TWI550162B - Construction method of underground retaining wall - Google Patents

Construction method of underground retaining wall Download PDF

Info

Publication number
TWI550162B
TWI550162B TW103112256A TW103112256A TWI550162B TW I550162 B TWI550162 B TW I550162B TW 103112256 A TW103112256 A TW 103112256A TW 103112256 A TW103112256 A TW 103112256A TW I550162 B TWI550162 B TW I550162B
Authority
TW
Taiwan
Prior art keywords
wall
box seat
retaining wall
underground retaining
construction method
Prior art date
Application number
TW103112256A
Other languages
Chinese (zh)
Other versions
TW201538825A (en
Inventor
Ding-Hong Chen
Original Assignee
Ding-Hong Chen
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ding-Hong Chen filed Critical Ding-Hong Chen
Priority to TW103112256A priority Critical patent/TWI550162B/en
Publication of TW201538825A publication Critical patent/TW201538825A/en
Application granted granted Critical
Publication of TWI550162B publication Critical patent/TWI550162B/en

Links

Description

地下擋土牆施工方法 Underground retaining wall construction method

本創作係一種地下擋土牆施工方法,尤指一種可防止地層坍塌災害的地下擋土牆施工方法。其牆體結構斷面為中空矩形型狀,利用中空空間條件遂行施工機械架設與回收、牆體構築與沉降及回填灌漿成實體擋土牆三階段目標。 The present invention relates to a method for constructing an underground retaining wall, and more particularly to a method for constructing an underground retaining wall capable of preventing collapse of a stratum. The wall structure has a hollow rectangular shape, and uses the hollow space condition to carry out the three-stage goal of construction machinery erection and recovery, wall construction and settlement, and backfill grouting into a solid retaining wall.

高樓建築物之地下室開挖通常採用連續壁作為擋土結構,現有連續壁施工方法係先進行整地、放樣定位、設置安定液池、沉泥池等配套設備之準備工作,接著精確構築導溝。 The basement excavation of high-rise buildings usually adopts continuous wall as the retaining structure. The existing continuous wall construction method is to prepare the grounding, lofting and positioning, setting up the stability liquid pool, sinking mud and other supporting equipment, and then accurately construct the guiding ditch. .

待準備工作完成後,根據地質狀況、施工要求、環境條件及工程數量等因素選擇妥適的挖掘機械,逐一進行各公母單元槽溝之挖掘作業,地下連續壁槽溝的挖掘是利用安定液來維持施工中槽溝穩定,安定液由皂土摻合其他化學添加劑,各依重量百分比和清水攪拌而成的混合液,具特殊流動性的一種塑性流體,使槽溝壁產生泥膜,防止壁面剝落,並阻止槽溝內安定液逸流或地下水侵入,而達到防止槽溝壁崩坍之功效。 After the preparation work is completed, according to the geological conditions, construction requirements, environmental conditions and the number of projects, etc., the appropriate excavation machinery is selected, and the excavation work of each male and female unit trench is carried out one by one, and the underground continuous wall trench is excavated by using the stability liquid. To maintain the stability of the trench during construction, the stability liquid is mixed with other chemical additives by bentonite, and the mixture of each weight percentage and water is mixed, and a plastic fluid with special fluidity causes the mud wall of the groove wall to prevent mud The wall surface is peeled off, and the stability liquid flow or the groundwater intrusion in the groove is prevented, and the effect of preventing the wall of the groove from collapsing is achieved.

待挖掘機挖掘至預定設計深度後,將挖掘機取出並吊放鋼筋籠與特密管後進行混凝土灌漿。 After the excavator has been excavated to a predetermined design depth, the excavator is taken out and the steel cage and the special pipe are suspended to carry out concrete grouting.

連續壁之混凝土填灌方式特異,是利用特密管深入槽溝底,混凝土由底部向上,逐次將槽溝內之隔離液排擠而取待其體積。完成地下各單元連續壁築體作業。而安定液則於回收後重新使用。 The concrete filling method of the continuous wall is specific, and the special pipe is used to penetrate the bottom of the groove, and the concrete is pushed upward from the bottom, and the partitioning liquid in the groove is successively squeezed to take the volume. Complete the continuous wall construction of each unit in the underground. The tranquilizer is reused after recycling.

上述中,一單元連續壁施作完成後,需要時間養護以達到預定結構強度,所以其毗鄰單元附近不能接續施工,所以各單元連續壁採用跳接施工的方式。 In the above, after the completion of the operation of one unit of continuous wall, it takes time to maintain the predetermined structural strength, so that the adjacent unit cannot be connected to the vicinity, so the continuous wall of each unit adopts the method of jumper construction.

上述連續壁施工方法會產生以下問題: The above continuous wall construction method will cause the following problems:

1.成本高:連續壁施工方法中採用安定液的功能與特性來維持挖掘槽溝之穩定,其中,安定液的價格昂貴且需定時品質檢測,所費不貲,雖可回收處理再利用,而再利用的安定液性能仍需要符合嚴格之品質規範,而回收處理需要額外的處理費用。不合品質規範的安定液則無法繼續使用被迫回收處理,故採用安定液具有成本高的問題。 1. High cost: The function and characteristics of the stability liquid are used in the continuous wall construction method to maintain the stability of the excavation trench. Among them, the stability of the stability liquid is expensive and requires regular quality inspection, which is costly and can be recycled and reused. The performance of recycled stabilizers still needs to meet strict quality specifications, and recycling requires additional processing costs. The stabilizers that do not meet the quality specifications cannot be used continuously and are forced to be recycled. Therefore, the use of stabilizers has a high cost.

2.不環保:污染嚴重的安定液無法繼續循環使用,其廢棄回收需要特別處理,產生環保問題。 2. Not environmentally friendly: The stable liquid with serious pollution cannot continue to be recycled, and its waste recycling needs special treatment, which causes environmental problems.

3.易發生災變:由於安定液價格昂貴,承造單位為了節省成本儘可能節省其用量,或者採用劣質品,甚或以黏土充當使用之,無法有效發揮安定液的正常功能。以至於槽溝挖掘階段:造成槽溝崩坍的災害發生,在連續壁體澆灌混凝土階段:劣質安定液將導致壁體單元產生蜂巢結構而降低壁體單元的結構強度與施工接縫水密性,進而影響地下室深開挖階段時:壁體滲水與開挖區外地面坍塌等災變的發生率。 3. Prone to catastrophic changes: Due to the high price of the stabilizer, the contractor can save the amount of its use in order to save costs, or use inferior products, or even use clay as the use, can not effectively play the normal function of the stabilizer. So that the trench excavation stage: the disaster causing the trench collapse, in the continuous wall watering concrete stage: the inferior stability liquid will cause the wall unit to generate the honeycomb structure and reduce the structural strength of the wall unit and the watertightness of the construction joint, and then When the deep excavation stage of the basement is affected: the incidence of catastrophes such as seepage of the wall and collapse of the ground outside the excavation area.

4.耗費時間:連續壁施工方法要完全開挖至確定深度後,確認壁體垂直度與安定液品質後,才會吊放鋼筋籠與特密管,始再灌注混凝土以形成各壁體單元。且壁體單元需要時間養護至一定結構強度,才可以進行毗鄰單元之施作,所以完成一個單元連續壁相當耗費時間,另外,公母單元必須跳接方式挖掘構築,無法縮短工時。 4. Time consuming: After the continuous wall construction method is completely excavated to a certain depth, after confirming the verticality of the wall and the quality of the stability liquid, the steel cage and the special pipe will be suspended, and the concrete will be re-infused to form each wall unit. . Moreover, the wall unit needs time to be maintained to a certain structural strength, so that the adjacent unit can be applied. Therefore, it takes a long time to complete one unit continuous wall. In addition, the male and female units must be jumped and excavated, and the working hours cannot be shortened.

本創作之主要目的在於提供一種連續壁施工方法,希藉此改善目前連續壁施工方法產生之成本高、工安問題、環安問題、災變難防且耗費工時的問題。 The main purpose of this creation is to provide a continuous wall construction method, which aims to improve the high cost, safety and safety problems, environmental safety problems, disasters and time-consuming problems caused by the current continuous wall construction method.

為達成前揭目的,本創作之地下擋土牆施工方法,包含有:準備作業,整理施工場地並設置沉砂池、工作間等配套設備,接著放樣定位後構築導溝;安裝作業,將預鑄沉箱座平整安置於預設之牆體單元導溝內,且在預鑄沉箱座內設置挖掘裝置、抽取裝置與水刀裝置。並於預鑄沉箱座與導溝之間注入隔離液,預鑄沉箱座內注水,保持預鑄沉箱座內的水的液面高度高於地面高程1公尺以上,以及預鑄沉箱座內架設框架、動力管線與抵撐的油壓千斤頂;牆體製作步驟,於預鑄沉箱座牆體上端設置模板設備,將鋼筋續接於預鑄沉箱座預留筋上,且模板設備的內模、外模分別位於鋼筋兩側並形成澆注空間,澆注混凝土至澆注空間,於混凝土初凝固化至一定程度後,將內模、外模利用油壓系統一同往上頂昇移動,空出空間再次澆注混 凝土至內模、外模之間並等待混凝土初凝固化,並以油壓千斤頂沉壓框架,重覆進行油壓頂昇內模、外模與澆注、固化的動作,以形成各單元的牆體;挖掘步驟,挖掘裝置進行挖掘,再由抽取裝置將土泥抽出,預鑄沉箱座與牆體遂往下沉降,同時於牆體與導溝之間注入隔離液,以及牆體內注水,保持水的液面高度高於地面高程1公尺以上;待牆體沉降至階段深度後,再以模板設備接續製作牆體,續接框架、油壓千斤頂、抽泥管及動力管線後再進行挖掘步驟,反覆施作至牆體與預鑄沉箱座的總長度達到地下擋土牆的預設深度;拆卸作業,先拆卸模板設備後,再將抽取裝置、框架、油壓千斤頂、挖掘裝置等設備全數依序自預鑄沉箱座上吊昇並逐節拆下,以及同步進行牆體中空斷面回填灌漿,完成實體斷面之地下擋土牆;收尾整理步驟,對地下擋土牆的牆體單元進行收尾整理。 In order to achieve the purpose of the previous disclosure, the construction method of the underground retaining wall of the present invention includes: preparing the work, finishing the construction site and setting up the supporting equipment such as the grit chamber and the working room, and then constructing the guiding groove after the positioning and positioning; The casting caisson seat is placed flat in the preset wall unit guide groove, and an excavating device, an extracting device and a water jet device are arranged in the caulking box seat. And injecting isolation liquid between the caisson and the guide groove, and injecting water into the sinking box seat, keeping the liquid level of the water in the sinking box seat more than 1 meter above the ground elevation, and erecting in the sinking box seat Frame, power line and hydraulic jack for resisting; wall making step, setting template device at the upper end of the wall of the caulking box seat, continuing the steel bar to the reserved rib of the sinking box seat, and the inner mold of the template device, The outer molds are respectively located on both sides of the steel bar and form a pouring space, and the concrete is poured into the pouring space. After the concrete is first solidified to a certain extent, the inner mold and the outer mold are lifted up together by the hydraulic system, and the empty space is poured again. Mixed Condensing the soil between the inner mold and the outer mold and waiting for the initial solidification of the concrete, and pressing the frame with the hydraulic jack, repeatedly performing the action of hydraulically lifting the inner mold, the outer mold, and pouring and solidifying to form each unit. Wall; excavation step, excavation device for excavation, and then the soil is extracted by the extraction device, the sinking box seat and the wall raft are set down, and the partitioning liquid is injected between the wall and the guiding groove, and the water is injected into the wall. Keep the liquid level of the water more than 1 meter above the ground elevation; after the wall is settled to the depth of the stage, continue to make the wall with the template equipment, continue the frame, the hydraulic jack, the mud pipe and the power line before proceeding The excavation step is repeated until the total length of the wall and the sinking box seat reaches the preset depth of the underground retaining wall; after the disassembly operation, the template device is first disassembled, and then the extracting device, the frame, the hydraulic jack, the excavating device, etc. All the equipments are hoisted and removed from the caisson seat in sequence, and the hollow section of the wall is backfilled and grouted simultaneously to complete the underground retaining wall of the solid section; the finishing step is on the wall of the underground retaining wall The body unit is finished finishing.

據上所述,該地下擋土牆施工方法於牆體製作步驟中,以模板設備製作的牆體,絕無破洞蜂巢劣質混凝土情形,可防地下水滲漏並具備足夠的結構強度,可以防止槽溝崩坍、地面坍塌等災害,達到防災與提升工安的目的。以及牆體已然結構成型可擋土/水壓力而減少安定液的使用量,進而可省下安定液的購買、回收與監測等成本,且更為環保並改善環安問題。而反覆循序進行牆體製作與掘降,可以縮短工時,並可依據地下水文與地質條件 而調整模板設備之內模與外模的間距,調整各階段深度之牆體厚度,以及選用適當尺寸之預鑄沉箱座與挖掘裝置,可一次施作大尺幅的地下擋土牆。另因牆體具有一定的結構強度,其毗鄰牆體單元可同步進行安裝作業、牆體製作步驟與挖掘、抽取步驟,進而縮短工時。 According to the above, the underground retaining wall construction method is in the wall making step, the wall made by the template device, and there is no broken hole honeycomb inferior concrete, which can prevent groundwater leakage and has sufficient structural strength to prevent Disasters such as trench collapse and ground collapse have achieved the goal of disaster prevention and improvement of work safety. And the wall structure has been formed to prevent soil/water pressure and reduce the amount of stabilizer solution used, thereby saving the cost of purchase, recovery and monitoring of the stabilizer solution, and being more environmentally friendly and improving the environmental safety problem. Repeated wall production and excavation can shorten working hours and can be based on groundwater and geological conditions. The distance between the inner mold and the outer mold of the template device is adjusted, the thickness of the wall at each stage is adjusted, and the caulking box seat and the excavating device of the appropriate size are selected, and the underground retaining wall of large size can be applied at one time. In addition, because the wall has a certain structural strength, the adjacent wall unit can simultaneously perform the installation work, the wall making step and the excavation, and the extraction step, thereby shortening the working hours.

10‧‧‧預鑄沉箱座 10‧‧‧預鑄箱箱座

11‧‧‧座體 11‧‧‧

12‧‧‧座腳 12‧‧‧ feet

13‧‧‧鋼趾部 13‧‧‧Steel toe

14‧‧‧凸部 14‧‧‧ convex

15‧‧‧預留空間 15‧‧‧ Reserved space

20‧‧‧挖掘裝置 20‧‧‧Excavating device

30‧‧‧抽取裝置 30‧‧‧ extraction device

40‧‧‧模板設備 40‧‧‧Template equipment

41‧‧‧內模 41‧‧‧Inner model

42‧‧‧外模 42‧‧‧External model

50‧‧‧牆體 50‧‧‧ wall

60‧‧‧導溝 60‧‧‧ Guide groove

70‧‧‧油壓千斤頂 70‧‧‧Hydraulic jack

圖1:為本創作地下擋土牆施工方法之一較佳實施例之構築導溝示意圖。 Fig. 1 is a schematic view showing the construction of a guide groove according to a preferred embodiment of the method for constructing an underground retaining wall.

圖2:為本創作地下擋土牆施工方法之一較佳實施例之吊置預鑄沉箱座示意圖。 Fig. 2 is a schematic view showing a hanging box seat of a preferred embodiment of the method for constructing an underground retaining wall.

圖3:為本創作地下擋土牆施工方法之一較佳實施例之預鑄沉箱座上安裝挖掘裝置與抽取裝置示意圖。 Fig. 3 is a schematic view showing the installation of an excavating device and an extracting device on a caulking box seat according to a preferred embodiment of the method for constructing an underground retaining wall.

圖4:為本創作地下擋土牆施工方法之一較佳實施例之預鑄沉箱座上端設置模板設備示意圖。 FIG. 4 is a schematic view showing a template device disposed at an upper end of a sump box seat according to a preferred embodiment of the method for constructing a subterranean retaining wall.

圖5:為本創作地下擋土牆施工方法之一較佳實施例之壁體製作步驟示意圖。 Fig. 5 is a schematic view showing the steps of fabricating a wall according to a preferred embodiment of the method for constructing an underground retaining wall.

圖6:為本創作地下擋土牆施工方法之一較佳實施例之壁體製作步驟中內、外模移動之示意圖。 Fig. 6 is a schematic view showing the movement of the inner and outer molds in the wall forming step of a preferred embodiment of the method for constructing an underground retaining wall.

圖7:為本創作地下擋土牆施工方法之一較佳實施例之挖掘步驟示意圖。 Fig. 7 is a schematic view showing the excavation steps of a preferred embodiment of the method for constructing an underground retaining wall.

本創作地下擋土牆施工方法包含準備作業、安裝作業、牆體製作步驟、挖掘步驟、反覆施作至階段深度、拆卸作業與收尾整理步驟。 The construction method of the underground retaining wall of the present invention includes preparation work, installation work, wall making step, excavation step, repeated application to stage depth, disassembly work and finishing finishing step.

於準備作業中,整理施工場地並設置沉砂池、工作間等配套設備,接著精確放樣定位並設置導溝60(如圖1所示),其中,工作間可放置機械、空壓機等物。 In the preparation work, the construction site is arranged and the supporting equipment such as the grit chamber and the working room are set up, and then the positioning groove 60 is accurately positioned and set (as shown in Fig. 1), wherein the working room can be placed with machinery, air compressor, etc. .

請參閱圖2、圖3所示,於安裝作業,將預鑄沉箱座10平整安置於預設之地下擋土牆的牆體單元處導溝內,預鑄沉箱座10與導溝60之間有間隙,且在預鑄沉箱座10內安裝挖掘裝置20、抽取裝置30與水刀裝置,並於預鑄沉箱座10與導溝60之間注入隔離液,預鑄沉箱座10內注水,並保持預鑄沉箱座10內的水面高度高於地面高程1公尺以上,以及在預鑄沉箱座10內架設框架與抵撐的油壓千斤頂70以維持框架垂直穩定。 Referring to FIG. 2 and FIG. 3, in the installation work, the caisson box seat 10 is placed flat in the guide groove at the wall unit of the preset underground retaining wall, between the sinker box seat 10 and the guide groove 60. There is a gap, and the excavating device 20, the extracting device 30 and the water jet device are installed in the caisson box seat 10, and the partitioning liquid is injected between the caisson box seat 10 and the guiding groove 60, and the sinking box seat 10 is filled with water, and The height of the water surface in the tamping tank seat 10 is maintained more than 1 metre above the ground elevation, and the frame and the hydraulic jack 70 are erected in the tamping tank seat 10 to maintain the frame vertical stability.

其中所述預鑄沉箱座10包含有一座體11,該座體11下方設有錐狀的座腳12,座腳12外覆設增加下切力的鋼趾部13,以利於預鑄沉箱座10下切移動。 The sump box 10 includes a body 11 , and the base 11 is provided with a tapered seat 12 . The foot 12 is covered with a steel toe 13 for increasing the lower cutting force to facilitate the sluice box seat. 10 under the cut movement.

該座體11上方設有凸部14,且凸部14的外周形成一預留空間15,注入隔離液以減少預鑄沉箱座10與土壁之間的摩擦力。 The seat body 11 is provided with a convex portion 14 above, and the outer periphery of the convex portion 14 forms a reserved space 15 to inject a spacer liquid to reduce the friction between the tamping box seat 10 and the soil wall.

請參閱圖4至圖7,於預鑄沉箱座10牆體上端設置模板設備40,以模板設備40於預鑄沉箱座10凸部14上進行牆體製作,先將鋼筋續接於該預鑄沉箱座預留筋上。 Referring to FIG. 4 to FIG. 7 , a stencil apparatus 40 is disposed on the upper end of the wall of the sluice box base 10 , and the stencil apparatus 40 is used for wall forming on the convex portion 14 of the sump box seat 10 , and the reinforcing bar is first connected to the rafter. The caisson seat is reserved for the ribs.

模板設備40的內模41、外模42及軛架(Yoke)腳等模板裝置分別位於鋼筋兩側並形成澆注空間,澆注混凝土至澆注空間。 Formwork devices such as the inner mold 41, the outer mold 42, and the yoke leg of the stencil apparatus 40 are respectively located on both sides of the steel bar and form a pouring space for pouring concrete into the pouring space.

於混凝土初凝後,開啟油壓系統,利用螺桿 向下壓之作用力,將內模41、外模42反向往上拉動,並以油壓千斤頂沉壓框架。 After the initial setting of the concrete, the hydraulic system is opened and the screw is used. Pressing the force downwards pulls the inner mold 41 and the outer mold 42 upward, and presses the frame with a hydraulic jack.

再次澆注混凝土至內模41、外模42之空間並等待混凝土初凝固化,重覆進行拉動內模41、外模42與澆注、固化的動作,以形成該牆體單元的部分牆體50。 The concrete is poured again into the space of the inner mold 41 and the outer mold 42 and waits for the initial solidification of the concrete, and the action of pulling the inner mold 41 and the outer mold 42 with casting and solidification is repeated to form a part of the wall 50 of the wall unit.

並逐段設置油壓千斤頂70頂撐牆體50,維持框架垂直穩定及後續牆體沉降時增強牆體勁度以抗衡側土壓力。 The oil pressure jack 70 top wall 50 is arranged one by one to maintain the vertical stability of the frame and to enhance the wall stiffness when the wall is settled to counter the lateral earth pressure.

待一部分牆體50成型後,接著進行挖掘步驟,請參閱圖7所示,預鑄沉箱座10的挖掘裝置20進行挖掘,抽取裝置30將挖掘裝置20所挖掘出的土層抽出,同時於牆體50與導溝60之間注入隔離液,以及牆體50內注水,保持水的液面高度高於地面高程1公尺以上。 After a part of the wall 50 is formed, the excavation step is carried out. Referring to FIG. 7, the excavating device 20 of the caisson box 10 performs excavation, and the extracting device 30 extracts the soil layer excavated by the excavating device 20, and simultaneously on the wall. The partitioning liquid is injected between the body 50 and the guide groove 60, and water is injected into the wall 50 to maintain the liquid level of the water more than 1 meter above the ground elevation.

預鑄沉箱座10受到自重、牆體50的重量、框架與水的重量,可順利往下沉降,且挖掘裝置20持續挖掘,直至前個牆體製作步驟中所製作的一部分牆體50已降至預定的深度,便停止挖掘。 The sinker 10 is subjected to its own weight, the weight of the wall 50, the weight of the frame and the water, can be smoothly lowered, and the excavating device 20 continues to excavate until a part of the wall 50 produced in the previous wall making step has been lowered. At the predetermined depth, the excavation is stopped.

啟動逐段設置之油壓千斤頂70頂撐牆體50,以穩固框架及維持框架垂直度。 The oil pressure jack 70 is supported by the stepped wall to support the wall 50 to stabilize the frame and maintain the verticality of the frame.

待挖掘至階段深度後,再以模板設備40接續製作牆體50,並進行挖掘步驟,反覆施作至牆體50與預鑄沉箱座10的總長度達到地下擋土牆的設計深度。 After the excavation to the depth of the stage, the wall 50 is continuously formed by the formwork device 40, and the excavation step is performed, and the total length of the wall 50 and the caulking box seat 10 is applied to reach the design depth of the underground retaining wall.

例如:先以牆體製作步驟製作6公尺高度的一部分牆體50後,接著進行挖掘作業,使前個步驟所製作的一部分牆體50下移至預定的深度後,停止挖掘作業 。 For example, after a part of the wall 50 having a height of 6 meters is produced by the wall making step, the excavation work is performed, and after a part of the wall 50 produced in the previous step is moved down to a predetermined depth, the excavation operation is stopped. .

接著又進行牆體製作步驟,於前次所製作的一部分牆體50上再接續製作出一6公尺高度的一部分牆體50,然後停止模板設備40,啟動挖掘裝置20進行挖掘作業,抽取裝置30則同步抽出土層,同時於牆體50內外分別注入水與隔離液。 Then, the wall forming step is further performed, and a part of the wall 50 of a height of 6 meters is continuously formed on a part of the wall 50 previously produced, and then the template device 40 is stopped, and the excavating device 20 is started to perform excavation work, and the extracting device is started. 30, the soil layer is simultaneously extracted, and water and a separating liquid are respectively injected into the inside and outside of the wall 50.

而第二次製作的一部分牆體50接著又下移至另一個階段深度。 A portion of the wall 50 produced in the second time is then moved down to another stage depth.

重覆數個循環的牆體製作步驟與挖掘作業至完成該地下擋土牆之設計深度為止。 Repeat several cycles of wall fabrication steps and excavation operations until the design depth of the subterranean retaining wall is completed.

配合牆體50各階段製作,鋼骨框架及其內的抽泥管、動力管路可逐節續接,其逐節遞增之載重,有利於牆體下降效率,且可抵擋地下水上浮力。 With the production of various stages of the wall 50, the steel frame and the mud pipe and the power pipeline therein can be connected one by one, and the load is increased step by step, which is beneficial to the wall drop efficiency and can resist the buoyancy of the groundwater.

且逐段設置之油壓千斤頂70頂撐牆體50,可穩固框架之垂直度,且可以平衡側土壓力。 The oil pressure jack 70 is supported by the wall jacking wall 50, which can stabilize the verticality of the frame and balance the lateral earth pressure.

待牆體50與預鑄沉箱座10的總長度達到地下擋土牆的設計深度後,先行拆卸下模板設備40,再將預鑄沉箱座10上的抽取裝置30與挖掘裝置20及鋼骨框架(含管路系統)與油壓千斤頂70等設備順序吊昇並逐節拆卸下來。該挖掘裝置20與抽取裝置30、油壓千斤頂70、鋼骨框架及管路系統可重複使用。 After the total length of the wall body 50 and the sinker box 10 reaches the design depth of the underground retaining wall, the lower stencil apparatus 40 is removed first, and the extracting device 30 on the tamping box seat 10 and the excavating device 20 and the steel frame are removed. Equipment (including piping system) and hydraulic jack 70 are sequentially hoisted and dismantled section by section. The excavating device 20 can be reused with the extraction device 30, the hydraulic jack 70, the steel frame and the piping system.

最後進行收尾整理步驟,對地下擋土牆的牆體單元進行收尾整理,可於牆體單元中空部分視結構設計需求,回填灌漿成實體擋土牆。 Finally, the finishing step is carried out to finish the finishing of the wall unit of the underground retaining wall, and the hollow part of the wall unit can be backfilled into a solid retaining wall depending on the structural design requirements.

上述中,在挖掘步驟執行前,可於預鑄沉箱 座10上放置用以增加下沉重力的增重物,例如水;且水可讓牆體50水養而有助於增強其結構強度。 In the above, before the excavation step is performed, it can be used in the caisson A weight gain, such as water, is placed on the seat 10 to increase the weight of the sinking; and the water allows the wall 50 to be hydrated to help enhance its structural strength.

其中,於該單元牆體施工之際,其毗鄰牆體單元亦可同步進行安裝作業,其牆體製作步驟與挖掘步驟皆同,相鄰之牆體單元的鄰接處可設置公、母接頭。 Wherein, in the construction of the unit wall, the adjacent wall unit can also be installed synchronously, and the wall making step and the digging step are the same, and the male and female joints can be arranged adjacent to the adjacent wall unit.

綜上所述,該地下擋土牆施工方法於牆體製作步驟中,以模板設備40先製作一部分牆體50,俟牆體50強度足夠後,停止牆體製作並進行挖掘作業,將預鑄沉箱座10與牆體50下移沉降。挖掘作業中,預鑄沉箱座10上的牆體50具備一定的結構強度且牆體完整無破損可防滲水,並可防止後續地下室深開挖施工時,發生開挖區外地表坍塌等災害,達到防災與提升工安的目的。 In summary, the underground retaining wall construction method is in the wall manufacturing step, and a part of the wall 50 is first formed by the template device 40. After the strength of the wall 50 is sufficient, the wall is stopped and excavated, and the concrete is removed. The caulking box 10 and the wall 50 are moved down and settled. In the excavation operation, the wall 50 on the caisson box seat 10 has a certain structural strength and the wall is intact without damage to prevent water seepage, and can prevent disasters such as collapse of the surface outside the excavation area during the deep excavation of the subsequent basement. To achieve disaster prevention and improve the safety of work.

其中,該地下擋土牆施工方法於牆體製作步驟中所製作的牆體50具有防滲漏水的功用,因此不需要使用大量的安定液,可節省安定液的購買、回收與檢測監控等成本費用支出,且更為環保並可改善安定液所引起的環安問題。 The wall 50 constructed by the underground retaining wall in the wall manufacturing step has the function of preventing leakage and water leakage, so that a large amount of stabilizer solution is not needed, which can save the cost of purchase, recovery, detection and monitoring of the stability liquid. Expenditure, and more environmentally friendly and can improve the environmental safety caused by the stability of the liquid.

另外,模板設備40、挖掘裝置20與抽取裝置30可以回收再重覆使用,也可節省成本且更為環保。 In addition, the formwork device 40, the excavating device 20, and the extracting device 30 can be recycled and reused, and can also be cost-effective and environmentally friendly.

該地下擋土牆施工方法的牆體製作步驟與挖掘步驟的施工流程可全天候重覆進行,有效縮短工期。 The wall forming step and the excavation step construction process of the underground retaining wall construction method can be repeated all the time, effectively shortening the construction period.

另外,可依據地下水文情況與地質條件之需求而調整模板設備40之內模41與外模42的間距、形態,製造可抗衡土/水之牆體厚度。 In addition, the spacing and shape of the inner mold 41 and the outer mold 42 of the stencil apparatus 40 can be adjusted according to the requirements of the groundwater and the geological conditions, and the wall thickness of the soil/water can be made.

且可選用適當尺寸之預鑄沉箱座10、挖掘裝 置20與抽取裝置30。 And can choose the appropriate size of the caisson seat 10, excavation equipment The device 20 is placed 20 and the extraction device 30.

另因牆體50已具備一定的結構強度,可於其毗鄰單元處同步進行安裝作業、牆體製作步驟與挖掘步驟,發揮縮短工期的優點。 In addition, since the wall 50 has a certain structural strength, the installation work, the wall making step and the excavation step can be simultaneously performed at the adjacent unit, and the advantage of shortening the construction period can be exerted.

甚至藉油壓系統管路均壓連通的原理,規劃同步一次性施作大範圍的多個牆體單元,更符經濟利益。 Even with the principle of pressure equalization and communication of the oil pressure system, it is more economical to plan to simultaneously apply a large number of wall units in a large scale.

10‧‧‧預鑄沉箱座 10‧‧‧預鑄箱箱座

11‧‧‧座體 11‧‧‧

12‧‧‧座腳 12‧‧‧ feet

13‧‧‧鋼趾部 13‧‧‧Steel toe

14‧‧‧凸部 14‧‧‧ convex

15‧‧‧預留空間 15‧‧‧ Reserved space

20‧‧‧挖掘裝置 20‧‧‧Excavating device

30‧‧‧抽取裝置 30‧‧‧ extraction device

40‧‧‧模板設備 40‧‧‧Template equipment

41‧‧‧內模 41‧‧‧Inner model

42‧‧‧外模 42‧‧‧External model

60‧‧‧導溝 60‧‧‧ Guide groove

70‧‧‧油壓千斤頂 70‧‧‧Hydraulic jack

Claims (7)

一種地下擋土牆施工方法,其包含:準備作業,整理施工場地並設置沉砂池、工作間等配套設備,接著放樣定位後構築導溝;安裝作業,將預鑄沉箱座平整安置於預設之牆體單元處導溝內,且在預鑄沉箱座內設置挖掘裝置、抽取裝置與水刀裝置。並於預鑄沉箱座與導溝之間注入隔離液,預鑄沉箱座內注水,保持預鑄沉箱座內的水的液面高度高於地面高程1公尺以上,以及預鑄沉箱座內架設框架、動力管線與抵撐的油壓千斤頂;牆體製作步驟,於預鑄沉箱座牆體上端設置模板設備,將鋼筋續接於預鑄沉箱座預留筋上,且模板設備的內模、外模分別位於鋼筋兩側並形成澆注空間,澆注混凝土至澆注空間,於混凝土初凝固化至一定程度後,將內模、外模利用油壓系統一同往上頂昇移動,空出空間再次澆注混凝土至內模、外模之間並等待混凝土初凝固化,並以油壓千斤頂沉壓框架,重覆進行油壓頂昇內模、外模與澆注、固化的動作,以形成各單元的牆體;挖掘步驟,挖掘裝置進行挖掘,再由抽取裝置將土泥抽出,預鑄沉箱座與牆體往下沉降,同時於牆體與導溝之間注入隔離液,以及牆體內注水,保持水的液面高度高於地面高程1公尺以上;待牆體沉降至階段深度後,再以模板設備接續製作牆體、續接框架、油壓千斤頂、抽泥管及動力管線後再進行挖掘步驟,反覆施作至牆體與預鑄沉箱座的總長度達到地 下擋土牆的預設深度;拆卸作業,先拆卸模板設備後,再將抽取裝置、框架、油壓千斤頂、挖掘裝置依序自預鑄沉箱座上吊昇並逐節拆下,以及同步進行牆體中空斷面回填灌漿,完成實體斷面之地下擋土牆;以及收尾整理步驟,對地下擋土牆的牆體單元進行收尾整理。 The utility model relates to a construction method for underground retaining wall, which comprises: preparing work, finishing the construction site and setting up supporting equipment such as grit chamber and working room, and then constructing guiding groove after lofting and positioning; installation operation, placing the sinking box seat flatly in the preset The wall unit is located in the guiding groove, and an excavating device, an extracting device and a water jet device are arranged in the sinking box seat. And injecting isolation liquid between the caisson and the guide groove, and injecting water into the sinking box seat, keeping the liquid level of the water in the sinking box seat more than 1 meter above the ground elevation, and erecting in the sinking box seat Frame, power line and hydraulic jack for resisting; wall making step, setting template device at the upper end of the wall of the caulking box seat, continuing the steel bar to the reserved rib of the sinking box seat, and the inner mold of the template device, The outer molds are respectively located on both sides of the steel bar and form a pouring space, and the concrete is poured into the pouring space. After the concrete is first solidified to a certain extent, the inner mold and the outer mold are lifted up together by the hydraulic system, and the empty space is poured again. Concrete to the inner mold and the outer mold and waiting for the initial solidification of the concrete, and pressing the frame with the hydraulic jack, repeating the hydraulic pressure to lift the inner mold, the outer mold and the pouring and solidifying action to form the wall of each unit Excavation step, excavation device for excavation, and then the soil is extracted by the extraction device, the sinking box seat and the wall are set down, and the partitioning liquid is injected between the wall and the guiding groove, and the water in the wall is filled. The liquid level of the water holding is higher than the ground elevation by more than 1 meter; after the wall is settled to the depth of the stage, the wall, the continuous frame, the hydraulic jack, the mud pipe and the power line are connected by the template equipment. The excavation step is repeated until the total length of the wall and the sinking box seat reaches the ground The preset depth of the lower retaining wall; after the disassembly operation, the stencil device is first disassembled, and then the extracting device, the frame, the hydraulic jack and the excavating device are hoisted from the sumping box seat and removed step by step, and the wall is synchronized. The hollow section of the body is backfilled and grouted to complete the underground retaining wall of the solid section; and the finishing step is completed to finish the finishing of the wall unit of the underground retaining wall. 如請求項1所述之地下擋土牆施工方法,其中,於收尾整理步驟中,根據結構設計需求可於壁體單元中空部位回填填充物。 The underground retaining wall construction method according to claim 1, wherein in the finishing finishing step, the filler can be backfilled in the hollow portion of the wall unit according to the structural design requirement. 如請求項1所述之地下擋土牆施工方法,其中,地下擋土牆施工方法中,於預鑄沉箱座的座腳外覆設增加下切力的鋼趾部,以利於預鑄沉箱座及隨後製作之牆體切割土體下移。 The underground retaining wall construction method according to claim 1, wherein in the underground retaining wall construction method, a steel toe portion for increasing the lower shear force is disposed outside the seat of the sinker box seat, so as to facilitate the sinking box seat. And the wall that was subsequently produced cut the soil down. 如請求項2所述之地下擋土牆施工方法,其中,地下擋土牆施工方法中,於預鑄沉箱座的座腳外覆設增加下切力的鋼趾部,以利於預鑄沉箱座及隨後製作之牆體切割土體下移。 The underground retaining wall construction method according to claim 2, wherein in the underground retaining wall construction method, a steel toe portion for increasing the lower shear force is disposed outside the foot of the sinker box seat, so as to facilitate the sinking box seat And the wall that was subsequently produced cut the soil down. 如請求項1至4中任一項所述之地下擋土牆施工方法,其中,該地下擋土牆施工方法於預設之地下擋土牆的相鄰牆體單元處可同步進行安裝作業、牆體製作步驟與挖掘步驟。 The underground retaining wall construction method according to any one of claims 1 to 4, wherein the underground retaining wall construction method is synchronously installed at an adjacent wall unit of the predetermined underground retaining wall, Wall making steps and digging steps. 如請求項1至4中任一項所述之地下擋土牆施工方法,其中,於收尾整理步驟採用水底灌漿方式填充牆體單元。 The underground retaining wall construction method according to any one of claims 1 to 4, wherein the wall unit is filled with a bottom grouting method in the finishing finishing step. 如請求項5所述之地下擋土牆施工方法,其中,於收尾整理步驟採用水底灌漿方式填充牆體單元。 The underground retaining wall construction method according to claim 5, wherein the wall unit is filled by the bottom grouting method in the finishing finishing step.
TW103112256A 2014-04-02 2014-04-02 Construction method of underground retaining wall TWI550162B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW103112256A TWI550162B (en) 2014-04-02 2014-04-02 Construction method of underground retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW103112256A TWI550162B (en) 2014-04-02 2014-04-02 Construction method of underground retaining wall

Publications (2)

Publication Number Publication Date
TW201538825A TW201538825A (en) 2015-10-16
TWI550162B true TWI550162B (en) 2016-09-21

Family

ID=54851223

Family Applications (1)

Application Number Title Priority Date Filing Date
TW103112256A TWI550162B (en) 2014-04-02 2014-04-02 Construction method of underground retaining wall

Country Status (1)

Country Link
TW (1) TWI550162B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI637095B (en) * 2017-06-02 2018-10-01 李坤得 Construction method of collimating continuous wall

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW382034B (en) * 1998-12-18 2000-02-11 Chi Shiu Underground continuous wall construction method of excavate-subside stack double wall type

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW382034B (en) * 1998-12-18 2000-02-11 Chi Shiu Underground continuous wall construction method of excavate-subside stack double wall type

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI637095B (en) * 2017-06-02 2018-10-01 李坤得 Construction method of collimating continuous wall

Also Published As

Publication number Publication date
TW201538825A (en) 2015-10-16

Similar Documents

Publication Publication Date Title
CN107313431B (en) Close on not contour foundation pit method for synchronously constructing
CN105672348A (en) Construction method for cropping bridge pile foundation at sandy gravel stratum of abyssal region
CN106638640A (en) Modular coffer construction method for concrete without subsealing in the geologic condition of stratum
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN112376589A (en) Landslide belt pile plate type comprehensive protection construction system and construction method
CN109653197B (en) Pile foundation construction method capable of being expanded in three dimensions
CN103541352B (en) A kind of at ground, sandy soil stratum major diameter Vertical spots underground continuous construction method
CN106013053A (en) Steel sheet pile support construction method for building underground garage open caisson
CN103422510A (en) Steel pipe frame type cofferdam structure and construction method
CN203213131U (en) Open caisson combining water drainage sinking and water-drainage-free sinking
CN106592600A (en) Construction method for early warning supporting system adjacent to running subway in complex environment
CN100443673C (en) Method of construction
TWI550162B (en) Construction method of underground retaining wall
CN111733853A (en) Tongue-and-groove type prefabricated underground continuous wall structure
CN114263187B (en) Foundation pit bottom plate force transmission structure and construction method thereof
CN114908782B (en) Foundation pit dewatering construction method
CN203049588U (en) Pit-in-pit cylindrical mould
CN210031875U (en) Open caisson device for pushing
CN110863496B (en) Method for replacing, supporting, excavating and constructing arch center foundation by concrete supporting in stone-filled island building area
CN109653213B (en) Underground diaphragm wall grooving construction method
CN211646351U (en) Cast-in-situ bored pile
CN204326089U (en) A kind of structure for foundation ditch Yield rainfall relation
CN109653193B (en) Reverse construction method for underground continuous wall
CN109972644B (en) Open caisson device for pushing and construction method thereof
CN206346200U (en) Special-shaped foundation ditch corner constructing structure

Legal Events

Date Code Title Description
MM4A Annulment or lapse of patent due to non-payment of fees