and method for replacing parts of molding apparatus
CN104191167A (en) Forging forming method for titanium alloy thin-wall special-shaped ring
CN104476145B (en) The manufacture method of pad
KR101641786B1 (en) Method of hydroforming work and method and system of making high strength steel pipe using thereof
CN101116935B (en) Valve collet producing technology
TWI558480B (en) A method of hot forging press for shaping metal rods
JP2003053437A (en) Continuous press working equipment for magnesium alloy
CN102441585A (en) Preparation method of aluminium alloy composite pipe
CN108237197B (en) A kind of forging method improving the flaw detection of structural steel large-sized ring part
TW201323109A (en) Method for manufacturing magnesium alloy
CN109663875B (en) Forging process for die pressing groove of groove ring
US20170072455A1 (en) Burr-freebolt forging mould
CN112846064A (en) Isothermal forming method and device for aluminum alloy flange forging material distribution control
JP7215343B2 (en) METHOD FOR MANUFACTURING TUBE MEMBER WITH CLOSED END
TWI647048B (en) Method for forming a spanner
TWI531429B (en) Hand tool forming method
CN205362366U (en) Can realize cut -out press of self -cooling
CN103528408A (en) Platform machining method of heat radiator
CN203764668U (en) Extruding device of magnesium alloy welding wire
JP6039986B2 (en) Hollow rack bar manufacturing apparatus and hollow rack bar manufacturing method
US11065673B2 (en) Hot steel forging in horizontal press
CN105855439A (en) Machining method for planet carrier

Legal Events

Date Code Title Description
MM4A Annulment or lapse of patent due to non-payment of fees