TW573270B - Multiple constrains planning and scheduling system - Google Patents

Multiple constrains planning and scheduling system Download PDF

Info

Publication number
TW573270B
TW573270B TW91121071A TW91121071A TW573270B TW 573270 B TW573270 B TW 573270B TW 91121071 A TW91121071 A TW 91121071A TW 91121071 A TW91121071 A TW 91121071A TW 573270 B TW573270 B TW 573270B
Authority
TW
Taiwan
Prior art keywords
order
planning
time
production process
scope
Prior art date
Application number
TW91121071A
Other languages
Chinese (zh)
Inventor
Shiou-Hua Hu
Chih-Min Fan
Original Assignee
Asiatek Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Asiatek Inc filed Critical Asiatek Inc
Priority to TW91121071A priority Critical patent/TW573270B/en
Priority to JP2003142433A priority patent/JP2004110767A/en
Application granted granted Critical
Publication of TW573270B publication Critical patent/TW573270B/en

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

573270 五、發明說明(1) 發明之領域 本發明係提供一種規劃排程系統,尤指一種使用多重 限制條件以進行生產流程規劃的規劃排程系統。 背景說明 對於 以及 訂單 若該 少存 同時 趨激 規格 戶可 一產 或者 一產 存上 影響 ,若 期限 流失 供應 客戶 鍵, 以減 亦可 爭曰 不同 此客 加另 力, 取消 的庫 可能 延期 預定 客戶 製造業而言,如何依據現有的物料(fflaterial) 生產產能(capacity)來進行排程規劃以使各個 能於預定期限前完成已變成企業競爭力的重要關 製造業能做好物料與生產的規劃與管理,不但可 貨(inventory)累積壓力,可避免訂單延期, 降低生產成本而提高獲利。然而,隨著企 烈,同時產品的生命週期亦日漸縮短,如^ $ 的制訂’因此電腦產品的生命週期 能隨時更改產…,或是取消;而: 品的需求,因此極易造成生產線上:訂早而增 各產品間包含有共通的關鍵性物料,二的庫存壓 品訂單而增加另一產品的需求時\不,客戶臨時 升,同時該產品由於耗用了共诵沾M但原來產品 另一產品的生產排程,並造^該另一 f性物料而 該企業無法快速地回應客戶的g w :產品的訂單 内完成該訂單所規定的產品數量早=動’並且於 而影響該企業的獲利。目前聿χ 4 f後極易由於 J茶界係使用習知企業573270 V. Description of the invention (1) Field of the invention The present invention provides a planning and scheduling system, especially a planning and scheduling system that uses multiple constraints to plan production processes. Background note: If and when the order is kept small, the specification households will be able to produce one product or one product will be affected. If the deadline loses the supply of customer keys, it can also be argued that different customers can work harder. The cancelled library may be postponed. As far as the customer manufacturing industry is concerned, how to plan according to the existing material production capacity (capacity) so that each can be completed before the scheduled deadline has become an important issue for the competitiveness of the manufacturing industry. Planning and management not only accumulate pressure on inventory, can avoid order delays, reduce production costs and increase profits. However, as the enterprise is fierce, the life cycle of the product is also gradually shortening, such as the formulation of ^ $, so the life cycle of computer products can be changed at any time ... or canceled; and: the demand for products, it is very easy to cause production lines : Order early and increase each product contains common key materials. When the inventory of two products increases the demand for another product \ No, the customer temporarily rises. At the same time, the product consumes the common chanting M but the original Product production schedule of another product, and create another f sex material and the company can not quickly respond to the customer's gw: the product order is completed within the order, the number of products specified in the order is early = move, and then affect the Profits for the business. At present, after 易 χ 4 f, it is very easy for J tea industry to use known companies.

573270 五、發明說明(2) — :貝源規劃(enterprise resource planning, ERP)系統來 進行物料規劃(material requirement planning)以及 生產規劃(manufacturing resource planning),然而 j述物料規劃與生產規劃係假定物料供應以及生產線產能 ^為無限的前提下進行訂單的相關排程規劃,由於無限= 料供應以及生產線產能係背離實際的狀況,因此經 ^ =誤則提來進行規劃亦必定會造成訂單的延遲。請參 ^了而知生產排程規劃的示意圖,橫軸代表時 工廠於充足物料供應下的最大產能,當一 ^ 單A、B、C時,對於訂單a而古,i六Γ /業接 張訂 口。a、 ° 其父期(duedate)為 ί於^-夂付/門早進撕料的時間為Tl,因此訂單A可排 其交期為T2而取^於訂^而言,若 單B可排定於TH2,之間的時間為 交期為T3,,若取得訂單c所 對於訂單C而言,其 C可排定於T3 —T3,之間進行生產,4由於時間产T3,因此訂單 於訂皁B的交期T2,,而訂單b的交^早A的父期ΤΓ早 T3,,因此排程的順序為訂單A、訂g早於訂單C的交期 實際生產線的最大產能為被B/訂單C,然而由於 用,*於習知技術未考慮^級丁卜n,之間佔 合理的排程,所以當訂單β欲於 透過產能分配來進行 會因為無可用產能而 、進行產品製造時即 地,訂單…生產亦會受 (3) 573270 ,習知企業 以人工方式 生產排程產 訂單之間會 規劃系統並 的影響,因 可能不易做 的物料供應 ’經由習知 直接運用, 各易出錯, 知企業資源 及未完成的 響該企業誤 五、發明說明 題。此時 身經驗而 有複數個 調整後的 企業資源 線之排程 但耗時且 加入有限 雜。因此 劃並無法 時費力且 會造成習 單資料, 料更會影 發明概述 資源規劃 來調整發 生問體, 互相影響 無法顯示 此僅靠該 出最佳的 條件,則 技術所計 而必須以 此外,錯 規劃系統 物料採購 判目前營 系統的操作人員 生問題的訂單排 當該操作人員進 而仍會造成問題 某一訂單調整後 操作人員以人工 生產排程規劃, 將會使前述排程 畫出來的物料規 人工方式進行調 誤的物料規劃與 §己錄了大量未完 訂單資料等,上 運狀況而做出錯 必須依據本 程,若同時 行修訂時, ,然而習知 對整個生產 方式調整不 此外,若再 調整更加複 劃與生產規 整,不但費 生產規劃更 成的客戶訂 述不正確資 誤決策。 因此,★ & 其考虚札二日^主要目的在於提供一種規劃排程 重限制(constrain) 統,其者發明的主要目的在於 決上述問^。料、產能等多重限制 本發明之 仃之規劃排程^明專利乾圍提供一種於一電腦系 規劃—製造裝置1 and scheduling)方法, 置之生產流程以於一完成時間輸出歹“ 573270 五、發明說明(4) 單(order)之預定數量的產品,該訂單具 (due date),該製造裝置包 、有—玎早父期 制,其係為該製造裝置於一單 capacity)限 之最大值,該產品係對;* # 時間内可生產之產品數量 material,BOM),該物料清單規範該製造 品所需的物料,該生產流程對廍 裒置製仏忒產 睡兮褚宗赵旦夕吝㈡抓+ ί應於物科限制,其規範採 購該預^數里之產。口所茜之物料的採購時間 period),該採購時間係為提 (purc g 之需求至取得該製造裝置預產品之物料 之時間。該規劃排程方法3 = 產品所需物料 ϋ i t Μ β i ^ ί據產能限制以及該預 疋數里彳异70成該訂早所系之製造時間(manufacturi period),並依據該訂單交期以及該製造時間計算該訂單 父期月il之一最晚啟始時間(1 a t e s t p 〇 s s i b 1 e s t a r t t ime,LPST),該最晚啟始時間與該訂單交期之差係為該 製造時間;使用該生產流程之一規劃啟始時間(p丨ann丨^ start time)以及該採購時間計算該規劃啟始時間後之一573270 V. Description of the invention (2) —: The enterprise resource planning (ERP) system is used for material requirement planning and manufacturing resource planning. However, the material planning and production planning described above assume materials. The supply and production line capacity ^ is unlimited, and the relevant schedule planning of the order is performed. Because unlimited = material supply and production line capacity are deviated from the actual situation, planning by mistake ^ = will definitely cause delay in the order. Please refer to the schematic diagram of the production schedule planning. The horizontal axis represents the maximum production capacity of the factory with sufficient material supply. When A ^ orders A, B, and C, for the order a and old, i six Γ / industry connection Zhang booked. a, ° The parent period (duedate) is ί ^-夂 pay / door early feed tearing time is Tl, so order A can arrange its delivery time to be T2 and take ^ for ordering, if order B can Scheduled at TH2, the time between them is T3. If order c is obtained, for order C, its C can be scheduled to be produced between T3 and T3, 4 because the time is T3, the order The order B2 of the soap B is delivered, and the parent B of the order B is earlier than the delivery time T3 of the order B. Therefore, the order of the order is A, and the order g is earlier than the order C. The maximum capacity of the actual production line is B / order C. However, due to the use of *, the conventional technology does not consider ^ grade Dingbu n, which accounts for a reasonable schedule, so when the order β is intended to be carried out through capacity allocation, it will be carried out because there is no available capacity. When the product is manufactured, the order ... Production will also be affected by (3) 573270. Knowing companies will manually plan the system and influence the production order between production orders, because the supply of materials that may not be easy to make is directly applied through the knowledge Each is prone to errors, knowing the enterprise resources and unfinished answers to the enterprise's mistakes. 5. Inventive explanation questions. At this time, I have multiple adjustments to the schedule of the enterprise resource line based on experience, but it is time consuming and has limited additions. Therefore, planning can not be laborious and time-consuming, and it will cause learning list materials. It is expected that the invention will outline the resource planning to adjust the occurrence of the problem. The mutual influence cannot show that this is only based on the best conditions. The technology must be calculated in addition to, Wrong planning system Material purchase judgment The operator of the current system has a problem with the ordering of the operator. This operator will still cause problems. After an order is adjusted, the operator plans the manual production schedule, which will make the materials drawn in the foregoing schedule. The material planning and manual adjustment of manual material planning and § have recorded a large amount of uncompleted order data, etc., errors in the shipping status must be based on this process. If the revision is performed at the same time, however, it is known that the entire production mode is not adjusted. In addition, if The readjustment is more reorganized and the production is more regular, and not only the customers who have spent more time on production planning have formulated incorrect incorrect decisions. Therefore, the main purpose of ★ & its research is to provide a constraining system for planning and scheduling. The main purpose of the invention is to solve the above problems ^. Multiple restrictions on materials, production capacity, etc. The planning schedule of the invention ^ It is clear that the patent patent provides a computer system planning-manufacturing device 1 and scheduling method. The production process is set to output at a completion time. Description of the Invention (4) A predetermined number of products of the order, the order date (due date), the manufacturing device package, and the early paternity system, which is the maximum limit of the manufacturing device in a single capacity) Value, the product is right; * # the number of products that can be produced in time (material, BOM), the bill of materials regulates the materials required for the manufactured product, and the production process is for the production of the production system Chu Zong Zhao Danxi吝 ㈡ Grab + ί should be subject to material restrictions, which regulates the purchase of the product within a few miles. The procurement time period of the materials used by the mouth is specified as the purchase time for purg g to obtain the manufacturing equipment. The material time of the product. The planning and scheduling method 3 = the material required for the product ϋ it Μ β i ^ 据 According to the capacity limit and the number of miles in advance is 70% of the manufacturi period of the order, And pay according to the order And the manufacturing time calculates the latest start time (1 atestp 〇ssib 1 estartt ime, LPST) of the parent month il of the order, and the difference between the latest start time and the order delivery time is the manufacturing time; use One of the production processes is planned starting time (p 丨 ann 丨 ^ start time) and one of the purchasing time is calculated after the planned starting time

最早啟始時間(earliest possible start time,£PST ),該規劃啟始時間與該最早啟始時間之差係為該採購時 間,以及於该最早啟始時間後之該完成時間與該最早啟妒 時間之間隔中將該製造裝置於該產能限制下可使用之第二 產能排入該生產流程,該第一產能係等於該預定數量。 本發明之申請專利範圍另提供一種於一電腦系統中所 執行之規劃排程(planning and scheduling)方法,用Earliest possible start time (£ PST), the difference between the planned start time and the earliest start time is the purchase time, and the completion time after the earliest start time and the earliest envy In the interval of time, a second capacity that is usable by the manufacturing device under the capacity limit is discharged into the production process, and the first capacity is equal to the predetermined number. The patent application scope of the present invention also provides a planning and scheduling method performed in a computer system.

573270 五、發明說明(5) 來規劃一製造裝置之生產流程以於一完成時間輸出列於一 訂單(order)之預定數量的產品’該訂單具有一訂單交 期C due date),該製造裝置包含有一產能(capacity) 限制’其係為該製造裝置於一單位時間内可生產之產品數 量之最大值,該產品係對應於一物料清單(b丨丨i 〇 f material, BOM),該物料清單規範該製造裝置製造該產 品所需的物料,該生產流程對應於一物料限 Λ 購該預定數量之產品所需之物料的採購時 ^ '木 period),該採購時間係為提出該預定數(^rchasing 之需求至取得該製造裝置生產該預 =之產品之物料 之時間。該規劃排程方法包含^f 產品所需物料 啟始時間(latest pos丄=二:-期前之-最晚 晚啟始時間與該訂單交期之iPST),該最 之第—產能係與該預定數以置ί 該生產&程之一規劃啟始時間 4,以及使用 ?及該】採購時間計算該規劃啟始:t,:) (earliest possible ^ 敢早啟始時間 時間與該最早啟始時間之差 lme’ EPST),該規劃啟始 早啟始時間早於該最晚啟ΐ =該…該最 生產流程,該完成時間即為該訂星i Ζ第—產能排入該 始時間早於該最早啟始時間,二=2,,以及若該最晚啟 成時間與該最早啟始時間 /,最早.啟始時間後之該完 限制下可使用之第二產能排二;:J 3造襄置於該產能 等於該預定數量。 Λ生產"丨L長’該第二產能係573270 V. Description of the invention (5) To plan the production process of a manufacturing device to output a predetermined number of products listed in an order at a completion time 'the order has an order due date (C due date), the manufacturing device Includes a capacity limit, which is the maximum number of products that the manufacturing device can produce in a unit time. The product corresponds to a bill of materials (BOM), the material The list specifies the materials required by the manufacturing device to manufacture the product, and the production process corresponds to a material limit Λ when the material required to purchase the predetermined quantity of product is purchased ^ 'wood period), the purchase time is the proposed number (^ Rchasing demand time to obtain the manufacturing equipment to produce the material of the pre- = product. The planning and scheduling method includes ^ f product start time required for the product (latest pos 丄 = 2:-before the period-the latest Late start time and iPST of the delivery date of the order), the first-production capacity and the predetermined number to set the planned start time of the production & process 4, and the use of the purchase time calculation Planning start: t, :) (earliest possible ^ The difference between the early start time and the earliest start time lme 'EPST), the planning start is earlier than the latest start = this ... this For the most production process, the completion time is the ordering time of the booking star. The capacity is entered into the start time earlier than the earliest start time, two = 2, and if the latest start time and the earliest start time / , The earliest. The second capacity that can be used under the end of the limit after the start time is ranked second;: J 3 is placed at the capacity equal to the predetermined amount. ΛProduction " 丨 L 长 ’This second capacity system

573270 五、發明說明(6) 發明之詳細說明 明參閱圖一 ’圖一為本發明規劃排程(planning and schedul ing)系統10的方塊圖,規劃排程系統1〇包含有一 訂單答交系統(demand fulfillment planner) 12,一資 源規劃系統(r e s o u r c e p 1 a η n e r) 1 4,一生產規劃系統 (production planner) 16’以及一模擬規劃系統' (simulation Planner) 18。規劃排程系統1〇的運 贫當一業務人員接到一客戶所提供之預測訂單時:例 :提供-第二季預測訂單予㈣務“、然J = : j 將該預測訂單盘目前實P打置沾如, Μ業務人員 眘、、塔拍*丨4 ” 貫際訂早的相關產品數量等資帑匯λ :源規劃系統14中,然後依據一包含該 t =訊匯入 劃的物料清單(bill of material βΩϋ_;τ早之預測規 2類需求與完成採購所需 :)來得:所需物 :傳遞給物料供應商以詢問確^的可即將上述資 料::Ϊ f所回覆的可交數量與曰期即為對庫二1该 ,限制,然後該採購 應該物枓之物 劃系統16中,缺德生產:2將物科供給限制匯入生產招 料供给限制以產生各訂單二12上6依據工廠產能限制斑物 產能限制納入規叫ί j:程劃,因此由於將物;i 訂單所ς ί業務人員即可將訂單交期回岸淡宏^將更為 的產⑽數里便可匯入訂單答交门時该 ^ ,而該573270 V. Description of the invention (6) For a detailed description of the invention, please refer to FIG. 1 'FIG. 1 is a block diagram of a planning and scheduling system 10 of the present invention. The planning and scheduling system 10 includes an order response system ( demand fulfillment planner) 12, a resource planning system (resourcep 1 a η ner) 1 4, a production planning system (production planner) 16 'and a simulation planning system' (simulation planner) 18. When the sales staff of the planning and scheduling system 10 receive a forecast order provided by a customer: For example: provide-the second quarter forecast order to the service ", then J =: j P set Zanru, Μ sales staff cautiously, and tower shot * 4 ”The number of related products that have been ordered early, etc. λ: source planning system 14, and then based on a t = Bill of material (bill of material βΩϋ_; τ early forecast rule 2 requirements and completion of procurement :) to get: what is required: pass to the material supplier to inquire about the above information :: : f The deliverable quantity and the date are the limit and the limit of the second storehouse. Then the purchase should be in the material allocation system 16. The lack of moral production: 2 The material supply limit is remitted into the production supply and supply limit to generate each order. 12 on 6 According to the factory's capacity limit, the spot capacity limit is included in the code ί j: schedule, so because of the goods; i order personnel ί business staff can return the order to the shore lightly ^ will increase the number of production Here you can import orders when the order is answered ^, and the

川270 --—-—. 五、發明說明(7) 訂單所對應的產品蠡旦 行沖銷以修正調整二二f先前的預測訂單之產品數量 後的預測產品數量邀^ ί早之預測產品數量,然後該調整 資源規劃系統14以^别貫際訂單的產品數量則重新匯Λ 外,本發明規劃排_,上述操作以進行相關訂單排程。此 其功能敘述如下,^ 1 0另包含有一模擬規劃系統1 8, 如客戶取消訂單, "^規劃的過程中一旦遭遇問題, 先的供給產生變動時增加訂單,或是物料供應商屌 擬各項異動對訂單挑因素時,可透過模擬規劃系統1 8來桓 對應該訂單的物料程的影響,例如當客戶取消訂單時,、 訂單延遲的數量,及產能即可應用於其他訂單,以減>Ν 的訂單會佔用物料=反地’當客戶臨時增加訂單時,姆^ 擬規劃系統18於運;;產能而造成其他訂單延遲。所以f才= 單,物料等相關資時會先取得目前規劃的資料(例如訂 物料的内容,沛^ ',然後依據變動情形來修改訂單戋 揭到έA、4由生產規劃系統1 6來重新規劃,而楹挺 类Γ隹二、呈9依據模擬變動後的規劃結果於原先的規劃妙 =進仃差異比較,同時顯示於規劃排程系統1 0之營理者m 刖’因此該管理者即可依據模擬規劃系統1 8的輸出來得知 刖述問題(例如客'戶取消訂單,臨時增加訂單)對實際訂 單排程的影響,因此便能快速地採取對策因應。 請參閱圖三,圖三為本發明多重限制規劃方法的流孝 I圖,對於圖二所示之規劃C丄2是使月 -多重限制規劃方法來進行订早排序規,该夕重限制夫 573270Chuan 270 ------. V. Description of the invention (7) The product corresponding to the order is written off once to revise and adjust the forecasted product quantity after adjusting the previous forecasted product quantity on February 22f. ^ Early forecasted product quantity Then, the resource planning system 14 adjusts the quantity of products in different orders, and re-sends Λ. The present invention plans to schedule the above operations to perform related order scheduling. This function is described as follows, ^ 1 0 also includes a simulation planning system 18, if the customer cancels the order, " ^ once the planning process encounters problems, increase the order when the first supply changes, or the material supplier to simulate When various changes affect the order selection factor, the simulation planning system 18 can be used to influence the material process of the order. For example, when the customer cancels the order, the amount of the order delay, and the capacity can be applied to other orders. Orders that reduce > N will take up materials = reverse ground. When the customer temporarily increases the order, the planned system 18 will be shipped; the capacity will cause delays in other orders. Therefore, f == orders, materials and other related information will first obtain the current planning information (such as ordering the content of the material, Pei ^ ', and then modify the order according to the change situation, unveiled to A, 4 by the production planning system 16 to re- According to the planning results after the simulation changes, the planning results are compared with the original planning results. The original planning results are compared with the original planning results, and the differences are shown in the planning schedule system. According to the output of the simulation planning system 18, you can learn the impact of the description problem (such as the customer's cancellation of the order and the temporary increase of the order) on the actual order scheduling, so you can quickly take countermeasures. See Figure 3, Figure The third is the flow chart I of the multi-restriction planning method of the present invention. For the plan C 图 2 shown in Figure 2, the monthly-multiple-restriction planning method is used to make early ordering rules. The restriction is 573270.

五、發明說明(8) 劃方法包含有下列步驟: 步驟1 0 0 :開始; 步驟1 02 :彙整所有訂單,並依據客戶及交期等優先順序 (priority)設定來執行一訂單排序操作; 步驟104:在不考慮產能限制下,計算製造’一訂需 品數量之製造時間,並依據該訂單的交期,亦即最晚可能 兀成時間(latest possible complete time, LPCT)推 算其製造時間,亦即最晚可能啟始時間( possible start time, LPST); ΐ =:進依行據的物Λ,時間以及物料_ 早十ft進订的取早可能啟始時間(earliest possible EPST),並經由該製造時間求出一相對應最 ΕΡ(:τΓ ^ 時間(earl lest possible complete time, 二^B¢考τ慮產能限制,並依據該訂單之最晚可能完成 二能啟始時間,㉟早可能啟始時間,以及最早 ί Ϊ 气進行排程以佔用可使用的產能;V. Description of the invention (8) The planning method includes the following steps: Step 1 0 0: Start; Step 1 02: Aggregate all orders, and execute an order sorting operation according to the priority settings of customers and delivery dates; Steps 104: Calculate the manufacturing time of manufacturing a quantity of a required product without considering the capacity limit, and estimate its manufacturing time based on the delivery date of the order, that is, the latest possible complete time (LPCT). That is, the latest possible start time (LPST); ΐ =: the item Λ, time and material _ which are according to the original data, _earliest possible EPST of the order of ten ft, and Based on the manufacturing time, a corresponding maximum EP (: τΓ ^ time (earl lest possible complete time, ^ B ¢) considering τ considering capacity constraints, and based on the latest possible completion time of the order, the soonest Possible start time, and the earliest tritium to be scheduled to use available capacity;

步驟1 1 0 ·判斷 I 該訂單是否r 疋否進行優化(optimization)處理以及 ^ ^驟Tl 2^執行過優化處理’若已執行過優化處理則執 處^,則進行&牛未j行過優化處理’且一使用者啟動優化 者不啟動.優化114,若未執行過優化處理,且該使用 步驟1丨2:執行處理/則進行步驟112; U叮一多階物料清單的調整以減低最後產品之Step 1 1 0 · Identify whether the order is r 疋 optimized or not, and ^ ^ Step Tl 2 ^ has performed optimization processing 'If optimization processing has been performed, then execute ^, then perform & Niu Wei j line Over optimization processing 'and one user starts the optimizer and does not start. Optimization 114, if the optimization processing has not been performed, and the use step 1 丨 2: execute processing / then proceed to step 112; Uding a multi-level bill of materials adjustment to Reduce the final product

第12頁 573270 五、發明說明(9) 啟始時間(possible start time, PST)與其各個組成半 成品(work in process,WIP)之完成時間[p〇ssibU complete time,PCT)之間的差距,執行步驟118; 步驟11 4 :該訂單是否延遲?若是,則進行步驟丨丨6,否 執行步驟112 ; 步驟11 6 :執行訂單優化處理,執行步驟丨〇 4 ; 步驟11 8 ··結束。 ’ 該多重限制規劃方法的運作簡述如下, '同時設定各訂單的優先順序,該設定的規則 了依據客戶的重要性,訂單交期的先後順序,或是訂 ,購金額等條件來設定各訂單的優先順序,其中優先戽 ^的訂單會先排入生產線的生產流程規劃中^步驟i〇2 i拄對於每一訂單而言,其均具有一交期,因此必須於交 期時將該訂單所規定的產品數量交至客戶手以 完成時間,因此若依據完成;ΐ Τ Λ 求出該訂單的最晚啟始時間Page 12 573270 V. Description of the invention (9) The gap between the possible start time (PST) and the completion time of each component in process (WIP) [p〇ssibU complete time (PCT), implementation Step 118; Step 11 4: Is the order delayed? If yes, go to step 丨 6; no, go to step 112; step 116: execute order optimization processing, go to step 丨 〇 4; step 11 8 ·· End. The operation of this multiple-restriction planning method is briefly described below. 'At the same time, the order of priority of each order is set. The rules of this setting are based on the importance of the customer, the order of order delivery, or the order and purchase amount. The order of priority of orders, where the order of priority ^^ will be included in the production process planning of the production line ^ step i〇2 i 拄 For each order, it has a delivery period, so it must be The quantity of the product specified in the order is delivered to the customer to complete the time, so if it is based on completion; Τ Τ Λ find the latest start time of the order

(乂驟1 04),請參閱圖四,圖四為本發明多重限劍招 方法的第一示意圖,橫軸代表時間,縱 S,J 產能上限為3,若一訂單的交期為t8,二代表產二,其中 ίΐ I:於f ϊΐ為3,所以若不考慮產能上 k下,而要四個早位時間才可完成該訂單, 妒 (t8)即可得到最晚啟始時間,喑注咅国斤士、,工由父期 程規劃開始的時間點,而斜J區;俜;另圖::t()係為排 η深吐塊你马另一優先順序較高(Step 104), please refer to FIG. 4. FIG. 4 is the first schematic diagram of the multiple-restricted swordsmanship method of the present invention. The horizontal axis represents time, and the vertical S, J capacity limit is 3. If the delivery time of an order is t8, Two represents production two, of which ίΐ I: Yu f ϊΐ is 3, so if you do not consider the capacity up and down k, but it takes four early time to complete the order, jealous (t8) can get the latest start time,喑 Note: The time point when the country ’s father planned, and the worker started from the schedule of the father, and the area J is oblique; 俜; Another picture: t () is a row η deep spit block. Your horse has a higher priority.

573270 發明說明(1〇) 與 該 訂單所佔用的產能,由於 _~ :應時間係為該物料的供給限:應1所提供的物料數量 ^枓供應商下單購買至收到所需的=當一採購人員對 旦間,若考慮該採購時間即可到=數量間具有一採 2明多重限制規劃方法的第二示意;圖參閱圖五,圖五為 姐耗代表產能’其中產能上限為3, 仏軸代表時間, ί ί要3個單位時間,因此當於to下單ί 2 =訂單所需物 =成該訂單之物料準備的時間物料供應商,則 3,如前所述,由於不考岸產二二17最早啟始時間為 i k 个可應屋能上限的箭担π ^ 位時間才可完成該訂單,因此若 ^下,吊要四個 則可於t7完成該訂單,,亦即早自七3開始進行, Ϊί考慮產能限制,因此必須加:產ί 3 t?,上述操作 &正確”’所以本發明係;Π :峻完成時間’最晚可能啟始時間,最晚 (i : ΐ〇1) Λ4時二乂,排程來佔用尚可使用的產能 能 入產此限制可區分為兩方面,若最早可 可最晚可能啟始時間,則先考慮最晚 以ϋ Λ已完成時間之間的產能,由於時間 於最另—優先順序較高的訂單所佔用,因此 最晚可犯啟始時間與最晚可能完成時間之間僅能使用時573270 Description of the invention (1〇) and the capacity occupied by the order, because _ ~: the time should be the supply limit of the material: the amount of material provided by 1 should be ^ 枓 the supplier places the purchase order to receive the required = When a purchaser compares the purchase time, if the purchase time is taken into consideration, the second schematic diagram of the multiple-restriction planning method with a limit of 2 can be obtained; the figure refers to Figure 5, which represents the capacity consumption. 3, the y-axis represents time, and ί requires 3 units of time, so when placing an order at to 2 2 = what is required for the order = time for the material preparation of the order material supplier, then 3, as mentioned earlier, because This order can be completed without considering that the earliest start time of the shore production 2217 is ik ^ ^ ^ of the upper limit of the available room capacity. Therefore, if the order is ^, four orders can be completed at t7, That is to say, as early as July 3rd, considering the limitation of production capacity, it is necessary to add: the production of 3 t ?, the above operation & correct "so the present invention department; Π: the completion time 'latest possible start time, the most Late (i: ΐ〇1) Λ4 o'clock, schedule to use the available capacity This restriction can be divided into two aspects. If the earliest possible start time of cocoa is the earliest, then consider the production capacity between the finished time at the latest Λ Λ, because the time is at the other-the order with the higher priority Occupied, so only the time between the latest start time and the latest possible completion time can only be used

573270 五、發明說明(11) 間t 6〜t 9之間的產能,由於時間16〜t 9之間的產能為6並益 法達到該訂單所需的數量為1 2,所以必須尋找其他可用”的 產能,因此接著考慮最早可能啟始時間(t3)與最晚可能 啟始時間(t4)之間可用的產能為3,此時該訂單於最早% 可能啟始時間(t3)與最晚可能完成時間(t8)之間可得 到的產品數量為9仍小於該訂單所需的數量為1 2,因此必 須接著考慮最晚可能完成時間(18)之後可使用的產能, =以該訂單的實際完工時間係為t9,另一方面,若最$可 能啟始時間晚於最晚可能啟始時間,表示該訂單 : 丁寸供應不及而必定會造成訂單延遲,因為物料於最早 =始時間時才能完成準備,所以該訂單亦必須自最;月: 間之後來尋找尚可使用的產能,直到該訂單所需= 时^ ^成為止,綜合上述,經由步驟1 0 4〜1 0 8即可得到~ 早的合理交期。 ]訂 划,m 』早的埋交期可能會晚於該訂單的預 序I:牛^使用者可依據需要來決定是否啟動一優化處理藉 後上3110),若使用者決定啟動該優化處理程序, 曰,丨π ^行一判斷以彳貞測該訂單是否延期,若該訂嚴去: 佼會進行一判斷以偵測該訂單9丕证划,若嗲~ 1 ·、'、、 則不需進扞接庐俱彳h卢撕早疋否延期右該訂早未延| 驟11 fn 後、,,只優化處理,否則會啟動訂單優化處理cj 鄉116),該訂單優化處理的垃从从1 ^下,认々免里^ ^ ^ ^ ^ m f ^ 处理係經由更改物料限制條盥‘= ,该叮單優十 遲時間縮μ並小於—預定臨;^ =制條件來訂單的为 界值,亦即該訂單優化處理々573270 V. Description of the invention (11) The production capacity between t 6 ~ t 9 is because the production capacity between time 16 and t 9 is 6 and the quantity required to reach this order is 1 2, so we must find other available ", And then consider the available capacity between the earliest possible start time (t3) and the latest possible start time (t4) is 3, at which time the order is at the earliest possible start time (t3) and latest The number of available products between possible completion time (t8) is 9 and the quantity required for this order is 12, so the next step is to consider the capacity available after the latest possible completion time (18), = according to the order's The actual completion time is t9. On the other hand, if the maximum possible start time is later than the latest possible start time, it means that the order: The supply of T-inch is not enough and will definitely cause an order delay because the material is at the earliest = start time In order to complete the preparation, the order must also be searched for the available capacity from the end of the month; until the order required = time ^ ^ becomes the end, based on the above, you can go through steps 1 0 4 ~ 1 0 8 Get ~ early reasonable delivery.] m ”The early delivery period may be later than the pre-order of the order I: The user can decide whether to start an optimization process according to the needs and then borrow 3110). If the user decides to start the optimization process, said,丨 π ^ A judgment is made to test whether the order is postponed. If the order is tightened: The judge will make a judgment to detect the order. If it is 嗲 ~ 1 ·, ',, you do not need to defend it. If the order is not postponed, the order should not be postponed. After step 11 fn, only the optimization process will be performed, otherwise the order optimization process will be started (cj town 116), and the order optimization process will be from 1 ^ Next, the recognition is free. ^ ^ ^ ^ ^ ^ Mf ^ The processing is through changing the material restriction bar. '=, The time delay is reduced by ten and the time is less than-scheduled to come; That is, the order is optimized for processing 々

第15頁 573270 五、發明說明(12) 判斷造成交期延遲的主因係為物料或產能造成,若是物料 所造成的延遲,則可使用替代物料或是替代供應商來改善 物料供給的數量及時間,若是產能所造成的延遲,則可使 用替代製程(例如另一生產線),或增加生產工時來改善 產能不足的問題,若造成訂單延遲係由物料與產能所共同 造成,則使用上述所有可能的組合直到延遲時間縮短並小 定臨^為A,請注意,上述減低訂單延遲的方法 ^對應-預定定義的優先順彳,舉例來說,解決物料與產 月b所造成之交期延遲的方法依據優先順序總共有 M,A2, A3, A4, A5, A6,因此該訂單優化處理會先採用“並 f由步驟104〜108以判斷該訂單延遲時間是否 巧;單延遲時間並未小於該預定臨界值,則該 ^早優化處理會另採用A2並經由步驟1〇4〜1〇8以判斷該訂 二延遲時間是否小於該預定臨界值,#此時該訂單延遲時 j係小於該預定臨界值,表示該訂單優化處理已完成,因 〜"I就广乂被不該訂單優化處理所採用,然後使用 步疋接受該訂單優化處理的結果以進一 2更新排程規劃,然後當訂單延遲時,則 ^12以調整多階物料清單,請參閱圖七,圖七為了發^明^ 示意圖,橫軸代表時間,成品‘ =+成B、C所製成,而半成品c則由半成品卜 士,經由上述排程規劃可以得到該訂單中的生產,,立 :半成品D的啟始時間為T2而完成時間為T4,半 / ^ 始時間為Τ1而完成時…,半成品C的啟始以= 啟Page 15 573270 5. Description of the invention (12) The main cause of the delay in delivery is the material or capacity. If it is the delay caused by the material, you can use alternative materials or suppliers to improve the quantity and time of the material supply. If the delay is caused by capacity, you can use an alternative process (such as another production line) or increase production hours to improve the problem of insufficient capacity. If the delay caused by the order is caused by materials and capacity, use all of the above possibilities. The combination until the delay time is shortened and settled ^ is A. Please note that the above-mentioned method of reducing order delays ^ corresponds to-the predefined priority order, for example, to solve the delay in delivery due to materials and production month b The method has a total of M, A2, A3, A4, A5, A6 according to the priority order. Therefore, the order optimization process will first use "and f from steps 104 to 108 to determine whether the order delay time is coincident; the single delay time is not less than this. A predetermined threshold, the ^ early optimization process will additionally use A2 and go through steps 104 to 108 to determine whether the second delay time is less than the predetermined threshold , #At this time, the j is less than the predetermined threshold when the order is delayed, indicating that the order optimization process has been completed, because ~ " I was widely used by the order optimization process, and then use the step to accept the order optimization process The result is to update the schedule plan by one and two, and then when the order is delayed, ^ 12 to adjust the multi-level bill of materials. B and C are made, and semi-finished product c is made of semi-finished product. Through the above-mentioned schedule planning, the production in the order can be obtained. Li: The start time of semi-finished product D is T2 and the completion time is T4. When the time is completed for T1 ..., the start of semi-finished product C starts with =

573270 五、發明說明(13) f成時間為T5,半成品B的啟始時間為T3而完 ^,成品Α的啟始時間為Τ6而完成時間為η,$以二= 品C完成於Τ5時,半成品β尚未完成,直 田+成 據半成品B、C來生產成品Α,並於時間τ ^間Τ6時此可依 Π成Π一成時,、ΐ必須等待-時=隔= 起用來產生成品Α,因此於時間τςτβ ,成半成品c的存貨累積,所以將半成品’ c盘1 之Β曰 D、Ε的排程位移dT以避免半成品 ?、積、相關+成: 該多階物料清單調整後的排程如圖七之\\積部/所此^由 發明‘ ΐ U : J : ^同時考慮產能限制亦可達到本 此該訂單;可始時間,由於考慮產能限制,因 而前述說明可知3ΐ = ί時間t2〜t4以及時間t6~t8,然 此該訂單原先於;;3 最早開始時間為t3係晚於t2,因 將原先時間t2〜\3所規1二:佔用2產能必須調整,因此 後,因此最後亦能調整^訂單交期(t8)之 發明之範疇。T仵到圖六所示之生產流程規劃,均屬本 本實施例中,#夕^ 制,然後再考廣吝Ϊ夕重限制規劃方法係先考慮物料限 產業,例如電g ^ ^制,因此可適用於注重物料規劃的 極高,且各工礙=f f ^其材料的成本佔其營運成本比重 °的生產數量決定於材料供給而非機器產573270 V. Description of the invention (13) The completion time of T is T5, the start time of semi-finished product B is T3 and finished ^, the start time of finished product A is T6 and the completion time is η, $ 2 = product C is completed at T5 , Semi-finished product β has not yet been completed, Naoda + Cheng according to semi-finished products B, C to produce finished product A, and at time τ ^ time T6, this can be achieved by Π to Π 10%, ΐ must wait-time = interval = starting to produce finished Α, so at time τςτβ, the inventory of the semi-finished product c accumulates, so the schedule of the semi-finished product 'c disk 1 B, D, E is shifted by dT to avoid the semi-finished product? , Product, Relevance + Success: The adjusted schedule of the multi-level bill of materials is shown in Figure 7 \\ Product Department / So ^ Invented by you ΐ: U: J: ^ At the same time, considering capacity constraints, this order can also be reached; can start Time, due to the consideration of capacity constraints, the foregoing description shows that 3ΐ = ί time t2 ~ t4 and time t6 ~ t8, but the order was originally earlier; 3 earliest start time is t3 is later than t2, because the original time t2 ~ \ Rule No. 2 2: Occupation 2 Production capacity must be adjusted, so later, therefore, the scope of the invention of order delivery (t8) can also be adjusted at the end. From T 流程 to the production process plan shown in Figure 6, all belong to the # xi ^ system in this embodiment, and then consider the Guangxi Xi's heavy-restriction planning method that first considers the material-limited industry, such as electricity g ^^^ system, so it can be Applicable to the extremely high emphasis on material planning, and each obstacle = ff ^ The cost of its materials as a proportion of its operating costs ° The production quantity is determined by the supply of materials rather than the production of machinery

^>73270^ > 73270

能 響 因 ,當 重限 制, 必須 的規 所需產 該物料 來排定 點之產 料限制 依據不 多 限其制 此必須 所需物 制規劃 可適用 以產能劃,以 能來決 的相關 一工廠 能,便 來決定 同的限 先做好物料限制的規劃, 料皆齊備後才開始進行產 方法亦可先考慮產能限制 於注重產能規劃的產業, 利用率為優先考量,因此 提高工廠機器的利用率為 定所需物料,並經由一物 時間限制條件,舉例來說 對於各訂單的產能規劃, 可得到其所需的物料數量 該物料需於何時進料。因 制條件考慮順序來進行規 其係先考慮 能規劃。然 ’然後再考 例如半導體 必須先做好 目標,然後 料限制而決 ’先依據產 因此對於每 ’然後便可 此,不同產 劃以符合其 慮物料 產業, 產能限 才依據 定取得 能限制 一時間 依據物 業便可 需求。Responsiveness, when the restrictions are important, the required production of the material to determine the point of production and material restrictions is not based on the system. This must be required material planning can be applied to capacity planning, to determine the relevant factory If you can, you can decide the same limit to plan the material limit first, and start the production method after all the materials are available. You can also consider the capacity limit to the industry that focuses on capacity planning. The utilization rate is a priority, so the use of factory machinery is improved. Determine the required materials, and pass a material time limit. For example, for the capacity planning of each order, you can get the required quantity of the material and when the material needs to be fed. Regarding the order in which the conditions are considered, it is planned first. However, 'then the test, for example, the semiconductor must first make the target, and then the material is limited.' First, according to the production, so for each, then you can do this, different production plans to meet the consideration of the material industry, and the capacity limit can be limited based on the availability. Demand is based on property.

相較於習知技術,本發明規劃排程系統係應用一多 限制規劃方法來進行訂單的相對應生產排程規劃,該多 限制規劃方法係考慮物料限制與產能限制等不同限制條件 來進4于排程’若訂單的完成時間晚於預定交期,則可依據 使用者需求而執行一優化處理,該優化處理先找出造成延 遲的物料因素或產能因素,並依據對應物料因素或產能因 素之各解決方法的優先順序來依序執行該解決方法以使訂 單延遲小於一預定臨界值為止,然後該使用者再判斷是否 以該調整後的生產規劃來更新原先的生產規劃。此外,當 執行本發明規劃排程系統而遭遇問題時,該使用者亦可二 由一模擬規劃系統來模擬該問題所造成的影響,並產生模Compared with the conventional technology, the planning and scheduling system of the present invention uses a multi-restriction planning method to carry out the corresponding production scheduling planning of orders. The multi-restriction planning method considers different restrictions such as material restrictions and capacity restrictions to make progress. In the schedule, if the order's completion time is later than the scheduled delivery date, an optimization process can be performed according to the user's needs. The optimization process first finds the material factor or capacity factor causing the delay, and according to the corresponding material factor or capacity factor Each solution is executed in order of priority so that the order delay is less than a predetermined threshold, and then the user determines whether to update the original production plan with the adjusted production plan. In addition, when the implementation of the planning and scheduling system of the present invention encounters a problem, the user can also simulate the impact of the problem with a simulation planning system and generate a simulation.

573270 五、發明說明(15) 擬前與模擬後的差異報表以使管理者依據該差異報表即時 地做出決策。因此,本發明規劃排程系統可產生合理的物 料與生產計畫,同時可以準確地完成客戶所指定的訂單交 期以提升企業競爭力。573270 V. Description of the invention (15) The difference report before and after the simulation is made so that the manager can make a decision instantly based on the difference report. Therefore, the planning and scheduling system of the present invention can generate reasonable materials and production plans, and at the same time can accurately complete the order delivery period specified by the customer to improve the competitiveness of the enterprise.

第19頁 573270 圖式簡單說明 圖示之簡單說明 圖一為習知生產排程規劃的示意圖。 圖二為本發明規劃排程系統的方塊圖。 圖三為本發明多重限制規劃方法的流程圖。 圖四為本發明多重限制規劃方法的第一示意圖。 圖五為本發明多重限制規劃方法的第二示意圖。 圖六為本發明多重限制規劃方法的第三示意圖。 圖七為本發明多重限制規劃方法的第四示意圖。 圖示之符號說明 10 規劃排程系統 12 訂單答交系統 14 資源規劃系統 16 生產規劃系統 1 8 模擬規劃系統Page 19 573270 Simple illustration of the diagram Simple illustration of the diagram Figure 1 is a schematic diagram of the conventional production schedule planning. FIG. 2 is a block diagram of a planning and scheduling system of the present invention. FIG. 3 is a flowchart of a multiple-restriction planning method according to the present invention. FIG. 4 is a first schematic diagram of a multiple-restriction planning method of the present invention. FIG. 5 is a second schematic diagram of the multiple-restriction planning method of the present invention. FIG. 6 is a third schematic diagram of the multiple-restriction planning method of the present invention. FIG. 7 is a fourth schematic diagram of the multiple-restriction planning method of the present invention. Explanation of symbols in the diagram 10 Planning and scheduling system 12 Order response system 14 Resource planning system 16 Production planning system 1 8 Simulation planning system

第20頁Page 20

Claims (1)

573270 六、申請專利範圍 1β 一種於一電腦系統中所執行之規劃排程(ρ 1 ann丨ng and schedul ing)方法,用來規劃一製造裝置之生產流程 以於一完成時間輸出列於一訂單(order)之預定數量的 產110 ’該訂早具有一訂早父期(due date),該製造裝置 ^含有一產能(capacity)限制,其係為該製造裝置於一 時間内可生產之產品數量之最大值,該產品係對虡於 ^物料清單(bill 〇f material,B0M),該物料清單規 產品所需的物料,該生產流程對應於 採,絶採購該預定數量之產品所需之物料的 asi:g peri〇d) ’該採購時間係為提出 Θ預疋數里之產品之物料之需求至取得該 預定數量之產品所需物料之時間; 、 “ 該規劃排程方法包含有·· 依據該產能限制以及該預定數 之製造時間(manufacturing 十异=成该訂导T j 期以及該製造時間計算該訂單 ),並依據該訂皁父 (latest P〇ssible st 期則之一最晚啟始時間 間與該訂單交期之差係為該製時^PST),該最晚啟始時 使用該生產流程之_ 仏 , time)以及該採購時間間(Planning start 始時間(earliest 亥規劃啟始時間後之一最早啟 劃啟始時間與該最早啟始 =time,EPST),該規 於該最早啟始時間德夕j ^係為該採購時間;以及 之間隔中將該製造梦罢认# = 70成時間與該最早啟始時間 裝置於该產能限制下可使用之第一產能573270 6. Scope of patent application 1β A planning and execution (ρ 1 ann ng and scheduling) method executed in a computer system is used to plan the production process of a manufacturing device to output and list it in an order at a completion time (Order) of a predetermined number of productions 110 'the order has a due date, the manufacturing device contains a capacity limit, which is the product that the manufacturing device can produce within a time The maximum value of the product is based on ^ bill of materials (B0M). The bill of materials specifies the materials required for the product. The production process corresponds to the procurement and must be purchased for the predetermined quantity of products. Material asi: g peri〇d) 'The purchase time is the time from the request of the material of the product in the Θ advance number to the material required to obtain the predetermined quantity of product; "" The planning and scheduling method includes · · According to the production capacity limit and the predetermined number of manufacturing times (manufacturing ten different = calculate the order T j period and the manufacturing time), and according to the order soap parent (latest P. The difference between the latest start time of the ssible st period and the delivery date of the order is the system time ^ PST). The latest start time uses the production process time (_ 仏, time) and the purchase time period ( Planning start time (one of the earliest planning start time after the earliest planning start time and the earliest start time = time, EPST), which is the purchase time at the earliest start time on the day of the evening; and In the interval, the manufacturing dream is rejected # = 70% of the time and the earliest start time of the device can be used under the capacity limit of the first capacity 第21頁 573270 六、申請專利範圍 排入該生產流程,該第一產能係等於該預定數量 第1項所述之規劃排程方法 流程之步驟包含有: 於該最晚啟始時間時,於該 間隔中將該製造裝置於該產 入該生產流程’若該第二產 啟始時間與該最晚啟始時間 能限制下可使用之第三產能 能與該第三產能之和小於該 後之該完成時間與該訂單交 產能限制下可使用之第四產 ,其中該 最晚啟始 能限制下 能小於該 之間隔中 排入該生 預定數 期之間隔 能排入該 2. 如申請專利範圍 第一產能排入該生產 當該最早啟始時間早 時間與該訂單交期之 可使用之第二產能排 預定數量,於該最早 將該製造裝置於該產 產流程,若該第二產 量,則於該訂單交期 中將該製造裝置於該 生產流程; 其中該第二產能,該第三產能,以及該第四產能之和係為 該第一產能。 3. 如申請專利範圍第1項所述之規劃排程方法,其另包 含: 依據一預定排序規則設定複數個訂單之優先順序 (priority); 其中該複數個訂單中對應最高優先順序之訂單先排定於該 製造裝置之生產流程。 4. 如申請專利範圍第1項所述之規劃排程方法,其中該Page 21 573270 6. The scope of the patent application is included in the production process. The first production capacity is equal to the planned quantity. The steps of the planning and scheduling method process described in item 1 include: At the latest start time, at In the interval, the manufacturing device is in the production process. If the start time of the second production and the latest start time can be limited, the sum of the third production capacity and the third production capacity can be less than The completion time and the fourth product that can be used under the delivery capacity limit of the order, where the latest start can be limited to be less than the interval can be included in the interval of the predetermined number of students can be included in the 2. If applied The scope of the patent is that the first production capacity is included in the production when the earliest start time and the available second production capacity are scheduled for the delivery date of the order, and the manufacturing device is included in the production process at the earliest. For the output, the manufacturing device is included in the production process during the delivery of the order; wherein the sum of the second capacity, the third capacity, and the fourth capacity is the first capacity. 3. The planning and scheduling method described in item 1 of the scope of patent application, further comprising: setting a priority order of a plurality of orders according to a predetermined sorting rule; wherein the order of the plurality of orders corresponding to the highest priority order is first Scheduled for the production process of the manufacturing device. 4. The planning and scheduling method described in item 1 of the scope of patent application, wherein the 第22頁 573270 六、申請專利範圍 定排序規則係為各訂單=、 交期之先後來設定其===單父期,並依據各訂單之 心丹相對應優先順序。 平之吁 如申請專利範圍第】頂 定排序規則係為各訂單之述之規劃排程方法,其中該 要性來設定其相對應優先順序。’並依據各訂單之客戶之 如申請專利範圍笫 办忐Bi Μ咕认4固弟1項所述之規劃排程方法,並中A 兀成時間晚於該訂單交袁# ^ Ύ ^ • 平乂期時,該規劃排程方法另包含 預 單 5 預 重 6 該 有 邊供複數個處理策略,用來分 限制; 用术刀別調整该產能限制或該物料 設定該複數個處理策略之優先順序; 設定一臨界值(criteri〇n);以及 ί ί ί ί ϊ ί處理策略之優先順序而依序執行該複數個處 里1略以調整該生產流程,直到該完成時間與該訂單交期 之間隔小於該臨界值為止。 7·如申請專利範圍第1項所述之規劃排程方法,其中當 ,完成時間晚於該訂單交期,且該產品係經由複數個半成 品(work in progress,WIP)構成,該複數個半成品係 由該製造裝置產生,該規劃排程方法另包含有: 當該半成品之完成時間與該產品之啟始時間之間具有一時 間差時’調整該半成品之完成時間以使該時間差小於一預Page 22 573270 VI. Scope of Patent Application The ordering rules are set for each order, and set before the delivery date === single parent period, and according to the priority of each order. Ping Zhiyu The top priority of ordering patents is the planning and scheduling method described for each order, where the importance is to set the corresponding priority order. 'And according to the customer's application scope of each order as described in the scope of the patent application, Bi M Gu recognized 4 Gudi described in the planning and scheduling method, and the A time is later than the order delivery Yuan # ^ Ύ ^ • Ping At the end of the period, the planning and scheduling method also includes advance orders 5 and pre-weights 6. The edge has multiple processing strategies to divide the restrictions; use the knife to adjust the capacity limit or the material to set the priority of the multiple processing strategies Sequence; set a critical value (criteri〇n); and ί ί ί ϊ ί priority of the processing strategy and sequentially execute the plurality of locations 1 to adjust the production process until the completion time and the order delivery The interval is less than the critical value. 7. The planning and scheduling method as described in item 1 of the scope of patent application, wherein when the completion time is later than the delivery date of the order, and the product is constituted by a plurality of work in progress (WIP), the work in progress (WIP) Generated by the manufacturing device, the planning and scheduling method further includes: when there is a time difference between the completion time of the semi-finished product and the start time of the product, 'adjust the completion time of the semi-finished product so that the time difference is less than a predetermined 第23頁 573270Page 573270 六、申請專利範圍 定值。 8 ·如申請專利範圍第 用於一規劃排程系統, 系統(simulation PL 1項所述之規劃排程方法,其係應 該規劃排程系統包含有一模擬規割 planner),用來依據一調整條件修改 該生產流程,並執行一模擬規劃程序以經由該調整條^產 生一模擬生產流程,並輸出該模擬生產流程盥該生產汽 之差異。 " 9·如申請專利範圍第8項所述之規劃排程方法,其中該 調整條件係為吏動對應該生產流程之訂單。 I 0·如申請專利範圍第8項所述之規劃排程方法,其中該 調整條件係為更動對應該生產流程之物料限制。’、^ II ·如申請專利範圍第8項所述之規劃排程方法,其中該 調整條件係為更動對應該生產流程之產能限制。 1 2 · —種於一電腦系統中所執行之規劃排程(p丨a n n i n g and schedul ing)方法,用來規劃一製造裝置之生產流程 以於一完成時間輸出列於一 CT單(order)之預定數量的 產品,該訂單具有一訂單交期(due date),該製造裝置 包含有一產能(capac i ty)限制’其係為該製造裝置於一 單位時間内可生產之產品數量之最大值,該產品係對應於 573270 六 申請專利範圍 二 f 單(bil1 〇f materia1,β〇Μ),該物料清單規 ,二祖^裝置製造該產品所需的物料,該生產流程對應於 採構^制,其規範採購該預定數量之產品所需之物料的 該預2間(purchasing period),該採購時間係為提出 疋數量之產品之物料之需求至取得該製造裝置生產誃 又數量之產品所需物料之時間; 以 該規劃排程方法包含有: 計算訂單交期前之一最晚啟始時間(1 a t e s t fusible start time,LPST),該最晚啟始時間與該訂 車交期之間隔中,該製造裝置於該產能限制下可使用之第 產成係與該預定數量相等;以及 •使用該生產流程之一規劃啟始時間(planning start lme)以及該採購時間計算該規劃啟始時間後之一最早啟 =時間(earliest possible start time, EPST),該規 啟始時間與該最早啟始時間之差係為該採購時間; 其中若該最早啟始時間早於該最晚啟始時間,則將該 第〜產能排入該生產流程,該完成時間即為該訂單交期,Λ 乂及若該最晚啟始時間早於該最早啟始時間,於該最早啟 2時間後之該完成時間與該最早啟始時間之間隔中將該製 ^裝置於該產能限制下可使用之第二產能排入該生產流 程,該第二產能係等於該預定數量。 1 3 ·如申請專利範圍第1 2項所述之規劃排程方法,其另包Sixth, the scope of patent application. 8 · If the scope of the patent application is used for a planning and scheduling system, the system (the planning and scheduling method described in Simulation PL 1 should be a planning and scheduling system including a simulation planner) to adjust conditions based on a Modify the production process, and execute a simulation planning program to generate a simulation production process through the adjustment bar, and output the difference between the simulation production process and the production steam. " 9 · The method of planning and scheduling as described in item 8 of the scope of patent application, wherein the adjustment condition is an order corresponding to the production process. I 0 · The method of planning and scheduling as described in item 8 of the scope of patent application, wherein the adjustment condition is to change the material limitation corresponding to the production process. ′, ^ II • The planning and scheduling method as described in item 8 of the scope of patent application, wherein the adjustment condition is to change the capacity limit corresponding to the production process. 1 2 · — A planning and scheduling method implemented in a computer system, used to plan the production process of a manufacturing device to output a listed in a CT order at a completion time A predetermined number of products. The order has a due date. The manufacturing device includes a capacity limit. This is the maximum number of products that the manufacturing device can produce in a unit time. This product corresponds to the 573270 six-application patent scope of the second f single (bil1 〇f materia1, β〇M), the bill of materials regulations, Erzu ^ device required to manufacture the product materials, the production process corresponds to the procurement structure , Which regulates the pre-purchasing period of the materials needed to purchase the predetermined quantity of products, and the purchase time is the time required to raise the quantity of materials required for the product to obtain the manufacturing equipment to produce the quantity of products required The time of the material. The planning and scheduling method includes: Calculating the latest start time (1 atest fusible start time, LPST) before the delivery date of the order, the latest start time In the interval between the delivery date and the order, the production capacity of the manufacturing device that can be used under the capacity limit is equal to the predetermined quantity; and • using a planning start time (planning start lme) of the production process and the The purchase time is calculated as one of the earliest possible start time (EPST) after the planned start time. The difference between the start time of the rule and the earliest start time is the purchase time; where the earliest start time Earlier than the latest start time, the first capacity is included in the production process, and the completion time is the order delivery time. Λ Λ and if the latest start time is earlier than the earliest start time, In the interval between the completion time after the earliest start time and the earliest start time, a second capacity that can be used by the manufacturing device under the capacity limit is included in the production process, and the second capacity is equal to the predetermined amount . 1 3 · The planning and scheduling method described in item 12 of the scope of patent application, which is separately included 573270 六、申請專利範圍 含: 、w 依據一預定排序規則設定複數個訂單之優先順序 (priority); 其中該複數個訂單中對應最高優先順序之訂單先排定於該 製造裝置之生產流程。 1 4.如申請專利範圍第1 2項所述之規劃排程方法,其中今亥 預定排序規則係為各訂單之訂單交期,並依據各訂單之^ 單交期之先後來設定其相對應優先順序。 6T 1 5·如申請專利範圍第1 2項所述之規劃排程方法,其中= 預定排序規則係為各訂單之客戶’並依據各訂單之客戶該 重要性來設定其松對應優先順序° ^ 1 6·如申請專利範圍第1 2項所述之規劃排程方法,其中去 該完成時間晚於該訂單交期時,該規劃排程方法另包含§ 有: 3 提供複數個處理策略,用來分別調整該產能限制或該物 限制; ; 設定該複數個處理策略之優先順序; 設定一臨界值(criterion);以及 依據該複數個處理策略之優先順序而依序執行該複數個产 理策略以調整該生產流程,直到該完成時間與該訂單交g 之間隔小於該臨界值為止。 /573270 6. Scope of patent application Including:, w Set the priority of a plurality of orders according to a predetermined sorting rule; among the plurality of orders, the order corresponding to the highest priority is first scheduled in the manufacturing process of the manufacturing device. 1 4. The planning and scheduling method described in item 12 of the scope of patent application, in which the scheduled ordering rule is the order delivery date of each order, and the corresponding order is set according to the ^ single delivery date of each order. Priority. 6T 1 5 · The planning and scheduling method described in item 12 of the scope of patent application, where = the predetermined ordering rule is the customer of each order 'and the priority order of loose correspondence is set according to the importance of the customer of each order ° ^ 16. The planning and scheduling method as described in item 12 of the scope of patent application, wherein when the completion time is later than the order delivery date, the planning and scheduling method further includes § There are: 3 Provide multiple processing strategies, use To adjust the capacity limit or the property limit separately; set the priority order of the plurality of processing strategies; set a critical value; and execute the plurality of production strategy in sequence according to the priority order of the plurality of processing strategies To adjust the production process until the interval between the completion time and the order g is less than the critical value. / 573270 六、申請專利範圍 1 7 ·如申請專利範圍第1 2項所述之規劃排程方法 #哀元成時間晚於該訂單交期,且該產品係經由複 品(work in progress, WIP)構成,該複數個」 由該製造裝置產生,該規劃排程方法另包含有: 當該半成品之完成時間與該產品之啟始時間之間 間差時,調整該半成品之完成時間以使該時間差 定值。 1 8 ·如申請專利範圍第丨2項所述之規劃排程方法 用於一規劃排程系統,該規劃排程系統包含有一 系統(simulation planner),用來依據一調整 該生產流程,並執行一模擬規劃程序以經由該調 生一模擬生產流程,並輸出該模擬生產流程與該 之差異。 1 9 ·如申請專利範圍第1 8項所述之規劃排程方法 調整條件係為更動對應該生產流程之訂單。 2 〇 ·如申請專利範圍第1 8項所述之規劃排程方法 調整條件係為更動對應該生產流程之物料限制。 2 1 ·如申請專利範圍第1 8項所述之規劃排裎方法 調整條件係為更動對應該生產流程之產能限制。 ’其中當 數個半成 -成品係 具有一時 小於一預 ,其係應 模擬規劃 條件修改 整條件產 生產流程 ,其中該 ,其中該 ,其中該573270 VI. Scope of patent application 1 7 · The planning and scheduling method as described in item 12 of the scope of patent application #AI Yuancheng time is later than the order delivery time, and the product is through work in progress (WIP) Composition, the plurality of "is produced by the manufacturing device, and the planning and scheduling method further includes: when the difference between the completion time of the semi-finished product and the start time of the product, adjusting the completion time of the semi-finished product so that the time difference Value. 1 8 · The planning and scheduling method described in item No. 丨 2 of the scope of patent application is used in a planning and scheduling system, and the planning and scheduling system includes a system (simulation planner) for adjusting the production process according to a and executing A simulation planning program generates a simulation production process through the simulation, and outputs the difference between the simulation production process and the simulation production process. 1 9 · The planning and scheduling method described in item 18 of the scope of patent application. The adjustment conditions are to change the order corresponding to the production process. 2 〇 · The method of planning and scheduling as described in item 18 of the scope of patent application. The adjustment conditions are to change the material restrictions corresponding to the production process. 2 1 · The planning and arrangement method described in item 18 of the scope of patent application. The adjustment conditions are to change the production capacity limit corresponding to the production process. ’Where several semi-finished products-the finished product has a time less than a forecast, it should simulate the planning conditions to modify the entire condition production process, where the, where the, where the 573270 六、申請專利範圍 2 2 · —種於一電腦系統所執行之規劃排程(p 1 a η n i n g a n d schedul ing)方法,用來規劃一製造裝置之生產流程以於 一完成時間輸出列於一訂單(order)之預定數量的產 品,該訂單具有一訂單交期(due date),該製造裝置包 含有一產能(capaci ty)限制,其係為該製造裝置於一單 位時間内可生產之產品數量之最大值,該產品係對應於一 物料清單(bill of material, Β0Μ),該物料清單規範 該製造裝置製造該產品所需的物料,該生產流程對應於一 物料限制,其規範採購該預定數量之產品所需之物料的採 構時間(purchasing period),該採購時間係為提出該 ,定數量之產品之物料之需求至取得該製造裝置生產該^ 定數量之產品所需物料之時間; 該規劃排程方法包含有: 計算訂單交期前之一最晚啟始時間(latest 二sible start time, LPST),該最晚啟始時間與該訂 ^交期之間隔中,將該製造裝置於該產能限制下可使用之 一產能排入該生產流程,該第一產能係與該預定數量相 荨;以及 倉使用該採購時間以及該最晚啟始時間計算提出該預定 星之產品之物料之需求的時間。 ^3·如申請專利範圍第22項所述之規劃排程方法,其另包 含:573270 VI. Scope of patent application 2 2 · —Planning and scheduling (p 1 a η ning and scheduling) method implemented in a computer system, used to plan the production process of a manufacturing device so that the output is listed in one at a completion time A predetermined number of products in an order. The order has a due date. The manufacturing device includes a capaci ty limit, which is the number of products that the manufacturing device can produce in a unit time. The maximum value of the product corresponds to a bill of material (B0M), which specifies the materials required by the manufacturing device to manufacture the product. The production process corresponds to a material limit, which regulates the purchase of the predetermined quantity. Purchasing period of the materials required for the product. The purchase time is the time from the demand for the material of the specified quantity of product to the acquisition of the material required by the manufacturing device to produce the product of the specified quantity; the The planning and scheduling method includes: Calculate the latest start time (LPST) before the delivery date of the order, which is the latest start time During the interval between the time and the delivery date, one of the production capacity of the manufacturing device that can be used under the capacity limit is discharged into the production process, the first capacity is related to the predetermined quantity; and the warehouse uses the purchase time and The latest start time calculates the time when the demand for the materials of the predetermined star product is raised. ^ 3. The planning and scheduling method described in item 22 of the scope of patent application, which further includes: 573270 六、申請專利範圍 依據一預定排序規則設定複數個訂單之優先順序 (priority); 其中該複數個訂單中對應最高優先順序之訂單先排定於該 製造裝置之生產流程。 2 4 ·如申請專利範圍第2 2項所述之規劃排程方法,其中該 預定排序規則係為各訂單之訂單交期,並依據各訂單之訂 單交期之先後來設定其相對應優先順序。 2 5 ·如申請專利範圍第2 2項所述之規劃排程方法,其中該 預定排序規則係為各訂單之客戶,並依據各訂單之^戶^ 重要性來設定其相對應優先順序。 2 6 ·如申請專利範圍第2 2項所述之規劃排程方法,其係應 用於一規劃排程系統,該規劃棑程系統包含有_模^規書1 系統(s i m u 1 a t i ο η p 1 a η n e r),用來依據一調整條件修改 該生產流程,並執行一模擬規劃程序以經由該調整條&產 生一模擬生產流程,並輸出該模擬生產流程與該生^流程 之差異。 々丨L王 2 7 · —種於一電腦系統中所執行之規劃排程(p丨ann丨% and schedul ing)方法,用來規劃一製造裝置之生產流程 以於一完成時間輸出列於一訂單(order)之預定數量的 產品,該訂單具有一訂單交期(due date)係早於對應該573270 6. Scope of patent application Set the priority order of a plurality of orders according to a predetermined sorting rule; among the plurality of orders, the order corresponding to the highest priority order is first placed in the manufacturing process of the manufacturing device. 2 4 · The planning and scheduling method described in item 22 of the scope of patent application, wherein the predetermined ordering rule is the order delivery time of each order, and the corresponding priority order is set according to the order delivery date of each order . 2 5 · The planning and scheduling method described in item 22 of the scope of patent application, wherein the predetermined ordering rule is the customer of each order, and the corresponding priority order is set according to the importance of each order. 2 6 · The planning and scheduling method as described in item 22 of the scope of patent application, which is applied to a planning and scheduling system, which includes a _modular 1 system (simu 1 ati ο η p 1 a η ner), used to modify the production process according to an adjustment condition, and execute a simulation planning process to generate a simulation production process via the adjustment bar & and output the difference between the simulation production process and the production process. 々 丨 L 王 2 7 · —Planning schedule (p 丨 ann 丨% and scheduling) method implemented in a computer system, used to plan the production process of a manufacturing device so that the output is listed in one at a completion time A predetermined number of products for an order, the order having a due date is earlier than the corresponding 第29頁Page 29
TW91121071A 2002-09-13 2002-09-13 Multiple constrains planning and scheduling system TW573270B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
TW91121071A TW573270B (en) 2002-09-13 2002-09-13 Multiple constrains planning and scheduling system
JP2003142433A JP2004110767A (en) 2002-09-13 2003-05-20 Scheduling system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW91121071A TW573270B (en) 2002-09-13 2002-09-13 Multiple constrains planning and scheduling system

Publications (1)

Publication Number Publication Date
TW573270B true TW573270B (en) 2004-01-21

Family

ID=32294708

Family Applications (1)

Application Number Title Priority Date Filing Date
TW91121071A TW573270B (en) 2002-09-13 2002-09-13 Multiple constrains planning and scheduling system

Country Status (2)

Country Link
JP (1) JP2004110767A (en)
TW (1) TW573270B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7035704B2 (en) 2004-06-30 2006-04-25 Powerchip Semiconductor Corp. Capacity management system and method
CN104700157A (en) * 2015-02-03 2015-06-10 北京理工大学 Cross-cell workpiece production path search method considering limited transportation capacity
CN110826949A (en) * 2018-08-08 2020-02-21 北京京东振世信息技术有限公司 Capacity control implementation method and device
CN111694330A (en) * 2019-03-15 2020-09-22 西门子股份公司 Method and system for automatically managing buffer system

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111489048A (en) * 2020-02-18 2020-08-04 深圳坤湛科技有限公司 Method and system for matching requirements and productivity of shoe manufacturing enterprise
CN111915139B (en) * 2020-07-04 2023-11-14 广东科龙模具有限公司 Pushing type high-efficiency high-accuracy intelligent production scheduling algorithm and information recording medium
CN113298428A (en) * 2021-06-18 2021-08-24 成都普朗克科技有限公司 Automatic production scheduling method suitable for discrete industry
CN114742662A (en) * 2022-04-15 2022-07-12 卡奥斯工业智能研究院(青岛)有限公司 Production management method, production management device, electronic device, and storage medium
CN118068794B (en) * 2024-04-19 2024-07-05 北京谷器数据科技有限公司 Production management system and method based on MES intelligent manufacturing

Family Cites Families (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2518155B2 (en) * 1993-06-28 1996-07-24 日本電気株式会社 Parts information system
JPH09319809A (en) * 1996-05-29 1997-12-12 Sony Corp Material supply management system
JP2000122705A (en) * 1998-10-16 2000-04-28 Zexel Corp Production controller
JP2002074115A (en) * 2000-06-14 2002-03-15 Daito Seiki Co Ltd Apparel production/distribution management system using information system
JP2002073145A (en) * 2000-08-28 2002-03-12 Matsushita Electric Works Ltd Process designing method for product made to order
JP2002183544A (en) * 2000-12-13 2002-06-28 Nec Corp Ordering/accepting method and ordering/accepting system for purchase
JP2004537772A (en) * 2001-01-29 2004-12-16 マニュギスティックス・インコーポレイテッド System and method for allocating supply of critical material components and manufacturing capacity
JP2002259778A (en) * 2001-02-28 2002-09-13 Kuon System:Kk Medical material management system and method
JP2002269400A (en) * 2001-03-12 2002-09-20 Juken Sangyo Co Ltd On-line order placement/receipt processing method and system
JP2002279236A (en) * 2001-03-16 2002-09-27 Mitsubishi Materials Corp System and method for procuring purchased articles
JP2002279244A (en) * 2001-03-19 2002-09-27 Juken Sangyo Co Ltd Simplified order receiving/placing method and system therefor
JP2002373191A (en) * 2001-06-14 2002-12-26 Ntn Corp Wide area factory production managing system
JP3985996B2 (en) * 2001-08-21 2007-10-03 株式会社日立製作所 Automatic delivery date inquiry system, method, and program
JP2003157308A (en) * 2001-11-20 2003-05-30 Nikko Materials Co Ltd Recycle production control system for sputter chamber part
JP2004118834A (en) * 2002-09-04 2004-04-15 Mutoo Seiko Kk Production control system

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7035704B2 (en) 2004-06-30 2006-04-25 Powerchip Semiconductor Corp. Capacity management system and method
CN104700157A (en) * 2015-02-03 2015-06-10 北京理工大学 Cross-cell workpiece production path search method considering limited transportation capacity
CN104700157B (en) * 2015-02-03 2018-10-09 北京理工大学 A kind of across unit work piece production method for searching path considering that transport capacity is limited
CN110826949A (en) * 2018-08-08 2020-02-21 北京京东振世信息技术有限公司 Capacity control implementation method and device
CN111694330A (en) * 2019-03-15 2020-09-22 西门子股份公司 Method and system for automatically managing buffer system

Also Published As

Publication number Publication date
JP2004110767A (en) 2004-04-08

Similar Documents

Publication Publication Date Title
Koh et al. Managing uncertainty in ERP-controlled manufacturing environments in SMEs
US7933793B2 (en) Constraint-based production planning and scheduling
US20060212323A1 (en) Production management system
TW200410108A (en) Main production schedule managing system and method
CN101329746A (en) System and method for automatically arranging production plan
US20050209732A1 (en) Decision support system for supply chain management
US20050065830A1 (en) System and method for the acquisition and analysis of data for print shop performance evaluation and adjustment
TW573270B (en) Multiple constrains planning and scheduling system
JP5028991B2 (en) Manufacturing plan creation system and manufacturing plan creation method
EP2610696A1 (en) Process design/production planning device
JP2019008501A (en) Production managing system and production managing method
Subash Babu Strategies for enhancing agility of make‐to‐order manufacturing systems
AU769097B2 (en) System and method of scheduling manufacturing resources
JP2009289056A (en) Device for supporting personnel arrangement planning
Azzahra et al. The Accounting Information Systems Of Conversion Cycle (Raw Materials, Labor And Overhead) Special In The Pharmaceutical Industry
JP2009134399A (en) Sales production planning method, sales production planning system and computer program
TW200410109A (en) Production capability simulating system and method
CN111898914A (en) Enterprise manufacturing and operating system and storage medium
Sarkar et al. A simple case study of material requirement planning
JP5793449B2 (en) Production plan creation device, production plan creation system, and production plan creation program
JP2010244228A (en) Support method for efficiency promotion of supply chain
JP2008015873A (en) Producible limit planning system and method
JP5068845B2 (en) A method and system for integrated production management with full development of core management process using management process matrix table
JP4318162B2 (en) Production schedule planning management method and production schedule planning management program
JP2004292101A (en) System and method for supporting order processing

Legal Events

Date Code Title Description
GD4A Issue of patent certificate for granted invention patent
MM4A Annulment or lapse of patent due to non-payment of fees