CN109577312A - A kind of silt geology vibro-replacement stone compacting pile construction method - Google Patents

A kind of silt geology vibro-replacement stone compacting pile construction method Download PDF

Info

Publication number
CN109577312A
CN109577312A CN201811401026.1A CN201811401026A CN109577312A CN 109577312 A CN109577312 A CN 109577312A CN 201811401026 A CN201811401026 A CN 201811401026A CN 109577312 A CN109577312 A CN 109577312A
Authority
CN
China
Prior art keywords
pile
construction
pipe
vibro
compacting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811401026.1A
Other languages
Chinese (zh)
Inventor
周能祥
陈振宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FUJIAN JINDONG MINING Co Ltd
Original Assignee
FUJIAN JINDONG MINING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FUJIAN JINDONG MINING Co Ltd filed Critical FUJIAN JINDONG MINING Co Ltd
Priority to CN201811401026.1A priority Critical patent/CN109577312A/en
Publication of CN109577312A publication Critical patent/CN109577312A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • E02D3/123Consolidating by placing solidifying or pore-filling substances in the soil and compacting the soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention discloses a kind of silt geology vibro-replacement stone compacting pile construction methods, including following construction procedure: (1) site clearing is smooth, (2) surveying setting-out, (3) construction equipment assembling is in place, and (4) pile press machine is in place, (5) impact holing, (6) tube drawing, (7) pile, (8) compacted compacting pore-forming, (9) remove top and loosen layer and the compacting that paves.The compacted inter-pile soil form compound foundation of construction method energy of the invention, can save construction machinery, reduce construction cost, working efficiency is improved, noise and mud pollution are reduced, consumption dregs keeps environment, and the method for the present invention step is simple, design is reasonable, construction technology is simple, and progress is fast, it is at low cost, it is succinct efficient, it is easy to Standardize operation, sequencing, standardization, operator and manager are easy to grasp, the intensity and overall stability that ensure that ground, ensure that construction quality.

Description

A kind of silt geology vibro-replacement stone compacting pile construction method
Technical field
The present invention relates to Foundation Treatment technical field, specifically a kind of silt geology vibro-replacement stone compacting pile construction side Method.
Background technique
Passing Dense Broken Stone Peg is by, to the compacted and vibration densification of silt around, sandy soils, leaning on rubble in formation of pile Indentation obtain consolidation effect, rearrange the grogs around stake closely knit, void ratio reduce, compactness increase.Meanwhile it being formed Dense Broken Stone Peg reinforcement, itself is again a good drainage channel, its presence not only contributes to sand, in powder soil horizon The dissipation of excess pore water pressure effectively enhances the anti-liquefying ability of the soil body, and under the action of load, Dense Broken Stone Peg increases Strong body forms Dense Broken Stone Peg composite earth layer again with sand, powder soil horizon shared load action.
Dense Broken Stone Peg is suitable for loose silt, sand, plain fill and Artifical Fill Ground.Broken stone pile is main in engineering Applied to highway, railway, municipal administration and room build etc. liquescency that flabbiness ground strengthened, embankment slope reinforces, eliminates liquefiable sandy soil, The collapsibility of Compaction variables loess, the shearing resistance non-deformability for increasing ground.Traditional construction construction technology speed is slow, internal broken Stone vibrates unevenly, and stressed effect is poor.
Summary of the invention
The purpose of the present invention is to provide a kind of silt geology vibro-replacement stone compacting pile construction methods, to solve above-mentioned background The problem of being proposed in technology.
To achieve the above object, the invention provides the following technical scheme:
A kind of silt geology vibro-replacement stone compacting pile construction method, including following construction procedure:
(1) site clearing is smooth: being cleared up according to the arrangement and method for construction of design construction site, while eliminating construction site High-altitude and ground obstacle;
(2) surveying setting-out: restoring middle line, releases the stake of section sideline, clears up smooth construction section foundation surface, measure stake Position, and drilling machine is laid in designated position;
(3) construction equipment assembling is in place: assembling pilot hole water filling hidden pipe pile machine and its bracket, and assembling, which is rammed, expands equipment, completes stake Base degree control, water injection equipment debugging;
(4) pile press machine is in place: after selected hydraulic static pile pressing machine installation and debugging are good, at row to stake position, making hydraulic Static pile press clamping jaw center is substantially aligned with the sample stake on ground, levels hydraulic static pile pressing machine, it is ensured that in construction Not run-off the straight and movement, check again it is errorless, by long stride land stress;
(5) impact holing: hammer hidden pipe method pore-forming, when pile top starts to bury, first low hammer tap or low mention are beaten again, wait sink to In soil 1~2m and various aspects it is normal after, then with scheduled speed, fall away from hammer hidden pipe to projected depth.
(6) tube drawing: pile pipe is extracted in time after sinking to projected depth, in order to avoid difficulty in decannulation after frictional resistance increase;Tube drawing is true When real difficult, the method for soaking or try to rotate pile pipe pipe week is taken to reduce resistance in soil.
(7) pile: by defined fillings rubble amount by rubble loading pile pipe, if pile pipe is not accommodated once and should be poured into Whole rubbles, remaining rubble are supplemented being packed into after pile pipe promotes blanking pressure by cibration for a period of time.
(8) compacted compacting pore-forming: compacted pore-forming is combined using equilateral triangle arrangement, pore-forming using " interlacing is beaten every row, jump " Method, compaction in layers pile survives for four times, while at the compacted formation Dense Broken Stone Peg of hole edge filling tamped;
(9) remove top and loosen layer and the compacting that paves: after pilot hole, ramming, surface loosens, and is gone according to condition of construction Except surface loosens layer, surface loosens layer and with backfill carries out place Min layers and fill out to be densified to designed elevation.
As a further solution of the present invention: the hydraulic static pile pressing machine is the piling of hugging pressure type hydraulic static.
As a further solution of the present invention: the hydraulic static pile pressing machine is top press type hydralic static pile press machine.
As a further solution of the present invention: when step (5) hammer hidden pipe, when the gradient of stake is more than 1.5%, pulling out Pipe filling perforation is beaten again.
As a further solution of the present invention: in the step (5), when immersed tube speed be less than 1m/min when, by it is inner outward It hits;When pilespacing is 2.0~2.5 times of stake diameters or pilespacing is less than 2m, constructed using the method that jump point, the row of jump beat.
As a further solution of the present invention: when step (5) impact holing, steel pipe guider on drilling machine, by wall The seamless steel pipe of thick 10mm or more is made, and internal diameter is greater than tup diameter, is highly 2 times of block stamp length.
As a further solution of the present invention: starting tube drawing, side again after should first vibrating 5~10s when step (6) tube drawing Vibration side is pulled out, and tube drawing 1.2m, anti-plug 0.6m mention pipe 0.3m;Land pile pipe, 15~20s of vibration-extrusion, then tube drawing 1.2m, so anti- Again until full pipe is extracted.
Compared with prior art, the beneficial effects of the present invention are:
The compacted inter-pile soil form compound foundation of construction method energy of the invention, can save construction machinery, reduction is constructed into This, improves working efficiency, reduces noise and mud pollution, consumption dregs keeps environment, and the method for the present invention step is simple, design Rationally, construction technology is simple, and progress is fast, at low cost, succinct efficient, is easy to Standardize operation, sequencing, standardization, operator It is easy to grasp with manager, ensure that the intensity and overall stability of ground, ensure that construction quality.
Specific embodiment
Technical solution of the present invention will be clearly and completely described below, it is clear that described embodiment is this hair Bright a part of the embodiment, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art are not having Every other embodiment obtained under the premise of creative work is made, shall fall within the protection scope of the present invention.
Embodiment 1
A kind of silt geology vibro-replacement stone compacting pile construction method, including following construction procedure:
(1) site clearing is smooth: being cleared up according to the arrangement and method for construction of design construction site, while eliminating construction site High-altitude and ground obstacle;
(2) surveying setting-out: restoring middle line, releases the stake of section sideline, clears up smooth construction section foundation surface, measure stake Position, and drilling machine is laid in designated position;
(3) construction equipment assembling is in place: assembling pilot hole water filling hidden pipe pile machine and its bracket, and assembling, which is rammed, expands equipment, completes stake Base degree control, water injection equipment debugging;
(4) pile press machine is in place: after selected hydraulic static pile pressing machine installation and debugging are good, at row to stake position, making hydraulic Static pile press clamping jaw center is substantially aligned with the sample stake on ground, levels hydraulic static pile pressing machine, it is ensured that in construction Not run-off the straight and movement, check again it is errorless, by long stride land stress;Hydraulic static pile pressing machine is that hugging pressure type is hydraulic at this time Static press piling;
(5) impact holing: hammer hidden pipe method pore-forming, when pile top starts to bury, first low hammer tap or low mention are beaten again, wait sink to In soil 1m and various aspects it is normal after, then with scheduled speed, fall away from hammer hidden pipe to projected depth;When immersed tube speed is less than 1m/ When min, hit outward by inner;When pilespacing is 2.0 times of stake diameters or pilespacing is less than 2m, constructed using the method that jump point, the row of jump beat;Hammer When sinking pipe, when the gradient of stake is more than 1.5%, tube drawing filling perforation is beaten again;
When impact holing, steel pipe guider on drilling machine is made of the seamless steel pipe of wall thickness 10mm or more, and internal diameter is greater than hammer Head diameter is highly 2 times of block stamp length;
(6) tube drawing: pile pipe is extracted in time after sinking to projected depth, in order to avoid difficulty in decannulation after frictional resistance increase;Tube drawing is true When real difficult, the method for soaking or try to rotate pile pipe pipe week is taken to reduce resistance in soil;It is opened again after 5s should first be vibrated when tube drawing Beginning tube drawing is pulled out in vibration, and tube drawing 1.2m, anti-plug 0.6m mention pipe 0.3m;Land pile pipe, vibration-extrusion 15s, then tube drawing 1.2m, such as This is repeatedly until full pipe is extracted;Pipe-pulling speed is uniform.
(7) pile: by defined fillings rubble amount by rubble loading pile pipe, if pile pipe is not accommodated once and should be poured into Whole rubbles, remaining rubble are supplemented being packed into after pile pipe promotes blanking pressure by cibration for a period of time.
(8) compacted compacting pore-forming: compacted pore-forming is combined using equilateral triangle arrangement, pore-forming using " interlacing is beaten every row, jump " Method, compaction in layers pile survives for four times, while at the compacted formation Dense Broken Stone Peg of hole edge filling tamped;
(9) remove top and loosen layer and the compacting that paves: after pilot hole, ramming, surface loosens, and is gone according to condition of construction Except surface loosens layer, surface loosens layer and with backfill carries out place Min layers and fill out to be densified to designed elevation.
Embodiment 2
A kind of silt geology vibro-replacement stone compacting pile construction method, including following construction procedure:
(1) site clearing is smooth: being cleared up according to the arrangement and method for construction of design construction site, while eliminating construction site High-altitude and ground obstacle;
(2) surveying setting-out: restoring middle line, releases the stake of section sideline, clears up smooth construction section foundation surface, measure stake Position, and drilling machine is laid in designated position;
(3) construction equipment assembling is in place: assembling pilot hole water filling hidden pipe pile machine and its bracket, and assembling, which is rammed, expands equipment, completes stake Base degree control, water injection equipment debugging;
(4) pile press machine is in place: after selected hydraulic static pile pressing machine installation and debugging are good, at row to stake position, making hydraulic Static pile press clamping jaw center is substantially aligned with the sample stake on ground, levels hydraulic static pile pressing machine, it is ensured that in construction Not run-off the straight and movement, check again it is errorless, by long stride land stress;Hydraulic static pile pressing machine is that roof pressing type is hydraulic at this time Static pile press;
(5) impact holing: hammer hidden pipe method pore-forming, when pile top starts to bury, first low hammer tap or low mention are beaten again, wait sink to In soil 2m and various aspects it is normal after, then with scheduled speed, fall away from hammer hidden pipe to projected depth;When immersed tube speed is less than 1m/ When min, hit outward by inner;When pilespacing is 2.5 times of stake diameters or pilespacing is less than 2m, constructed using the method that jump point, the row of jump beat;Hammer When sinking pipe, when the gradient of stake is more than 1.5%, tube drawing filling perforation is beaten again;
When impact holing, steel pipe guider on drilling machine is made of the seamless steel pipe of wall thickness 10mm or more, and internal diameter is greater than hammer Head diameter is highly 2 times of block stamp length;
(6) tube drawing: pile pipe is extracted in time after sinking to projected depth, in order to avoid difficulty in decannulation after frictional resistance increase;Tube drawing is true When real difficult, the method for soaking or try to rotate pile pipe pipe week is taken to reduce resistance in soil;It is opened again after 10s should first be vibrated when tube drawing Beginning tube drawing is pulled out in vibration, and tube drawing 1.2m, anti-plug 0.6m mention pipe 0.3m;Land pile pipe, vibration-extrusion 20s, then tube drawing 1.2m, such as This is repeatedly until full pipe is extracted;Pipe-pulling speed is uniform;
(7) pile: by defined fillings rubble amount by rubble loading pile pipe, if pile pipe is not accommodated once and should be poured into Whole rubbles, remaining rubble are supplemented being packed into after pile pipe promotes blanking pressure by cibration for a period of time;
(8) compacted compacting pore-forming: compacted pore-forming is combined using equilateral triangle arrangement, pore-forming using " interlacing is beaten every row, jump " Method, compaction in layers pile survives for four times, while at the compacted formation Dense Broken Stone Peg of hole edge filling tamped;
(9) remove top and loosen layer and the compacting that paves: after pilot hole, ramming, surface loosens, and is gone according to condition of construction Except surface loosens layer, surface loosens layer and with backfill carries out place Min layers and fill out to be densified to designed elevation.
The foregoing descriptions are merely the embodiment using this origination techniques content, any those skilled in the art use this wound Make done modifications and changes, all belong to the scope of the patents of this creation opinion, and is not limited to those disclosed embodiments.
If not specified, technological means employed in embodiment is conventional means known to those skilled in the art, institute The reagent and product of use are also available commercial.The source of agents useful for same, trade name and its composition is listed when necessary Ingredient person, is indicated on the first occurrence.

Claims (7)

1. a kind of silt geology vibro-replacement stone compacting pile construction method, including following construction procedure:
(1) site clearing is smooth: being cleared up according to the arrangement and method for construction of design construction site, while eliminating the height of construction site Empty and ground obstacle;
(2) surveying setting-out: restoring middle line, releases the stake of section sideline, clears up smooth construction section foundation surface, measure stake position, and Drilling machine is laid in designated position;
(3) construction equipment assembling is in place: assembling pilot hole water filling hidden pipe pile machine and its bracket, and assembling, which is rammed, expands equipment, completes pile foundation and hangs down Straight degree control, water injection equipment debugging;
(4) pile press machine is in place: after selected hydraulic static pile pressing machine installation and debugging are good, at row to stake position, making hydraulic static Pile press machine clamping jaw center is substantially aligned with the sample stake on ground, levels hydraulic static pile pressing machine, it is ensured that do not send out in construction Raw inclination and mobile, checks errorless again, and long stride is landed stress;
(5) impact holing: hammer hidden pipe method pore-forming, when pile top starts to bury, first low hammer tap or low mention are beaten again, wait sink in soil 1~2m and various aspects it is normal after, then with scheduled speed, fall away from hammer hidden pipe to projected depth.
(6) tube drawing: pile pipe is extracted in time after sinking to projected depth, in order to avoid difficulty in decannulation after frictional resistance increase;Tube drawing is stranded really When difficult, the method for soaking or try to rotate pile pipe pipe week is taken to reduce resistance in soil.
(7) pile: rubble is packed into pile pipe by defined filling rubble amount, if pile pipe does not accommodate the whole that should be poured into once Rubble, remaining rubble are supplemented being packed into after pile pipe promotes blanking pressure by cibration for a period of time.
(8) compacted compacting pore-forming: the side that compacted pore-forming uses " interlacing is beaten every row, jump " using equilateral triangle arrangement, pore-forming is combined Method, compaction in layers pile survives for four times, while at the compacted formation Dense Broken Stone Peg of hole edge filling tamped;
(9) remove top and loosen layer and the compacting that paves: after pilot hole, ramming, surface loosens, and removes table according to condition of construction Face loosens layer, and surface loosens layer and with backfill carries out place Min layers and fill out to be densified to designed elevation.
2. silt geology vibro-replacement stone compacting pile construction method according to claim 1, characterized in that the hydraulic static Pile press machine is the piling of hugging pressure type hydraulic static.
3. silt geology vibro-replacement stone compacting pile construction method according to claim 1, characterized in that the hydraulic static Pile press machine is top press type hydralic static pile press machine.
4. silt geology vibro-replacement stone compacting pile construction method according to claim 1, characterized in that the step (5) When hammer hidden pipe, when the gradient of stake is more than 1.5%, tube drawing filling perforation is beaten again.
5. silt geology vibro-replacement stone compacting pile construction method according to claim 1, characterized in that the step (5) In, when immersed tube speed is less than 1m/min, hit outward by inner;When pilespacing is 2.0~2.5 times of stake diameters or pilespacing is less than 2m, adopt The method construction beaten with jump point, the row of jump.
6. silt geology vibro-replacement stone compacting pile construction method according to claim 1, characterized in that the step (5) When impact holing, steel pipe guider on drilling machine is made of the seamless steel pipe of wall thickness 10mm or more, and internal diameter is greater than tup diameter, The block stamp length that height is 2 times.
7. silt geology vibro-replacement stone compacting pile construction method according to claim 1, characterized in that the step (6) Start tube drawing again after 5~10s should first be vibrated when tube drawing, is pulled out in vibration, tube drawing 1.2m, anti-plug 0.6m mention pipe 0.3m;Landing stake Pipe, 15~20s of vibration-extrusion, then tube drawing 1.2m, repeatedly until full pipe is extracted.
CN201811401026.1A 2018-11-22 2018-11-22 A kind of silt geology vibro-replacement stone compacting pile construction method Pending CN109577312A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811401026.1A CN109577312A (en) 2018-11-22 2018-11-22 A kind of silt geology vibro-replacement stone compacting pile construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811401026.1A CN109577312A (en) 2018-11-22 2018-11-22 A kind of silt geology vibro-replacement stone compacting pile construction method

Publications (1)

Publication Number Publication Date
CN109577312A true CN109577312A (en) 2019-04-05

Family

ID=65923436

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811401026.1A Pending CN109577312A (en) 2018-11-22 2018-11-22 A kind of silt geology vibro-replacement stone compacting pile construction method

Country Status (1)

Country Link
CN (1) CN109577312A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110847163A (en) * 2019-12-17 2020-02-28 徐鹏 Pulse pile foundation bottom expanding construction method and device

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101319500A (en) * 2008-07-21 2008-12-10 中铁七局集团第三工程有限公司 Construction method of static pressure compaction pile
CN102864774A (en) * 2012-10-10 2013-01-09 江苏南通六建建设集团有限公司 Shrinkage treatment construction method for composite foundation- lime soil compaction piles
CN107905212A (en) * 2017-09-27 2018-04-13 中铁三局集团有限公司 A kind of construction method of original position water filling element earth pile composite foundation
CN108643172A (en) * 2018-04-02 2018-10-12 济南城建集团有限公司 Silt geology vibro-replacement stone compacting pile construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101319500A (en) * 2008-07-21 2008-12-10 中铁七局集团第三工程有限公司 Construction method of static pressure compaction pile
CN102864774A (en) * 2012-10-10 2013-01-09 江苏南通六建建设集团有限公司 Shrinkage treatment construction method for composite foundation- lime soil compaction piles
CN107905212A (en) * 2017-09-27 2018-04-13 中铁三局集团有限公司 A kind of construction method of original position water filling element earth pile composite foundation
CN108643172A (en) * 2018-04-02 2018-10-12 济南城建集团有限公司 Silt geology vibro-replacement stone compacting pile construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110847163A (en) * 2019-12-17 2020-02-28 徐鹏 Pulse pile foundation bottom expanding construction method and device

Similar Documents

Publication Publication Date Title
CN106013191B (en) Environment-friendly type grass planting Concrete Highway protective slope structure and construction method
CN106638673B (en) A kind of construction method of compound retaining structure
CN205999903U (en) Environment-friendly type grass planting Concrete Highway protective slope structure
CN101736738B (en) Production method of pressure resistance and pull-out resistance grouted gravel pile
CN106677154A (en) Collapsible loess foundation rubble frame structure reinforcement system and reinforcement method
CN104499479A (en) Dig-hole pile construction method based on penetration of sand gravel backfilling layer
CN111058443B (en) Precast pile composite foundation construction method for eliminating loess collapsibility
CN102864774A (en) Shrinkage treatment construction method for composite foundation- lime soil compaction piles
CN104314078A (en) Concrete pile construction equipment and construction method thereof
CN110685286A (en) Deep foundation pit supporting construction process for adjacent road under complex geological condition
CN106948340A (en) A kind of construction method of the Manual excavated pile structure of high polymer grouting protection
CN104480956B (en) A kind of minor diameter mold-bagged concrete pile composite foundation
CN109594442A (en) Garden path construction technology
CN1191257A (en) Method for construction of concrete pile
CN108824412B (en) Soft foundation treatment method based on gabion wall reinforced soil and dynamic compaction combination
CN1043263C (en) Construction method for building foundation pit stope support
CN109577312A (en) A kind of silt geology vibro-replacement stone compacting pile construction method
CN108385667A (en) A kind of geotextiles anti-block water permeable pile driving construction device and method
CN104727295A (en) Pre-hole-forming padding substitution hammer flattener dynamic compaction method
CN100396854C (en) Column-hammer strong-tamper displacing base kit supporting construction method
CN206625207U (en) A kind of collapsible loess foundation rubble frame structure reinforcement system
CN1137311C (en) Vibration compacted galet pile resisting pull-up and floatation, and its forming method
CN1514073A (en) Supporitng structure of breast wall
CN1047716A (en) Utilize the method and the facility of industrial residue comprehensive treatment soft foundation
CN209760216U (en) reinforcement system based on soft soil foundation drainage consolidation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190405