SU135413A1 - The method of construction of concrete dams without drainage device - Google Patents

The method of construction of concrete dams without drainage device

Info

Publication number
SU135413A1
SU135413A1 SU635557A SU635557A SU135413A1 SU 135413 A1 SU135413 A1 SU 135413A1 SU 635557 A SU635557 A SU 635557A SU 635557 A SU635557 A SU 635557A SU 135413 A1 SU135413 A1 SU 135413A1
Authority
SU
USSR - Soviet Union
Prior art keywords
construction
dams
drainage device
concrete
concrete dams
Prior art date
Application number
SU635557A
Other languages
Russian (ru)
Inventor
А.А. Беляков
ков А.А. Бел
А.А. Беляков_
ков_ А.А. Бел
И.Ф. Ярошеня
И.Ф. Ярошен
Original Assignee
ков А.А. Бел
ков_ А.А. Бел
И.Ф. Ярошен
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ков А.А. Бел, ков_ А.А. Бел, И.Ф. Ярошен filed Critical ков А.А. Бел
Priority to SU635557A priority Critical patent/SU135413A1/en
Application granted granted Critical
Publication of SU135413A1 publication Critical patent/SU135413A1/en

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Description

Изобретение касаетс  способа возведени  бетонных плотин без устройства осушаемого котлована с искусственным основанием в текущей Г5оде, в узких створах и в услови х большнх глубин.The invention relates to a method for erecting concrete dams without a device for draining a foundation pit with an artificial foundation in the current substructure, in narrow sections and in conditions of great depths.

Существенна  особенность предлагаемого способа состоит в том, что искусственное основание под илотнну устраивают посредством возведе1 и  послойно с верховой и низовой сторон каменных дамб с последующим подводным бетонированием слоев между нпми путем укладки бетона от верхнего кра  к низовому методом «восход щего раствора.The essential feature of the proposed method is that the artificial foundation under the bottom is arranged by erection 1 and layer by layer from the upstream and downstream sides of stone dams with the subsequent underwater concreting of the layers between the materials by placing the concrete from the top edge to the bottom one.

При применении предлагаемого способа возведени  бетонных плотин полностью отпадает необходимость возведени  перемычек, водоотлива и выемки котлована, а также резко уменьщаютс  работы по возведению отвод щих туннелей.When applying the proposed method of erecting concrete dams, there is no need for erection of jumpers, drainage and excavation of the excavation, as well as dramatically reducing the work on the construction of diverting tunnels.

На фиг. 1 изображена схема возведени  бетонных плотин методом послойного подводного бетонировани  на нервом этапе; на фиг. 2 - то же, на втором этапе.FIG. Figure 1 shows a scheme for the construction of concrete dams by the method of layering underwater concreting at the nerve stage; in fig. 2 - the same at the second stage.

Первый этап работы - создание тиховода путем отсыпки дамб обр .аловани  из камн  крупных фракций, заполнение пространства между дамбами бетоном методом «восход идего раствора и сооружение обводного канала дл  спуска меженных вод.The first stage of the work is the creation of a quiet water conduit by dumping dams by forming large fractions of stone, filling the space between dams with concrete using the “rising of the solution” method and building a bypass channel for lowering low-flow waters.

Второй этан работы - наращивание по высоте подводной части сооружени  путем последовательного повторени  операций первого этапа и устройство бетонной плиты.The second work ethane is building up the height of the underwater part of the structure by successively repeating the operations of the first stage and arranging a concrete slab.

Предмет изобретени Subject invention

Способ возведени  бетонных плотин без устройства осушаелгого котлована , отличающийс  тем, что, с целью создани  выступающего над водой подводного основани  дл  возведени  па нем известными приемами плотины, в створе сооружени  отсыпают в воду каменную наброA method of erecting concrete dams without a drainage pit device, characterized in that, in order to create an underwater foundation protruding above the water to erect a dam on it, at the construction site, the stone bed is poured into the water

SU635557A 1959-07-27 1959-07-27 The method of construction of concrete dams without drainage device SU135413A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU635557A SU135413A1 (en) 1959-07-27 1959-07-27 The method of construction of concrete dams without drainage device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU635557A SU135413A1 (en) 1959-07-27 1959-07-27 The method of construction of concrete dams without drainage device

Publications (1)

Publication Number Publication Date
SU135413A1 true SU135413A1 (en) 1960-11-30

Family

ID=48291734

Family Applications (1)

Application Number Title Priority Date Filing Date
SU635557A SU135413A1 (en) 1959-07-27 1959-07-27 The method of construction of concrete dams without drainage device

Country Status (1)

Country Link
SU (1) SU135413A1 (en)

Similar Documents

Publication Publication Date Title
SU135413A1 (en) The method of construction of concrete dams without drainage device
IT1205390B (en) LAND SUPPORT WALL AND SIMILAR
RU2638186C1 (en) Method of concrete dam construction in river canyon
Droz Swiss dam engineering in the world
ES434509A1 (en) Improvements in the construction of pools with prefabricated concrete elements. (Machine-translation by Google Translate, not legally binding)
RU2791119C1 (en) Method for construction of geotechnical structures in the water area of urban rivers and canals
RU2045613C1 (en) Process of erection of hydraulic power station from floating module units
SU1142580A1 (en) Method of constructing a cellular dam
RU99022U1 (en) HIGH GROUND WEIR
Boryaev et al. Experience in the operation of the structures of the Kama hydroelectric station
SU874849A1 (en) Method of erecting an earth dam with counter-filtration elements
SU129994A1 (en) Arochna dam
GB1343198A (en) Method of laying a foundation for an underwater structural element
RU2005843C1 (en) Method for construction of earth dam
SU935561A1 (en) Water power plant dam
SU1211381A1 (en) Dam
SU1629375A1 (en) Method for hydraulic filling of structures
SU1629379A1 (en) Backwater water development works
RU1791521C (en) Construction method for spillway tailwater structure
SU1717708A1 (en) Method of constructing concrete dam
SU1127939A1 (en) Method for erecting water engineering plant with power plant building on rock base
SU1698354A1 (en) Method of erecting weirs
SU1758153A1 (en) Method of erecting river head in hydraulic tunnel
RU2228995C2 (en) Cellular barrage
SU1476047A1 (en) Method of building-up a dam