SU1719641A2 - Method of draining flooded peat beds - Google Patents

Method of draining flooded peat beds Download PDF

Info

Publication number
SU1719641A2
SU1719641A2 SU904836338A SU4836338A SU1719641A2 SU 1719641 A2 SU1719641 A2 SU 1719641A2 SU 904836338 A SU904836338 A SU 904836338A SU 4836338 A SU4836338 A SU 4836338A SU 1719641 A2 SU1719641 A2 SU 1719641A2
Authority
SU
USSR - Soviet Union
Prior art keywords
channels
design
dryers
peat
length
Prior art date
Application number
SU904836338A
Other languages
Russian (ru)
Inventor
Юрий Васильевич Краснов
Вячеслав Георгиевич Степаничев
Виталий Константинович Кириллов
Original Assignee
Научно-производственное объединение "Радченкоторф"
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Научно-производственное объединение "Радченкоторф" filed Critical Научно-производственное объединение "Радченкоторф"
Priority to SU904836338A priority Critical patent/SU1719641A2/en
Application granted granted Critical
Publication of SU1719641A2 publication Critical patent/SU1719641A2/en

Links

Landscapes

  • Drying Of Gases (AREA)

Abstract

Изобретение относитс  к торф ному производству и м.б. использовано при осушении сильнообводненных торф ных залежей (ТЗ). Цель - интенсификаци  процесса осушени  за счет рыть  картовых каналов на подсушенной ТЗ преимущественно верхового типа, ускорение ввода площадей в эксплуатацию и снижение объемов земл ных работ. Способ заключаетс  в отрытии после проведени  осушителей первой очереди наполовину проектной длины спуст  три мес ца по середине между ними аналогичным по параметрам осушителей второй очереди на длину, равную проектной длине картовых каналов. В зимнее врем  после промерзани  ТЗ не менее, чем на 0,1 м, по концам осушителей первой очереди прокладывают сбросной канал. На следующий год от него отрывают осушители третьей очереди. Их прокладывают по трассам будущих картовых каналов на проектную длину. Зимой после промерзани  ТЗ не менее, чем на 0,1 м, по концам осушителей второй очереди прокладывают валовый канал. В дальнейшем осушители между валовыми каналами довод т до проектных параметров. Осушители отрывают вдоль естественного уклона поверхности ТЗ. 1 з.п. ф-лы, 3 ил. СThe invention relates to peat production and m. used for draining highly watered peat deposits (TZ). The goal is to intensify the drainage process by digging out the card channels on the dried TK of a predominantly high type, speeding up the commissioning of areas and reducing the volume of earthworks. The method consists in opening, after the dehumidifiers of the first stage are half the design length after three months in the middle between them, the same in terms of the parameters of the second stage dehumidifiers for a length equal to the design length of the card channels. In winter, after freezing, TK is not less than 0.1 m; a discharge channel is laid at the ends of the first-line dryers. The following year, third stage dryers are being torn from it. They are laid along the tracks of future map channels to the design length. In winter, after freezing, TK is not less than 0.1 m, and the gross channel is laid at the ends of the second-stage dryers. Further, the driers between the gross channels are adjusted to the design parameters. Dehumidifiers tear along the natural slope of the surface TZ. 1 hp f-ly, 3 ill. WITH

Description

Изобретение относитс  к торф ному производству и может быть использовано в торф ной промышленности, мелиорации, сельском и лесном хоз йствах дл  осушени  сильнообводненных торф ных месторождени х и  вл етс  дополнительным к основному авт.св. № 1138505.The invention relates to peat production and can be used in the peat industry, land reclamation, agriculture and forestry for the drainage of highly watered peat deposits and is complementary to the main auth. No. 1138505.

Известный способ осушени  сильнообводненных торф ных месторождений предусматривает рытье валовых каналов на подсушенной залежи. Осушители отрывают сначала наполовину проектной длины, затем углубл ют и довод т до проектной длины . Затем перпендикул рно осушителем на половине проектной длины роют сбросной канал и производ т углубление осушителей,The known method of drainage of highly watered peat deposits involves the digging of gross canals in a dried deposit. The dryers are first torn off to half the design length, then deepened and brought to the design length. Then, perpendicular to the dehumidifier, at half of the design length, the discharge channel is dug and the dehumidifiers are deepened,

начина  от сбросного канала, в обе стороны и дальнейшее рытье осушителей еще наполовину их проектной длины вглубь осваиваемого месторождени . Затем роют валовый канал и производ т дальнейшее осушение от него в той же последовательности.starting from the discharge channel, in both directions and further digging of dehumidifiers, still half of their design length into the explored field. Then the gross canal is dug and further drainage is effected from it in the same sequence.

Практическое использование способа показало, что в процессе работ приходитс  сталкиватьс  со значительными деформаци ми сечений отрываемых осушителей и сбросных каналов. Основным видом деформаций  вл етс  схождение откосов осушителей вплоть до образовани  по их длине непроницаемых пробок. Дл  обеспечени  осушающей и водопровод щей способностей каналов необходимо проводить неодюPractical use of the method has shown that in the course of work one must encounter significant deformations of the sections of detachable dehumidifiers and discharge channels. The main type of deformation is the convergence of the slopes of the driers until the formation of impermeable plugs along their length. In order to provide drainage and water supplying capacity of the channels, it is necessary to carry out

оabout

ЪB

ЬB

некратное их углубление или прочистку. Первое углубление осушителей на практике очень трудно реализуемо из-за чрезвычайно сложных условий эксплуатации землеройной техники и вызывает резкое разупрочнение откосов каналов.their repeated deepening or cleaning. The first deepening of dehumidifiers in practice is very difficult to implement due to the extremely difficult operating conditions of the earthmoving equipment and causes a sharp softening of the slopes of the channels.

Цель изобретени  - интенсификаци  процесса осушени  сильнообводненных торф ных залежей за счет повышени  водо- провод щей способности осушителей и сбросных каналов.The purpose of the invention is to intensify the process of draining highly watered peat deposits by increasing the water-carrying capacity of desiccants and waste channels.

Поставленна  цель достигаетс  тем, что осушители выполн ютс  ориентированными вдоль укло.на поверхности месторождени ; первый раз осушители не углубл ютс , а отрываютс  заново на проектную длину между ранее выполненными; прокладка сбросных каналов осуществл етс  после промерзани  торф ной залежи на глубину не менее 0,1 м.The goal is achieved by the fact that the dehumidifiers are oriented along the corner of the field; for the first time, the dryers do not penetrate, but re-open to the design length between the previously performed ones; laying of waste channels is carried out after freezing of the peat deposit to a depth of at least 0.1 m.

Сущность изобретени  заключаетс  в использовании дл  повышени  водопрово- д щей способности каналов естественного уклона поверхности месторождений, снижени  их деформаций за счет углублени  сбросных каналов по слою мерзлрты и введени  операции рыть  осушительной заново между ранее проложенных вместо их углублени .The essence of the invention is to use for increasing the water supply capacity of the channels of natural inclination of the surface of deposits, reducing their deformations by deepening the drainage channels along the permafrost layer and introducing the operation of digging a drainage between the previously laid instead of their deepening.

На фиг.1, 2 и 3 показаны схемы предварительного осушени  сильнообводненных торф ных залежей и стадии поэтапного выполнени  работ.Figures 1, 2, and 3 show diagrams of pre-drainage of highly watered peat deposits and stages of the phased execution of works.

Первоначально на окрайке торф ного месторождени  прокладываетс  магистральный 2 и валовый 3 каналы. Магистральный канал 2 прокладывают в полный профиль в направлении против уклона поверхности , а валовый канал 3 также в полный профиль- перпендикул рно к магистральному каналу 2, последний еоеди- н ют с водоприемником 1. Одновременно с прокладкой валового канала 3 перпендикул рно ему по трассам будущих картовых каналов вглубь торф ного месторождени  в направлении против уклона поверхности прокапывают осушители 4 первой очереди наполовину проектной длины картовых каналов . По окончании прокладки осушителей 4 спуст  3 мес посередине между ними отрывают аналогичные по параметрам осушители 5 второй очереди на длину, равную проектной длине картовых каналов, т.е. на удвоенную прот женность осушителей 4, В зимнее врем  после промерзани  торф ной залежи не менее чем на 0,1 м по концам осушителей 4 прокладываетс  сбросной канал 6 параллельно валовому каналу 3. На следующий год от сбросного канала 6 отрывают осушители 7 по трассам будущих картовых каналов на длину, соответствующую проектному значению. Затем в зимнее врем  после промерзани  торф ной залежи не менее чем на 0,1 м по концам осушителе й 5Initially, trunk 2 and gross 3 channels were laid on the edge of the peat deposit. The main channel 2 is laid in full profile in the direction opposite to the surface slope, and the gross channel 3 is also full profile perpendicular to the main channel 2, the latter is connected to the water receiver 1. Simultaneously with the laying of the gross channel 3, it is perpendicular to it along the routes of the future Kart channels into the peat field in the direction opposite to the slope of the surface, dryers 4 of the first stage are drilled to the half of the designed length of the card channels. At the end of the installation of the driers 4 after 3 months in the middle between them, the dehumidifiers 5 of the second stage are similar in parameters for a length equal to the design length of the card channels, i.e. On the doubled length of the driers 4, In winter, after the peat deposit freezes at least 0.1 m, a discharge channel 6 is laid at the ends of the dehumidifiers 4 parallel to the gross channel 3. Next year, the dryers 7 are torn from the discharge channel 6 channels for the length corresponding to the design value. Then in winter after the freezing of the peat deposit at least 0.1 m at the ends of the dessicator 5

прокладываетс  валовый канал 8. Спуст  3- 6 мес картовые каналы 4 между валовыми каналами 3 и 8 довод т до проектных параметров . В дальнейшем осушение производ т в следующей последовательности - отThe gross channel 8 is laid. After 3-6 months, the card channels 4 between the gross channels 3 and 8 are brought to the design parameters. Subsequently, drainage is performed in the following sequence, from

валового канала 8 отрывают осушители 9 на проектную длину картовых каналов, а в зимнее врем  по концам осушителей 7 отрывают сбросной канал 10 и т.д. В зависимости от наличи  техники работы по осушениюof the shaft channel 8, the desiccants 9 are torn off by the design length of the card channels, and in winter, the outlet channel 10 is opened at the ends of the desiccants 7, etc. Depending on the availability of drainage equipment

провод т как вглубь, так и в шмрь торф ного месторождени .carried out both inland and in the shmra of the peat deposit.

Применение предлагаемого способа позволит быстро сбрасывать с осушаемого участка сильнообводненной торф ной залежи поверхностные воды и существенно понизить уровень грунтовых вдд. В результате снижени  содержани  влаги в поверхностном слое залежи увеличитс  ее прочность и глубина промерзани  в зимний период.The application of the proposed method will allow the surface waters to be quickly discharged from the drained area of the highly watered peat deposits and to significantly reduce the level of the sub-surface airborne formations. As a result of a decrease in the moisture content in the surface layer of the deposit, its strength and freezing depth in the winter period will increase.

Кроме того, возрастает несуща  способность торф ной залежи. Рытье осушительных , сбросных и валовых каналов будет проводитьс  на подсушенных участках. Сократитьс  количество проходов техникиIn addition, the bearing capacity of the peat deposit increases. The digging of drainage, waste and gross channels will be carried out on the dried areas. Reduce the number of vehicle passes

дл  углублени  каналов, что как и рытье сбросных и валовых каналов в залежи, промерзшей не менее, чем на 0,1 м будет способствовать снижению деформаций сечений каналов и уменьшению объемовto deepen channels, which, like digging waste and gross channels in a reservoir frozen by at least 0.1 m, will help reduce the deformations of the channel sections and decrease

земл ных работ. Сроки строительства осушительной системы могут быть доведены до 4-5 л.land works. The construction time of the drainage system can be reduced to 4-5 liters.

Ф о р м у л а и з о б р е т е н и  FORUMAWLAH AND ISLANDS

Claims (2)

1. Способ осушени  сильнообводненных торф ных залежей по авт.св. № 1138505, отличающийс  тем, что, с целью интенсификации процесса осушени  за счет рыть  картовых каналов на подсушенной1. The method of drainage of highly watered peat deposits according to the author. No. 1138505, characterized in that, in order to intensify the drying process by digging the card channels on the dried залежи преимущественно верхового типа, ускорени  ввода площадей в эксплуатацию и снижени  объемов земл ных работ, после отрыти  осушителей первой очереди наполовину проектной длины спуст  три мес цаthe deposits are mainly of top type, accelerate the commissioning of areas and reduce the volume of earthworks, after opening the first-stage dryers half of the design length after three months по середине между ними отрывают аналогичные по параметрам осушители второй очереди на длину, равную проектной длине картовых каналов, затем в зимнее врем  после промерзани  торф ной залежи не менее чем на 0,1 м, по концам осушителей первой очереди прокладываетс  сбросной канал, от которого на следующий год отрывают осушители третьей очереди по трассам будущих картовых каналов на длину, соответствующую проектному значению, и вin the middle between them, second-line driers of similar type are cut by a length equal to the design length of the card channels, then in winter, after the peat deposit freezes over at least 0.1 m, a waste channel is laid at the ends of the first-turn driers, from which next year, the third stage dryers will be torn off along the routes of the future map channels for the length corresponding to the design value, and in зимнее врем  после промерзани  торф ной залежи не менее чем на 0,1 м, по концам осушителей второй очереди прокладываетс  валовый канал, а между валовыми канапараметров и дальнейшее осушение прово- дитс  в аналогичном пор дке.the winter time after freezing of the peat deposit is not less than 0.1 m, the gross channel is laid at the ends of the second-line driers, and between the gross canals and further drying is carried out in a similar order. 2. Способ по п.1,отличающийс  тем, что осушители отрываютс  вдоль есте2. The method according to claim 1, characterized in that the desiccants are torn off along natural lines. лами осушители довод тс  до проектных 5 ственного уклона поверхности.Lamine dryers are brought to the design 5 surface slope. фаг. 2phage. 2
SU904836338A 1990-04-16 1990-04-16 Method of draining flooded peat beds SU1719641A2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU904836338A SU1719641A2 (en) 1990-04-16 1990-04-16 Method of draining flooded peat beds

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU904836338A SU1719641A2 (en) 1990-04-16 1990-04-16 Method of draining flooded peat beds

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
SU1138505 Addition

Publications (1)

Publication Number Publication Date
SU1719641A2 true SU1719641A2 (en) 1992-03-15

Family

ID=21519327

Family Applications (1)

Application Number Title Priority Date Filing Date
SU904836338A SU1719641A2 (en) 1990-04-16 1990-04-16 Method of draining flooded peat beds

Country Status (1)

Country Link
SU (1) SU1719641A2 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Авторское свидетельство СССР № 1138505, кл. Е 21 С 49/00, 1985. *

Similar Documents

Publication Publication Date Title
Imeson Heather burning and soil erosion on the North Yorkshire Moors
SU1719641A2 (en) Method of draining flooded peat beds
CN210840602U (en) Coastal area heavy saline-alkali soil improvement system
SU1138505A1 (en) Method of dewatering saturated peat deposits
Harker et al. Leaching of a highly saline-sodic soil in southern Alberta: A laboratory study
Hartung Woodlands of the Northeast: Erosion and sediment control guides
CN112703847A (en) Coastal saline-alkali soil improvement method based on physical salt elimination
SU1023024A2 (en) Method of erecting hydraulic fill earth structures
SU1483018A1 (en) Method of drying saturated peat deposits
SU821648A1 (en) Land reclamation system
RU23915U1 (en) MILLING PEAT TECHNOLOGY LINE
SU1721248A1 (en) Method of preparing peatlands for working season
SU1323650A1 (en) Method of washing salinated land
SU1208132A1 (en) Method of restoring the water intake capacity of closed drainage
SU844670A1 (en) Drain construction method
SU1006595A1 (en) Drain outfall
SU1652576A1 (en) Method for mining sapropel deposit
SU1359405A1 (en) Method of constructing drainage
SU1082955A1 (en) Method of drying highly flooded reat deposits of top kind
RU2103510C1 (en) Method for extraction of mineral ore lying under peat stratum
SU1399469A1 (en) Method of recovering peat from flooded peat fields
Moukhtar et al. Soil amelioration technique of cover drainage combined subsoiling for saline-sodic clay in North Egypt
JPH0241605B2 (en)
SU1701815A1 (en) Drainage laying method
SU655764A1 (en) Method of aggradation of earth hydraulic engineering structure