SU876854A1 - Method of producing foundation pit in swampy soils - Google Patents

Method of producing foundation pit in swampy soils Download PDF

Info

Publication number
SU876854A1
SU876854A1 SU802880621A SU2880621A SU876854A1 SU 876854 A1 SU876854 A1 SU 876854A1 SU 802880621 A SU802880621 A SU 802880621A SU 2880621 A SU2880621 A SU 2880621A SU 876854 A1 SU876854 A1 SU 876854A1
Authority
SU
USSR - Soviet Union
Prior art keywords
soil
pit
solution
ramming
soils
Prior art date
Application number
SU802880621A
Other languages
Russian (ru)
Inventor
Владимир Иванович Крутов
Иван Алексеевич Тютюнов
Олег Закирович Халимов
Original Assignee
Ордена Трудового Красного Знамени Научно-Исследовательский Институт Оснований И Подземных Сооружений Им. Н.И.Герсеванова
Абаканский Филиал Красноярского Политехнического Института
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ордена Трудового Красного Знамени Научно-Исследовательский Институт Оснований И Подземных Сооружений Им. Н.И.Герсеванова, Абаканский Филиал Красноярского Политехнического Института filed Critical Ордена Трудового Красного Знамени Научно-Исследовательский Институт Оснований И Подземных Сооружений Им. Н.И.Герсеванова
Priority to SU802880621A priority Critical patent/SU876854A1/en
Application granted granted Critical
Publication of SU876854A1 publication Critical patent/SU876854A1/en

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Description

(54) СПОСОБ О№АЗОВАНИЯ КОТЛОВАНОВ В ПУЧИНИСТЫХ ГРУНТАХ(54) METHOD OF CUTTING FOR WELLS IN LEFTING SOILS

Claims (2)

Изобретение относитс  к строительству и может быть использовано при образовании котлованов в пучинисгых грунтах. В современном фундамент остр оении дл  образовани  котлованов примен ют метод вытрамбовывани , заключающийс  в сбрасывании трамбовки по направл ющей штан- ге 1 .. Недостатком этого способа  вл етс  то что при выполнении работ в пучинистых грунтах не обеспечиваетс  противопучинна  стабилизаци  основани  и стенйс котлована . Известен способ образовани  котловане в песчаных грунтах, заключающийс  в пред варительной пропитке в жущим раствором и последующем вытрамбовывании котлована трамбовкой, сбрасываемой по направ .л юшей . Однако несмотр  на то, что в аанном способе введение в жущего раствора спси. собствует укреплению стенок вытрамбованного котлована, оно все-таки не снимает опасности морозного пучени  грунта. в особеннсжти в ус лежн х высокого уровн  грунтовых вод. к тому же грунт, пропитанный в жущим раствором пр  вьпрам- ; бовывании, остаетс  в вахней чж:тн стенок котлована, уменьша сь с глубиной. Цель изобретени  - жосвидаин  пученн  основани  и стенок котлована. Поставленна  цель достнгаетс  тем, что в известном способе образовани  кот лов ан ОБ, вк1вочаюшем пропитку грунта в жущим раствором и последующее в трамбовыван 1е котлована трамбовкой, в процессе вытрамбовывшн  котлована производ т аопоп ител,ную пропитку грунта в жущим раствором с одас ременной подсыпкой щебн . Введите химического реагента в процессе вытрак бовывани  совместно с по{ сыпкой щебнл обеспечивает более качествевную обработку грунта к уплотнение, что в совокупности привоовт к прекращению миграции влага при промерзани  н пнкввдадии пучени  грунта (противопучиннс . 367 ствбипиаааи1 основани  и стенок котлсюа на). Способ осуществл етс  следующим образом , . На псверхность грунта в лунку, устроен ную по центру будущего котлована, зал№° ваетс  раствор КСЙ (1л 2р%-го раствора ). Вытрамбовьюание производитс  тра1ъ« бовкой в виог заостренного усеченного конуса по направл ющее штанге. В процессе вытрамбовываний производитс  дополнительна  заливка химического реагента с поосыпкой .щебн  в несколько этапов. Поосыпка щебн  обусловлена переувшжнением грунта в результате заливки раствора хи-; мического реагента и засасыванием трам бовки. Использование предлагаемого способа образовани  котлованов в пучинистых грунтах, обеспечивает по сравнению с су шествующими способами возможность уменьшени  глубины заложени  фундамен тов за счет противопучинной обработки основани  вытрамбованного котлована и качествсашое введение реагента в нижние 4 слои грунта путем подсыпки щебн  в прс цессе вытрамбовывани . Формула изобретени  Способ образовани  котлованов в пучииистых грунтах, включающий пропитку грунта в жущим раствором и последующее вытрамбовывание котлсжана трамбовкой, сбрасываемой . lio направл ющей, отличающийс  тем, что, с ивПзЮ ЛИКВ ааиии пучени  основани  и стенок котлована , в пршессе вытрамбовывани  котло . вана производ т дополнительную пропитку грунта в жущим раствором с одновременной подсыпкой щебн . Источники инфqэмaции, прин тые во внимание при экспертизе 1.Авторское свидетельство СССР Mi 702114, хл. Е 02 0 17/00, 1977.  The invention relates to construction and can be used in the formation of pits in retractable soils. In the modern basement of oenia, a ramming method is used to form the trenches, which consists in dropping the tamping along the guide rod 1. The disadvantage of this method is that, when working in heaving soils, the foundation foundation and wall wall of the pit are not provided. There is a known method of forming a pit in sandy soils, which consists in pre-impregnation in a holding solution and subsequent compaction of the pit with a tamper, discharged along the direction of a yushi. However, despite the fact that in the aann method, the introduction of a spsi into the holding solution. contributes to the strengthening of the walls of the rammed pit, it still does not remove the danger of the frosty heel of the soil. especially in high groundwater levels. besides, the soil is impregnated with a grouting solution; Bovyvani, remains in Vahney chzh: tn walls of the pit, decreasing with depth. The purpose of the invention is zhosvidain pusenn the base and walls of the pit. The goal is achieved by the fact that in a known method of formation of coppers en OB, including impregnation of the soil with a holding solution and subsequent tamper removal of the foundation pit by tamping, in the process of extinguishing the excavation, the impregnation of the flow of the treatment of the flow of the material is completed. Enter the chemical reagent in the process of pulling together with the {rubble) rubble to provide better soil treatment to compaction, which together leads to the cessation of migration of moisture when the soil is freezing and frosting (countermeasure of the base and walls of the boiler). The method is carried out as follows. On the surface of the soil in the hole, arranged in the center of the future pit, room # раствор KSY solution (1 L 2 p% solution). The ramming is performed by trapping the pointed truncated cone on the guide bar into the viog. In the process of disintegration, an additional chemical reagent is poured with powder filling in several stages. The sprinkling of rubble is caused by over-drying of the soil as a result of pouring a solution of chi-; chemical reagent and traction suction. The use of the proposed method for the formation of pits in heaving soils provides, compared to existing methods, the possibility of reducing the foundation depth by means of an anti-shoe treatment of the base of the rammed pit and the quality of introducing the reagent into the lower 4 layers of soil by sprinkling gravel in the process of ramming. The invention of the method of formation of pits in the muddy soils, including the impregnation of the soil in the baking solution and the subsequent ramming of the boiler by ramming, discharged. A lio guide, characterized by the fact that, with a thinning of the base and walls of the excavation, in the process of ramming the boiler. An additional impregnation of the soil is carried out in the holding solution with simultaneous addition of rubble. Sources of information taken into account during the examination 1. USSR author's certificate Mi 702114, chl. E 02 17/00, 1977. 2.Автс эское свидетельство СССР по за вке Mi 2768О81/03, кп. Е 02 D 17/04, 1979 (прототип).2.Avts Eskoy certificate of the USSR on the application Mi 2768O81 / 03, CP. E 02 D 17/04, 1979 (prototype).
SU802880621A 1980-02-04 1980-02-04 Method of producing foundation pit in swampy soils SU876854A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU802880621A SU876854A1 (en) 1980-02-04 1980-02-04 Method of producing foundation pit in swampy soils

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU802880621A SU876854A1 (en) 1980-02-04 1980-02-04 Method of producing foundation pit in swampy soils

Publications (1)

Publication Number Publication Date
SU876854A1 true SU876854A1 (en) 1981-10-30

Family

ID=20876893

Family Applications (1)

Application Number Title Priority Date Filing Date
SU802880621A SU876854A1 (en) 1980-02-04 1980-02-04 Method of producing foundation pit in swampy soils

Country Status (1)

Country Link
SU (1) SU876854A1 (en)

Similar Documents

Publication Publication Date Title
CN110344400A (en) The hard rock pore-forming construction technology of churning driven opportunity
CN106522191A (en) Transformer substation foundation treatment method and application thereof
SU876854A1 (en) Method of producing foundation pit in swampy soils
Abelev Compacting loess soils in the USSR
RU2054502C1 (en) Method for making cement/soil piles in caved-in soils
RU2275470C1 (en) Method of floating pile load-bearing capacity increase
RU2289655C1 (en) Method for deep ground compaction
CN104988981B (en) A kind of well construction method of riding on present situation operation shield method drainage pipeline
CN205954647U (en) Miniature stake professional equipment of real airborne water high frequency compaction
CN109577312A (en) A kind of silt geology vibro-replacement stone compacting pile construction method
SU1629415A1 (en) Method of erecting foundation for twin columns and walls
SU1469027A1 (en) Method of working a pit
SU1097744A1 (en) Method of preparing foundation of hydraulic structures on weak soils
RU2097488C1 (en) Consolidation of ground
SU887733A1 (en) Method of constructing a foundation
JPS57108328A (en) Formation of basement
SU1760018A1 (en) Method for erection of foundation
RU2059749C1 (en) Method for erecting walls in ground
SU1719548A1 (en) Method for making foundation
RU1788147C (en) Method for preparation of beds
SU881254A1 (en) Method of erecting cast-in-place pile in bulging soil
SU1742423A1 (en) Method of erection of building foundation
SU1559049A1 (en) Method of making foundation pit
SU1201417A1 (en) Method of improving soil at the base of foundation
SU969824A1 (en) Method of constructing a pile foundation