TW461932B - Quick construction method for multiple-floor building and form employed in the method - Google Patents

Quick construction method for multiple-floor building and form employed in the method Download PDF

Info

Publication number
TW461932B
TW461932B TW90109848A TW90109848A TW461932B TW 461932 B TW461932 B TW 461932B TW 90109848 A TW90109848 A TW 90109848A TW 90109848 A TW90109848 A TW 90109848A TW 461932 B TW461932 B TW 461932B
Authority
TW
Taiwan
Prior art keywords
formwork
template
floor
building
scope
Prior art date
Application number
TW90109848A
Other languages
Chinese (zh)
Inventor
Nien-Hung Lai
Original Assignee
Lai Nien Hung
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Lai Nien Hung filed Critical Lai Nien Hung
Priority to TW90109848A priority Critical patent/TW461932B/en
Application granted granted Critical
Publication of TW461932B publication Critical patent/TW461932B/en

Links

Abstract

This invention of quick construction method for multiple-floor building and form employed in the method speeds up the construction process through its original form structure that allows concrete construction of the upper level before the concrete of its under level becomes dry and stable. Besides besides saving time, this method will improve integral strength and quake-resistance of the building as well for it betters the concrete bonding.

Description

461932 五、發明說明(1) 本發明係關於一種多樓層R C建築快速施工法及其模板 結構,進一步,而言,尤指一種不需等待混凝土結構乾固即 可更於其上構建上層建築結構之施工法及其施工所使用的 模板結構者。 【背景說明】461932 V. Description of the invention (1) The present invention relates to a rapid construction method of a multi-story RC building and its formwork structure. Furthermore, in particular, it particularly refers to a superstructure structure that can be constructed thereon without waiting for the concrete structure to dry. The construction method and the formwork structure used in construction. [Background note]

目前一般RC (註:鋼筋混凝土)結構之多樓層建築在建 構樓層的混凝土結構時,其皆係先搭設支柱及外牆的鋼筋 和模板後灌注混凝土,等牆壁、支柱的混凝土凝固後,再 搭設更上樓層的鋼筋和模板,後再灌注混凝土,如此依序 施作建構各樓層;並於各樓層預留施作樓梯的空間,待各 内牆、樓層板之水泥漿凝固后,以灌漿方式在樓梯預定處 作出一傾斜底面,接著在傾斜底面上再架構模板,以形成 樓梯形狀空間,然後再二次灌漿形成樓梯。以上施工方式 雖能製得樓房的基本架構,卻存在著以下缺點: (1 ) 由,於該施工方法必須等待下樓層之牆壁、支柱及 樓地板的混凝土完全凝固且結構穩定後,才進一步進行更 上樓層的模板建構及灌注混凝土,而每一樓層的混凝土結 構完全凝固,約需費時二十天以上,致建築整體的施工期 長,且若建築的樓層數越多,其施工期越長,造成建商的 資金負擔沉重。At present, when multi-story buildings with general RC (Note: reinforced concrete) structures are used to construct concrete structures on floors, they are all constructed by placing pillars and external walls of reinforced steel and formwork, and then pouring concrete. After the concrete of the walls and pillars is solidified, they are erected. Reinforce the steel bars and formwork on the upper floor, and then infuse the concrete, so that each floor is constructed in order; and the space for the staircase is reserved on each floor. After the cement slurry of each interior wall and floor slab is solidified, it is grouted. An inclined bottom surface is made at the predetermined position of the stair, and then a template is formed on the inclined bottom surface to form a stair-shaped space, and then grouting is performed again to form a stair. Although the above construction methods can make the basic structure of the building, there are the following disadvantages: (1) The construction method must wait for the concrete of the walls, pillars and floor floor of the lower floor to completely solidify and the structure to be stable before proceeding further. Formwork construction and pouring concrete on the upper floor, and the concrete structure of each floor is completely solidified, which takes about 20 days or more, resulting in a long construction period for the entire building, and the more construction floors, the longer the construction period , Resulting in heavy financial burden on the builders.

(2) 其牆壁、支柱和各樓層板的混凝土係分次灌注而 成,其彼此間的吸著凝固力不佳(即耐震力差);倘若不肖 建商為趕工期,未等下一層的混凝土完全凝固,即搭建上 層模板及灌注混凝土,則此楝樓房的結構安全性則更令人(2) The walls, pillars and concrete of each floor are poured in stages, and their adsorption and solidification forces are not good (that is, the seismic resistance is poor); if the construction period is not met, the builders have not waited for the next floor. The concrete is completely solidified, that is, the upper formwork and the poured concrete are added, and the structural safety of this concrete building is even more impressive.

第4頁 461932 五、發明說明(2) 擔憂。 (3) 習見RC建築在施工時所使用之模板,歷年來多以 用木質板材釘製而成或採取鐵板切割而成,但由於木質模 板不耐久用,根據發明人實際經驗約經七至八個月使用後 ,即已不堪使用,且其製作及施工之複雜性及困難度均高 ,若無熟練及經驗豐富之技術人員施工,即難以勝任製作 及施工之工作,且木質模板表面粗糙凹凸不平,完工後之 外牆面,另需塗抹或喷塗水泥漿,使其外牆面整齊光滑, 故施工過程中,既費工又費事,增加建築及材料成本,更 增加了施工時間,對於建築業而言,時間就是金錢,施工 時間拖長,資金積壓s無形中造成嚴重負擔。 至於使用鐵板製作之模板,因為沒有標準尺寸規格, 有時將整塊鐵板隨便湊合使用,因為其笨重,故在大樓施 工時,吊掛作業上下起落相當費力,且危險性極高,這幾 年公共工程之施工安全性,備受媒體炒作,即為其主因。 再者_,一般如牆壁、圍牆之搭建,係由兩塊以上相同 的模板,並排後且預留一灌注空間,俾予以灌漿;然,該-各模板之外緣,使用鐵絲對向絞拉以固定模板,其灌注水 泥漿之空間是否等寬,必需——檢視並調整,所以其組裝 與施工,必將費時、費工且施工品質掌握不易。 (4 ) 一般如造橋、造屋建築工地,其模板之搭建,皆 由數支支撐樁支撐其模板,但由於建築工地並非一概平坦 的平地,而是凹陷或凸起的地勢,故一般建築業者在工地 施工時,均以普通的腳墊墊於該支撐樁底端,俾使該各支Page 4 461932 V. Description of Invention (2) Worry. (3) It has been learned that the formwork used by the RC building during construction has been nailed or cut with iron plates over the years. However, because the wood formwork is not durable, according to the actual experience of the inventor, it takes about seven to seven After eight months of use, it is unusable, and the complexity and difficulty of its production and construction are high. Without skilled and experienced technical personnel, it is difficult to be competent for production and construction, and the surface of the wooden formwork is rough The uneven surface, after the completion of the external wall, you need to apply or spray cement slurry to make the external wall neat and smooth. Therefore, during the construction process, it is labor-intensive and labor-intensive, increasing the cost of construction and materials, and increasing the construction time. For the construction industry, time is money, the construction time is prolonged, and the backlog of funds causes a serious burden. As for the formwork made of iron plate, because there is no standard size specification, sometimes the entire iron plate is used randomly. Because of its bulkiness, it is very laborious to lift up and down during construction, and it is extremely dangerous. The construction safety of public works over the past few years has been the subject of much media hype. Furthermore, generally, such as the construction of walls and fences, it is composed of two or more identical formwork, and a pouring space is reserved after the side by side, and the grouting is performed; however, the outer edges of the formwork are twisted with iron wires. With fixed formwork, whether the space for pouring cement slurry is the same width must be inspected and adjusted, so its assembly and construction will be time-consuming, labor-intensive, and difficult to grasp the construction quality. (4) Generally, such as bridge and house construction sites, the formwork is constructed by several supporting piles to support the formwork. However, since the construction site is not a generally flat land, but a depressed or raised terrain, general buildings When the operator is at the construction site, ordinary foot pads are placed on the bottom of the support pile to make the branches

第5頁 461932 五、發明說明(3) 撐樁腳頂抵該模板,而使模板達到理想的真平面。 (5 ) —般樓梯施工主要先以灌漿方式在預定空間處製 作出一傾斜底面,接著在傾斜底面上再架構模板,以形成 樓梯形狀空間,然後再二次灌漿形成樓梯。此等施工方式 雖能製得樓梯,但施工上有以下缺點: 1. 由於不同建築的設計,致不同建築内的樓梯規格不 一,而架構樓梯結構之模板為一般具固定規格的建築模板 ,彼此並無共通性,因此針對每一樓梯規格必須重新剪裁 模板以供使用,如此一來顯然相當費時不便,而且剪裁後 的模板通常無法再次重覆使用,明顯浪費資源,不合實用Page 5 461932 V. Description of the invention (3) The supporting feet abut against the template, so that the template reaches the ideal true plane. (5) —Generally, the construction of staircases is mainly made by sloping the floor at a predetermined space, then forming a template on the sloping floor to form a stair-shaped space, and then grouting again to form a staircase. Although these construction methods can produce stairs, the construction has the following disadvantages: 1. Due to the design of different buildings, the specifications of the stairs in different buildings are different, and the template for the staircase structure is generally a building template with fixed specifications. There is no commonality between each other, so the template must be re-cut for each staircase specification for use. This is obviously time-consuming and inconvenient, and the cut template cannot usually be reused again, which obviously wastes resources and is not practical.

〇 2. 當施工者拆除模板後,樓梯表面因粗糙而須以水泥 砂漿作細部整平(依實際泥作經驗得整平兩次),如此施工 上相當費時不便、浪費成本。 3. 樓梯整平後還需貼設磁磚,施工上多利用貼劑(如 洋菜粉加水調製而成者對各階樓梯逐一貼設磁磚,如此 施工費時不便,而且通常會有多人同時對一樓梯進行貼設 磁磚工作,以求在較短時間内完工,相對有多人同時踩踏 樓梯,其重量、壓力將對剛成型之樓梯結構造成負面影響〇 2. After the constructor removes the formwork, the stair surface must be leveled with cement mortar due to the rough surface (leveling twice based on the actual mud experience), which is quite time-consuming, inconvenient and costly. 3. Tiles need to be installed after the stairs are leveled up. Many patches are used in the construction (such as agar meal powder and water). The tiles are placed on each staircase one by one. This construction is time-consuming and inconvenient, and usually there are many people at the same time. Tile a staircase to complete the work in a short period of time. Relatively many people step on the staircase at the same time. The weight and pressure of the staircase will adversely affect the newly formed staircase structure.

,同時又影響到磁磚的附著力,容易造成磁磚脫落;一旦 磁磚脫落,除樓梯外觀不雅外,尚需一筆修繕費用,因此 並不合實際施工所需。 有鑑於此,本案發明人乃依據多年從事R C建築施工之 經驗,針對上述的種種缺失,不斷的研究改良,而終有一At the same time, it also affects the adhesive force of the tile, and it is easy to cause the tile to fall off. Once the tile falls off, in addition to the unsightly appearance of the stairs, a repair cost is required, so it is not practical for construction. In view of this, the inventor of this case is based on years of experience in R C building construction, and constantly researches and improves the above-mentioned shortcomings.

第6頁 461932 五、發明說明(4) 種RC建築簡便施工法及結構,仍非常卓越的創作完成。 【發明目的】 本發明之主要目的在於提供一種多樓層R C建築快速施 工法及其模板結構,其不需要等待各樓層的混凝土結構乾 固、穩定,即可立即進行更上樓層混凝土結構的建構施工 ,以大幅縮短工期,且各樓層的混凝土結構彼此結合性良 好,以提升整體強度及耐震度者。 本發明之次要目的在於提供一種多樓層RC建築快速施 工法及其模板結構,於壁面和樓層板及樓梯施工時,將磁 磚、大理石或花崗石等欲貼設於壁面及樓梯面之飾物,在 水泥灌注之前,即已貼合於模板上,故能於混凝土灌漿施 工時,即同步完成磁磚等表面飾物的貼設,故所花費的工 時及材料成本,相較而言較習用者低廉。 【實施例說明】 為使 貴審查委員對本發明之目的、功效及特徵有更 進一步之瞭解及認同,茲舉較佳之實施例,並配合圖式說 明於后: 本發明多樓層R C建築快速施工法係按以下步驟施工: 基地施作:請參閱第1圖,在建築的基礎施工時,即 在水泥基地(A ) 預埋複數個模栓(1 0 ),且各個模栓(1 0 )成 列配設於預定施設牆壁處,並使建築牆壁及立枉内之鋼筋 之根部預埋於基地(A)内,此時,牆壁之鋼筋於樓梯預定 施作處,預留一段橫向凸出,藉以於後續施作樓梯時與樓 梯之鋼筋相連接,且模栓(1 0 )之兩端頭凸出於基地(A ) 表Page 6 461932 V. Description of the invention (4) The simple construction methods and structures of RC buildings are still very outstanding. [Objective of the Invention] The main object of the present invention is to provide a rapid construction method for a multi-story RC building and a formwork structure thereof, which can immediately perform the construction of the concrete structure on the upper floor without waiting for the concrete structure on each floor to dry and stabilize. In order to greatly shorten the construction period, and the concrete structures of each floor are well combined with each other to improve the overall strength and seismic resistance. A secondary object of the present invention is to provide a rapid construction method for a multi-floor RC building and a template structure thereof. During wall and floor slab and stair construction, tiles, marble, or granite to be attached to the wall and stair surface The ornaments are already attached to the formwork before the cement is poured, so the surface ornaments such as tiles can be installed simultaneously during the concrete grouting construction, so the man-hours and material costs spent are relatively high. The user is cheap. [Explanation of the Example] In order for your review committee to have a better understanding and recognition of the purpose, effect and characteristics of the present invention, the preferred embodiment is given below, and illustrated in conjunction with the drawings: The multi-storey RC rapid construction method of the present invention The construction is performed according to the following steps: Base construction: Please refer to Figure 1. During the foundation construction of the building, that is, a plurality of mold bolts (1 0) are embedded in the cement base (A), and each mold bolt (1 0) is formed. The columns are arranged at the planned installation wall, and the roots of the steel bars in the building wall and the upright are pre-buried in the base (A). At this time, the steel bars in the wall are projected at the scheduled place of the stairs, and a section of horizontal protrusion is reserved. Therefore, it is connected with the reinforcement of the staircase when the staircase is subsequently constructed, and both ends of the mold bolt (1 0) protrude from the base (A).

第7頁 461932 五、發明說明(5) 面。 模板(tot立ΐ 2橫模板··在建築立柱間相對立向建構立 、板(2 0 )且立梃板(2 0 )底端利用模栓(丨〇 )露出 之兩端頭限制定位,藓以於相^偶栓U U ;蕗出基地(A ) 注混凝土之空間,同日^,在建箪:立模板(2 0 )間圍設灌 在支柱(6 0 )頂端横向鋪嗖产模^ (立複數根支柱(6 0 ), 撐橫模板(30)。 “核板(3°) ’以利用支柱(6〇)支 ,使狀2模板(3〇)頂緣空間縱橫交錯鋪設鋼筋 之Ξ筋此等鋼筋與相對二立模板(2〇)間 (35)。 乂錯呈網狀之若干網格内塞設支撐塊 内及參閱第2圖,在相對立模板(2〇)之間的空間 及第ϊί ϋ頂端灌注混凝土,以形成第一樓層之牆壁 夂第一樓層之樓層板。 如土 :請板、下樓層了1緣之橫模板及上樓層之橫模板 壁之立楛& f \,在混凝土未乾固前,即可於第一樓層牆 在ϋΪΪ( )上緣建構第二樓層牆壁之立模板(2〇),並 撐樓層也ί 1頂緣橫設橫模板(3〇),而利用支撐塊(35)支 柱(6〇S)頁緣之橫模板(30),再於橫模板(30)頂緣豎立支 、)’以支撐建構第三樓層之橫模板(30)。 模板及設鋼筋、灌滎、建構立模板、下樓層頂緣之橫 i a i上樓層之橫模板等步驟,即可一一建構所f: Μ I # 樓層板及牆壁直至頂樓(如第4ffi戶斤示)。建構所需的各樓 拆模待各樓層樓層板、牆壁之混凝土乾固且結構強Page 7 461932 V. Description of the invention (5). Formwork (tot stand 2 horizontal formwork......... Moss is used for the formation of the UU; the base (A) is filled with concrete. On the same day ^, the construction formwork (20) is surrounded by irrigation at the top of the pillar (60). (A plurality of pillars (60) stand up and support the formwork (30). "Nuclear board (3 °) 'uses the support (60) to support the top edge space of the form 2 formwork (30) in a crisscross pattern. Reinforcement of these rebars and the opposite two-dimensional formwork (20) (35). A number of grids are staggered into the support block and referring to Figure 2, between the opposite formwork (2) The concrete space and the top of the first floor are filled with concrete to form the wall of the first floor and the floor slab of the first floor. Such as soil: Please slab, a horizontal formwork with a margin on the lower floor and a vertical formwork on the upper floor. f \, before the concrete is dry, you can construct the vertical formwork (20) of the second floor wall on the upper edge of ϋΪΪ () on the first floor wall, and support the floor and set a horizontal mold on the top edge. (30), and use the horizontal block (30) of the support block (35) pillar (60S) page edge, and then erected on the top edge of the horizontal form (30) to support the horizontal template of the third floor. (30). Formwork and setting of reinforcing bars, irrigation, construction of standing formwork, horizontal iai on the top edge of the lower floor, and horizontal formwork on the upper floor can be constructed one by one f: Μ I # floor boards and walls to the top floor (such as The 4ffi households are shown). Demolish the formwork required for each floor until the concrete of the floor slabs and walls on each floor is dry and strong in structure.

第8頁 461932 五、發明說明(6) 拆除各立模板(2〇)、支撐柱(60)及橫模 度穩定後,始 板(3 〇 ) 〇 建構樓梯:在各樓層起*„ , 樓層得以連通。 層板之間,施工建構樓梯,以使名 經執行前述步驟,〜 構,只需再對建築内 I^建構元成建築物的基本架 以的施作’本發明不需要等待各 本發明可於短時間内,快过士 ^整體建名而§ 產業價i 有效降低資金積壓,而具極高的 #4· * ^述爿05壁之立模板(2 〇 )的架構方法,係先於基地(A ) 氧應心壁處等距預埋適量的模栓(1〇),請參閱第5圖,該 模栓(1 0 )係概呈u型之桿體,其中段埋設於基地(A)内, 而兩端分別為螺紋段(π )並同向彎延凸伸於基地(A)上方 ,二立模板(2 0 )分別立設於該各螺紋段(11 )之間,且立模 板(2 0 )緣邊分別向外彎延形成一邊條(2 1 ),該邊條(2 1 )外 緣邊抵靠該螺紋段(1 1 )内側’該螺紋段(1 1 )於該邊條(2 1 ) 頂緣依序樞穿壓制塊(1 2 )、墊圈(1 3 )並鎖接一螺帽(1 4 ), 據螺帽(1 4 )迫緊壓制塊(1 2 )’以科用壓制塊(1 2 )壓制該邊 條(2 1 ),以定位相對峙之二立模板(2 0 ),避免相對立模板 (2 0 )彼此底端間之間距外擴變形者;又,請參閱第6圖, 該立模板(2 0 )係概呈矩形之板體,該各邊條(2 1 )分別凸設 於該立模板(2 0 )同侧緣邊,且該邊條(2 1 )徑向穿設複數個Page 8 461932 V. Description of the invention (6) After removing the standing formwork (20), supporting columns (60) and the transverse modulus, the starting plate (30) is constructed. ○ Constructing the stairs: starting from each floor *, floor Between the floors, construction and construction of stairs, so that the classics to perform the aforementioned steps, ~ structure, only need to apply the basic structure of the building in the building, the invention does not need to wait for each In the short time, the present invention can quickly surpass the overall name and § industry price i effectively reduce the backlog of funds, and has a very high # 4 · * ^ description 爿 05 wall standing template (200) architecture method, An appropriate amount of mold bolts (10) are equidistantly embedded at the oxygen core wall before the base (A). Please refer to Fig. 5. The mold bolts (10) are generally U-shaped rods with a middle section embedded. Inside the base (A), the two ends of which are respectively thread sections (π), and are curved and projected above the base (A) in the same direction, and two standing templates (20) are respectively arranged on the thread sections (11); And the edge of the riser plate (2 0) is respectively bent outward to form a side strip (2 1), and the outer edge of the edge strip (2 1) abuts against the inside of the thread segment (1 1) 'the thread (1 1) The top edge of the side strip (2 1) is pivoted through the pressing block (1 2), the washer (1 3) in sequence and locked with a nut (1 4), and the nut (1 4) is tightly tightened. The pressing block (1 2) 'uses the pressing block (1 2) to press the edge strip (2 1) to locate the opposite vertical template (2 0), and avoids the opposite vertical template (2 0) between the bottom ends of each other. Those whose distance is expanded and deformed; see also FIG. 6, the vertical formwork (20) is a generally rectangular plate, and the edges (2 1) are respectively protruding from the vertical formwork (2 0). A side edge, and a plurality of the edge strips (2 1) are radially arranged

第9頁 461932Page 9 461932

五、發明說明(7) ’據使側向鄰靠之立模板(2〇)得以藉結合螺栓 側向)ίϊ ^(2丨2)後鎖接一螺帽(23),俾供結合彼此 縱之複數個立模板(2〇)者;該立模板(2〇) 一側等距 兮設有肋條(24),該肋條(24)與該邊條(21)位於 之同側,且該肋條(24)緣面與該邊條(21)緣 ί於同一平面為較佳’至於該肋條(24 )數目,可依據大 去,、小不同立模板(2〇)規格之長、寬面積而選定之,再 該立模板(2 0 )穿設複數個貫孔(2 5 ),該貫孔(2 5 )位於 该肋條(24 )所分隔區塊之中央處為較佳者。 ^ 上、下相鄰之二立模板(20)之間夾設有退模條(40), 睛參閱第7圖,該退模條(40)緣邊同向凸設有邊壁(42 ), 該各邊壁(42 )依據其長度分別貫穿一至數個不等之另栓孔 Μ4),據以利用結合螺栓(22)穿套該另拴孔(44)及相鄰立 模板(2 0 )之栓孔(2 1 2 )後鎖接一螺帽(2 3 ),俾供結合該退 模條(40)與鄰靠之立模板(2〇)者;該退模條(4〇)於該邊壁 (4 2 )之同側面等距凸設複數個栓座(4 6 ),該检座(4 6 )貫穿 有螺孔( 46 2 ),以配合螺設退模螺栓(48),俾供旋鎖該退 模嫘栓(4 8 )抵推混凝土牆,以促使該退模條(4㈧與牆壁之 混凝土結構分離者。 請配合參閱第5圖’兩相對之立模板(2 0 )間設有定厚 管(2 8 ),該定厚管(2 8 )兩端壁分別與該各立模板(2 〇 )相抵 靠’據以限定兩相對立模板(2 〇 )之間距,且該定厚管(2 8 ) 長度恰與建築所設計之牆壁厚度相同’俾供簡化模板建構 工序者’兩相對立模板(2 0 )之外側分別立設具有相當長度V. Description of the invention (7) 'According to the side-by-side standing template (20), the bolts can be laterally combined with the bolts.' Ϊ (2 丨 2), a nut (23) is locked after the bolts are used to bond each other vertically. A plurality of vertical formwork (20); a rib (24) is equidistantly arranged on one side of the vertical formwork (20), the rib (24) is located on the same side as the side strip (21), and the rib (24) The edge surface and the edge of the edge strip (21) are preferably on the same plane. As for the number of the ribs (24), the length and width of the ribs (24) can be different according to the length and width of the different standing template (20). When selected, a plurality of through holes (2 5) are penetrated through the standing template (20), and the through holes (2 5) are preferably located at the center of the block partitioned by the rib (24). ^ A mold release strip (40) is sandwiched between the two adjacent vertical formwork plates (20). See Figure 7 for details. The edge of the mold release strip (40) is provided with a side wall (42) protruding in the same direction. The side walls (42) pass through one to several other bolt holes (M4) of different lengths according to their lengths, so that the bolts (22) are used to cover the other bolt holes (44) and adjacent risers (20). ) After the bolt hole (2 1 2) is locked with a nut (2 3), for the combination of the ejector strip (40) and the adjacent standing template (20); the ejector strip (40) A plurality of bolt sockets (4 6) are equidistantly protruded from the same side of the side wall (4 2), and the inspection socket (4 6) is penetrated with screw holes (46 2) to cooperate with the screwing of the ejector bolt (48).俾 For screwing the ejector bolt (4 8) against the concrete wall to push the ejector strip (4㈧ apart from the concrete structure of the wall. Please refer to Figure 5 'two opposite formwork (2 0 ) Are provided with fixed-thickness pipes (2 8), and the two end walls of the fixed-thickness pipes (2 8) are respectively abutted against the respective standing templates (20), thereby defining the distance between two opposing standing templates (20), And the length of the fixed-thickness pipe (2 8) is exactly the thickness of the wall designed by the building Same 'template to serve for a simplified construction of the step by' two opposite template (20) are erected outside of considerable length

第10頁 4 6 1 9 3 2 五、發明說明(8) 之壓條(2 6 ) ’該壓條(2 6 )徑向貫穿複數個過孔(2 6 2 ),該 壓條(2 6 )壓靠著該邊條(2 1 )、該肋條(2 4 ),該定厚管(2 8 ) 内軸樞一連結桿(29),該連結桿(29)兩端分別延伸於該貫 孔(2 5 ),並於端面軸向凹設螺孔(2 9 2 ),據使螺栓(2 6 4 ) 自該屢條(26)外側軸入該過孔(26 2 )與該螺孔(2 9 2 )螺固 相接’俾供限制該立模板(2 〇 ),並撐持提高該立模板(2 〇 ) 抵抗混凝土毁液壓力之強度者。 另’請參閱第8圖,在二垂直鄰接之立模板(2〇)與立 模板(2 0 )間’垂設有外角模條(2 1 〇 )相連結,該外角模條 (21 0)具有二接板(21 02) ’該各接板(21 〇2)分別配合立模 板(2 0 )之該栓孔(2 1 2 )穿設有結合孔(2 1 〇4 ),據此於該接 板(2 1 0 2 )穿套該結合螺栓(2 2 ),藉以分別結合該外角模條 (2 1 0 )與鄰接之二立模板(2 〇 ),俾相鄰接之二立模板(2 〇 ) 彼此垂直結合者。橫模板(3 0 )的架構方法,係於建築設計 所設定樓層板咼度所在立模板(2 〇 )處以内角模條(5〇 )橫尚 結合橫模板(3 0 )與該立模板(2 〇 )(如第1至4圖),該橫$莫板 (3 0 )緣邊凸設有邊條(3 1 ) ’而得以藉由結合螺栓(3 2 )軸穿 該邊條(3 1 )與螺帽(3 3 )螺接,以使複數個相鄰之該橫模板 (3 0 )彼此結合及該橫模板(3 〇 )與該内角模條(5 〇 )相結合者 ’該橫模板(3 0 )於該邊條(3 1 )之同側面等距縱橫交錯凸設 有肋條(34 )’俾供強化該橫模板(30 )之強度者;請參閱第 9圖,該内角模條(5 0 )係矩形管體(或為方形管體),令該 内角模條(5 0 )相鄰之二管壁分別為第一管壁(5 2 )、第二管 壁(54) ’該第一管壁(52)於緊鄰該第二管壁(54)之緣邊處Page 10 4 6 1 9 3 2 V. The strip (2 6) of the description of the invention (8) 'The strip (2 6) passes through a plurality of via holes (2 6 2) radially, and the strip (2 6) is pressed against A connecting rod (29) is pivoted on the inner axis of the fixed-thickness tube (2 8), and the two ends of the connecting rod (29) extend from the through hole (2). 5), and a screw hole (2 9 2) is axially recessed on the end face, and the bolt (2 6 4) is axially inserted into the through hole (26 2) and the screw hole (2 9) from the outside of the multiple strip (26). 2) The screw-solid phase connection is used to limit the vertical formwork (20), and support those who increase the strength of the vertical formwork (20) to resist the pressure of the concrete liquid. Also, please refer to FIG. 8, between two vertically adjacent vertical formwork plates (20) and the vertical formwork plates (20), an external corner mold strip (2 1 0) is connected perpendicularly, and the external corner mold strip (21 0) There are two connecting plates (21 02) 'The respective connecting plates (21 〇2) are respectively matched with the bolt holes (2 1 2) of the riser plate (2 0), and are provided with a coupling hole (2 104). The connecting plate (2 1 0 2) passes through the coupling bolt (2 2), thereby respectively combining the outer corner mold strip (2 1 0) and the adjacent two vertical formwork (20), and the adjacent two vertical formwork (2) Those who are perpendicular to each other. The structural method of the horizontal formwork (30) is based on the internal formwork (50) of the vertical formwork (20) where the floor slab angle set by the architectural design is set. The horizontal formwork (30) and the vertical formwork (30) 2 〇) (as shown in Figures 1 to 4), the edge of the horizontal plate (3 0) is convexly provided with a side strip (3 1) ', so that the side strip (3 1) screwing with the nut (3 3), so that a plurality of adjacent horizontal templates (30) are combined with each other, and the horizontal template (30) and the internal corner strip (50) are combined The horizontal template (30) is provided with ribs (34) 'on the same side of the side strip (31) at equal intervals, and is provided with a rib (34)' for strengthening the strength of the horizontal template (30); please refer to FIG. 9, the inner corner The mould strip (50) is a rectangular pipe body (or a square pipe body), so that the two adjacent pipe walls of the inner corner mould strip (50) are a first pipe wall (52) and a second pipe wall (54). ) 'The first pipe wall (52) is immediately adjacent to the edge of the second pipe wall (54)

第11頁 461932 五、發明說明(9) 開設長形之缺口( 5 6 ),該第一、二管壁(5 2 )( 5 4 )分別貫穿, 複數個栓孔( 5 2 2 )( 5 4 2 ),據此穿套該結合螺栓(32),以分-別結合該内角模條(50)與該立模板(20)、該橫模板(3〇)( 如第1 0圖所示)’俾該立模板(2 0 )與該橫模板(3 〇 )彼此垂. 直結合者。 該橫模板(30)頂面依據樓層板面積於適當處設置該支 樓塊(35)(如第1圖、第11圖),該支撐塊(3 5)恰位於^橫--模板(3 0 )之肋條(3 4 )對應處,該支撐塊(3 5 )周邊得以鐵線 (3 5 4 )纏繞箍套,並與鋼筋(c )焊接定位,待灌注混凝土 — 時’該支撐塊(3 5 )不虞受混凝土之流動影響位移,且該支 撐塊(3 5 )之南度與建築所設定之樓層板厚度相同,俾供支 撐位於樓層板頂緣之該橫模板(3〇)者;該支撐塊(35)徑向 貫穿有一個或一個以上之嵌孔(3 5 2 ),藉以在灌漿時供混 凝土渗入’俾該支撐塊(3 5 )與混凝土固結定位,該支撐塊 (3 5 )可選自塑'鋼、金屬、石材、水泥塊·....·等堅硬性質 材,且該支撐塊(3 5 )係斷面為矩形或圓形(如第1 2圖)或其 ' 它幾何形狀之柱體,而位於樓層板下緣之該橫模板(3 〇 )底 — 緣藉複數根該支柱(6 0 )支撐,該支柱(6 〇 )設於相鄰之該各 橫模板(3 0 )彼此相對鄰接之對應處,且該各支撐塊(3 5 )相 對應處亦設有該支柱(60)。 . 請參閱第2圖及第1 3圖,該支柱(6 〇 )頂端套設一承座「 (6 1 ) ’該承座(6 1 )頂端兩侧分別立設一護板(6丨2 ),並於 該各護板(6 1 2 )間形成一承槽(6 1 4 ),該承座(6 1 )底端端 面於中央部份配合該支柱(6 0 )斷面軸向挖設一套孔(6 1 6 )Page 11 461932 V. Description of the invention (9) A long notch (56) is opened, the first and second pipe walls (5 2) (5 4) are respectively penetrated, and a plurality of bolt holes (5 2 2) (5 4 2), according to this, the sleeve bolt (32) is sleeved to combine the inner corner mold strip (50) with the vertical template (20) and the horizontal template (30) separately (as shown in FIG. 10). ) '俾 The standing template (20) and the horizontal template (30) are perpendicular to each other. The top plate of the horizontal formwork (30) is provided with the branch block (35) (as shown in Figures 1 and 11) at the appropriate place according to the floor slab area, and the supporting block (3 5) is located at ^ horizontal-formwork (3 Corresponding to the ribs (3 4) of 0), the periphery of the support block (3 5) can be wound around the hoop by iron wire (3 5 4), and welded and positioned with the steel bar (c). 3 5) Displacement is not affected by the flow of concrete, and the south of the support block (3 5) is the same as the thickness of the floor slab set by the building, so as to support the horizontal formwork (3) at the top edge of the floor slab; The support block (35) is radially penetrated with one or more embedded holes (3 5 2), so that the concrete can be infiltrated during grouting. 支撑 The support block (3 5) and the concrete are fixed and positioned, and the support block (3 5) It can be selected from hard materials such as plastic, steel, metal, stone, cement block, etc., and the supporting block (3 5) is rectangular or circular in cross section (as shown in Figure 12) or It's a cylinder of other geometric shapes, and the bottom of the horizontal formwork (30) located at the lower edge of the floor slab—the margin is supported by a plurality of pillars (60), and the pillars (60) are set Pillars (60) are also provided at the corresponding positions of the adjacent horizontal template (30) adjacent to each other, and at the corresponding positions of the support blocks (35). Please refer to FIG. 2 and FIG. 13. A support is provided on the top of the pillar (60), and (6 1) 'two sides of the top of the support (6 1) are respectively provided with a protective plate (6 丨 2 ), And a bearing groove (6 1 4) is formed between the protective plates (6 1 2), and the bottom end surface of the bearing seat (6 1) is matched with the pillar (60) in the central part to dig axially Set a set of holes (6 1 6)

第12頁 4 6 1 93 2 五、發明說明(ίο) ’該支柱(60)末端軸伸插套於該套孔(616) 内,樓層板頂 、底緣之該各橫模板(3 0 )分別於夾設於二夾條(3 6 )之間, 位於樓層板底緣之該夾條(3 6 )靠搭於該承座(6 1 ),並嵌靠 通過該承槽(6 1 4 ),俾該支柱(6 0 )支承該橫模板(3 0 ),而 位於樓層板頂緣之該夾條(3 6 )則襯墊支承著上一樓層之支 柱(60);該支柱(60)係斷.面呈方形(或圓形)之柱狀體(或 管狀體),其係選自木材、塑膠、電木、金屬......等材 質製成,該支柱(6 0 )徑向等距貫穿複數個插孔(6 2 ),相鄰 之二支柱(6 0 )間靠設有連結爪(6 3 )、連結釘(6 4 ),據以連 結定位二支柱(6 0 ),該連結爪(6 3 )具有四根呈輻射狀向外 延伸之鉤體(631 ),該各鉤體(631)末端分別側向凸設一 鉤部(6 3 1 1 ),該鉤部(6 3 1 1 )分別插入相鄰二支柱(6 〇 )之該 插孔(6 2 ),該連結釘(6 4 )係為桿狀體,其兩端同向凸設有 插塊(6 4 1 ),該各插塊(6 4 1 )分別插入相鄰二支柱(6 〇 )之 該插孔(6 2 ),俾供定位連結相鄰之二支柱(6 〇 ),以避免該 支柱(6 0 )歪斜傾倒者;該支柱(6 〇 )於底端墊設有二彼此相 疊之調節墊(6 5 ),該各調節墊(6 5 )於相疊靠之接觸面係分 別形成斜面(6 5 2 ),據使該各調節墊(6 5 )彼此得以相對或 相背位移,俾調節該支柱(6 〇 )頂端高度,以支撐該橫模板 (3 0 )者;另,請參閱第1 4圖’二調節墊(6 5,)彼此接觸之 斜面( 6 5 2,)可相對凹設有半圓形缺口( 6 54,),據使該缺口 (654’)相對合並配合插置定位塊(Mg’)於該缺口(654,), 俾相對卡制定位該調節墊(6 5 ’) 者。 由於建築所設計之樓層挑高並不儘相同,若為因應不Page 12 4 6 1 93 2 V. Description of the invention (') The end of the pillar (60) is inserted into the hole (616), and the horizontal formwork (30) at the top and bottom edges of the floor The clip strips (3 6) located between the two clip strips (3 6), which are located at the bottom edge of the floor board, rest on the bearing seat (6 1), and are inserted into the slot (6 1 4). ), The pillar (60) supports the horizontal formwork (30), and the clamp strip (36) located on the top edge of the floor plate supports the pillar (60) of the previous floor; the pillar (60) ) Is broken. A columnar body (or a tubular body) with a square (or circular) surface is made of wood, plastic, bakelite, metal, etc. The pillar (6 0 ) Radially spaced through a plurality of sockets (6 2), connecting claws (6 3) and connecting nails (6 4) are arranged between two adjacent pillars (60), and the two pillars (6 0), the connecting claw (6 3) has four hook bodies (631) extending radially outward, and a hook portion (6 3 1 1) is protruded laterally from the end of each hook body (631), and The hooks (6 3 1 1) are respectively inserted into the jacks (2) of the adjacent two pillars (60). 6 2), the connecting nail (6 4) is a rod-shaped body, and both ends of the connecting nail (6 4 1) are convexly protruded in the same direction, and the insertion pieces (6 4 1) are respectively inserted into two adjacent pillars (6 〇) of the socket (62), for positioning and connecting the adjacent two pillars (60), to avoid the pillar (60) skewed and dumped; the pillar (60) is provided with two The adjustment pads (6 5) stacked on each other, and the adjustment pads (6 5) form inclined surfaces (6 5 2) on the contact surfaces that overlap each other, so that the adjustment pads (6 5) can face each other or Displace each other, and adjust the height of the top of the pillar (60) to support the horizontal template (30). Also, please refer to Fig. 14 'the inclined surfaces (6 5) where the two adjustment pads (6, 5) contact each other. 2,) A semi-circular notch (6, 54) can be relatively concave, according to which the notch (654 ') is relatively merged with the insertion positioning block (Mg') in the notch (654,). The adjustment pad (6 5 '). Because the height of the floors designed by the building is not the same,

第13頁 461932 ------------ 五、發明說明(11) 〜 --- =^層挑南而分別製作多種不同規格長度的支柱(6 〇)顯不 2 σ經濟效益,此時’若建築設計之樓層挑高大於該支柱 )長度’而致該支杈(6〇)之規格長度不足以支撐該橫模 板(3 0 )時’得以藉由接續器(7 0 )(如第1 5圖及第1 6圖)於支 柱(6〇_)末端連結另—根相同規格長度的支.柱(60)或規格長 度較短的支柱(6 0 ’) ’該接續器(70 )適用於管狀之該支柱 (6\) ’該接續器(70) —端徑向縮束形成一凸體(72),其另 一端端面中央部份軸向挖設一嵌槽(7 4 ),該凸體(7 2 )插設 於一支柱(6 0 )頂端管内’而另一支柱(6〇 )底端則嵌插於該 敬槽(74)内’俾供連結二支柱(6〇)者;另,請參閱第17圖 ’其係顯示另一種可通用於連結、接續實心柱狀或管狀支 柱(6 0 )之接續器(7 0 ’),該接續器(7 0 ’)兩端端面分別於 中央部份凹設一嵌槽(74,),且該各嵌槽(74’)間藉——隔 ^(76,)分隔而不連通,據使二支柱(6〇)末端分別嵌插於 該各嵌槽(7 4 ’)内,俾供連結二支柱(6 〇 )者。 續參閱第18、19及20圖所示’樓梯之建構施工法包括 下列步驟: 預埋定位釘:建築樓層板於灌漿時,即在鄰近樓梯設 置處’預先埋設概呈U形之定位釘(8 7 ),且該定位釘(8 7 ) 兩端穿出樓層板頂緣面外露。 標線:在牆面(Β )預定位置,針對欲施設樓梯所在位 置與傾斜角度,預先標記墨線。 設相對之接板(8 1 )( 8 2 ):對應標線步驟所標記墨線, 傾斜地設置二接板(8 1 ) ( 8 2 ),並使二塊接板(8 1 ) ( 8 2 )彼此Page 13 461932 ------------ V. Description of the invention (11) ~ --- = ^ layer to pick the south and make a variety of different specifications of the length of the pillars (60) is significantly less than 2 σ economy Benefit, at this time, 'if the floor height of the architectural design is greater than the length of the pillar), and the length of the branch (60) is not enough to support the horizontal formwork (30), it is possible to use the connector (70) ) (As shown in Figure 15 and Figure 16) at the end of the pillar (60_) to connect another-the same length of the branch. Post (60) or shorter length of the pillar (60 0 ')' This connection The device (70) is suitable for the tubular support (6 \) 'the connector (70)-the radial end of the connector is reduced to form a convex body (72), and the central part of the end surface of the other end is axially excavated with an embedded slot ( 7 4), the convex body (7 2) is inserted into the top tube of one pillar (60), and the bottom of the other pillar (60) is inserted into the gutter (74) for connecting the two pillars (60)); also, please refer to FIG. 17 ', which shows another connector (7 0') which can be commonly used to connect and connect a solid columnar or tubular support (60). The connector (70) ') Ends of both ends A recessed groove (74,) is recessed in the central part, and the recessed grooves (74 ') are separated by _ (76,) and are not connected. According to this, the ends of the two pillars (60) are respectively inserted into Within each of these cavities (7 4 ′), there is a connection for two pillars (600). Continued to refer to Figures 18, 19, and 20, 'The construction method of the stairs includes the following steps: Pre-buried positioning nails: When the building floor slab is grouting, that is, near the stair setting,' pre-buried U-shaped positioning nails ( 8 7), and both ends of the positioning pin (8 7) are exposed through the top edge surface of the floor board. Marking line: Mark the ink line in advance at the predetermined position on the wall (B) according to the position and inclination angle of the stairs to be installed. Set the opposite connection plate (8 1) (8 2): corresponding to the ink line marked in the marking step, set the second connection plate (8 1) (8 2) obliquely, and make the two connection plates (8 1) (8 2) each other

第14頁 461932 五、發明說明(12) 相對者。 固設階梯模板(8 3 ):係將複數個階梯模板(8 3 )橫設在 相對之接板間(81 )(82),且使各階梯模板(83)以垂直地面 角度,或略呈内傾斜角度,依序升降排列。 . 固設托板角鐵(84):複數個托板角鐵(84)依序固設在 接板Ul)(82)下方’且使托板角鐵(84)左右相對者。 、设底層模板(8 5 ):將底層模板(8 5 )搭置在相對之托板 角鐵上(84),且底層模板(85)兩端與上、丁相鄰樓層板相 靠。如此’接板(8 1 ) ( 8 2 )、階梯模板(8 3 )、底層模板(8 5 ) 間便成了樓梯形狀之空間。 μ灌聚成型:在底層模板(8 5 )頂緣空間交錯鋪設竹節式 鋼筋(圖中未示)’且鋼筋與自牆壁内部延伸而出的鋼筋以 釣釘焊接聯結,而得以提升樓梯與牆壁之結合性,縱遇地 震亦不輕易斷離,而後將混凝土直接灌入前述樓梯形狀之 空間,俟混凝土乾固後即完成樓梯成型工作,在樓梯灌漿 成型出階梯平面同時’磁磚、大理石或花崗石等表面飾物 即可一次同步施工貼設。於此,由於該定位釘(8 γ )中段埋 s史於樓層板内,其兩端穿出樓層板進入樓梯之混凝土結構 內’而得以提高樓梯之定位,避免滑移者。: 而為達前.述施工步驟’係可藉接板(8丨)(8 2 )、階梯模 板(8 3 )、托板角鐵(8 4 )及底層模板(8 5 )的組合予以完成, 其中: 請配合參閱第2 1、2 2圖,該接板(8 1 )係可製成階梯狀 ’並藉螺栓(8 1 1 )將若干接板(8 1 )予以釘固在牆面(按,Page 14 461932 V. Description of the invention (12) The opposite. Fixed step template (8 3): a plurality of step templates (8 3) are horizontally arranged between the opposite connection plates (81) (82), and each step template (83) is at a vertical ground angle, or slightly The inclination angle is arranged in order. Fixing the bracket angle iron (84): A plurality of bracket angle irons (84) are sequentially fixed below the connecting plate Ul) (82) 'and the bracket angle irons (84) are opposite to each other. 1. Set the bottom formwork (85): place the bottom formwork (85) on the opposite angle bracket (84), and the two ends of the bottom formwork (85) are adjacent to the upper and lower adjacent floor boards. In this way, the space between the connection plate (8 1) (8 2), the step formwork (8 3), and the bottom formwork (8 5) becomes a staircase-shaped space. μ pouring and forming: staggered bamboo reinforcement bars (not shown) are staggered on the top edge space of the bottom formwork (85), and the steel bars and the steel bars extending from the interior wall are connected by fishing nails, so that the stairs and the wall can be lifted. Due to the combination, it is not easy to be disconnected in the event of an earthquake, and then the concrete is directly poured into the space of the aforementioned staircase shape. After the concrete is dried, the staircase forming work is completed, and the staircase is grouted to form a stepped surface. Granite and other surface ornaments can be applied simultaneously. Here, since the middle part of the positioning pin (8 γ) is buried in the floor slab, its two ends penetrate the floor slab into the concrete structure of the stair ', thereby improving the positioning of the stair and avoiding slippery persons. : In order to reach the front, the construction steps described above can be completed by the combination of the slab (8 丨) (8 2), the step formwork (8 3), the pallet angle iron (8 4), and the bottom formwork (8 5). Among them: Please refer to Figures 2 and 2 for cooperation. The connection plate (8 1) can be made into a stepped shape, and a plurality of connection plates (8 1) are nailed to the wall surface by bolts (8 1 1). (press,

第15頁 461932 五、發明說明(13) 一般室内樓梯的一侧大都貼靠於牆面),且令該接板(8 1 ) 呈傾斜狀’此外,該接板(8 1 )表面上對應每一階梯形狀固 設有接塊(812)(按,接塊可以製成角鐵形狀或是方鐵狀) ’另一接板(8 2 )係長板狀,其外側面靠接於該支柱(6 〇 )供 支抵在地面’而内侧面設有若干接塊(8 2 2 ),並使二接板 (81 ) (82)上的各接塊(8 1 2 ) ( 8 2 2 )左右相對;另,支柱(60) 的底端襯墊有二相對之該調節墊(65),以調節該支柱(6〇) 南度者。 該 (831) ( 822 ) ,依序 該 置成傾 設在接 煮,可 板角鐵 者。 該 之托板 ;而實 底層模 (85)與 以 階梯模板(83) ’藉此鎖接在 上,並且令各 排列者。 托板角鐵(84) 斜排列狀,例 板(81 )下方之 直_接使托板角 (84)乃平行相 底層模板(8 5 ) 角鐵(84)上, 際施工時,為 板(8 5 )上方另 混凝土接觸黏 上,相對之接Page 15 461932 V. Description of the invention (13) Generally, one side of the indoor staircase abuts on the wall surface), and the connecting plate (8 1) is inclined. In addition, the connecting plate (8 1) corresponds to the surface. Each stepped shape is fixed with a connection block (812) (press, the connection block can be made into an angle iron shape or a square iron shape) 'Another connection plate (8 2) is a long plate shape, and its outer side abuts against the pillar (6) The supply and support are on the ground, and a number of connecting blocks (8 2 2) are provided on the inner side, and each connecting block (8 1 2) (8 2 2) on the second connecting plate (81) (82) is provided. The left and right sides are opposite to each other. In addition, the bottom end of the pillar (60) is provided with two opposite adjustment pads (65) to adjust the pillar (60) south. The (831) (822), in turn, should be set to be tilted and set at the angle of the plate. The support plate; the solid bottom mold (85) and the step template (83) 'are thereby locked to the array, and each arrayer is arranged. The supporting plate angle iron (84) is arranged obliquely, and the straight under the example plate (81) is connected to the supporting plate angle (84) is a parallel phase bottom formwork (8 5) on the angle iron (84). It is a plate during the international construction. (8 5) The other concrete is glued on the top, and it is connected

係呈長板狀,其兩端各配設有二螺栓 接板(8 1 ) ( 8 2 )所設之相對接塊(8 1 2 ) 階梯模板(8 3 )垂直地面或略呈内傾斜 ,乃分別固設在接板(8 1 )( 8 2 )下方位 如對應階梯狀接板(8 3 )者,可直接固 牆面上’而對應另一長板狀接板(8 2 ) 鐵(8 4 )與接板(8 2 )結合,惟二側之托 對’且與階梯模板(8 3 )相距預定間距 係適當大小之長板體,供跨置在相對 據以與階梯模板(8 3 )相距適當間距者It is in the shape of a long plate, and two opposite ends of the two bolts (8 1) (8 2) are provided with opposite connection blocks (8 1 2), and the step template (8 3) is vertical or slightly inclined inward. Those which are respectively fixed below the splicing plate (8 1) (8 2) and corresponding to the stepped splicing plate (8 3) can be directly fixed on the wall surface, and correspond to another long plate-shaped splicing plate (8 2). (8 4) is combined with the connecting plate (8 2), but the supporting plate on the two sides is a long plate with a proper distance from the step template (8 3). 8 3) Those with proper spacing

提高底層模板(8 5 )的再利用性,可在 配設一概板(86) ’藉此避免底層模板 結。 板(81) (82)與階梯模板(83)、底層模To improve the reusability of the underlying template (85), a profile board (86) 'can be provided to avoid the knotting of the underlying template. Plate (81) (82), step template (83), bottom mold

第16頁 Λ 6 1 9 3 2 五、發明說明(14) 板(8 5 )間,恰構成一樓梯形狀之空間,故當在此空間内灌 注混凝土後,即可成型出預定之樓梯結構。 / 惟,一般室内樓梯雖多有一面靠牆者,但亦有兩面土 牆者,因此為適用於兩面靠牆之樓梯施工,前述實施 $ ,可將接板(8 1 )( 8 2 )均製作成階梯狀,並分別固&在^ 上’而接板(8 1 ) ( 8 2 )上仍固接有橫向之階梯模板(8 3 ),°面Page 16 Λ 6 1 9 3 2 5. Description of the invention (14) The space between the plates (85) is just a staircase-shaped space, so when concrete is poured into this space, a predetermined staircase structure can be formed. / However, although most indoor staircases have one person leaning against the wall, but there are also two people leaning against the wall, so for the construction of stairs with two leaning against the wall, the aforementioned implementation of $ can be used to connect the panels (8 1) (8 2). It is made into a step shape, and it is respectively fixed on the ^ ', and a horizontal step template (8 3) is still fixed on the splice plate (8 1) (8 2), ° surface

方配合有托板角鐵(84)與底層模板(85),據此得以構成I 梯形狀空間,並供灌注混凝土以形成樓梯結構。 而即使是二側不靠牆之樓梯結構,亦可將二相對之 板(8 1 ) ( 8 2 )製作成長形板狀,並使各接板(8丨)(8 2 )藉支柱 (60)支抵定位,而接板(81)(82)上同樣配接階梯模 、2板角鐵(84)及底層模板(85),如此構成樓結 ,並可供灌漿成型樓梯者。 傅工间 再者’一般樓梯、牆壁、樓層板在成型後, Ϊ ΪΪ磚ΪΐΐΪίΞ飾物以求美觀,但傳統先成型混凝 :更;對此,本發明提出良善的解…; $板(83)的内側面以雙面膠帶 設磁 圖,亦可貼設大理石碑、花尚石磚等),J 向樓梯結構空間,如此者况 :1 、占面(9 2 )朝 或大理石磚、花岗石二;灌漿,該磁磚(9〇) 拆除各模板後,便可同‘ ί 2 Ϊ混凝ί ?構結合定位,俟 梯模板U3)頂緣處對;t S,施工人員即可站立於該階 t h梯的平面鋪設水泥細沙漿與黏貼劑The supporting plate angle iron (84) and the bottom formwork (85) are matched with each other, thereby forming an I-ladder-shaped space and pouring concrete to form a staircase structure. And even if the staircase structure on the two sides does not lean against the wall, the two opposite plates (8 1) (8 2) can be made into a long plate shape, and each connecting plate (8 丨) (8 2) is borrowed by the pillar (60 ) Is supported and positioned, and the step plate, the two-plate angle iron (84), and the bottom formwork plate (85) are also connected to the connection plate (81) (82), thus forming a building knot, and it can be used for grouting stairs. Fu Gongjian again 'After the general staircase, wall and floor slabs are molded, they are decorated with ΪΪ ΪΐΐΪ bricks ΪΐΐΪ Ξ to be beautiful, but traditionally shaped first and coagulated: more; for this, the present invention proposes a good solution ...; $ 板 ( The inner side of 83) is set with magnetic tape with double-sided tape, and marble monuments, flower tiles, etc. can also be pasted), J-direction staircase structure space, in this case: 1, Zhan face (9 2) facing or marble tiles, Granite II; grouting, the tiles (90) can be combined with the '定位 2 Ϊ concrete ί structure after the removal of each template, the top edge of the ladder template U3); t S, the construction staff is Fine cement mortar and adhesive can be laid on the plane of this step

第17頁 d6 1 932 五、發明說明(15). (洋菜粉)的混合物並貼附磁磚(9 〇 )或大理石磚、花崗石磚 ’如此即不需等待混凝土結構定型乾固即可完成磁磚(9 0) 或大理石磚、花崗石磚等表面飾物的施設,且此等表面飾 物的黏著t與混凝土結構間的結合強度隹;又,該立模板 (2 0 )今該檢模板(3 0 )表面亦可預先貼設表面飾物,據以在 該立模板(20)及該橫模板(3 〇)拆除後,牆面及樓層之地面 即已貼附有表面飾物’俾提高施工效率、縮短工期者;另 ’請配合參閱第24圖’該磁磚(90)於黏貼面(92)凹設有斷 面呈塢尾形之溝槽(9 2 1 ),如此當混凝土與黏貼面(9 2 )接 觸時’混凝土可更進—步滲入該溝槽(9 2丨),相對便如同 該黏貼面(9 2 )嵌入混凝土結構中-般,俾提升磁磚(9㈧之 貼附定位效果者,除此之外,該磁磚(9〇)的邊角處又可斜 削形成傾斜角(93)(如第24圖),如此混凝土結構可更容易 包覆磚〇0)四周,而使磁磚(9〇)獲致良好定位者。 哭Μ二ί閱ί25圖所示係一磁磚施配器(94),該磁磚施配 (Vn日i ί ί複數個網格(942 ),欲在模板内側貼設磁磚 時,I將該磁磚施配器(94)置於模板之上,再將磁磚 (90) — 一填入該網格(942 )内, 妯 磚(90)間距之工時。 匕Τ郎々排列及凋整磁 意圖請圖係顯示使用另—種模检(1〇,)之施工示 S壓制C M' 9,、 ) f、概呈U形,其兩端相對彎靠分別形 邊之邊佟Γ9·η水,术设立模板(2〇)時,該立模板(20)底緣 ΐΐί 於該壓制塊(12’)與基地⑴表面之間 ,而不虞灌注混凝土時該立模板(20)位移,拆模時,只需Page 17 d6 1 932 V. Description of the invention (15). (Agar powder) mixture and attached with tiles (90) or marble tiles, granite tiles' so that you do not need to wait for the concrete structure to set and dry. It can complete the installation of surface ornaments such as tiles (90), marble tiles, granite bricks, etc., and the bonding strength between the adhesion t of these surface ornaments and the concrete structure 隹; also, the standing formwork (2 0) should The surface of the inspection template (30) can also be pre-applied with surface ornaments, so that after the vertical formwork (20) and the horizontal formwork (30) are removed, the surface ornaments are already attached to the walls and floors. Those who improve the construction efficiency and shorten the construction period; also 'please refer to Figure 24' for the tile (90) is recessed on the adhesive surface (92) with a grooved section (9 2 1) in the shape of a dock. When the adhesive surface (9 2) is in contact, 'concrete can be further advanced-it penetrates into the groove (9 2 丨) step by step, as if the adhesive surface (9 2) is embedded in the concrete structure-as if the adhesive surface (9㈧) is lifted With the positioning effect, in addition, the corners of the tile (90) can be beveled to form an inclined angle (93) ( FIG. 24), so the structure can be more easily coated concrete bricks 〇0) around the tile (9〇) attainable locator good. Cry M2, read 25, is a tile dispenser (94), the tile distribution (Vn day i ί a plurality of grids (942), when you want to place the tiles inside the template, I will The tile applicator (94) is placed on the template, and then the tile (90) is filled into the grid (942), and the working hours of the tile (90) are spaced. The magnetization intent is shown in the figure, showing the use of another type of mold inspection (1〇,), the construction is shown to suppress CM '9, f), it is generally U-shaped, and its two ends are relatively bent against the edge of the respective shape 佟 Γ9 · η water, when the template (20) is set up, the bottom edge of the vertical template (20) is between the pressed block (12 ') and the surface of the base, and the vertical template (20) is displaced when the concrete is poured, and disassembled. Die, just

第18頁 461932 五、發明說明(16) 將該壓制塊(1 2 ’) 以切割機切除,即可輕易地解除對該立 模板(2 0 )之壓制。 請參閱第2 7圖係顯示使用另一種連結桿(2 9 ’) 之施工 示意圖,該連結桿(2 9 ’) 係兩端分設有陽螺紋段之螺柱, 該連結桿(29’) 軸套於定厚管(28’)内,且其兩端分別軸 穿立模板(2 0 ’) 之貫孔(2 5 ’)、壓條(2 6 ’) 之過孔(2 6 2 ’) 後螺鎖一螺帽(2 7 ’),據以壓制定位該壓條(2 6 ’),以限 制該立模板(2 0 ’),俾構成另一實施例者。 依據前述本發明較佳實施例,本發明具有以下優點: (1 )由於不需要等待各樓層的混凝土結構完全乾固穩 定,即可進行下一工序的施工,而得以在短時間内快速建 構完成所有樓層的混凝土結構,此種施工方法,較易安排 人工並控制工程進度,縮短施工工期,有效纾解建築工程 的資金壓力。 (2 ) 本發明之牆壁、樓層板於短時間即快速進行模板 建構及灌漿,各樓層間的混凝土結構彼此結合性較強,各 樓層混凝土結構彼此間的吸著凝固較佳較強,完工後的建 築耐震力佳。Page 18 461932 V. Description of the invention (16) The pressing block (1 2 ′) is cut by a cutting machine, and the pressing of the standing template (20) can be easily released. Please refer to Figure 27 for a schematic diagram showing the use of another connecting rod (2 9 '). The connecting rod (2 9') is a stud with male thread segments at both ends. The connecting rod (29 ') The shaft sleeve is inside the fixed-thickness tube (28 '), and the two ends of the shaft sleeve pass through the through hole (2 5') of the template (2 0 ') and the through hole (2 6 2') of the bead (2 6 '). The rear screw locks a nut (2 7 ′), and presses and positions the bead (2 6 ′) to restrict the stand template (2 0 ′), thereby forming another embodiment. According to the foregoing preferred embodiments of the present invention, the present invention has the following advantages: (1) Since it is not necessary to wait for the concrete structure on each floor to be completely dry and stable, the next step of construction can be performed, and the rapid construction can be completed in a short time. The concrete structure of all floors, this construction method, it is easier to arrange labor and control the progress of the project, shorten the construction period, and effectively relieve the financial pressure of construction projects. (2) The wall and floor slab of the present invention can quickly formwork and grout in a short period of time. The concrete structures on each floor have strong bonding with each other, and the concrete structures on each floor have better adsorption and solidification. After completion, The building has good seismic resistance.

(3 ) 本發明之各樓層板模之架構,係該於各樓層之相 對應之上、下樓層模板間隔等距垂直設置複數個支撐塊, 支撐塊下方以支柱對應支撙,故每一樓層板於同一位置承 受上層壓力,可支撐灌注混凝土的壓力。 (4 ) 本發明的牆壁最底層的立模板,係藉由基地預埋 的模栓相對限制定位,使立模板和基地緊緊結合,在灌入(3) The structure of each floor formwork of the present invention is that a plurality of support blocks should be vertically arranged at equal intervals on the corresponding upper and lower floors of each floor. The support blocks are correspondingly supported by pillars, so each floor The slab bears the upper layer pressure at the same position and can support the pressure of the poured concrete. (4) The bottommost formwork of the wall of the present invention is relatively restricted in positioning by the pre-embedded mold bolts of the base, so that the formwork is tightly combined with the base, and is poured in

第19頁 461932 五、發明說明(17) 混凝土時, (5) 本 各支柱間的 便微幅調節 ,及不虞灌 ,及方便拆 (6) 本 先貼設表面 .表面飾物即 綜上所 法及其模板 備,在多樓 成混凝土的 此結合性良 值,具備發 早曰賜與專 立模板不虞受力崩塌。 發明各支柱間藉連結爪、連結釘定位 彼此平行,且支柱的下方襯墊有調節 支柱頂端的高度,利於調節橫模板的 注混凝土時橫模板受力崩模,或支柱 模。 發明可在各立模板、橫模板及階梯模 飾物(磁磚、大理石磚或花崗石磚等) 可於灌漿時同步施工貼設。 述,本發明係提供一種多樓層RC建築 結構,其藉由全新之施工方法及創新 層R C建築之混凝土結構建構施工時, 建構,可縮短施工期,且各樓層間的 好,有效提升建築的耐震強度,而極 明專利之要件,爰依法提呈發明申請 利,至感德便。 ,以保持 墊,以方 水平狀態 受力位移 板表面預 ,建築之 快速施工 之施工設 可快速完 混凝土彼 具產業價 ,並懇請P.19 461932 V. Description of the invention (17) When concrete, (5) Slight adjustment of the support between the pillars, and easy to irrigate, and easy to disassemble (6) The surface is first affixed. The surface decoration is the summary method And its formwork preparation, the good value of this combination of concrete in many floors, has a special formwork issued early on, it is not subject to force collapse. It is found that the pillars are positioned parallel to each other by connecting claws and nails, and the bottom of the pillars is adjusted to adjust the height of the top of the pillars, which is beneficial to adjust the horizontal formwork's force to collapse the mold or the pillar form when injecting concrete. The invention can be used for simultaneous construction and installation of various standing templates, horizontal templates and step-shaped decorations (such as tiles, marble tiles or granite tiles) during grouting. As mentioned above, the present invention provides a multi-story RC building structure, which can shorten the construction period by constructing a concrete structure using a new construction method and an innovative layer of RC building. The construction period can be shortened, and the quality of each floor can be effectively improved. Shock resistance, and the very important element of the patent, it is beneficial to file an invention application according to law. In order to keep the pads in a horizontal state, the surface of the slab is prestressed, and the construction of the rapid construction of the building can quickly complete the industrial price of concrete.

第20頁Page 20

Claims (1)

46 1 93 2 六、申請專利範圍 1. 一種多樓層R C建築快速施工法,其包含以下步驟: 基地施作:在建築的基礎施工時,即在水泥基地預埋 建築牆壁及立柱内部立向鋼筋之根部,且牆壁之鋼筋於樓 梯預定施作處,預留一段橫向凸出,俾供連接樓梯之鋼筋 者; 建構牆壁之模板及樓層板之下模板:在基地頂緣相對 立向建構模板,藉以於相對之二模板間圍設可供灌入混凝 土之空間,同時,豎立複數根支柱,在支柱頂端橫向鋪設 下模板,以利用支柱支撐下模板; 鋪設鋼筋:在下模板頂緣空間縱橫交錯鋪設鋼筋,且 此等鋼筋與牆壁内之鋼筋相連結,並於下模板頂緣置設複 數個支撐塊; 灌漿:在兩相對模板之間及下模板頂端灌注混凝土漿 液,俾供分別形成牆壁及樓層板; 建構牆壁之模板、相鄰樓層之上、下模板:在混凝土 漿液未乾固前,即於牆壁之模板上緣再建構更上樓層牆壁 之模板,並在樓層板頂緣橫設上模板,再於上模板頂緣豎 立支柱,以支撐建構更上樓層之下模板,俾縮短工期者; 重複鋪設鋼筋、灌漿及建構牆壁之模板、相鄰樓層之 上、下模板步驟,即可——建構所需的各樓樓層板及牆壁 直至頂樓; 拆模:待各樓層樓層板' 牆壁之混凝土乾固且穩定定 型後,始--拆除各樓層之模板、支撐柱及上、下模板; 建構樓梯:在各樓層板之間,施工建構樓梯,以使各46 1 93 2 VI. Scope of Patent Application 1. A multi-storey RC building rapid construction method, which includes the following steps: Base construction: During the foundation construction of the building, that is, the steel bars are embedded in the wall of the building and the vertical columns inside the column The root of the wall, and the reinforcement of the wall at the scheduled application of the staircase, a section of horizontal protrusion is reserved for the reinforcement of the staircase; the template to build the wall and the template below the floor: the template is opposite to the top edge of the base, The space between the two forms is used to fill the concrete. At the same time, a plurality of pillars are erected, and the lower formwork is laid horizontally at the top of the pillars to use the pillars to support the lower formwork. Laying steel bars: criss-cross the space at the top edge of the lower formwork Reinforcement, and these reinforcement bars are connected to the reinforcement in the wall, and a plurality of support blocks are placed on the top edge of the lower formwork; grouting: pouring concrete slurry between the two opposite formwork and the top of the lower formwork to form walls and floors respectively Slabs; formwork for wall construction, upper and lower formwork for adjacent floors: before the concrete slurry is dry The upper edge further constructs the formwork of the upper floor wall, and the upper formwork is horizontally installed on the top edge of the floor slab, and then the pillars are erected on the top edge of the upper formwork to support the construction of the lower formwork on the upper floor, which shortens the construction period; The steps of grouting and constructing the formwork of the walls, the upper and lower forms of the adjacent floors, can be-the required floor slabs and walls to the top floor are constructed; demoulding: wait for the concrete on the floor slabs of each floor to be dry and stable After finalization, the formwork, support columns and upper and lower formwork of each floor are removed; building stairs: between each floor slab, constructing building stairs so that each 第24頁 461932 六、 申請專利範圍 樓層得以連通。 利範圍第所述多樓祕建築快速施 工法’其中’樓梯之建構施工包括下列 』標線··針對欲施設樓梯所在位置與傾斜角度,預先標 記墨線, 設相對之接板:對應輕綠半踩^ α 置 咕把# # _ ^ =應铋線步驟所標記墨線,傾斜地設 接板’並使一塊接板彼此相對者. 固設階梯模板··將複數個階梯模板橫Μ 接板 間’且使各階梯模板依序升降排列;υ相十 固設托板角鐵:複數個杯也& ,且使托板角鐵左右ί;:托板角鐵依序固設在接板下方 設底雇模板:將底層模板搭置, 且底層模板兩端與上、下相鄰樓層^目,之托板角鐵上 梯模板 '底層模板間形成樓梯形去俾於接板、階 灌漿成型:將混凝土 .直^二間者, 俟混凝土乾固後即完成、樓梯成型。則述樓梯形狀之空間, 3·依據申請專利範圍第2項所'十.夕地 工法,其中,在樓梯灌 ^ 述夕樓層R c建築快速施 錯舖設鋼筋•自牆,内部延伸=出:·板頂緣空間交 ,俾提升樓梯與牆壁之結合性者。1 、鋼肋以鉤釘、焊接聯結 工法4: 申請專利範圍第2項所述多樓層RC建s也 5分,该接板得以固設於牆面者。 桌快速施 •义象申請專利範圍第2項戶斤.'+、交4*· a 工法’其中,該階梯模板内面預先配‘磁=速施 , 以配合灌漿Page 24 461932 VI. Scope of patent application Floors are connected. The rapid construction method of the multi-story secret building described in the first section of the scope of interest, among which, the construction of the staircase includes the following "marking lines ..." For the location and inclination angle of the stairway to be installed, mark the ink line in advance, and set the opposite connection plate: corresponding light green half Step on ^ α Zhigurda # # _ ^ = The ink line marked by the bismuth line step shall be installed obliquely so that one connection plate is opposite to each other. Fixing the step template ·· A plurality of step templates shall be horizontally connected to the plate ' And the ladder templates are arranged up and down in sequence; υ phase ten fixed pallet angles: several cups are also & and the pallet angles are fixed to the bottom of the splicing plate in order. Bottom employment template: Lay the bottom template, and the two ends of the bottom template and the upper and lower adjacent floors ^, the bracket angle iron upstairs template 'the bottom template forms a staircase shape to be connected to the board and step grouting: After the concrete is straightened, the concrete is finished and the stairs are formed. The space in the shape of a staircase is described. 3. According to the "X. Xixi Construction Method" of the 2nd place of the scope of the patent application, in the staircase, the construction of the Rx building on the staircase is quickly misplaced and the steel bars are laid. • From the wall, the internal extension = out: · The top edge of the board intersects with the space, and enhances the combination of the stairs and the wall. 1. Steel ribs are connected by hook nails and welding. Construction method 4: The multi-floor RC building described in item 2 of the scope of patent application also has 5 points, and the splicing plate can be fixed on the wall. Quick application on the table • Yixiang applies for the second item of the patent scope. '+, Pay 4 * · a method' where the inner surface of the step template is pre-configured with ‘magnetic = speed application’ to match the grouting 第25頁 4 6 1 9 3 2 六、申請專利範圍 同步完成磁碑貼設作業者。 6 . —種多樓層RC建築快速施工之模板結構,其主要包 含模栓、立模板、橫模板、内角模條及外角模條,其中, 該模栓中段埋設於基地内,而兩端同向彎延凸伸於基地上 方,二立模板分別立設於該模栓兩端之間,且該立模板緣 邊向外彎延形成邊條分別抵靠該模栓兩端之内側,該模栓 兩端分別設有壓制塊壓制該邊條,俾以定位兩相對峙之二 -立模板者; 該立模板係概呈矩形之板體,該邊條徑向穿設複數個 栓孔,據使側向鄰靠之立模板得以藉結合螺栓穿套該栓孔 後鎖接一螺帽,俾供結合彼此側向鄰靠之複數個立模板者 ( ;該立模板穿設複數個貫孔5 上、下相鄰之二立模板間夾設有退模條,該退模條緣 邊同向凸設有邊壁,該各邊壁分別貫穿有另栓孔,俾藉結 合螺栓、螺帽結合該退模條與鄰靠之立模板者;該退模條 於該邊壁之同側凸設複數個栓座,該栓座貫穿有螺孔,以 配合螺設退模螺栓,俾據該退模螺栓抵推混凝土牆,以促 使該退模條與牆壁之混凝土結構分離者; 兩相對之立模板間設有定厚管,該定厚管兩端壁分別 與該各立模板抵靠.,該定厚管長度j恰與.設定之牆壁厚度相 同,該定厚管内軸樞一連結桿…,:兩'相對立模板之外側分別r < 立設有壓條壓靠著該立模板外側,該壓條徑向貫穿複數個’ 過孔,該連結桿兩端定位壓制相對之二立模板,俾供撐持 提高該立模板抵抗混凝土漿液壓力之強度者;Page 25 4 6 1 9 3 2 VI. Scope of patent application Synchronous completion of magnetic monument placement operator. 6. — A formwork structure for the rapid construction of a multi-floor RC building, which mainly includes a mold bolt, a vertical formwork, a horizontal formwork, an inner corner moulding strip and an outer corner moulding strip. Among them, the middle part of the mould bolt is buried in the base, and the two ends are in the same direction. Curved and protruding above the base, two vertical formwork plates are respectively erected between the two ends of the mold pin, and the edge of the vertical formwork is bent outward to form edge bars that respectively abut against the inner sides of the two ends of the mold pin. Pressing blocks are respectively provided at both ends to suppress the edge strip, so as to locate the two opposite ones—the vertical template; the vertical template is a generally rectangular plate body, and the edge strip is provided with a plurality of bolt holes in the radial direction. The side-adjacent stand template can be used to cover the bolt hole through a bolt and then lock a nut, which is used to combine the side-adjacent plurality of stand templates (; the stand template is provided with a plurality of through holes 5 A stripper is sandwiched between the two adjacent lower and vertical formwork plates, and the edge of the stripper is provided with a side wall protruding in the same direction, and each side wall is respectively penetrated with another bolt hole, which is combined by a bolt and a nut. The ejector strip and the adjacent standing template; the ejector strip is provided with a plurality of bolt seats on the same side of the side wall, The bolt seat is penetrated with screw holes to cooperate with the setting of ejection bolts, and according to the ejection bolts, it pushes against the concrete wall to promote the separation of the ejection strips from the concrete structure of the wall; For thick pipes, the two walls of the fixed-thickness pipe abut against the respective risers. The length of the fixed-thickness pipe is exactly the same as the thickness of the wall. The fixed-thickness pipe pivots a connecting rod ... The opposite side of the opposing template is r < there are standing bars pressed against the outside of the standing template, the pressing bars pass through a plurality of through holes in the radial direction, and the two ends of the connecting rod are positioned to suppress the two opposite standing templates to support and improve the standing The strength of the formwork resisting the pressure of the concrete slurry; 第26頁 4 6 1 93*2 六、申請專利範圍 該外角模條垂設於垂直鄰接之二立模板間,該外角模 條具有二接板分別與相鄰立模板之邊條藉結合螺栓、螺帽 相結合; 該橫模板橫設於建築樓層板高度所在處,且該橫模板 與相鄰之立模板間藉該内角模條結合;該橫模板緣邊凸設 有邊條,結合螺拴軸穿該邊條與螺帽螺接,俾相鄰之橫模 板及橫模板相鄰之該内角模條結合者; 該内角模條係為管體,令該内角模條相鄰之二管壁分 別為第一管壁、第二管壁,該第一管壁於緊鄰該第二管壁 之緣邊處開設長形之缺口 ,該第一、二管壁分別貫穿複數 個栓孔,據此穿套該結合螺栓,以分別結合該内角模條與 ( 相鄰之該立模板、該橫模板,俾該立模板與該橫模板垂直 結合者」 該橫模板頂緣依擄樓層板面積於適當處設置複數個支 .樓塊,且該支撐塊高度與樓層板厚度相同,俾供支撐位於 樓層板頂緣之橫模板者;位於樓層板下緣之橫模板底緣藉 複數根支柱支撐,該支柱設於相鄰之該各橫模板彼此相對 鄰接之對應處,且該各支撙塊相對應處亦設有該支柱;該 支柱頂端套設一承座,該承座頂端兩分別立設一護板,_ 並於該各護板成一承槽,_息.承座底端端面中央部.愈靡一 合該支柱軸向挖設一套孔,'諸支枉末端轴伸插套於該套孔 〔 内,樓層板頂、底緣之該各橫模板分別於夾設於二夾條之 間,位於樓層板底緣之該夾條靠搭於該承座,並嵌靠通過 該承槽,俾該支柱支承該橫模板者;位於樓層板頂緣之該Page 26 4 6 1 93 * 2 VI. Scope of patent application The outer corner moulding bar is erected vertically between two vertical formwork plates. The outer corner moulding bar has two connecting plates and the side bars of the adjacent formwork plates respectively by combining bolts, Nuts are combined; the horizontal formwork is horizontally located at the height of the building floor slab, and the horizontal formwork and the adjacent vertical formwork are combined by the internal corner strip; the edge of the horizontal formwork is provided with an edge strip, which is combined with a bolt The shaft passes through the side strip and the nut is screwed together, and the adjacent horizontal template and the internal angle die strip adjacent to each other are combined; the internal angle die strip is a pipe body, so that the internal angle die strip is adjacent to the two pipe walls. There are a first pipe wall and a second pipe wall, respectively. The first pipe wall is provided with a long gap near the edge of the second pipe wall, and the first and second pipe walls respectively pass through a plurality of bolt holes. Thread the binding bolts to combine the inner corner mold strip and (adjacent the vertical formwork, the horizontal formwork, the vertical formwork and the horizontal formwork are vertically combined) the top edge of the horizontal formwork according to the floor board area is appropriate A plurality of support blocks are provided at the place, and the height of the support block is the same as the thickness of the floor slab For the support of the horizontal formwork at the top edge of the floor board; the bottom edge of the horizontal formwork at the lower edge of the floor board is supported by a plurality of pillars, which are provided at the corresponding positions of the adjacent horizontal formwork adjacent to each other, and The support is also provided at the corresponding position of each support block; a support is sleeved at the top of the support, and a guard plate is set up on each of the top of the support, and a bearing groove is formed on each guard plate, and the bearing The central part of the end face of the bottom end. A set of holes is dug axially in the pillar, and the ends of the branches and shafts are inserted into the set of holes [inside, the horizontal templates at the top and bottom edges of the floors are clamped respectively. It is located between two clip bars, and the clip bar located at the bottom edge of the floor board rests on the bearing seat, and is embedded through the bearing slot, and the pillar supports the horizontal formwork; 第27頁 461932 六、申請專利範圍 夾條則襯墊支承著上一樓層之支柱; 該支柱徑向貫穿複數個插孔,相鄰之二支柱間靠設有 連結爪、連結釘,據以連結定位相鄰之二支柱,談連結爪 具有四根呈輻射狀向外延伸之鉤體,該各鉤體末端側向凸 設一鉤部分別插入相鄰二支柱之該各插孔,該連結釘係為 桿狀體,其兩端同向凸設有插塊分別插入相鄰二支柱之該 插孔,俾供定位連結相鄰之二支柱者;該支柱於底端墊設 有二彼此相疊之調節墊; 該各調節墊於相疊靠之接觸面係分別形成斜面,據使 該各調節墊彼此得以位移,俾調節該支柱頂端高度,以支 樓該橫模板者。 7 ,依據申請專利範圍第6項所述多樓層RC建築快速施 工之模板結構,其更包含有接續器,其中,該接續器兩端 端面分別於中央部份凹設一嵌槽,且該各嵌槽間藉一隔板 分隔而不連通,據使二支柱末端分別嵌插於該各嵌槽内, 俾供配合樓層高度遂結二支柱者。. 8. 依據申請專利範圍第6項所述多樓層R C建築快速施 工之模板結構,其更包含有接續器,其中,該支柱係為管 狀體,該接續器一端徑向縮束形成一凸體,其另一端端面 ..中央部偷向....掠..設..一表槽乂麗凸.體插.設.於.一支_柱.頂端管肩-,而另—支柱底端嵌插於談嘗槽内,俾供連結二支枉者。 9. 依據申請專利範圍第6項所述多樓層RC建築快速施 工之模板結構,其中,該模栓兩端分別為螺紋段並凸伸於 基地上方,該螺紋段於該邊條頂緣依序柩穿該壓制塊、墊Page 27 461932 VI. The patent application clip clamps support the pillars on the previous floor; the pillars radially penetrate through a plurality of jacks, and the adjacent two pillars are provided with linking claws and linking nails to connect them. Positioning the adjacent two pillars, the connecting claws have four hook bodies extending outward in a radial shape, and a hook portion is protruded laterally from the end of each hook body and is respectively inserted into each of the jacks of the adjacent two pillars. The connecting nails It is a rod-shaped body. Two ends of the two pillars are inserted into the jacks of the adjacent two pillars in the same direction. They are used for positioning and connecting the adjacent two pillars. The adjusting pads form inclined surfaces on the contact surfaces that are stacked next to each other, so that the adjusting pads can be displaced from each other, and the height of the top end of the pillar is adjusted to support the horizontal formwork. 7. According to the formwork structure for rapid construction of a multi-story RC building as described in item 6 of the scope of the patent application, it further includes a connector, wherein the end surfaces of the two ends of the connector are recessed in the central part respectively, and each The cavities are separated by a partition and are not connected, so that the ends of the two pillars are respectively inserted into the cavities, so that the two pillars can be completed according to the height of the floor. 8. According to the formwork structure for rapid construction of a multi-story RC building according to item 6 of the scope of the patent application, it further includes a connector, wherein the pillar is a tubular body, and one end of the connector is radially contracted to form a convex body. , The other end of the face .. The central part steals ..... Sweeping..Setting .. a table slot 乂 convex. Body plug. Setting. At. A _ column. Top tube shoulder-and the other-the bottom of the pillar The end is inserted into the tassel, and it is used to connect two tadpoles. 9. According to the formwork structure for rapid construction of a multi-story RC building as described in item 6 of the scope of the patent application, the two ends of the mold bolt are respectively threaded sections and project above the base, and the threaded sections are sequentially on the top edge of the edge strip. Pierce the pressed block and pad 461932 六、申請專利範圍 圈並鎖接一螺帽,俾該壓制塊壓制該邊條,以定位相對峙 之二立模板者。 1 0依據申請專利範圍第6項所述多樓層RC建築快速施 工之模板結構,其中,該模栓兩端相對彎靠分別形成該壓 制塊,立模板底緣邊之該邊條夾設於該屢制塊與基地表面 之間,俾供定位相對峙之二立模板者。 1 1依據申請專利範圍第6項所述多樓層RC建築快速施 工之模板結構,其中,該立模板一側等距縱橫交錯凸設有 肋條,該肋條與該邊條位於該立模板之同側,俾供強化該 立模板者。461932 VI. Scope of patent application Circle and lock a nut, and then press the block to press the side bar to locate the two opposite template. 10 According to the formwork structure for rapid construction of a multi-story RC building according to item 6 of the scope of the patent application, the two ends of the mold bolt are oppositely bent to form the pressed block respectively, and the edge strip at the bottom edge of the vertical formwork is sandwiched in the Between the repeated block and the surface of the base, there are two types of templates for positioning. 1 1 According to the formwork structure for rapid construction of a multi-story RC building according to item 6 of the scope of application for patents, wherein one side of the standing formwork is provided with ribs that are crisscrossed at equal intervals, and the ribs and the side strips are located on the same side of the standing formwork For those who strengthen the legislation template. 1 2依據申請專利範圍第1 1項所述多樓層RC建築快速施 工之模板結構,其中,該貫孔位於該肋條所分隔區塊之中 央.處為較佳.者。 13依據申請專利範圍第6項所述多樓層RC建築快速施 工之模板結構,其中,該橫模板於該邊條之同側面等距縱 橫交錯凸設有肋條,俾供強化該橫模板之強度者。 1 4依據申請專利範圍第1 3項所述多樓層RC建築快速施 工之模板結構,其中,該支撐塊恰位於該橫模板之肋條對 應處者。12 According to the template structure for rapid construction of a multi-floor RC building according to item 11 of the scope of the patent application, the through hole is preferably located at the center of the block separated by the rib. 13 According to the formwork structure for rapid construction of a multi-story RC building according to item 6 of the scope of the patent application, wherein the horizontal formwork is provided with ribs that are crisscrossed at equal intervals on the same side of the side strip, so as to strengthen the strength of the horizontal formwork . 14 According to the formwork structure for rapid construction of a multi-story RC building as described in Item 13 of the scope of the patent application, the support block is located exactly where the ribs of the horizontal formwork correspond. 1々依據.电讀.專利範圍J1項所述多樓層RC建築農速 工之模板結構,其中,談支:撐塊周邊得以鐵線纏繞箍套-, 並與鋼筋焊接定位,俾供定位該支撐塊者。 1 6依據申請專利範圍第6項所述多樓層RC建築快速施 工之模板結構,其中,該支撐塊徑向貫穿有嵌孔,藉以在1々 Basis. Electric reading. The scope of the patented J1 multi-storey RC building agricultural quick work template structure, in which, the support: the support block can be wrapped around the ferrule with iron wire, and welded to the steel bar for positioning. Supporters. 16 According to the formwork structure for rapid construction of a multi-floor RC building as described in item 6 of the scope of the patent application, the support block is radially penetrated with embedded holes for 第29頁 461932 六、申請專利範圍 灌漿時供混凝土滲入,俾該支撐塊與混凝土固結定位者。 1 7依據申請專利範圍第6項所述多樓層R C建築快速施 工之模板結構,其中,二調節墊彼此接觸之斜面相對凹設 有半圓形缺口 ,據使該缺口相對合並配合插置定位塊於該 缺口 ,俾相對卡制定位該調節墊者。 1 8依據申請專利範圍第6項所述多樓層R C建築快速施 工之模板結構f其中,該立模板、該橫模板内面配設有磁 磚,俾以配合灌漿同步完成磁磚貼設作業者。 1 9依據申請專利範圍第1 8項所述多樓層RC建築快速施 工之模板結構,其中,該磁磚於黏貼面凹設有溝槽,以供 混凝土滲入該溝槽,俾提升磁磚之貼附定位效果者。 k 2 0依據申請專利範圍第1 9項所述多樓層RC建築快速施 工之模板結構,其中,該溝槽斷面係呈鸠尾形者。 21依據申請專利範圍第18項所述多樓層RC建築快速施 工之模板結構,其中,該磁磚的緣邊斜削形成傾斜角,俾 供混凝土結構包覆於該磁碑四周,以定位δ亥磁碑者。 2 2依據申請專利範圍第1 8項所述多樓層RC建築快速施 工之模板結構,其更包含磁磚施配器,該磁磚施配器穿設 複數個網格,俾供磁磚填入該網格内,以節省排列及調整 該磁碍嚴麗矣廉:者。、. . . : — 2 3依據肀請專利範圍第6項所述多樓層R C建築快速施( 工之模板結構,其中,該連結桿兩端分別延伸於該貫孔, 並於端面軸向凹設有螺孔,螺栓自該壓條外側軸入該過孔 與該螺孔螺固相接,俾供限制相對之二立模板者。Page 29 461932 VI. Scope of patent application For the concrete to be infiltrated during grouting, the support block and the concrete should be positioned. 17 According to the formwork structure for rapid construction of a multi-story RC building according to item 6 of the scope of the patent application, wherein the inclined surfaces of the two adjustment pads contact each other are relatively concave with a semi-circular notch, according to which the notch is relatively combined with the insertion of a positioning block With this gap, you can fix the adjustment pad with the card. 18 According to the formwork structure for rapid construction of a multi-floor RC building according to item 6 of the scope of the application for patent, f, the vertical formwork and the horizontal formwork are provided with tiles on the inside, so as to coordinate the grouting to complete the tile placement operator. 19 According to the formwork structure for rapid construction of a multi-story RC building according to item 18 of the scope of the patent application, the tile is recessed with a groove on the adhesive surface to allow concrete to penetrate into the groove and enhance the tile tile. With positioning effect. k 2 0 is a formwork structure for rapid construction of a multi-story RC building as described in item 19 of the scope of the patent application, wherein the groove section is dovetail-shaped. 21 According to the formwork structure for rapid construction of a multi-story RC building according to item 18 of the scope of the patent application, the edge of the tile is beveled to form an inclination angle, so that the concrete structure is wrapped around the magnetic monument to locate the delta Magnetizer. 2 2 According to the template structure of the multi-storey RC building rapid construction described in item 18 of the scope of the patent application, it further includes a tile applicator, and the tile applicator is provided with a plurality of grids for the tiles to be filled into the net. In order to save the arrangement and adjust the magnetic obstruction Yan Liyilian :. ...: — 2 3 According to the 6th patent scope of the patent application, the rapid construction of multi-floor RC building (the formwork structure of the construction, in which the two ends of the connecting rod respectively extend from the through hole, and are axially concave at the end face. A screw hole is provided, and a bolt is axially inserted into the through hole from the outside of the bead to be screwed with the screw hole, so as to limit the opposite vertical template. 第30頁 a B193 2P. 30 a B193 2
TW90109848A 2001-04-23 2001-04-23 Quick construction method for multiple-floor building and form employed in the method TW461932B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW90109848A TW461932B (en) 2001-04-23 2001-04-23 Quick construction method for multiple-floor building and form employed in the method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW90109848A TW461932B (en) 2001-04-23 2001-04-23 Quick construction method for multiple-floor building and form employed in the method

Publications (1)

Publication Number Publication Date
TW461932B true TW461932B (en) 2001-11-01

Family

ID=21678062

Family Applications (1)

Application Number Title Priority Date Filing Date
TW90109848A TW461932B (en) 2001-04-23 2001-04-23 Quick construction method for multiple-floor building and form employed in the method

Country Status (1)

Country Link
TW (1) TW461932B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112270025A (en) * 2020-09-30 2021-01-26 晟通科技集团有限公司 Template combination design method
CN113674573A (en) * 2019-12-16 2021-11-19 浙江建设职业技术学院 Practical training classroom for engineering building electrical construction technology training

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113674573A (en) * 2019-12-16 2021-11-19 浙江建设职业技术学院 Practical training classroom for engineering building electrical construction technology training
CN113674573B (en) * 2019-12-16 2023-08-01 浙江建设职业技术学院 Practical training classroom for engineering building electrical construction technical training
CN112270025A (en) * 2020-09-30 2021-01-26 晟通科技集团有限公司 Template combination design method

Similar Documents

Publication Publication Date Title
US6401417B1 (en) Concrete form structure
US20090151281A1 (en) Method of constructing a wall or fence with panels
WO2005107388A2 (en) Column block system
US20130214227A1 (en) Fence
US10267011B2 (en) Pre-cast decorative retaining wall system
US20140260038A1 (en) Modular Construction System
US10053833B2 (en) Pre-cast decorative retaining wall system
US5226276A (en) Free standing wall construction, a method of constructing same, and a precast elongated construction member
JP2002167959A (en) Quick execution method for multi-story rc building and its template structure
US20080061213A1 (en) Cantilevered and textured concrete form
TW461932B (en) Quick construction method for multiple-floor building and form employed in the method
US20020100247A1 (en) Method for quickly building a building and moldboard employed in the method
US20030218265A1 (en) Mold and process for casting and manufacturing of concrete structural columns
TWM495384U (en) Support model base for opening type reinforced concrete
KR101566891B1 (en) Method for building construction of Korean-style house
KR20230010189A (en) Cladding bonding system and method
WO2001048327A1 (en) A quickly building method with permanent fancy self-fixing plate
WO2017115254A1 (en) Assembly for applying a screed and method for applying a screed
CN105926820A (en) Construction method for prefabricated beam steel bearing plate resistance net piece combination floor
JP3603957B2 (en) On-site manufacturing method for PC members
KR100264386B1 (en) Method and construction of panel of reinforced siol using unartificial marble
RU2285771C1 (en) Method for building and building structure erection, renewal and reconstruction
US2648116A (en) Method of making hollow monolithic concrete slabs
CN1309219A (en) Construction method for assembling shutterings of multi-storey building at same time and pouring cement grout once
JPH11323958A (en) Execution method of building and concrete product used therefor

Legal Events

Date Code Title Description
GD4A Issue of patent certificate for granted invention patent
MM4A Annulment or lapse of patent due to non-payment of fees