TWI540237B - Construction method of steel-structure bridge - Google Patents
Construction method of steel-structure bridge Download PDFInfo
- Publication number
- TWI540237B TWI540237B TW102102729A TW102102729A TWI540237B TW I540237 B TWI540237 B TW I540237B TW 102102729 A TW102102729 A TW 102102729A TW 102102729 A TW102102729 A TW 102102729A TW I540237 B TWI540237 B TW I540237B
- Authority
- TW
- Taiwan
- Prior art keywords
- pier
- completed
- bridge
- block
- deck
- Prior art date
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Description
本發明係有關於一種鋼構橋樑的施工方法,特別是與一種鋼構橋樑的節塊吊裝有關的施工方法。 The invention relates to a construction method of a steel bridge, in particular to a construction method related to the lifting of a steel bridge.
請參照圖1,在習知的鋼構橋樑施工方法中,節塊通常在地面上組裝。進行節塊吊裝作業時,一般先在已完成橋面之內外腹鈑之間鋪設兩條軌道21,並提供一推移工作車20將節塊G1懸吊於橋面下方。推移工作車20以另兩油壓千斤頂水平的沿兩條軌道21向前推移,而將節塊G1由橋台運送至一吊裝工作車10的前方,之後再以吊裝工作車10將節塊G1由橋面下方往上拉至節塊A之前端。 Referring to Figure 1, in the conventional steel bridge construction method, the segments are usually assembled on the ground. When performing the block lifting operation, generally two rails 21 are laid between the inner and outer webs of the completed bridge deck, and a shifting work cart 20 is provided to suspend the mass G1 below the deck surface. The shifting work vehicle 20 is moved forward along the two rails 21 at the level of the other two hydraulic jacks, and the mass G1 is transported from the abutment to the front of a hoisting work vehicle 10, and then the gantry work vehicle 10 is used to lift the block G1. Pull up below the deck to the front of block A.
吊裝工作車10包括一本體桁架結構11、一主架設樑12及兩台垂直吊昇用之油壓千斤頂13、14。吊昇節塊之作業係利用固定於主架設樑12上之兩台油壓千斤頂13、14及穿過千斤頂13、14之二條鋼纜15,以油壓千斤頂13、14拉上或降下鋼纜15為之。需注意的是,吊裝工作車10在就定位之後,是在一定點將鋼纜15放下去,再將節塊G1拉上來。換句話說,節塊G1的起吊點及其安裝位置在同一垂直線上。因為只要吊裝工作車10之鋼纜15一受力,則主架設樑12即無法水平移動,所以在吊裝工作車10的水平移動過程中,並無法橫向搬運節塊G1。 The hoisting work vehicle 10 includes a body truss structure 11, a main erection beam 12, and two hydraulic jacks 13, 14 for vertical lifting. The operation of lifting the lifting block is to pull or lower the steel cable with the hydraulic jacks 13, 14 by using two hydraulic jacks 13, 14 fixed on the main erection beam 12 and two steel cables 15 passing through the jacks 13, 14. 15 for it. It should be noted that after the hoisting work vehicle 10 is positioned, the steel cable 15 is lowered at a certain point, and the block G1 is pulled up. In other words, the lifting point of the segment G1 and its mounting position are on the same vertical line. Since the main erection beam 12 cannot be horizontally moved as long as the steel cable 15 of the work vehicle 10 is hoisted, the node G1 cannot be laterally conveyed during the horizontal movement of the hoisting work vehicle 10.
圖2則顯示另一習知應用於小跨度的節塊吊裝作業,係利用一桁架式工作車30,其具有一水平桁架31及複數直立桁架32。水平桁架31的長度是固定的,但直立桁架32可以更換位置,以配合不同的橋墩間隔距離。然而,在橋墩間隔距離太長而大於水平桁架31之長度時,桁架式工作車30即不適用。 Figure 2 shows another conventional segment hoisting operation applied to a small span using a truss work vehicle 30 having a horizontal truss 31 and a plurality of upright trusses 32. The length of the horizontal truss 31 is fixed, but the upright truss 32 can be replaced to match the spacing of the different piers. However, the truss type work vehicle 30 is not suitable when the distance between the piers is too long and is greater than the length of the horizontal truss 31.
本發明之一目的在於提供一種鋼構橋樑的施工方法,所包含的節塊吊裝方式適用於橋墩間隔距離太長或橋面為曲線或非直線延伸的鋼構橋樑的建造。 An object of the present invention is to provide a method for constructing a steel bridge, and the method for hoisting the block is suitable for the construction of a steel bridge with a long distance between the piers or a curved or non-linear extension of the bridge.
為了達到上述之一或部份或全部目的或是其他目的,本發明提供一種鋼構橋樑的施工方法,包括:建造一部分的鋼構橋樑而形成一已完成橋面,使已完成橋面具有一前端節塊及一後端節塊,前端節塊係朝向鋼構橋樑之中央,後端節塊係朝向鋼構橋樑之一邊端;設置一吊車、一台車及一工作車於已完成橋面之上方,並且工作車位於已完成橋面之前端節塊上,其中工作車具有一前側部與一後側部,後側部相對於前側部,前側部伸出已完成橋面之前端節塊之外,且前側部與後側部之間具有一平移機構,平移機構上則設有一垂直懸吊裝置;利用吊車將一新節塊的複數零件吊上已完成橋面之上方,並將這些零件組裝而成一新節塊;利用台車在已完成橋面之上方運送新節塊至工作車之後側部;利用工作車之平移機構在已完成橋面之上方將新節塊由其後側部平移至其前側部,並且利用垂直懸吊裝置將位於前側部之新節塊下移至可與已完成橋面之前端節塊接合之高度;將新節塊與已完成橋面之前端節塊接合在一起;接著,重覆前述新節 塊的組裝及接合過程,直到完成鋼構橋樑。 In order to achieve one or a part or all of the above or other objects, the present invention provides a method for constructing a steel bridge, comprising: constructing a part of a steel bridge to form a completed bridge deck, so that the completed bridge mask has a front end block and a rear end block, the front end block is oriented toward the center of the steel bridge, and the rear end block is oriented toward one side of the steel bridge; a crane, a car and a work vehicle are disposed on the completed bridge deck Above, and the work vehicle is located on the front end block of the completed bridge deck, wherein the work vehicle has a front side portion and a rear side portion, the rear side portion is opposite to the front side portion, and the front side portion protrudes from the front end portion of the completed bridge deck In addition, there is a translation mechanism between the front side and the rear side, and a vertical suspension device is arranged on the translation mechanism; the plurality of parts of a new section are suspended by the crane above the completed bridge deck, and these parts are Assembled into a new section; use the trolley to transport the new section above the completed deck to the side of the rear of the work vehicle; use the translation mechanism of the work vehicle to translate the new section from the rear side above the completed deck a front side thereof, and a vertical suspension device is used to move the new section located at the front side to a height engageable with the front end of the completed deck; the new section is joined to the front end of the completed deck Together; then, repeat the aforementioned new section The assembly and joining process of the blocks until the completion of the steel bridge.
在一實施例中,鋼構橋樑係橫跨一地形,因此上述形成已完成橋面的較詳細步驟為:設置一第一橋墩及一第二橋墩於地形之一側,並且設置一第三橋墩及一第四橋墩於地形之另一側,使得第二橋墩與第三橋墩分別緊鄰於地形之兩側邊緣;在第一橋墩與第二橋墩之間架設複數支堡,並且在第三橋墩與第四橋墩之間架設複數支堡;以及在地面組裝複數節塊,並將這些節塊以一吊車向上吊至這些橋墩與這些支堡之上,而從第二橋墩往第一橋墩的方向依序連接於第二橋墩與第一橋墩之間,並且,從第三橋墩往第四橋墩的方向依序連接於第三橋墩與第四橋墩之間,分別在地形之兩側形成兩已完成橋面,此兩已完成橋面即為鋼構橋樑的兩側邊跨部。 In an embodiment, the steel bridge spans a terrain, so the more detailed steps of forming the completed bridge deck are: setting a first pier and a second pier on one side of the terrain, and setting a third pier And a fourth pier on the other side of the terrain, such that the second pier and the third pier are respectively adjacent to the two sides of the terrain; a plurality of berths are erected between the first pier and the second pier, and the third pier is A plurality of berths are erected between the fourth piers; and a plurality of segments are assembled on the ground, and the segments are hoisted by a crane to the piers and the bunkers, and the direction from the second pier to the first pier is The sequence is connected between the second pier and the first pier, and is connected between the third pier and the fourth pier from the third pier to the fourth pier, respectively forming two completed bridges on both sides of the topography. In the face, the two completed bridge faces are the side edges of the steel bridge.
在一實施例中,架設複數支堡的步驟包括:設置二支堡分別緊鄰第二橋墩之兩側;以及設置二支堡分別緊鄰第四橋墩之兩側。 In an embodiment, the step of erecting the plurality of bastions includes: arranging two treasurys respectively adjacent to the two sides of the second pier; and arranging the two berths respectively adjacent to the two sides of the fourth pier.
在一實施例中,所述之鋼構橋樑的施工方法更包括以下步驟:在兩側邊跨部形成之後,撤除靠近第一橋墩與第四橋墩的這些支堡中的一部分。在兩側邊跨部形成之後,架設複數門架於第二橋墩與第三橋墩之間的地形上。在完成最後一個節塊的接合後,拆除這些門架。 In an embodiment, the method of constructing the steel bridge further comprises the steps of: removing a portion of the forts adjacent to the first pier and the fourth pier after the two side spans are formed. After the two side spans are formed, a plurality of gantry are erected on the topography between the second pier and the third pier. After completing the joining of the last segment, remove the gantry.
在一實施例中,所述之鋼構橋樑的施工方法更包括以下步驟:在將新節塊與已完成橋面之前端節塊組裝在一起之後,將工作車移至新節塊上方,使前側部伸出於新節塊之外;重覆前述移動工作車,組裝新節塊的零件及接合新節塊與已完成橋面的過程,使地形兩側的兩已完成橋面逐漸延伸向地形的中央靠隴。 In an embodiment, the construction method of the steel bridge further comprises the following steps: after assembling the new block with the front end block of the completed bridge deck, moving the work vehicle to the top of the new block, so that The front side protrudes beyond the new section; repeats the aforementioned moving work vehicle, assembles the parts of the new section and joins the new section and the completed deck surface, so that the two completed bridge decks on both sides of the terrain gradually extend toward The center of the terrain depends on the raft.
在一實施例中,設置吊車的步驟包括:先於已完成橋面上組裝一作業平台,再將吊車移至作業平台上。設置台車及工作車的步驟包括:以吊車將工作車的零件吊上已完成橋面上,在已完成橋面上組裝工作車;以及以吊車將台車的零件吊上已完成橋面上,在已完成橋面上組裝台車。 In an embodiment, the step of setting up the crane comprises: assembling a work platform prior to the completed bridge deck, and then moving the crane to the work platform. The steps of setting up the trolley and the work vehicle include: lifting the parts of the work vehicle onto the completed bridge surface by the crane, assembling the work vehicle on the completed bridge surface; and lifting the parts of the trolley on the completed bridge surface by the crane, The assembled trolley on the bridge has been completed.
10‧‧‧習知的吊裝工作車 10‧‧‧Study hoisting work vehicle
11‧‧‧本體桁架結構 11‧‧‧ Body truss structure
12‧‧‧主架設樑 12‧‧‧Main erection beam
13、14‧‧‧垂直吊昇用之油壓千斤頂 13, 14‧‧‧ hydraulic jack for vertical lifting
15‧‧‧鋼纜 15‧‧‧Steel cable
A‧‧‧節塊 Section A‧‧‧
G1‧‧‧節塊 G1‧‧‧ blocks
21‧‧‧橋面上之軌道 21‧‧‧ Tracks on the bridge
20‧‧‧推移工作車 20‧‧‧Change work car
30‧‧‧習知的桁架式工作車 30‧‧‧Legs of trussed work vehicles
31‧‧‧水平桁架 31‧‧‧ horizontal truss
32‧‧‧直立桁架 32‧‧‧Upright Truss
P192、P193、P194、P301‧‧‧橋墩 P192, P193, P194, P301‧‧ ‧ piers
S1、S11、S12、S2、S21、S22‧‧‧支堡 S1, S11, S12, S2, S21, S22‧‧ ‧ Fort
G1~G39‧‧‧節塊 G1~G39‧‧‧ blocks
OP1、OP2‧‧‧作業平台 OP1, OP2‧‧‧ operating platform
H1、H2‧‧‧吊車 H1, H2‧‧‧ crane
W1、W2‧‧‧懸臂工作車 W1, W2‧‧‧ cantilever work vehicle
W11‧‧‧前側部 W11‧‧‧ front side
W12‧‧‧後側部 W12‧‧‧ rear side
W13‧‧‧平移機構 W13‧‧‧ translation mechanism
W14‧‧‧垂直懸吊裝置 W14‧‧‧Vertical Suspension
F1、F2‧‧‧台車 F1, F2‧‧‧ trolley
M1~M4‧‧‧門架 M1~M4‧‧‧ gantry
圖1為一習知的橋樑施工方法。 Figure 1 shows a conventional bridge construction method.
圖2為另一習知的橋樑施工方法。 Figure 2 is another conventional bridge construction method.
圖3A至圖3T為本發明之一實施例的鋼構橋樑施工方法。 3A to 3T illustrate a method of constructing a steel bridge according to an embodiment of the present invention.
圖4為本發明之一實施例的鋼構橋樑。 4 is a steel bridge according to an embodiment of the present invention.
有關本發明之前述及其他技術內容、特點與功效,在以下配合參考圖式之一較佳實施例的詳細說明中,將可清楚的呈現。以下實施例中所提到的方向用語,例如:上、下、左、右、前或後等,僅是用於參照隨附圖式的方向。因此,該等方向用語僅是用於說明並非是用於限制本發明。 The above and other technical contents, features and advantages of the present invention will be apparent from the following detailed description of the preferred embodiments. The directional terms mentioned in the following embodiments, such as upper, lower, left, right, front or rear, etc., are only used to refer to the directions of the accompanying drawings. Therefore, the directional terms are used for illustration only and are not intended to limit the invention.
圖3A至3Z是本發明的一實施例,說明一種鋼構橋樑的施工方法。 3A to 3Z are views showing an embodiment of the present invention, illustrating a construction method of a steel bridge.
如圖3A,設置四根橋墩P192、P193、P194、P301,橋墩P192與P193之間為鋼構橋樑的左側邊跨部,橋墩P193與P194之間為鋼構橋樑所跨越的道路或河川等地形,橋墩P194與P301之間為鋼構橋樑的右側邊跨部。在橋墩P193的兩側架設兩支堡S11、S12,並在橋墩P194的兩側架設兩支堡S21、S22。在地面上將節塊G11組裝好,再以一般吊車將節塊G11往上 吊,並安裝在橋墩P193的上方。右側邊跨部的節塊G29則以同樣地方法安裝在橋墩P194的上方。 As shown in Fig. 3A, four piers P192, P193, P194, and P301 are set. The piers P192 and P193 are the left side spans of the steel bridge. The piers P193 and P194 are the roads or rivers that the steel bridges span. The pier between the piers P194 and P301 is the right side span of the steel bridge. Two fort S11 and S12 are set on both sides of the pier P193, and two fort S21 and S22 are set on both sides of the pier P194. Assemble the block G11 on the ground, and then lift the block G11 up by the general crane. Hang and install it above the pier P193. The node G29 of the right side span is mounted above the pier P194 in the same manner.
如圖3B,在左側邊跨部的橋墩P192與P193之間設置複數支堡S1,同樣地在右側邊跨的橋墩P194與P301之間設置複數支堡S2。將節塊G10在地面上組裝完成後,再以一般吊車將節塊G10往上吊至支堡S1上方,並連接在節塊G11的左側。之後,節塊G9、G8、G7依序連接在G10之左側而形成一部分已完成的橋面。在右側邊跨部亦以相同的方式將節塊G30、G31、G32、G33依序向右連接在節塊G29的右側而形成另一部分已完成的橋面。之後在左、右兩個已完成的橋面上分別組裝一作業平台OP1及OP2,以供一般吊車作業所需。 As shown in Fig. 3B, a plurality of slings S1 are provided between the piers P192 and P193 of the left side span, and a plurality of slabs S2 are similarly provided between the piers P194 and P301 of the right side. After assembling the block G10 on the ground, the block G10 is lifted up above the bunker S1 by a general crane and connected to the left side of the block G11. Thereafter, the segments G9, G8, and G7 are sequentially connected to the left side of the G10 to form a part of the completed bridge deck. In the same way, the segments G30, G31, G32, G33 are sequentially connected to the right side of the block G29 in the same manner to form another completed bridge deck. Then, a working platform OP1 and OP2 are respectively assembled on the left and right completed bridge surfaces for the general crane operation.
圖3C顯示將一般吊車H1及H2分別放置於作業平台OP1及OP2上。在左側的已完成橋面續接上節塊G6,在右側的已完成橋面續接上節塊G34。 FIG. 3C shows that the general cranes H1 and H2 are placed on the work platforms OP1 and OP2, respectively. The completed bridge deck on the left side continues to the upper block G6, and the completed bridge deck on the right side continues to the upper block G34.
如圖3D,以吊車H1及H2將工作車W1與W2的零組件吊上左側邊跨部及右側邊跨部之已完成橋面上,在橋面上分別組裝成具有特殊結構設計的懸臂工作車W1與W2。由於鋼構橋樑之左右兩側僅施工方向不同,其餘施工過程相同,因此以左側邊跨部之施工過程為例作後續的說明。工作車W1具有一前側部W11與一後側部W12,後側部W12相對於前側部W11,且前側部W11與後側部W12之間具有一平移機構W13及一鋼架所圍成的通道,平移機構W13上設有一垂直懸吊裝置W14。 As shown in Fig. 3D, the components of the work vehicles W1 and W2 are suspended by the cranes H1 and H2 on the completed bridge deck of the left side span and the right side span, and are assembled on the bridge deck into a cantilever work with a special structural design. Cars W1 and W2. Since the left and right sides of the steel bridge are only in different construction directions, the rest of the construction process is the same. Therefore, the construction process of the left side span is taken as an example for subsequent description. The work vehicle W1 has a front side portion W11 and a rear side portion W12, the rear side portion W12 is opposite to the front side portion W11, and a translation mechanism W13 and a passage surrounded by a steel frame are provided between the front side portion W11 and the rear side portion W12. A vertical suspension device W14 is disposed on the translation mechanism W13.
如圖3E,在本實施例中,工作車W1之腳位固定於節塊G11上表面,其前側部W11伸出左側邊跨之已完成橋面的前端節塊G11之外。以 吊車H1將台車F1的零件吊上橋面上,在作業平台OP1(或吊車H1)與工作車W1之間的已完成橋面上組裝成一台車F1。台車F1是用來將吊車H1組裝好的新節塊運往工作車W1之後側部W12。在組裝作業平台OP1、台車F1及工作車W1之期間,左側邊跨部的已完成橋面仍持續地接上節塊G2~G5。在右側邊跨部台車F2、吊車H2及工作車W2,三者相配合的作業方式亦同。 As shown in Fig. 3E, in the present embodiment, the position of the work vehicle W1 is fixed to the upper surface of the node G11, and the front side portion W11 extends beyond the front end node G11 of the completed bridge deck on the left side. Take The crane H1 hoists the parts of the trolley F1 onto the bridge deck and assembles a vehicle F1 on the completed bridge deck between the work platform OP1 (or the crane H1) and the work vehicle W1. The trolley F1 is used to transport the new block assembled by the crane H1 to the rear side W12 of the work vehicle W1. During the assembly of the work platform OP1, the trolley F1 and the work vehicle W1, the completed bridge deck of the left side span is continuously connected to the nodes G2 to G5. In the right side of the cross-section trolley F2, the crane H2 and the work vehicle W2, the three work modes are the same.
圖3F顯示由節塊G1~G11所接合而成的左側邊跨部,以及由節塊G29~G39所接合而成的右側邊跨部。 Fig. 3F shows the left side span which is joined by the segments G1 to G11, and the right side span which is joined by the segments G29 to G39.
圖3G至圖3H中,係將左、右兩側邊跨的支堡S1、S2的千斤頂回降,之後保留節塊G6、G7、G8、G9、G11及G29、G31、G32、G33、G34下方共12座支堡,並撤除其餘的支堡。在此實施例中,保留的12座支堡上方各自設有一支撐墊材,墊材的功能是作為將節塊重量傳遞到支堡的媒介。每個節塊包括一翼鈑。支撐墊材與節塊下翼鈑需保持10mm的空隙(gap),以預防鋼構橋樑翻倒直至所有節塊吊裝完成。 In Fig. 3G to Fig. 3H, the jacks of the slings S1 and S2 across the left and right sides are returned, and then the blocks G6, G7, G8, G9, G11 and G29, G31, G32, G33, G34 are retained. There are 12 bastions below and the remaining bastions are removed. In this embodiment, each of the remaining 12 berths is provided with a support mat which functions as a medium for transferring the weight of the slab to the bastion. Each segment includes a wing. The support mat and the lower wing of the segment need to maintain a gap of 10 mm to prevent the steel bridge from falling over until all the blocks are hoisted.
圖3I至圖3T的過程是建造橋墩P193與P194之間的橋面。如圖3I所示,完成左、右兩側邊跨後,接著在橋墩P193與P194之間(亦即在鋼構橋樑所預定橫跨的道路中央)架設四支門架M1~M4。值得一提的是,門架M2與M3之間的距離應該較為靠近,以供未來將此鋼構橋樑的中心節塊安裝在門架M2與M3之間的位置。 The process of Figures 3I to 3T is to construct a bridge deck between the piers P193 and P194. As shown in Fig. 3I, after completing the left and right side spans, four gantry M1~M4 are erected between the piers P193 and P194 (i.e., at the center of the road where the steel bridge is intended to straddle). It is worth mentioning that the distance between the gantry M2 and M3 should be relatively close for the future installation of the central section of the steel bridge between the gantry M2 and M3.
圖3J至圖3K說明節塊G12的零件組裝、運送及其與已完成橋面的接合。 Figures 3J through 3K illustrate the assembly, transport of the segments G12 and their engagement with the completed deck.
圖3L說明在節塊G12與已完成橋面的接合完成之後,此時左側已完成橋面的最前端節塊是G12,因此需將工作車W1右移至節塊G12上 方,以便進行後續節塊G13的接合。 FIG. 3L illustrates that after the engagement of the block G12 and the completed bridge deck is completed, the front end block of the completed bridge deck on the left side is G12, so the work vehicle W1 needs to be moved right to the block G12. In order to perform the joining of the subsequent block G13.
圖3M中的每個節塊G12~G19係重覆圖3J至圖3L之節塊G12零件組裝、運送、與已完成橋面的接合及工作車W1移動的過程,使已完成橋面由橋樑兩側往中央延伸,直到靠隴而完成整座鋼構橋樑。右側G28~G21之施工過程亦相同,僅新節塊的接續方向不同而已。 Each of the segments G12 to G19 in Fig. 3M repeats the assembly, transportation, joining of the completed bridge deck and the movement of the working vehicle W1 of the block G12 of Fig. 3J to Fig. 3L, so that the completed bridge deck is bridged. The sides extend to the center until the entire steel bridge is completed by the raft. The construction process of G28~G21 on the right side is also the same, only the connection direction of the new section is different.
圖3N中,左側的已完成橋面(由節塊G1~G19接合而成)與右側的已完成橋面(由節塊G21~G39接合而成)僅相距一個節塊的寬度。左側的工作車W1已由節塊G11向右移動至節塊G18上,右側的工作車W2已由節塊G29向左移動至節塊G22上。在一實施例中,為了確保施工過程安全,需要藉著頂昇門架M2而將橋墩P193對其上的節塊的支承受力降低。然而,頂昇門架M2的過程需要門架M1的輔助支撐力量來協助,否則可能會造成橋墩P193對其上的節塊的支承力量超出容許強度。頂昇門架M2之後,門架M1的輔助支撐力量會因門架M2頂昇而自然釋放。 In Fig. 3N, the completed bridge deck on the left side (joined by the segments G1 to G19) and the completed bridge deck on the right side (joined by the segments G21 to G39) are only one block apart from each other. The work vehicle W1 on the left side has been moved rightward from the block G11 to the block G18, and the work vehicle W2 on the right side has been moved to the left by the block G29 to the block G22. In an embodiment, in order to ensure the safety of the construction process, it is necessary to reduce the support force of the pier P193 on the support block by the jacking frame M2. However, the process of jacking up the gantry M2 requires the auxiliary support force of the gantry M1 to assist, otherwise the support force of the struts P193 on the nodules thereon may exceed the allowable strength. After jacking the mast M2, the auxiliary support force of the mast M1 will naturally release due to the jacking of the mast M2.
圖3O中,門架M2與M3採用墊材支撐。左側工作車W1往右移(即往里增方向移動)至節塊G19,右側工作車W2亦往右移至節塊G23,避免與左側工作車W1衝突。 In Fig. 3O, the gantry M2 and M3 are supported by a mat. The left working vehicle W1 moves to the right (ie, moves inward) to the block G19, and the right working vehicle W2 also moves to the right to the block G23 to avoid collision with the left working vehicle W1.
圖3P中,吊車H1開始在已完成橋面上進行節塊G20的零件組裝。圖3Q至圖3R顯示節塊G20由台車F1運經橋墩P193及節塊G15的上方,而送至工作車W1的後側部W12。圖3S至圖3T顯示工作車W1開始吊裝節塊G20,將節塊G20由後側部W12吊往前側部W11,並往下移至節塊G19及G21之間完成接合,至此完成整座鋼構橋樑100的吊裝作業。 In Figure 3P, the crane H1 begins assembly of the parts of the segment G20 on the completed bridge deck. 3Q to 3R show that the block G20 is transported by the carriage F1 above the pier P193 and the block G15, and is sent to the rear side W12 of the work vehicle W1. 3S to 3T show that the work vehicle W1 starts to lift the node G20, and the block G20 is hung from the rear side portion W12 to the front side portion W11, and moves down to the joint between the blocks G19 and G21 to complete the joint. Hoisting work of steel bridge 100.
圖4顯示在鋼構橋樑100完成吊裝後,移除兩部工作車W1及 W2、兩部吊車H1、H2,並拆除作業平台OP1及OP2,以及拆除所有支堡S1、S11、S12、S2、S21、S22及門架M1~M4,則鋼構橋樑100由四支橋墩P192、P193、P194、P301及節塊G1~G39接合而成。 Figure 4 shows that after the steel bridge 100 is hoisted, the two work vehicles W1 are removed. W2, two cranes H1, H2, and remove the operating platforms OP1 and OP2, and remove all the slings S1, S11, S12, S2, S21, S22 and the gantry M1 ~ M4, then the steel bridge 100 consists of four bridge piers P192 , P193, P194, P301 and the block G1 ~ G39 are joined together.
惟以上所述者,僅為本發明之較佳實施例而已,當不能以此限定本發明實施之範圍,即大凡依本發明申請專利範圍及發明說明內容所作之簡單的等效變化與修飾,皆仍屬本發明專利涵蓋之範圍內。另外本發明的任一實施例或申請專利範圍不須達成本發明所揭露之全部目的或優點或特點。此外,摘要部分和標題僅是用來輔助專利文件搜尋之用,並非用來限制本發明之權利範圍。 The above is only the preferred embodiment of the present invention, and the scope of the invention is not limited thereto, that is, the simple equivalent changes and modifications made by the scope of the invention and the description of the invention are All remain within the scope of the invention patent. In addition, any of the objects or advantages or features of the present invention are not required to be achieved by any embodiment or application of the invention. In addition, the abstract sections and headings are only used to assist in the search of patent documents and are not intended to limit the scope of the invention.
P192、P193、P194、P301‧‧‧橋墩 P192, P193, P194, P301‧‧ ‧ piers
S1、S11、S12、S2、S21、S22‧‧‧支堡 S1, S11, S12, S2, S21, S22‧‧ ‧ Fort
G1~G12;G29~G39‧‧‧節塊 G1~G12; G29~G39‧‧‧ blocks
H1、H2‧‧‧吊車 H1, H2‧‧‧ crane
W1、W2‧‧‧懸臂工作車 W1, W2‧‧‧ cantilever work vehicle
W11‧‧‧前側部 W11‧‧‧ front side
W12‧‧‧後側部 W12‧‧‧ rear side
W13‧‧‧平移機構 W13‧‧‧ translation mechanism
W14‧‧‧垂直懸吊裝置 W14‧‧‧Vertical Suspension
F1、F2‧‧‧台車 F1, F2‧‧‧ trolley
M1~M4‧‧‧門架 M1~M4‧‧‧ gantry
Claims (8)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
TW102102729A TWI540237B (en) | 2013-01-24 | 2013-01-24 | Construction method of steel-structure bridge |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
TW102102729A TWI540237B (en) | 2013-01-24 | 2013-01-24 | Construction method of steel-structure bridge |
Publications (2)
Publication Number | Publication Date |
---|---|
TW201430189A TW201430189A (en) | 2014-08-01 |
TWI540237B true TWI540237B (en) | 2016-07-01 |
Family
ID=51796783
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
TW102102729A TWI540237B (en) | 2013-01-24 | 2013-01-24 | Construction method of steel-structure bridge |
Country Status (1)
Country | Link |
---|---|
TW (1) | TWI540237B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
TWI489867B (en) * | 2010-05-10 | 2015-06-21 | Realtek Semiconductor Corp | Channel recall reminder system, signal source recall reminder system and related methods thereof |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111119070B (en) * | 2019-12-24 | 2022-02-11 | 江苏中铁山桥重工有限公司 | Method for erecting W-shaped steel truss girder by adopting symmetrical gantry crane suspension assembly |
-
2013
- 2013-01-24 TW TW102102729A patent/TWI540237B/en active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
TWI489867B (en) * | 2010-05-10 | 2015-06-21 | Realtek Semiconductor Corp | Channel recall reminder system, signal source recall reminder system and related methods thereof |
Also Published As
Publication number | Publication date |
---|---|
TW201430189A (en) | 2014-08-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US11634877B2 (en) | Method for removal of temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and equipment therefor | |
JP6476426B2 (en) | Member renewal method using lifting device | |
JP4872940B2 (en) | Bridge erection device, floor slab erection method, and bridge erection method | |
JP7568805B2 (en) | Method for moving heavy objects using a heavy object moving device and a heavy object moving device | |
JP4748420B2 (en) | Construction method of corrugated steel web bridge using girder for erection work | |
JP2008088782A (en) | Cantilever overhang erection method of corrugated steel plate web bridge | |
KR101287455B1 (en) | System and method for launching upper structure of bridege | |
CN102251483B (en) | Construction method for hoisting concrete-filled steel tube lattice bridge pier through self-lifting attached crane | |
CN102154988B (en) | Arch-after-girder construction method of large-span steel box tacked arch bridge | |
JP2014015808A (en) | Method for constructing scaffold for rebuilding construction of bridge, and apparatus for constructing scaffold for construction | |
JP5184248B2 (en) | Construction method of level crossing | |
JP2019044453A (en) | Replacement method and erection machine | |
JP5890060B1 (en) | Bridge dismantling method using erection girder | |
JP4361775B2 (en) | Bridge erection method and bridge erection device | |
CN109629449B (en) | Mounting and positioning support and alignment method for steel-concrete combined section of arch foot of steel box arch bridge | |
CN105463997A (en) | Erecting method for segmental beam | |
TWI540237B (en) | Construction method of steel-structure bridge | |
WO2020075511A1 (en) | Mobile scaffold installation method | |
KR100928063B1 (en) | Self-launching movable formwork | |
JP4033871B2 (en) | How to build a bridge girder | |
EP3964647B1 (en) | Tool for dismounting travellers for concreting large arches of viaducts | |
JP6672545B2 (en) | Removal member removal method and member replacement method | |
CN107285209A (en) | A kind of Novel U-shaped erection equipment and its operating method | |
CN112681144B (en) | Self-climbing installation method of steel cable tower | |
CN114232488A (en) | Method for erecting main beam of large-span cable-stayed bridge |