SU943082A1 - Method of constructing self-raising offshore platform - Google Patents

Method of constructing self-raising offshore platform Download PDF

Info

Publication number
SU943082A1
SU943082A1 SU803223429A SU3223429A SU943082A1 SU 943082 A1 SU943082 A1 SU 943082A1 SU 803223429 A SU803223429 A SU 803223429A SU 3223429 A SU3223429 A SU 3223429A SU 943082 A1 SU943082 A1 SU 943082A1
Authority
SU
USSR - Soviet Union
Prior art keywords
platform
pontoons
pier
under
lifting mechanisms
Prior art date
Application number
SU803223429A
Other languages
Russian (ru)
Inventor
Валерий Александрович Комаров
Вячеслав Вадимович Миронов
Николай Иванович Алексеев
Original Assignee
Предприятие П/Я В-8221
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Предприятие П/Я В-8221 filed Critical Предприятие П/Я В-8221
Priority to SU803223429A priority Critical patent/SU943082A1/en
Application granted granted Critical
Publication of SU943082A1 publication Critical patent/SU943082A1/en

Links

Description

Изобретение относитс  к технологии судостроени  и касаетс  способов постройки и спуска на воду самоподъемных платформ, например, дл  освоени  морского шельфа. Известен способ постройки морской самоподъемной платформы, включающий монтаж на степеле корпуса платфорг ол, установку на нем надстройки, буровой вышки, механизмов подъема и частичное формирование опорных колонн, причем платформу перемещают на достроечный мол, размешают кра  корпуса платформы с механизмами подъема и сформированными част ми опорных колонн со свесом над водой, а после монтажа плат форму ввод т с мола Г1 Недостатком известного способа  вл етс  высока  стоимость постройки самоподъемной платформы в св зи с повышенными затратами на транспортирование частей корпуса морской самоподъ- емной плаач{юрмы. Цель изобретени  - сокращение стоимости постройки. Это достига ;гс  тем, что нижние секции опорных колонн устанавливают в вырезы монтажно-спусковых понтонов, после чего подвод т последние к молу под корпус платформы, затем опускают сформированные части опорных колонн и стыкуют их с нижними секци ми, после чего вывод т монтажио-спусковые понтоны из-под корпуса, устанавливают на них опоры, вновь завод т под корпус и дебаАластируют монтажио-спусковые понтоны , а затем буксируют платформу на монтажно-спусковых понтонах до полного вывода с мола, опускают механизмами подъема опорные колонны до упора их в грунт и поднимают платформу над монтажно-спусковыми понтонами, после чего вывод т последние из-под корпуса платформы и опускакл платфорк у механизмами подъема до всплыти . На фиг. 1 изображены платформа на молу и монтажно-спусковые понтоны с 1гажними секци ми опорных колонн в отведенном положении; на фиг. 2 - то- же вид сверху; на фиг. 3 - платформа на молу и монтажно спусковые понтоны с нижними секци ми опорных колонн, подведенные под корпус; на фиг. 4 - плат форма на молу и монтажно спусковые понтоны с опорами в отведенном положе1пга; на фиг. 5 - то же, вид сверху; на фиг. 6 - платформа на монтажноспусковых понтонах вьшедена с мола; на фиг. 7 - то же, вид спереди; на фиг. 8 - платформа стоит на опорных колоннах, монтажно спусковые пойтоны отведены; на фиг. 9 - платформа на Способ осуществл етс  следуюшим образом. Корпус 1 морской самоподъемной платформы с установленными на нем Me низмами 2 подъема настройкой 3, буровой вышкой (не показано) и частично сформированными опорными колоннами 4 перемещают на судовозньпс- тележках 5 со стапел  6 на достроечный мол 7 так что корпус 1 с механизмами 2 и колоннами 4 оказываетс  над водой. Нижние секции 8 колонн 4 устанавли ваьот попарно в вырезы 9 двух монтажно-спусковых понтонов 1О, забалластированных дл  увеличени  их осадки, и фиксируют в вертикальном положении (фиг. 1 и 2). Понтоны 10 подвод т к молу 7 так, чтобы секции В оказались над сформиро ванными част ми колонн 4. С помопшю механизмов 2 колонны 4 опускают и стыкуют с секци ми 8, после чего прои вод т сварку их между собой и подъем вверх на длину одной секции (фиг. 3). Операцию повтор ют до полного формировани  колонн 4. Понтоны 10 вывод т из-под корпуса и устанавливают на них опоры 11 (фиг. и 5). Затем вновь подвод т понтоны Ю с опорами 11 под нависающие над водо части корщса 1. При этом колонны 4 свободно заход т в вырезы 9 понтонов 10. Последние за счет продувки баллас та подвсплывают и опорами 11 поднимают корпус 1 над тележками 5, после чегх) платформу буксируют вдоль мола 7 до полного вывода с мола (фиг. 6 и 7) С помощью механизмов 2 колонны 4 опускают до опирани  их в грунт и корпус 1 поднимают с опор 11 понтонов 10, которые затем вывод т из-под корпуса (фиг. 8). После этого колонны 4 поднимают механизмами 2 в крайнее верхнее положение, и корпус 1 платформы опускаетс  на воду (фиг. 9). Технико-экономический эффект от применени  изобретени  достигаетс  в св зи с исключением необходимости применени  сухого дока и затрат на его содержание ри постройке морских самоподъекшых платформ с помощью монтажно-спусковых понтонов. ормула изобретени  Способ постройки морской самоподъемной платформы, включающий монтаж на стапеле корпуса платформы, установку на нем надстройки, буровой вьппки, механизмов подъема и частичное формирование опорных колонн, причем платформу перемещают на достроечный мол, размещают кра  корпуса платформы с механизмами подъема и сформированными част ми опорных колонн со свесом над водой, а после монтажа платформу вывод т с мола , отличающийс  тем, что, с целью сокращени  стоимости постройки, нижние секции опорных, колонн устанавливают в вырезы монтажно-спусковых понтонов, после чего подвод т последние к молу под корпус платформы, затем опускают сформированные части опорных колонн и стыкуют их с нижними секци ми , после чего вывод т монтажно-спусковые понтоны из-под корпуса, устанавливают на них опоры, вновь завод т под корпус и дебалластируют монтажно-спусковые понтоны, а затем буксируют платформу на монтажно-спусковых понтонах до полного вывода с мола, опускают механизмы подъема до упора их в грунт и поднимают платформу над монтажно-спусковыми понтонами, после чего вывод т последние из-под корпуса платформы и опускают платформу механи;элами подъема до всплыти . Источники информации, прин тые во внимание при экспертизе 1. Авторское свидетельство СССР № 735478, кл. В 63 В 9/ОО, 27.О9.78 (прототип).The invention relates to shipbuilding technology and relates to methods for constructing and launching self-lifting platforms, for example, for the development of the sea shelf. There is a known method of building a marine self-lifting platform, including mounting on a stepper of a platform casing, installing superstructures on it, a derrick, lifting mechanisms and partial formation of supporting columns, the platform being moved to an outhouse pier, the edges of the platform casing are mixed with lifting mechanisms and columns with an overhang above the water, and after mounting the plate is inserted from the pier G1. A disadvantage of the known method is the high cost of building a self-lifting platform in connection with elevated the cost of transporting parts of the hull of the sea self-erecting platform {jurma. The purpose of the invention is to reduce the cost of construction. This is achieved; by the fact that the lower sections of the supporting columns are installed in the cut-outs of the installation and launch pontoons, after which the latter are brought under the platform body to the pier, then the formed parts of the supporting columns are lowered and joined to the lower sections, after which launching pontoons from under the hull, set up supports on them, re-enter the hull under the hull and de-assembled the erection-launching pontoons, and then tow the platform to the erection-launching pontoons to complete withdrawal from the pier, lower the support columns to the lifting mechanisms stop them in the ground and raise the platform above the assembly and triggers pontoons, and then output the last out of the platform hull and opuskakl platfork in lifting mechanisms to ascent. FIG. Figure 1 shows the platform on the pier and the mounting and launch pontoons with 1 main sections of the supporting columns in the designated position; in fig. 2 is also a top view; in fig. 3 - platform on the pier and mounting pontoons with lower sections of supporting columns, connected to the hull; in fig. 4 - plate shaped pier and mounting pontoons with supports in the assigned position; in fig. 5 - the same, top view; in fig. 6 - the platform on the mounting-start pontoons was removed from the pier; in fig. 7 - the same, front view; in fig. 8 - the platform stands on supporting columns, mounting and launching points are retracted; in fig. 9 is a platform for the method as follows. The hull 1 offshore self-lifting platform installed on it Memo 2 lifting lift setting 3, a derrick (not shown) and partially formed supporting columns 4 are moved on the ship carts 5 from the stocks 6 to the pier building 7 so that the housing 1 with mechanisms 2 and columns 4 is above water. The lower sections of the 8 columns 4 were installed in pairs in the cuts 9 of the two assembly and launch pontoons 1O, ballasted to increase their draft, and fixed in a vertical position (Fig. 1 and 2). The pontoons 10 are led to the pier 7 so that sections B are above the formed parts of the columns 4. With the help of the mechanisms 2, the columns 4 are lowered and joined to sections 8, after which they are welded together and raised up by one length sections (Fig. 3). The operation is repeated until the columns 4 are completely formed. The pontoons 10 are led out from under the hull and the supports 11 are mounted on them (Fig. 5). Then pontoons U with supports 11 are brought down below the overhanging bodies of water pipe 1. At the same time, columns 4 freely enter the notches of 9 pontoons 10. The latter, due to the blowing of the ballas, float and support 11 and lift the body 1 above the carriages 5 after it) The platform is towed along pier 7 to complete removal from the pier (figs. 6 and 7). Using mechanisms 2, columns 4 are lowered to ground in the ground and case 1 is lifted from supports 11 of pontoons 10, which are then removed from under the case (Fig. eight). After this, the columns 4 are raised by the mechanisms 2 to the extreme upper position, and the platform body 1 is lowered onto the water (Fig. 9). The technical and economic effect of the application of the invention is achieved in connection with the elimination of the need to use a dry dock and the cost of its maintenance when building offshore self-elevating platforms using mounting and launching pontoons. Formula of the invention. A method of building an offshore self-lifting platform, including mounting on the slipway of the platform body, installing a superstructure on it, a drilling rig, lifting mechanisms and partial formation of supporting columns, the platform being moved to an extension pier, the edges of the platform body with lifting mechanisms and formed parts of the supporting columns with an overhang above the water, and after installation the platform is removed from the pier, characterized in that, in order to reduce the cost of construction, the lower sections of the supporting columns are installed in The cutouts of the mounting and lowering pontoons, after which the latter are brought under the platform body to the pier, then the formed parts of the supporting columns are lowered and joined to the lower sections, after which the mounting and lowering pontoons are pulled out from under the body, they are supported plant under the hull and deball the mounting and launch pontoons, and then tow the platform to the mounting and launch pontoons to complete withdrawal from the pier, lower the lifting mechanisms until they stop into the ground and raise the platform above the mounting and launch pontoons, after outputting the latest from the platform body and the platform is lowered mechanical; elami lift to ascend. Sources of information taken into account during the examination 1. USSR Author's Certificate No. 735478, cl. B 63 B 9 / OO, 27.O9.78 (prototype).

WW

5 s .5 s.

И1.2And 1.2

If.If.

toФиг .5to .5

10ten

К ЧKH

11eleven

10ten

иand

/ /

и and

лl

лl

ffff

1L

АBUT

(пЛ(PL

-P

SS

тt

//

10 ten

ыs

оabout

лl

XX

ffff

77

F АF A

л l

II

II

Claims (1)

Формула изобретенияClaim Способ постройки морской самоподъемной платформы, включающий монтаж на стапеле корпуса платформы, установку на нем надстройки, буровой вышки, механизмов подъема и частичное формирование опорных колонн, причем платформу перемещают на достроечный мол, размещают края корпуса платформы с механизмами подъема и сформированными частями опорных колонн со свесом над водой, а после монтажа платформу выводят с мола, отл/ичающийся тем, что, с целью сокращения стоимости постройки, нижние секции опорных колонн устанавливают в вырезы монтажно-спусковых понтонов, после чего подводят последние к молу под корпус платформы, затем опускают сформированные части опорных колонн и стыкуют их с нижними секциями, после чего выводят монтажно-спусковые понтоны из-под корпуса, устанавливают на них опоры, вновь заводят под корпус и дебалластиру ют монтажно-спусковые понтоны, а затем буксируют платформу на монтажно-спусковых понтонах до полного вывода с мола, опускают механизмы подъема до упора их в грунт и поднимают платформу над монтажно-спусковыми понтонами, после чего выводят последние из-под корпуса платформы и опускают платформу механизмами подъема до всплытия.A method of constructing a marine self-elevating platform, including mounting a platform body on a slipway, installing an add-on, a derrick, lifting mechanisms and partial formation of support columns, the platform being moved to an outbuilding pier, the edges of the platform body with lifting mechanisms and formed parts of the supporting columns with overhang are placed above the water, and after installation, the platform is removed from the pier, distinguished by the fact that, in order to reduce the cost of construction, the lower sections of the support columns are installed in the cutouts pontoons, after which the latter are brought to the pier under the platform body, then the formed parts of the support columns are lowered and joined to the lower sections, after which the assembly and release pontoons are removed from under the body, the supports are mounted on them, re-placed under the body and de-ballast assembly and launch pontoons, and then tow the platform on the assembly and launch pontoons to the full withdrawal from the pier, lower the lifting mechanisms all the way into the ground and raise the platform above the assembly and launch pontoons, after which the latter are brought out from under rpusa platform and lower platform lifting mechanisms to ascent.
SU803223429A 1980-12-16 1980-12-16 Method of constructing self-raising offshore platform SU943082A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU803223429A SU943082A1 (en) 1980-12-16 1980-12-16 Method of constructing self-raising offshore platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU803223429A SU943082A1 (en) 1980-12-16 1980-12-16 Method of constructing self-raising offshore platform

Publications (1)

Publication Number Publication Date
SU943082A1 true SU943082A1 (en) 1982-07-15

Family

ID=20933977

Family Applications (1)

Application Number Title Priority Date Filing Date
SU803223429A SU943082A1 (en) 1980-12-16 1980-12-16 Method of constructing self-raising offshore platform

Country Status (1)

Country Link
SU (1) SU943082A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2608588C2 (en) * 2012-11-23 2017-01-23 Кеппел Офшор Энд Марин Текнолоджи Сенте Пте Лтд Jacking system with auxiliary structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2608588C2 (en) * 2012-11-23 2017-01-23 Кеппел Офшор Энд Марин Текнолоджи Сенте Пте Лтд Jacking system with auxiliary structure
RU2608588C9 (en) * 2012-11-23 2017-07-19 Кеппел Офшор Энд Марин Текнолоджи Сенте Пте Лтд Jacking system with auxiliary structure

Similar Documents

Publication Publication Date Title
US4648751A (en) Method and apparatus for erecting offshore platforms
SE8600498L (en) SET TO INSTALL THE OBJECT OF A OFFSHORE PLATFORM AND EQUIPMENT TO PERFORM THE SET
US3996754A (en) Mobile marine drilling unit
GB2201980A (en) Offshore oil/gas production
NO771673L (en) FIXED OFFSHORE PLATFORM AND PROCEDURE FOR SETTING UP THE SAME
US4002038A (en) Method and apparatus for rapid erection of offshore towers
US4012917A (en) Bridge beam tower erection methods and apparatus
JPS62215711A (en) Ocean structure and method for anchoring the same
SU943082A1 (en) Method of constructing self-raising offshore platform
US5237949A (en) Floating platform shallow draft hull/deck mating
US2873581A (en) Marine platform
JP2606799B2 (en) Installation method of marine platform
US20100296873A1 (en) Method for installing a topside module on an offshore support structure
GB2080860A (en) A process for mounting in relatively shallow or moderately deep water and installing at the work site a drilling and oil-production platform with base-weight.
US20020067958A1 (en) Methods of installing offshore platforms
GB1533032A (en) Method for assembling and siting an off-shore structure
RU2085659C1 (en) Method of building seaborne self-lifting platform
FR2416306A2 (en) Offshore platform in several sections - floats fully equipped and is lowered on to just-submerged support structure
JPS5789013A (en) Fabrication of marine structure, etc.
SU1184896A1 (en) Versions of method of erecting support columns of floating drilling rig
CN107653854B (en) Construction and folding method of self-elevating platform cantilever beam
SU1030489A1 (en) Method of installation of support pillars of self-lifting drilling sea platform
SU1108166A1 (en) Method and apparatus for constructing semi-submerged floating drilling rig
SU1021708A1 (en) Method of mounting self-lifting floating platform support columns in dry dock
RU2085660C1 (en) Method of building seaborne platform