Method of constructing a dam of locally available materials Download PDF

Info

Publication number
SU829770A1
SU829770A1 SU792729899A SU2729899A SU829770A1 SU 829770 A1 SU829770 A1 SU 829770A1 SU 792729899 A SU792729899 A SU 792729899A SU 2729899 A SU2729899 A SU 2729899A SU 829770 A1 SU829770 A1 SU 829770A1
Authority
SU
USSR - Soviet Union
Prior art keywords
dam
ice
constructing
banquet
available materials
Prior art date
Application number
SU792729899A
Other languages
Russian (ru)
Inventor
Владимир Иванович Астафичев
Original Assignee
Куйбышевский Филиал Всесоюзного Орденаленина Проектно-Изыскательского И Научно- Исследовательского Института "Гидропроект"Им. C.Я.Жука
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Куйбышевский Филиал Всесоюзного Орденаленина Проектно-Изыскательского И Научно- Исследовательского Института "Гидропроект"Им. C.Я.Жука filed Critical Куйбышевский Филиал Всесоюзного Орденаленина Проектно-Изыскательского И Научно- Исследовательского Института "Гидропроект"Им. C.Я.Жука
Priority to SU792729899A priority Critical patent/SU829770A1/en
Application granted granted Critical
Publication of SU829770A1 publication Critical patent/SU829770A1/en

Links

Landscapes

  • Revetment (AREA)

Description

VV

.Изобретение относитс  к гидротехническому строительству, а именно к способам сооружени  плотин из местных материалов в суровых климатических услови х при наличии в реке льда.The invention relates to hydrotechnical construction, in particular, to methods for constructing dams from local materials in severe climatic conditions if there is ice in the river.

Известен способ сооружени  плотин из местных материалов путем предварительного перекрыти  .русла банкетом с последующей отсыпкой тела плотины 1There is a known method of constructing dams from local materials by preliminarily blocking the floor with a banquet followed by dumping the body of the dam 1

Недостатком этого способа  вл етс  то, что его использование возможно только при отсутствии льда в реке.The disadvantage of this method is that its use is possible only in the absence of ice in the river.

Наиболее близким к изобретению по техническому решению  вл етс  способ сооружени  плотин из местных материалов, включающий перекрытие русла банкетом с образованием прорана и возведени  части плотины 2.The closest to the invention according to the technical solution is a method of constructing dams from local materials, including closing the channel with a banquet to form an aperture and erect part of the dam 2.

Недостатком этого способа  ол етс  то, что применение его возможно . лишь при отсутствии льда в реке, чтоThe disadvantage of this method is that it can be used. only in the absence of ice in the river that

вызывает необходимость более ранне .го перекрыти  русла реки, а, следовательно , и более раннего прекращени судоходства. Кроме того попадание льда в тело плотины снижает ее надежность .necessitates an earlier crossing of the river bed, and, consequently, an earlier cessation of navigation. In addition, the ingress of ice into the body of the dam reduces its reliability.

Цель изобретени  - повышение надежности плотины, посредством предупреждени  попадани  льда в ее телоThe purpose of the invention is to increase the reliability of the dam, by preventing ice from falling into its body.

Поставленна  цель достигаетс  тем, что осуществл ют перекрытие про рана фильтрующим сооружением, располагаемым выше по течению, а после удалени  льда за ним, возвод т замыкающую часть плотины, причем в качестве фильтрующего сооружени  может быть использована дамба из фильтрующего материала.The goal is achieved by overlapping the wound with a filtering structure located upstream, and after removing the ice behind it, the closing part of the dam is erected, and a dam of filtering material can be used as a filtering structure.

На фиг. 1 показана схема-организации сооружени  плотины; на фиг, банкет, разрез; на фиг. 3 дамба из фильтруюшего , поперечное сечение.FIG. 1 shows the organization of the construction of the dam; fig, banquet, section; in fig. 3 filter dam, cross section.

Способ осуществл етс  следующим образом.The method is carried out as follows.

Со стороны берега (или обоих бере гов) отсыпают банкет 1 из невлекомого материала, параллельно возвод т пло-тину 2. Причем намывают (или отсыпапают ) ее с .некоторым отставанием, . , обеспечивающим возведение плотины без выноса грунта выше допустимых пределов . После начала льдообразовани  и достижени  количества льда в плотине выше допустимых пределов отсыпку низового банкета 1 прекращают и окончательное перекрытие русла осуществл ют возведением дамбы 3 из фильтрующего воду материала, например камн .From the coast (or both banks), a banquet 1 is poured from unweakable material, and a dam 2 is erected in parallel. Moreover, it is washed in (or poured out) with some lag,. , ensuring the construction of the dam without the removal of the soil above the permissible limits. After the start of ice formation and reaching the amount of ice in the dam above the permissible limits, dumping of the downstairs banquet 1 is stopped and the final closing of the channel is carried out by erecting a dam 3 of water-filtering material, such as stone.

Вследствие того, что призма способна фильтровать воду, ниже нее возникает Поток t. Этим потоком из емкос ти, в зоне которой возводитс  замыкающий участок русловой плотины между .банкетом 1, дамбой 3 и торцами намытых частей плотины 2, лед 5 выноситс  8 ни) бьеф. При недостаточности транспортирующей способности фильтрационного потока увеличивают его расход путем закладки в дамбу труб 6, соориентированных в направление потока. При этом трубы укладывают таким образом, чтобы их входное отверстие 7 было отделено от в%рхового откоса дамбы слоем материала. Назначение этого сло  - задержать лер 8 в верхнем бьефе, т.е. выше дамбы.Due to the fact that the prism is capable of filtering water, a Flow t occurs below it. This flow from the tank, in the zone of which the closing section of the channel dam is erected between banquet 1, dam 3 and the ends of the washed parts of the dam 2, ice 5 is carried out 8 ni) pool. When insufficiency of the transporting ability of the filtration flow increases its flow rate by laying in the dam pipe 6, oriented to the direction of flow. In this case, the pipes are laid in such a way that their inlet opening 7 is separated from the dam slope of the dam in% by layer of material. The purpose of this layer is to delay ler 8 in the upstream, i.e. above the dam.

Дл  устранени  заполнени  трубы материалом дамбы на участке, примыкающем к входному отверстию трубы, устанавливают решетку или фильтр.To eliminate the filling of the pipe with the material of the dike in the area adjacent to the inlet of the pipe, install a grid or filter.

После выноса льда фильтрационным потоком производ т смыкание бан кета и возведение плотины на замыкающем участке.After the removal of ice by the seepage flow, the junction is closed and the dam is erected in the closing section.

Технико-экономическ,ий эффект от внедрени  изобретени  более 1 млн. руб. получен за счет более позднего прекращени  судоходства, а также за счет обеспечени  необходимого качества сооружени .Technical and economic effect of the invention implementation more than 1 million rubles. obtained by stopping shipping later, as well as by ensuring the required quality of the structure.

Claims (2)

1.Способ сооружени  плотин из местных материалов в суровых климатических услови х,включающий перек-рытие русла банкетом с оЬразованием прорана и возведение части плотины, отличающийс  тем, что, с целью повышени  надежности плотины посредством предупреждени  попадани  льда в ее тело, осуществл ют перекрытие прорана фильтрующим сооржением , располагаемым выше по течению , а после удалени  льда за ним, возвод т замыкающую часть плотины,1. A method of constructing dams from local materials in harsh climatic conditions, including overlapping a channel with a banquet, forming a hole and building a part of the dam, characterized in that, in order to increase the reliability of the dam by preventing ice from entering the body, upstream filtering, and after removing the ice behind it, the closing part of the dam is erected, 2.Способ по п„1, отличающий с   тем, что в качестве фильтрующего сооружени  используют дамбу из фильтрующего материала.2. A method according to claim 1, characterized in that a dam of filter material is used as the filtering structure. : Источники информации, прин тые во внимание при экспертизе: Sources of information taken into account in the examination 1.Волжска  ГЭС.им. ХХП съезда КПСС ,, т.2. 1969, рис. 1У-35.1.Volzhsk hydroelectric station HHP Congress of the CPSU, v.2. 1969, fig. 1U-35. 2.Николаев Ю. Г. и др. Пропуск расходов реки при строительстве гидроузлов, 19б9, Со 49.2.Nikolaev, Yu.G., et al. Passage of river discharge during the construction of waterworks, 19b9, Co 49. ОABOUT .g иг.Зig.Z
SU792729899A 1979-02-23 1979-02-23 Method of constructing a dam of locally available materials SU829770A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU792729899A SU829770A1 (en) 1979-02-23 1979-02-23 Method of constructing a dam of locally available materials

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU792729899A SU829770A1 (en) 1979-02-23 1979-02-23 Method of constructing a dam of locally available materials

Publications (1)

Publication Number Publication Date
SU829770A1 true SU829770A1 (en) 1981-05-15

Family

ID=20812346

Family Applications (1)

Application Number Title Priority Date Filing Date
SU792729899A SU829770A1 (en) 1979-02-23 1979-02-23 Method of constructing a dam of locally available materials

Country Status (1)

Country Link
SU (1) SU829770A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2007038851A1 (en) * 2005-10-03 2007-04-12 Sergej Mikhailovich Kozlov Dough-dividing head

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2007038851A1 (en) * 2005-10-03 2007-04-12 Sergej Mikhailovich Kozlov Dough-dividing head

Similar Documents

Publication Publication Date Title
SU829770A1 (en) Method of constructing a dam of locally available materials
CN112267419A (en) Automatic dredging, intercepting, sewage discharging and water transporting port on coastal region
RU2742145C1 (en) Alluvial hydraulic structure
DE29517681U1 (en) Removal shaft for the draining and suction of water from surface water
SU83153A1 (en) Dam intake
RU2758619C1 (en) Ground dam with filter spillway
SU595449A1 (en) Method of constructing earth-filled structures
SU918394A1 (en) Method of closing-off river bed in the presence of broken ice
SU1254098A1 (en) Method of passing flood flow over underconstructed dam of local materials
SU1569363A1 (en) Method of blocking bed of river
SU1291653A1 (en) Method of passing construction flaws under a dam
SU953074A1 (en) Method of damming a river bed
SU1114728A1 (en) Method for hydraulically filling structures
SU1117367A1 (en) Dam
JPS5949372B2 (en) Erosion control method for upstream rivers or small rivers, etc.
RU2050433C1 (en) Redundant spillway of earth retaining construction
SU1698354A1 (en) Method of erecting weirs
CN114351654A (en) Three-layer filtering bottom barrier dam structure
SU1446225A1 (en) Method of damming river flow
SU1596003A1 (en) Method of errecting earth-filled structure
AT205422B (en) River power plant
KR20010036230A (en) Drainage culvert to exclude sediment in front of gates in estuary
CN117721875A (en) Arc-shaped water taking structure of mountain area sediment-rich river channel and construction method thereof
SU1063915A1 (en) Method of constructing a dam of locally avaiable materials
RU1804436C (en) Burnt pyrites pulp accumulator