SU1627492A1 - Method of replacing ropes in friction-pulley mine winder - Google Patents

Method of replacing ropes in friction-pulley mine winder Download PDF

Info

Publication number
SU1627492A1
SU1627492A1 SU884400932A SU4400932A SU1627492A1 SU 1627492 A1 SU1627492 A1 SU 1627492A1 SU 884400932 A SU884400932 A SU 884400932A SU 4400932 A SU4400932 A SU 4400932A SU 1627492 A1 SU1627492 A1 SU 1627492A1
Authority
SU
USSR - Soviet Union
Prior art keywords
rope
ropes
balancing
mine
shaft
Prior art date
Application number
SU884400932A
Other languages
Russian (ru)
Inventor
Виктор Данилович Ковальский
Иренеуш Брониславович Доржинкевич
Владимир Иванович Диденко
Юрий Иванович Старостин
Елена Викторовна Альметова
Original Assignee
Криворожский горнорудный институт
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Криворожский горнорудный институт filed Critical Криворожский горнорудный институт
Priority to SU884400932A priority Critical patent/SU1627492A1/en
Application granted granted Critical
Publication of SU1627492A1 publication Critical patent/SU1627492A1/en

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B19/00Mining-hoist operation
    • B66B19/02Installing or exchanging ropes or cables

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

Изобретение относитс  к шахтному подъему и может быть использовано дл  замены уравновешивающих канатов в шахтных подъемных установках. Цель изобретени  - снижение трудоемкости замены уравновешивающих канатов в установках, в которых вес замен емых канатов превышает их грузоподъемность . Способ замены канатов при использовании подъемной машины состоит в том, что замен емый уравновешивающий канат выдают из ствола на шкив трени  подъемной машиной и затем свивают его на промплощадку шахты, после чего навешиваемый уравновешивающий канат с пром- площадки шахты выматывают той же подъемной машиной на шкив трени  и опускают его в ствол шахты. Далее концы навешиваемого каната присоедин ют к сосудам и приступают к замене головных канатов 7 илThis invention relates to a mine hoist and can be used to replace balancing cables in a mine hoist. The purpose of the invention is to reduce the labor intensity of replacing balancing cables in installations in which the weight of the replaced cables exceeds their carrying capacity. The method of replacing the ropes when using a lifting machine is to replace the balancing rope from the trunk to the pulley of the friction with a lifting machine and then twist it onto the mine’s industrial site, after which the hanging balancing rope from the mine’s platform is exhausted by the same lifting machine to the pulley of the shaft and lower it into the shaft shaft. Next, the ends of the hanging rope are attached to the vessels and proceed to the replacement of the head ropes 7 or

Description

Изобретение относитс  к шахтному подъему , в частности к способам замены канатов многоканатной подъемной установки, и может быть использовано в угольной, горнодобывающей и цветной отрасл х промышленности .The invention relates to a mine hoist, in particular to methods for replacing ropes of a multi-rope hoisting installation, and can be used in the coal, mining and color industries.

Цель изобретени  - раздельна  замена канатов и снижение трудоемкости замены уравновешивающих канатов в установках, в которых вес замен емых канатов превышает их грузоподъемность.The purpose of the invention is to replace ropes separately and reduce the complexity of replacing balancing ropes in installations in which the weight of the ropes being replaced exceeds their carrying capacity.

На фиг. 1 изображена схема подъемной установки с закрепленными к шкиву трени  монтажным канатом при замене уравновешивающих канатов; на фиг. 2 - схема подъемной установки с закрепленным к монтажному канату замен емым уравновешивающим канатом дл  выдачи его из ствола на шкив трени ; на фиг. 3 - схема подъемной установки при выдаче замен емого уравновешивающего каната на шкив трени  и с последнего на промплощадку шахты; на фиг. 4 - схема подъемной установки с закрепленным к монтажному канату навешиваемым уравновешивающим канатом дл  его выдачи с промплощадки шахты на шкив трени : на фиг. 5 - схема подъемной установки при опускании в ствол шахты навешиваемого уравновешивающего каната со шкива трени ; на фиг. 6 - схема подъемной установки с опущенным в ствол шахты навешиваемым уравновешивающим канатом , присоединенным к монтажному канат. на фиг. 7 - схема подъемной установки с присоединенным к подъемным сосудам навешенным уравновешивающим канатом. Многоканатна  подъемна  установка при замене канатов содержит приводной шкив 1 трени  подъемной машины, с которой сн ты замен емые головные канаты, закрепленный к шкиву трени  1 на период замены уравновешивающих канатов монтажный канат 2. подъемные сосуды 3 и 4. установленные приемных площадок на перекрытии ствола и копра, или завешенные на стропах к металлоконструкции ствола и копра, уравновешивающий канат 5, подлежащий замече. отводные ролики 6 и 7, установленные вFIG. 1 shows a diagram of a lifting installation with a mounting rope attached to the friction pulley when replacing balancing cables; in fig. 2 is a diagram of a lifting device with a replaceable balancing cable attached to the installation rope for issuing it from the barrel to the friction pulley; in fig. 3 is a diagram of a lifting installation when issuing a replacement equilibrium rope to a friction pulley and from the latter to the mine site; in fig. 4 is a diagram of a lifting installation with a hanging balance cable attached to the installation rope for issuing it from the mine site to the friction pulley: FIG. 5 is a diagram of a lifting device when lowering a balancing rope from a friction pulley into the shaft of a shaft; in fig. 6 is a diagram of a lifting installation with a hanging balance cable attached to the shaft shaft connected to the mounting rope. in fig. 7 is a diagram of a lifting installation with a suspended balance cable attached to the lifting vessels. When replacing ropes, a multi-gang lift installation contains a drive pulley 1 of a lifting machine, from which replaceable head ropes are removed, attached to the friction pulley 1 for a period of replacement of balancing ropes mounting cable 2. lifting vessels 3 and 4. installed receiving platforms on the overlap of the trunk and copra, or hung on the slings to the metal trunk and copra, balancing rope 5, to be noticed. diverting rollers 6 and 7 installed in

05 Ю05 Yu

4- СО ГО4- SO GO

копровом здании на период замены канатов, навешиваемый уравновешивающий канат 8, расположенный на промплощадке шахты, соединительные зажимы 9 дл  закреплени  к монтажному канату 2 замен емого каната 5 (фиг 2) или навешиваемого каната 8 (фиг 4 и фиг 6), зажимы 10 дл  удержани  на весу замен емого каната 5 (фиг 1 и фиг 2) или навешиваемого каната 8 (фиг 6), посадочный мост 11, на который опираютс  зажимы 10 В первом случае зажимы 10 используютс  при отсоединении замен емого каната 5 от сосудов 3 и 4 (фиг I и фиг 2), во втором случае - при присоединении навешиваемого каната 8 к сосудам 3 и 4 (фиг 6)a building building for the period of ropes replacement, a hanging balancing cable 8 located on the mine site, connecting clamps 9 for attaching a replaceable rope 5 (Fig 2) or a hanging rope 8 (Fig 4 and Fig 6) to the mounting rope 2, and holding clamps 10 on the weight of the cable to be replaced 5 (FIG. 1 and FIG. 2) or on the hanging cable 8 (FIG. 6), the landing bridge 11, on which the clamps 10 rest. In the first case, the clamps 10 are used when disconnecting the cable to be replaced 5 from vessels 3 and 4 (FIG. I and FIG. 2), in the second case, when attaching, we hang 8th rope to vessels 3 and 4 (Fig. 6)

Способ осуществл ют следующим обра зомThe method is carried out as follows.

Дл  сн ти  замен емого уравновешивающего каната 5 на канате 5 закрепл ют зажимы 10, которые опираютс  на посадочный мост 11 (фиг 1) Затем канат 5 отсоедин ют от сосудов 3 и 4 и верхний конец каната 5 прикрепл ют к монтажному канату 2 посредством соединительных зажимов 9 (фиг 2) Далее, враща  приводной шкив 1 трени  подъемной машиной, приподнимают замен емый канат 5 вместе с зажимами 10 с посадочного моста 11, провер ют надежность закреплени  канатов 2 и 5 в соединительных зажимах и снимают зажимы 10 Продолжа  вращать приводной шкив 1 трени , выдают на него из ствола шахты замен емый уравновешивающий канат 5 вместе с соединительными зажимами 9 (фиг 2 и фиг 3) После этого, враща  приводной шкив 1 трени  в противоположную сторону, выдают замен емый уравновешивающий канат 5 на промплощадк г шахты (фиг 3) При подходе соединительных сжимов 9 к приемной площадке, т е в поюжение, показанное на фиг 2, фиг 4 и фиг 6, замен емой канат 5 отсоедин ют от монтажного каната 2 и к канату 2 прикрепл ют расположенный на промплощадке шахты навешиваемый уравновешивающий канат 8 (фиг 4) Затем канат 8 выдают подъемной машиной на приводнойTo remove the replacement equilibrium cable 5, the cable 5 fastens the clips 10, which rest on the landing bridge 11 (Fig. 1). Then the cable 5 is disconnected from the vessels 3 and 4 and the upper end of the cable 5 is attached to the installation cable 2 by means of connecting clips. 9 (FIG. 2) Next, rotating the friction drive pulley 1 with a lifting machine, lift the replaceable rope 5 together with the clips 10 from the landing bridge 11, check the reliability of fixing the ropes 2 and 5 in the connecting clamps and remove the clips 10 Continuing to rotate the friction drive pulley 1 issued on a replaceable balancing cable 5 together with connecting clips 9 (FIG. 2 and FIG. 3) are replaced from the shaft of the shaft; then, rotating the drive pulley 1 in the opposite direction, a replaceable balancing cable 5 is delivered to the mine’s production site (FIG. 3). of the clamps 9 to the receiving site, that is, in the lower part shown in FIG. 2, FIG. 4 and FIG. 6, the replaceable rope 5 is disconnected from the installation rope 2 and a suspended balance rail 8 is attached to the rope 2 attached to the mine industrial site (FIG. 4) Then the rope 8 is issued lifting driving machine

шкив 1 трени  (фиг 5), после чего, враща  его в противоположную сторону, канат 8 опускают в ствол шахты (фиг 6) На посадочном мосту II на канат 8 устанавливают зажимы 10 (фиг 6) и .рассоедин ют канаты 2 и 8 в соединительных зажимах 9 Затем концы каната 8 присоедин ют к сосудам 3 и 4 (фиг 7) и снимают зажимы 10, удерживающие канат 8 на посадочном мос- т 11 На этом заканчиваетс  процесс замены уравновешивающих канатов 5 и 8friction pulley 1 (FIG. 5), after which, rotating it in the opposite direction, the rope 8 is lowered into the shaft shaft (FIG. 6) On the landing bridge II, clamps 10 are installed on the rope 8 (FIG. 6) and the ropes 2 and 8 are connected connecting clamps 9 Then the ends of the rope 8 are connected to vessels 3 and 4 (Fig. 7) and clamps 10 are removed, holding the rope 8 on the landing bridge 11. This completes the process of replacing the balancing cables 5 and 8

Затем поднимают посадочный мост 11, снимают отводные ролики 6 и 7 и монтажный канат 2 со шкива 1 трени  и приступают к заводке на шкив 1 трени  или к.навешива- нию головных канатовThen, the landing axle 11 is lifted, the discharge rollers 6 and 7 and the mounting rope 2 are removed from the friction pulley 1 and proceed to winding on the friction pulley 1 or the hanging ropes

00

2020

Claims (1)

Формула изобретени Invention Formula Способ замены канатов в шахтной подъемной установке со шкивом трени , включающий отсоединение закрепленных на горизон5 те сосудов от уравновешивающего и головного канатов, выдачу замен емых канатов на поверхность, подачу навешиваемых канатов в ствол шахты и их последующее присоединение к сосудам, отличающийс  тем, что, с целью снижени  трудоемкости заме0 ны уравновешивающих канатов, после отсоединени  замен емого уравновешивающего каната от сосуда верхний его конец соедин ют с концом предварительно заведенного на шкив трени  монтажного каната и выматывают замен емый канат до выходаThe method of replacing the ropes in the mine hoist installation with a friction pulley, including the detachment of vessels fixed on the horizon from the balancing and head ropes, issuing the replaced ropes to the surface, feeding the hung ropes into the shaft shaft and their subsequent joining to the vessels, characterized in that in order to reduce the complexity of replacing the balancing cables, after disconnecting the interchangeable balancing cable from the vessel, its upper end is connected to the end of the fi platemaking rope and rope exhaust the renewable hearth to yield гго нижнего конца на поверхность шахты, а после выдачи замен емых канатов на по верхность шахты навешиваемый канат соеди н ют с концом монтажного каната и выма тывают его с поверхности шахты в ееof the lower end to the surface of the shaft, and after issuing the replaced ropes to the surface of the mine, the hanging rope is connected to the end of the assembly rope and is wiped from the surface of the mine into its 4040 стволtrunk иand VV Фиг.11 Фиё.2Fiyo.2 Фиг. 5FIG. five Фие.6Fie.6 Фиг. 7FIG. 7
SU884400932A 1988-03-30 1988-03-30 Method of replacing ropes in friction-pulley mine winder SU1627492A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU884400932A SU1627492A1 (en) 1988-03-30 1988-03-30 Method of replacing ropes in friction-pulley mine winder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU884400932A SU1627492A1 (en) 1988-03-30 1988-03-30 Method of replacing ropes in friction-pulley mine winder

Publications (1)

Publication Number Publication Date
SU1627492A1 true SU1627492A1 (en) 1991-02-15

Family

ID=21364856

Family Applications (1)

Application Number Title Priority Date Filing Date
SU884400932A SU1627492A1 (en) 1988-03-30 1988-03-30 Method of replacing ropes in friction-pulley mine winder

Country Status (1)

Country Link
SU (1) SU1627492A1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1299967C (en) * 2004-09-27 2007-02-14 山西潞安矿业(集团)有限责任公司常村煤矿 Fast rope changing device of floor type multirope friction elerator
CN100341766C (en) * 2003-10-10 2007-10-10 淄博矿业集团有限责任公司许厂煤矿 Technology for exchanging hoisting cable wire of floor type friction hoist
CN102530694A (en) * 2012-03-09 2012-07-04 太原理工大学 Method for replacing head rope of tower-type multi-rope friction hoist
CN104071678A (en) * 2014-07-01 2014-10-01 南通力威机械有限公司 Rope replacement method for friction-type hoisting winch
CN108910668A (en) * 2018-08-07 2018-11-30 中煤第三建设集团机电安装工程有限责任公司 Method for quickly replacing vertical shaft lifting rope and lifting container in same cycle

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Авторское свидетельство СССР № 1451087, кл. В 66 В 19/02, 1986. *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100341766C (en) * 2003-10-10 2007-10-10 淄博矿业集团有限责任公司许厂煤矿 Technology for exchanging hoisting cable wire of floor type friction hoist
CN1299967C (en) * 2004-09-27 2007-02-14 山西潞安矿业(集团)有限责任公司常村煤矿 Fast rope changing device of floor type multirope friction elerator
CN102530694A (en) * 2012-03-09 2012-07-04 太原理工大学 Method for replacing head rope of tower-type multi-rope friction hoist
CN104071678A (en) * 2014-07-01 2014-10-01 南通力威机械有限公司 Rope replacement method for friction-type hoisting winch
CN104071678B (en) * 2014-07-01 2015-10-28 南通力威机械有限公司 A kind of friction hoisting winch method of replacing rope
CN108910668A (en) * 2018-08-07 2018-11-30 中煤第三建设集团机电安装工程有限责任公司 Method for quickly replacing vertical shaft lifting rope and lifting container in same cycle
CN108910668B (en) * 2018-08-07 2020-08-21 中煤第三建设集团机电安装工程有限责任公司 Method for quickly replacing vertical shaft lifting rope and lifting container in same cycle

Similar Documents

Publication Publication Date Title
CN201433079Y (en) High-altitude inclined supporting wire lifting device for construction curtain wall
CN108910668B (en) Method for quickly replacing vertical shaft lifting rope and lifting container in same cycle
SU1627492A1 (en) Method of replacing ropes in friction-pulley mine winder
CN115285821B (en) System and method for quickly separating new and old steel wire ropes from each other and replacing ropes of multi-rope friction type elevator
EP0893390A3 (en) Reactor internal equipment hoisting apparatus
CN108975181A (en) A kind of method for dismounting of derrick crane
CA2004972A1 (en) Anti-sway crane reeving apparatus
CN111847267A (en) Cantilever crane
RU2409513C1 (en) Method of replacement of ropes of mine winding plant with friction pulley, and device for its implementation
CN212712457U (en) Cantilever crane
SU740679A1 (en) Method of replacing ropes in mine multirope hoists with rope-guiding sheave
SU1493580A1 (en) Method of replacing leading rope of mine hoist
CN109534205B (en) Integrated automatic turnover normal hanging hoist and mounting structure thereof
CN2244546Y (en) Self-lifting guide support adding device for construction elevator cage
CN215974679U (en) Hoisting device for curtain wall construction
SU971772A1 (en) Method of replacing ropes in multirope hoisting installations
SU1286708A1 (en) Suspension cradle
CN214616557U (en) Supporting platform with rail beam dismounting function for suspension rail equipment
JP2000143122A (en) Main rope replacing method for side fork elevator
SU1249093A1 (en) Method of assembling a suspension bridge
SU1359243A1 (en) Method of successive replacement of head ropes of multirope hoist
CN211078279U (en) Combined electric device for portable lifting belt conveyor counterweight
KR910004264Y1 (en) Lift-apparatus for construction
SU1266827A1 (en) Method for mounting lift guides
SU370156A1 (en) ^ ILOTENL