Appliance for erecting monolithic reinforced concrete covering at building rigidity core

Info

Publication number
SU655803A1
SU655803A1 SU762408753A SU2408753A SU655803A1 SU 655803 A1 SU655803 A1 SU 655803A1 SU 762408753 A SU762408753 A SU 762408753A SU 2408753 A SU2408753 A SU 2408753A SU 655803 A1 SU655803 A1 SU 655803A1
Authority
SU
USSR - Soviet Union
Prior art keywords
building
reinforced concrete
appliance
monolithic reinforced
rigidity core
Prior art date
Application number
SU762408753A
Other languages
Russian (ru)
Inventor
Анатолий Кузьмич Астахов
Юрий Александрович Мизонов
Александр Гаврилович Курочкин
Станислав Иосифович Андреев
Original Assignee
Трест "Мосоргстроя" При Главмосстрое
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Трест "Мосоргстроя" При Главмосстрое filed Critical Трест "Мосоргстроя" При Главмосстрое
Priority to SU762408753A priority Critical patent/SU655803A1/en
Application granted granted Critical
Publication of SU655803A1 publication Critical patent/SU655803A1/en

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

кую раму 3 из двух параллельных двутавров , к которым приварены пеньки колонн 4 дл  закреплени  подъемников 2, и стойки 5. Коладевыв подмости 1 в двух  русах снабжены самозаход щими в проемы  дра жесткости шарнирными опорными кронштейнами 6, 7 с прети- вовесами 8. Опорные кронштейны ниж него  руса 6 закреплены на несъемной оси 9 и в рабочем положении упираютс  в упор 1О стоек подмостей 5, служащих дл  креплени  опорного кронштейна верхнего  руса 7, который поворачиваетс  вокруг оси 11 и фиксируетс  пальцевым замком 12 в рабочее положение . Стойки подмостей S снабжены ступен ми 13, образующими лестницу. К торцу опорного конца кронштейна приварена гайка 14 под болт 15 коромыслового анкера 16. КЬромысловый анкер 16 выполнен в виде балки с отверстием под болт. На болт ПОСТОЯННО надета шайба 17. Кольцевые подмости 1 снабжены со всех сторон упорными винтами 18. Опорный кронштейн нижнего  руса -6 снабже навешиваемым компенсирующим упорным пакетом 19. Пластины разной толщины креп тс  винтами к базовому компенса тору, образу  компенсирующий упорный пакет 19. К спаренной металлической раме 3 приварены консоли 20t на которых крепитс  настил подмостей и ограждение сплошное по внешнему периметру и с калиткой дл  входа по внутреннему периметру.which frame is 3 of two parallel I-beams, to which the stumps of the columns 4 for fixing the lifts 2 are welded, and the struts 5. The tandem of the scaffold 1 in two tusks is equipped with hinged support brackets 6, 7 with curtain weights 8. Self-supporting the lower shaft 6 is fixed on the fixed axis 9 and, in the working position, abut against the stop 1O of the scaffold posts 5, which serve to fasten the support bracket of the upper tier 7, which rotates around the axis 11 and is fixed by the finger lock 12 to the working position. The scaffold posts S are provided with steps 13 forming a staircase. A nut 14 under the bolt 15 of the beam anchor 16 is welded to the end of the support end of the bracket. The rocker anchor 16 is made in the form of a beam with a hole for the bolt. The washer 17 is permanently attached to the bolt. The annular scaffolding 1 is equipped with retaining screws 18 on all sides. The support bracket of the lower tier -6 is supplied with a hanging compensating support package 19. The plates of different thickness are screwed to the base compensator to compensate the thrust package 19. the metal frame 3 is welded to the console 20t on which the scaffolding is fixed and the fence is solid around the outer perimeter and with a wicket for entry along the inner perimeter.

Внизу на  дро жесткости одевают кольцевые подмости 1, состо щие из двух разъемных частей, и жестко соедин ют их между собой. Подъемники 2 надевают на опоры колонн 4 и закрепл ют упорными винтами 18, Производ т строповку лебедками, устаювлевными на крыше  дра жесткости, до первой сто нки кольцевых подмостей с подъемниками. При этом все шарнирно опорные кро{аитены 6, 7 под воздействием противовесов 8 вход т в проемы стен  дра жесткости. Опускают приспособление до посадки каждого кронштейна нижнего  руса 6 на порог проемов  дра ж«;ткости. Рабочие вход т на кольцевые йодмэсти 1, упор-At the bottom, an annular scaffolding 1 consisting of two detachable parts is attached to a stiffener and rigidly connected to each other. Lifts 2 are put on the supports of columns 4 and fixed with stop screws 18. They are slinged with winches, fixed on the roof of the rigidity core, up to the first side of the scaffold tower with the lifts. At the same time, all articulated support crocs {6, 7 under the influence of counterweights 8 enter the openings of the wall of the rigidity core. Lower the fixture before landing each bracket of the lower rusa 6 on the threshold of the openings of the floor block; Workers enter t he ring masts 1,

нь1ми винтами 18 со всех стороп привод т и фиксируют кольцевые подмости в проектное положение. Подклепывают металлические пластины под те опоры кронштейнов 6, 7, которые не коснулись порога проемов. Навешивают на опорный кронштейн нижнего  руса, компенсируюший упорный пакет 19, набранный таким образом, чтобы зазора между посто нным упором 1О и стеной  дра жесткости не было. Закрепл ют опорный кронштейн верхнего  руса 7 пальцевым замком 12, Устанавливают коромысловые анкеры и закрепл ют каждый из НИХ болтом к гайке опорного кронштейна 6 до упора 10 о внутреннюю стену  дра жесткости у проема .Screws 18 from all sides are brought and fixed annular scaffolding in the design position. Stuck metal plates under the supports of the brackets 6, 7, which did not touch the threshold of the openings. They hang on the lower arm support bracket, compensating the thrust pack 19, assembled in such a way that there is no gap between the fixed stop 1O and the wall of the rigidity core. Fix the upper arm support bracket 7 finger lock 12, Set the rocker anchors and fasten each of them with a bolt to the nut of the support bracket 6 until it stops 10 against the internal wall of the core stiffness at the opening.

Присоедин ют резьбовые т ги 21 к гюдъемникам. Внизу т ги 21 имеют гайки дл  захвата плиты перекрыти  за воро- ники . Перестановку устройства в новое рабочее положение или демонтаж производ т в обратной последовательноJTH,Attach the threaded rods 21 to the pullers. At the bottom, the gigs 21 have nuts to grip the slab over the rails. The device is relocated to a new operating position or dismantled in the reverse sequence JTH,

Применение приссюооблени  позвол ет исключить у 5щра жесткости монтажные колонны, устанавливаемые на всю высоту здани , что снижает его стоимость.The use of pruning makes it possible to exclude assembly columns installed on the entire height of the building from rigidity of the rigidity, which reduces its cost.

Claims (2)

Формула изобретениInvention Formula Приспособление дл  монтажа монолитного железобетонного перекрыти  у  дра жесткости здани , включающее подъемники с т гами, отличающеес  тем, что, с целью исключени  монтажных колонн и уменьшени  стойкости здани , оно снабжено кольцевыми подмост ми , Выполненными с опорами дл  закреплени  подъемников, упорными винтами, коромысловыми анкерами и опорными кронштейнами.A device for mounting a monolithic reinforced concrete floor at the rigidity core of a building, including lifts with traction, characterized in that, in order to eliminate assembly columns and reduce the durability of the building, it is equipped with an annular scaffold, Made with supports for fastening the lifts, with stop screws, root-beam anchors and support brackets. Источники информации, прин тые во внимание при экспертизеSources of information taken into account in the examination I. Авторское свидетельство № 393434 М. Кл, 2 ЕС 4 G 11/2О, 22.03.72.I. Copyright certificate № 393434 M. CL, 2 EU 4 G 11 / 2O, 03.22.72. 2. Шахназар н С. X. и др. Возведение зданий методом подъема этажей и перекрытий, Иддательство литературы по строительству, М, 1974, с, 147. .а ., 2. Shakhnazar and S. X. and others. Construction of buildings by the method of lifting floors and floors, Building Literature on Construction, M, 1974, p. 147..а., FiFi Фиг.ЗFig.Z vv 81| .y. t  81 | .y. t - t - - t - 2020 1one § §
SU762408753A 1976-09-28 1976-09-28 Appliance for erecting monolithic reinforced concrete covering at building rigidity core SU655803A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU762408753A SU655803A1 (en) 1976-09-28 1976-09-28 Appliance for erecting monolithic reinforced concrete covering at building rigidity core

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU762408753A SU655803A1 (en) 1976-09-28 1976-09-28 Appliance for erecting monolithic reinforced concrete covering at building rigidity core

Publications (1)

Publication Number Publication Date
SU655803A1 true SU655803A1 (en) 1979-04-05

Family

ID=20678581

Family Applications (1)

Application Number Title Priority Date Filing Date
SU762408753A SU655803A1 (en) 1976-09-28 1976-09-28 Appliance for erecting monolithic reinforced concrete covering at building rigidity core

Country Status (1)

Country Link
SU (1) SU655803A1 (en)

Similar Documents

Publication Publication Date Title
US4253549A (en) Method and a system for the erection of high buildings
US3299588A (en) Multilevel building structure with plural suspended revolving compartment units and method of making same
SU655803A1 (en) Appliance for erecting monolithic reinforced concrete covering at building rigidity core
SU481528A1 (en) Device for mounting high-rise buildings
JPH116310A (en) Demolition method of multi-story building
SU1366617A1 (en) Hoistable and shiftable forms
JPH0833032B2 (en) Construction method of building frame
JP3241896B2 (en) Steel frame stair hang down method
SU1527406A1 (en) Method of erecting industrial flues
SU369233A1 (en) FORMWORK FOR CONSTRUCTION OF MONOLITHIC STRUCTURES
SU1218029A1 (en) Mounting platform
JP2621748B2 (en) All-weather temporary shed
SU1178884A1 (en) Method of erecting the skeleton of high-rise structure with great cantilever spans
JP2876991B2 (en) Steel frame method for high-rise buildings
JPH07259191A (en) All-weather construction method of structure
JPH1179602A (en) Work floor device for installing elevator
SU861267A1 (en) Device for securing hoist mast
SU659709A1 (en) Device for erecting tall structures from monolithic reinforced concrete
SU939688A1 (en) Cellular plate hoistable scaffold
SU1663144A1 (en) Working area for installation of centring of external walls
SU393441A1 (en) BIB / P-1OTEKA Trust for reinforced concrete structures of the Ministry of Construction of the Lithuanian SSR
RU2097513C1 (en) Process of erection of superstructure of building
SU926198A1 (en) Slip-form
RU2029831C1 (en) Method to mount guy lining in a building of long span
JP3018267B2 (en) Composite Shoring for Building Exterior Components