SU990966A1 - Method of consolidating pit walls - Google Patents

Method of consolidating pit walls Download PDF

Info

Publication number
SU990966A1
SU990966A1 SU813325840A SU3325840A SU990966A1 SU 990966 A1 SU990966 A1 SU 990966A1 SU 813325840 A SU813325840 A SU 813325840A SU 3325840 A SU3325840 A SU 3325840A SU 990966 A1 SU990966 A1 SU 990966A1
Authority
SU
USSR - Soviet Union
Prior art keywords
pit
trench
consolidating
anchors
piles
Prior art date
Application number
SU813325840A
Other languages
Russian (ru)
Inventor
Сергей Сергеевич Надточий
Николай Петрович Богачев
Владимир Павлович Тимошкин
Андрей Александрович Филиппов
Original Assignee
Трест "Леноргинжстрой" Главленинградинжстроя Исполнительного Комитета Ленинградского Городского Совета Депутатов Трудящихся
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Трест "Леноргинжстрой" Главленинградинжстроя Исполнительного Комитета Ленинградского Городского Совета Депутатов Трудящихся filed Critical Трест "Леноргинжстрой" Главленинградинжстроя Исполнительного Комитета Ленинградского Городского Совета Депутатов Трудящихся
Priority to SU813325840A priority Critical patent/SU990966A1/en
Application granted granted Critical
Publication of SU990966A1 publication Critical patent/SU990966A1/en

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Description

(54) СПСХ:ОБ КРЕПЛЕНИЯ СТЕН КОТЛОВАНА(54) APS: ABOUT FIXING WALLS COILED

Изобретение относитс  к строительству , в основном к осуществлению креплени  котлованов и траншей при производстве земл ных работ под фундаменты , заглубленньле подземные сооружени , насосные станции, подвальные части зданий, трубопроводные подземные прокладки и щзугие объекты.The invention relates to the construction, mainly to the implementation of the fastening of pits and trenches in the production of earthworks for foundations, buried underground structures, pumping stations, basement parts of buildings, pipeline underground gaskets and szhuzhy objects.

Известны способы креплени  котлованов при помощи замораживани  грунта на всю глубину котлована, в основе которых лежит, создание сплс нного замороженного контура, своего рода цилиндрической оболочки по всей поверхности котлована 1 .Methods are known for fastening the trenches by freezing the soil to the full depth of the trench, which are based on creating a split frozen contour, a kind of cylindrical shell over the entire surface of the trench 1.

Недостатком указанного способа  вл етс  энергоемкость, продолжительность и больша  трудоемкость создани  замороженной зоны грунта на всю глубину котлована и по всему периметру.The disadvantage of this method is the energy consumption, the duration and the great complexity of creating a frozen soil zone over the entire depth of the pit and around the entire perimeter.

Наиболее близким по технической сущности и достигаемому результату к изобретению  вл етс  способ креплени  стен котлована, включающей погружение вокруг котлована продольно сопр женных свай с последующим закреплением их анкерами 2.The closest in technical essence and the achieved result to the invention is the method of fastening the walls of the pit, including immersion around the pit of longitudinally mated piles, followed by fixing them with anchors 2.

При этом способе по контуру котлована погружаютс  сваи или металлический шпунт, образу  ограждение котловача по всему его периметру. В процессе отрывки котлована устраиваетс  анкерное или распорное крепление шпунта металлическими т жами или распорками. Причем заделка анкеров, вынесена за пределы обрушени  грунта.In this method, piles or a metal sheet pile are immersed along the contour of the excavation, forming a fencing of the cauldron around its perimeter. In the process of extracting the pit, anchoring or expansion of the tongue is arranged with metal joints or struts. Moreover, the embedment of anchors, made outside the collapse of the soil.

К недостатку этого способа относитс  больша  металлоемкость и трудоемкость устройства анкерных по сов, The disadvantage of this method is the high intensity of metal and the laboriousness of the device for anchors,

10 закреплени  шпунтового ограждени  или свай.10 securing sheet piling or piles.

Целью изобретени   вл етс  снижение металлоемкости креплени  за счет уменьшени  длины анкеров и возможности многократного использовани .The aim of the invention is to reduce the metal intensity of the mount by reducing the length of the anchors and the possibility of repeated use.

1515

Поставленна  цель достигаетс  тем, что согласно способу креплени  стен котлована, включающему погружение The goal is achieved by the fact that, according to the method of fastening the walls of the pit, including immersion

20 вокруг котлована продольно сопр женных свай с последующим закреплением их анкерами, закрепление анкерами производ т путем отрывки в верхней части котлована траншеи, размещени  20 around the pit of the longitudinally connected piles with their subsequent fixing with anchors, fixing with anchors is carried out by cuttings in the upper part of the pit of the trench, placing

25 в траншее анкеров, обратной засыпки траншеи заполнителем и последуга«егс замораживани  заполнител .25 into the trench of the anchors, backfill the trench with aggregate and the subsequent “freezing of the aggregate.

На фиг.1 изображен котлован, вертикальный разрез; на фиг.2 - то же, Figure 1 shows the pit, vertical section; figure 2 - the same

30 в плане.30 in the plan.

Способ осуществл етс  следующим образом.The method is carried out as follows.

По наружному периметру свайного ограждени  1 котлована 2 производ т отрывку траншеи 3, глубиной 1-1,5 м при ширине до 2-2,5 м. В траншею 3 |укладывают трубы 4 по всему периметру котлована 2. По трубам 4 пропускают циркулирующий раствор хладоагента от замораживающей станции. Сваи 5 ограждени  котлована 2 короткими анкерами 6 заанкеривают в пределах поперечного сечени  траншеи 3. Транше  3 с тнательным уплотнением заполн етс  заполнителем в виде песчаного увлажненного грунта или более сложным составом из отходов промышленности строительного производства. По прошествии определенного расчетного времени , которое зависит от температуры пропускаемого хладоагента, физико-химических характеристик наполнител , параметров компрессоров замораживающей станции и других факторов конкретногхэ объекта, происходит промораживание заполнител  в пределах всего поперечного сечени  траншеи. По всему наружному периметру шпунтового ограждени  котлована 2 образуетс  мощный поверхностный опорный по с, в который и заанкерены сваи 5. Во избежание воздействи  положительных температур воздуха и действи  солнечных лучей, могущих вызвать оттаивание заполнител  в траншее 3, опорный по с 7 сверху (с поверхности) защищают матами 8 из пшаковаты (минеральной ваты) или коробом с засыпкой опилками и стружкой.Along the outer perimeter of the pile fence 1 of the excavation 2, a fragment of trench 3 is produced, with a depth of 1-1.5 m and width up to 2-2.5 m. In trench 3 | pipes 4 are laid along the entire perimeter of excavation 2. A circulating solution is passed through pipes 4 refrigerant from the freezing station. Piles 5 of the excavation of the pit 2 with short anchors 6 are anchored within the cross section of trench 3. Trench 3 with compaction seal is filled with aggregate in the form of sandy, wet soil or a more complex composition of the waste products of the building industry. After a certain estimated time, which depends on the temperature of the refrigerant being passed through, the physicochemical characteristics of the filler, the parameters of the compressors of the freezing station and other factors specific to the object, the aggregate freezes within the entire cross section of the trench. Across the outer perimeter of the sheet piling of the pit 2, a powerful surface support is formed, into which the piles 5 are anchored. To avoid exposure to positive air temperatures and the action of sunlight, which can cause the core to thaw, the reference is from 7 above (from the surface) protect mats 8 from pshakovaty (mineral wool) or a box filled with sawdust and shavings.

После окончани  всех строительных и монтажных работ в котловане 2- и осу1цествлени  обратной засыпки паэух, по трубам 4 вместо циркулирующего хладоагента пропускают пар или гор чую воду. Наполнитель траншей оттаивает . Его удал ют, трубы демонтируют, убирают анкеровку 6 свай 5 и извлекают сваи 5 ограждени  котлована 2.After completion of all construction and installation work in the trench 2- and implementation of the backfilling of the paweh, through pipes 4 instead of circulating refrigerant, steam or hot water is passed. Trench filler thaws. It is removed, the pipes are dismantled, the anchoring 6 of the piles 5 is removed, and the piles 5 of the fence of the excavation 2 are removed.

Использование данного способа позвол ет снизить металлоемкость креплени  за счет уменьшени  длины анкеров и повышени  их оборачиваемости.The use of this method allows to reduce the metal content of the mount by reducing the length of the anchors and increasing their turnover.

Claims (2)

1.Трупак Н.Г. Специальные спосо ,бы проведени  горных выработок. М.,1. Trupak N.G. Special ways to conduct mining. M., Недра, 1976, с. 190-201.Nedra, 1976, p. 190-201. 2.Способ строительства стена в грунте и перспективы его применени  в мелиоративном строительстве.. Обзорна  информаци . М., Министерство мелиорации и водного хоз йства. 1978, № 4, «с. 4-15 (прототип).2. A method of building a wall in the ground and the prospects for its use in land-improvement construction. Overview. M., Ministry of Land Reclamation and Water Management. 1978, No. 4, “p. 4-15 (prototype). -J J-J J
SU813325840A 1981-08-19 1981-08-19 Method of consolidating pit walls SU990966A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU813325840A SU990966A1 (en) 1981-08-19 1981-08-19 Method of consolidating pit walls

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU813325840A SU990966A1 (en) 1981-08-19 1981-08-19 Method of consolidating pit walls

Publications (1)

Publication Number Publication Date
SU990966A1 true SU990966A1 (en) 1983-01-23

Family

ID=20972281

Family Applications (1)

Application Number Title Priority Date Filing Date
SU813325840A SU990966A1 (en) 1981-08-19 1981-08-19 Method of consolidating pit walls

Country Status (1)

Country Link
SU (1) SU990966A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2451135C2 (en) * 2007-12-29 2012-05-20 Анатолий Дмитриевич Лобанов Method to manufacture technological wall of foundation pit
RU2639766C1 (en) * 2017-02-10 2017-12-22 Федеральное государственное бюджетное образовательное учреждение высшего образования "Национальный исследовательский Московский государственный строительный университет" (НИУ МГСУ) Prefabricated reinforced concrete fore shaft of multiple application

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2451135C2 (en) * 2007-12-29 2012-05-20 Анатолий Дмитриевич Лобанов Method to manufacture technological wall of foundation pit
RU2639766C1 (en) * 2017-02-10 2017-12-22 Федеральное государственное бюджетное образовательное учреждение высшего образования "Национальный исследовательский Московский государственный строительный университет" (НИУ МГСУ) Prefabricated reinforced concrete fore shaft of multiple application

Similar Documents

Publication Publication Date Title
CN111577383B (en) Method for treating tunnel leakage water in alpine region
CN104762955B (en) A kind of Belled Pile construction method based on freezing process
CN106088154B (en) Prefabricated assembled underground silo compound shaft construction method and silo structure
CN110565686A (en) Construction method for penetrating river channel under pipe gallery
SU990966A1 (en) Method of consolidating pit walls
CN101871218B (en) Trenchless construction method of underground station space and arc-shaped freezing pipe construction equipment thereof
CN106884438A (en) A kind of piping lane foundation trench compound support method of the following collapsible loess of groundwater level
CN107165640A (en) Tunnels and underground engineering surely builds method certainly
CN106638670B (en) Half prefabricated piping lane and construction method
RU2039158C1 (en) Method for erecting piles in permafrost ground
CN114622574A (en) Water-rich cast-fill deep foundation pit water-intercepting excavation supporting method and supporting device
RU2099534C1 (en) Method for support of underground working in water-logged frozen grounds
Sadovsky et al. The artificial freezing and cooling of soils at construction sites
JP3448408B2 (en) Ground improvement method by burying steel pipe and creating frozen soil
RU2753301C1 (en) Method for foundation construction under conditions of year-round negative temperatures
CN112962624B (en) Double-curtain freezing groove wall method for ultra-deep and ultra-large complex foundation pit construction
CN218759877U (en) Rich water ultra-deep subway shield tunnel terminal reinforcing structure that starts
RU206004U1 (en) Ground anchor
RU2707315C1 (en) Method of protecting a structure foundation in a building area to maintain a wet mode on heaving soils
CN209741857U (en) Deep underground space outer wall steel pipe pile freezes joint supporting construction
CN113931228B (en) Material platform construction method for basement construction
CN111577384B (en) Drainage structures is led to severe cold district tunnel lateral wall pilot tunnel
JP2852571B2 (en) Building underground structure construction method
RU1813850C (en) Method for erection of foundation
SU178746A1 (en)