SU697743A1 - Reinforcement for solidifying filling-in mass - Google Patents

Reinforcement for solidifying filling-in mass

Info

Publication number
SU697743A1
SU697743A1 SU782632225A SU2632225A SU697743A1 SU 697743 A1 SU697743 A1 SU 697743A1 SU 782632225 A SU782632225 A SU 782632225A SU 2632225 A SU2632225 A SU 2632225A SU 697743 A1 SU697743 A1 SU 697743A1
Authority
SU
USSR - Soviet Union
Prior art keywords
rods
beams
layer
hooks
soil
Prior art date
Application number
SU782632225A
Other languages
Russian (ru)
Inventor
Игорь Иосифович Ануфриев
Игорь Николаевич Агафонов
Иван Семенович Цыкалов
Петр Федорович Ракитин
Original Assignee
Предприятие П/Я М-5703
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Предприятие П/Я М-5703 filed Critical Предприятие П/Я М-5703
Priority to SU782632225A priority Critical patent/SU697743A1/en
Application granted granted Critical
Publication of SU697743A1 publication Critical patent/SU697743A1/en

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

(54) АРМАТУРА ДЛЯ ТВЕРДЕЮЩЕЙ ЗАКЛАДКИ(54) ARMATURE FOR FIRMING BOOKMARKING

Claims (2)

Изобретение относитс  к горной промышленности и может быть использовано при подземной разработке месторождений полезных ископаемых с закладкой выработанного пространства . Известна арматура дл  твердеющей закладки при обработке горизонтальными сло ми, включающа  металлические балки, концы которых заведены в ненарушенные вмещающие породы лежачего и вис чегобоков 1. Недостатком указаннойарматуры,  вл етс-  дополнительный объем горных работ по заделке концов балок в боковые породы. Кроме того,, известна арматура дл  твердеющей закладки при отработ сло ми сверху вниз, включающа  укла дываемые на каждую почву сло  балки с гибким перекрытием и стержни, прикрепленные одним концом к балкам и установленные р дами в плоскости, перпендикул рной почве сло . В балках выполнены резьбовые отверсти , в которые ввинчены анкеры (стержни) Анкеры соединены между собой и прикреплены к стенкам выработки дл  их устойчивости при вЪзведении закладо ного массива 2 . rieдocтaткaми данной арматуры  вл етс  то, что анкерные элементы устройства , расположенные в пределах одного отработанного сло , не св заны с вышележащими заложенными сло ми, а таскже больша  трудоемкость монтажных работ, установки и креплени  анкирующик стержней, больша  металлоемкость устройства. Целью насто щего изобретени   ветс  снижение трудоемкости монтажа арматуры i увеличение прочности твердеющей закладки. Это достигаетс  тем, что концы стержней выполнены в виде крюков и соединены другими концами с концами стрежней вышележащего сло , причем конщл каждого р да стержней нижележащего сло  соединены с концами стержней соседних р дов вьлиележащего С.17ОЯ, а в зоне контакта с балкой криволинейна  часть крюка дополнительно изогнута с меньшим радиусом кривизны. На фиг. 1 - разрез отрабатываемого участка; на фиг. 2 - разрез А-А фиг. 1; на фиг. 3 - конструкци  стержн . Афматура состоит из балок 1,стержней 2 и гибкого перекрыти  3. Стержень 2 представл ет собой мета.плический пруток 4 с отогнутыми концами 5 и 6 в виде ,дрюков. На криволинейной части крюка 5 выгюднейГ дополнительный изгиб (петл ) 7, Балки 1 помещены в крюки 5 стерж ей 2 . В отработаннотл, но еще не заложе ном слое 8 на почве, уложены в неско ко р дов балки 1 так, что петли 7 крюков 5 утоплены в породу, rfa балках 1 размещено гибкое предохраните ное перекрытие 3. Противоположные к цы анкеров с крюками б заведены в обнажившиес  после проходки петли 7 вышележащего сло  9 твердеющей закл ки,Стержни 2 расположены крестообразно , так что крюки на их противополохшых концах соединены со стрежн ми 2 соседних р дов. в случае необходимости в отрабатываемом слое 8 могут быть применены распоры 10. Дл  подачи закладочной смеси служит трубопровод 11. Монтаж арматуры осуществл етс  следующим образом. При отработке очередного сло , в кровле выработки 8 обнажаютс  петли 7 крюков 5 заложенного вышележащего сло  9. В эти крюки завод т отог тые концы 6 стержней 2, а в другие концы 5 укладываютс  балки 1. Петли 7 концов стрежней утапливаютс  в почву сло .8 так, что балки приход т в соприкосновение с почвой. Пр этом стержни 2 у кровли и почвы вы работки 8 оказываютс  св занными с балками 1 соседних р дов так, что прутки 4 крестообразно пересекаютс  в пространстве. На балки 1 укла дываетс  гибкое перекрытие 3. В подготовленное таким образом отработанное пространство сло  8 с помощью трубопровода 11 подаетс  закладочна  смесь. В результате весь закладочный м сив оказываетс  армированньм прост ранственной решеткой из св занных между собой стержней 2 и балок 1, что позвол ет устанавливать распоры 10 с большим шагом или вообще от них отказатьс . Така арматура позвол ет увеличить прочность закладочного массива , который оказываетс  армированным по всему объему св занным между стержн ми и балками. Боковой подвижке закладочной смеси в преелах этажа преп тствуют стержни, установленные крестообразно,с уменьшенной площадью проемов. Подвижке между соседними сло ми твердеющей закладке мешает св зь между стержн ми и балками в каждом из этих слоев. Операции по монтажу данной арматуры менее трудоемки. Отпадают операции завинчивани  анкеров в балки и крепление их в вертикальном положении специальными ст жками. Балки просто укладываютс  в крюки стержней , а заведение двух концов стержней в крюки кровли облегчаетс  тем, что на крюках выполнены специальные . петли. Така  конструкци  позвол ет, кроме того, снизить металлоемкость устройства , так как отпадает необходимость в крепежных детал х, специальных раст жках и пластинах дл  лучшего сцеплени  стержней с закладкой. Формула изобретени  1.Арматура дл  твердеющей закладки при отработке сло ми сверху вниз, вклющающа  укладываемые на почву каждого сло  балки с гибким перекрытием и .стержни, прикрепленные одним концом к балкам и установленные р дами в плоскости, перпендикул рной почве сло , отличающа с  тем ( что ( с целью снижени  трудоем-. кости монтажа арматуры и увеличени  прочности твердеющей закладки,, концы стрежней выполнены в виде крючков и соединены другими концами с концами стержней вышележащего сло , причем концы каждого р да стрежней нижележащего сло  соединены с концами стержней соседних р дов вышележащего сло . 2.Арматура по п. 1, отличающа с  тем, что в зоне контакта с балкой криволинейна  часть крючка дополнительно изогнута с меньшим радиусом кривизны. Источники информации, прин тые эо внимание при экспертизе 1.Авторское свидетельство ЧССР № 162540, кл. 5 с 15/48, опублик. 1976. The invention relates to the mining industry and can be used in the underground mining of mineral deposits with the laying of the goaf. Known reinforcement for hardening bookmarks in the processing of horizontal layers, including metal beams, the ends of which are inserted into the undisturbed host rock of the lying and visually side 1. The disadvantage of this reinforcement is the additional amount of mining work on embedding the ends of the beams in the lateral rocks. In addition, there is a well-known reinforcement for hardening bookmarks when worked with layers from top to bottom, including beams placed on each soil with flexible overlap and rods attached at one end to the beams and installed in rows in a plane perpendicular to the soil of the layer. The beams are made with threaded holes, into which the anchors (rods) are screwed. The anchors are interconnected and attached to the walls of the mine to ensure their stability when the mortgage array 2 is inserted. The reliance on this reinforcement is that the anchoring elements of the device located within the same waste layer are not associated with the overlying laid layers, and the greater laboriousness of the installation work, installation and fastening of the anchoring rods, is a greater metal intensity of the device. The aim of the present invention is to reduce the complexity of the installation of reinforcement and increase the strength of the hardening tab. This is achieved by the fact that the ends of the rods are made in the form of hooks and are connected to the other ends with the ends of the rods of the overlying layer, with each row of rods of the underlying layer being connected to the ends of the adjacent rows of overlying C.17OJ, and in the zone of contact with the beam the curved part of the hook additionally curved with a smaller radius of curvature. FIG. 1 - a section of the working area; in fig. 2 - section A-A of FIG. one; in fig. 3 - rod structures. Afmatura consists of beams 1, rods 2 and flexible overlap 3. Rod 2 is a metaplate rod 4 with bent ends 5 and 6 in the form of drikov. On the curvilinear part of the hook 5, the additional bend (loop) 7, Beams 1 are placed in the hooks 5 of the rod 2. In the developed, but not yet laid, layer 8 on the soil, several beams of rows 1 are laid in such a way that the loops of 7 hooks 5 are recessed into the rock, rfa beams 1 contain a flexible safety cover 3. Opposite to the chains of anchors with hooks are mounted in the exposed hinge 7 of the overlying layer 9 of the hardening hinge, the rods 2 are located crosswise, so that the hooks at their anti-slip ends are connected to the cores of 2 adjacent rows. if necessary, spacers 10 can be used in the layer 8 to be processed. Pipeline 11 serves to feed the filling mixture. The fittings are installed as follows. When working out the next layer, in the roof of the excavation 8, loops 7 of hooks 5 of the pledged overlying layer 9 are exposed. These ends are folded over the ends of 6 rods 2, and beams 1 are laid into the other ends of 5 loops. The 7 ends of the ends of the rods sink into the soil of the layer. 8 so that the beams come in contact with the soil. Before this, the rods 2 at the roof and the soil of excavation 8 are connected with the beams 1 of the adjacent rows so that the rods 4 cross crosswise in space. A flexible overlap 3 is placed on the beams 1. In the thus prepared waste space of the layer 8, a backfill mixture is fed through the pipe 11. As a result, the entire backfill space turns out to be a reinforced spatial lattice of interconnected rods 2 and beams 1, which allows you to install spacers 10 with a large pitch or refuse them altogether. Such reinforcement allows to increase the strength of the backfill array, which is reinforced throughout the entire volume connected between the rods and the beams. The lateral movement of the filling mixture in the floor area is hindered by rods that are installed crosswise with a reduced opening area. The movement between adjacent layers of the hardening tab is hampered by the connection between the rods and the beams in each of these layers. The installation of this valve is less time consuming. The operations of screwing anchors into the beams and fixing them in a vertical position with special brackets are no longer possible. The beams are simply placed in the hooks of the rods, and the insertion of the two ends of the rods into the hooks of the roof is facilitated by the fact that special hooks are made on the hooks. loops. Such a design also makes it possible to reduce the metal consumption of the device, since there is no need for fasteners, special tension and plates for better adhesion of the rods with the tab. 1. Armature for hardening bookmarks when working from top to bottom, including stacked on the soil of each layer of the beam with a flexible overlap and rods attached at one end to the beams and installed in rows in a plane, perpendicular to the soil of the layer, which differs from that (in order to reduce labor-intensive installation of the reinforcement and increase the strength of the hardening bookmark, the ends of the rods are made in the form of hooks and are connected to the other ends with the ends of the rods of the overlying layer, with the ends of each row and rods below 2. The fixture according to claim 1, characterized in that in the zone of contact with the beam, the curvilinear part of the hook is additionally bent with a smaller radius of curvature. Sources of information taken eto attention during the examination 1 .Certificate of Czechoslovakia No. 162540, Cl. 5 of 15/48, published 1976. 2.Патент ГДР № 113055, кл. 5 с 17/00, опублик. 1975 (прототип).2. Patent of the GDR No. 113055, cl. 5 from 17/00, published. 1975 (prototype).
SU782632225A 1978-06-21 1978-06-21 Reinforcement for solidifying filling-in mass SU697743A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU782632225A SU697743A1 (en) 1978-06-21 1978-06-21 Reinforcement for solidifying filling-in mass

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU782632225A SU697743A1 (en) 1978-06-21 1978-06-21 Reinforcement for solidifying filling-in mass

Publications (1)

Publication Number Publication Date
SU697743A1 true SU697743A1 (en) 1979-11-15

Family

ID=20771647

Family Applications (1)

Application Number Title Priority Date Filing Date
SU782632225A SU697743A1 (en) 1978-06-21 1978-06-21 Reinforcement for solidifying filling-in mass

Country Status (1)

Country Link
SU (1) SU697743A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102606205A (en) * 2011-11-29 2012-07-25 新奥气化采煤有限公司 In-situ treatment method for underground gob

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102606205A (en) * 2011-11-29 2012-07-25 新奥气化采煤有限公司 In-situ treatment method for underground gob
CN102606205B (en) * 2011-11-29 2014-11-26 新奥气化采煤有限公司 In-situ treatment method for underground gob

Similar Documents

Publication Publication Date Title
US4605338A (en) Culvert
NO320628B1 (en) Metal wire netting for protection against rock breeding or securing a soil layer, as well as methods and apparatus for making it
CN208328952U (en) Side slope Initiative Defence System
Haile Observations of the dynamic performance of South African tunnel support systems
SU697743A1 (en) Reinforcement for solidifying filling-in mass
US8485760B2 (en) Tire georeinforcing system
CN111425247B (en) Downward access filling body false roof with built-in prefabricated metal mesh reinforcing structure and construction method thereof
US4413928A (en) Reinforcing and confining earth formation
SU1745817A1 (en) Pit slope stabilizing covering
RU2471992C1 (en) Mine barrier
RU2197667C2 (en) Method of construction of underground pipeline in section of tectonic faults
CN108979641A (en) The construction method of structure in ground
RU2099539C1 (en) Device for reinforcing the fill mass
SU400704A1 (en) COMBINED SYSTEM FOR THE DEVELOPMENT OF POWERFUL RIGHT STRAAMS
RU160345U1 (en) MINING
SU1125380A1 (en) Flexible protecting web
RU116514U1 (en) PROTECTIVE COVERED MESH DESIGNS
RU114340U1 (en) BOARD CAREER
RU132094U1 (en) ANCHORED L-SHAPED BRACKET FOR UNIVERSAL FLEXIBLE PROTECTIVE CONCRETE MAT
SU1154487A1 (en) Reinforcement for strengthening laminar filling solid mass
SU635242A1 (en) Self-suspending inter-seam covering
SU935626A1 (en) Anchor bolt and top bar for workings with arched roof
RU1795109C (en) Movable shield-type support
KR200253330Y1 (en) Reinforced Earth Retaining-Wall for using Steel-Frame and Geogrid
SU622930A1 (en) Method of mounting soil anchor