Method of completing wells with loosely cemented collector rock Download PDFInfo
- Publication number
- SU1234587A1 SU1234587A1 SU843813931A SU3813931A SU1234587A1 SU 1234587 A1 SU1234587 A1 SU 1234587A1 SU 843813931 A SU843813931 A SU 843813931A SU 3813931 A SU3813931 A SU 3813931A SU 1234587 A1 SU1234587 A1 SU 1234587A1
- Authority
- SU
- USSR - Soviet Union
- Prior art keywords
- tubing
- reservoir
- cemented
- liner
- trunk
- Prior art date
Links
Landscapes
- Earth Drilling (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Description
1one
Изобретение относитс к горной промьшшенности, а именно к нефтега- зодобьгеающей, и может быть использовано при заканчивании нефт ных и газовых скважин со слабосцементированными коллекторами.The invention relates to the mining industry, namely to an oil and gas recovery, and can be used in the completion of oil and gas wells with weakly cemented reservoirs.
Целью изобретени вл етс повышение ремонтоспособности скважины за счет упрощени и ускорени операции по очистке ствола и повьпиение устойчивости слабосцементированного продуктивного пласта.The aim of the invention is to improve the maintainability of the well by simplifying and accelerating the operation for cleaning the wellbore and increasing the stability of the poorly cemented reservoir.
Сущность изобретени сводитс к созданию за колонной равномерной полости большого диаметра и последующей бесфильтровой эксплуатации скважины , при которой вследствие снижени фильтрационных нагрузок обеспечиваетс больша производительность скважины по сравнению с известными способами.The essence of the invention is the creation of a uniform cavity of a large diameter behind the column and the subsequent filterless operation of the well, in which, due to a decrease in filtration loads, greater well productivity is achieved in comparison with known methods.
Наличие полости с большой площадью обеспечивает снижение фильтрационных нагрузок и устойчивость ствола , но не устран ет осаждени частиц Выше полости песок не осаждаетс , та как имеет место значительное увеличение скорости потока. Промывку скважины осуществл ют в зкой нефтью или другой в зкой жидкостью, не ухудшающей свойств пласта, до полной очистки ствола.The presence of a cavity with a large area provides a decrease in filtration loads and a barrel stability, but does not eliminate the sedimentation of particles. The sand does not precipitate above the cavity, as there is a significant increase in the flow velocity. The well is washed with a viscous oil or other viscous fluid that does not impair the properties of the formation, until the well is completely cleaned.
Пор док проведени работ по данному способу включает крепление скважины до кровли продуктивного горизонта , вскрытие, пласта-коллектора и расширение ствола в этом интервале до диаметра 400-600 мм, спуск до забо на НКТ неперфорированного хвостовика с заходом его на 3-5 м в эксплуатационную колонну, отсоединение НКТ, подъем их на 0,3-0,5 м и полу-ор И. Горват 2962/39The order of work on this method includes attaching the well to the roof of the producing horizon, opening, the reservoir and the expansion of the wellbore in this interval to a diameter of 400-600 mm, descending to the tubing of the non-perforated liner with an approach of 3-5 meters to the operational the column, the detachment of tubing, lifting them to 0.3-0.5 m and semi-op I. Gorvat 2962/39
Составитель Е. Молчанова Техред О.СопкоCompiled by E. Molchanova Tehred O. Sopko
Ко ПодCo Pod
Тираж 548 ВНШШИ Государственного комитета СССРCirculation 548 of the USSR State Committee
по делам изобретений и открытий 113035, Москва, Ж-35, Раушска наб., д. 4/5for inventions and discoveries 113035, Moscow, Zh-35, Raushsk nab., 4/5
Производственно-полиграфическое предпри тие, г. Ужгород, ул. Проектна , 4Production and printing company, Uzhgorod, st. Project, 4
234587i234587i
чение притока флюида через кольцевое пространство и зазор между хвостовиком и НКТ, а после снижени дебита соединение лифтовых труб с хвостови- 5 ком и проведение пр мой промывки дл удалени песчаной пробки,fluid flow through the annulus and the gap between the shank and the tubing, and after reducing the flow rate, connecting the elevator pipes with the shank 5 and performing a direct flush to remove the sand plug,
Данным способом бьши закончены скважины. № 90 и 91 месторождени Каражанбас Казахской ССР, На этом 10 месторождении продуктивные горизонты на глубинах 300-350 м сложены слабосцементированными песчаниками, а нефть имеет высокую в зкость. Дл ее извлечени создают депрессии до 15 2-3 МПа, что приводит к разрушению пласта.The wells were completed in this way. Nos. 90 and 91 of the Karazhanbas field of the Kazakh SSR. At this 10 field, productive horizons at depths of 300–350 m are composed of poorly cemented sandstones, and oil has a high viscosity. For its extraction, depressions of up to 15–3 MPa are created, which leads to fracture of the formation.
Сквсжины № 90 и 91 бьши пробурены до кровли пласта-коллектора и обсажены 168-мм эксплуатационной колонной , после чего на глубинах 300- 315 м и 320-323 м были вск:рыты продуктивные объекты Г и Д, против которых ствол был расширен гидромониторным способом до диаметра 550- 640 мм. До забо на 73-мм НКТ были спущены хвостовики из расчета входа их в эксплуатационную колонну на 5 м. Низ хвостовиков был оборудован башмачной направл ющей пробкой и обратным клапаном, а верх - левым переводником. После отсоединени и установки НКТ в 0,3-0,5 м от хвостовика создали депрессию и получили .Skvszhin No. 90 and 91 were drilled to the roof of the reservoir bed and lined with a 168-mm production column, after which at the depths of 300-315 meters and 320-323 meters there were open areas: productive objects D and D, against which the trunk was expanded with a jetting method up to a diameter of 550-640 mm. Before the 73-mm tubing, shanks were lowered at the rate of entering them into the production string by 5 m. The bottom of the shanks was equipped with a shoe guide plug and non-return valve, and the top was equipped with a left sub. After disconnecting and installing the tubing in 0.3-0.5 m from the shank, they created a depression and got it.
устойчивый приток нефти. Анализ показал присутствие в добываемой про- дукии 0,05-0,1% мехпримесей, что указывало на нормальную работу скважин . Через 4 мес ра-боты соединилисьsteady flow of oil. The analysis showed the presence of 0.05-0.1% of mechanical impurities in the extracted product, which indicated normal operation of the wells. After 4 months, the workers joined
с хвостовиком, промыли скважинуwith shank, well washed
нефтью, очистив полость от песчаной пробки, и вновь пустили ее в работу.oil, clearing the cavity of the sand plug, and again let her work.
Корректор И. Эрдейи ПодписноеProofreader I. Erdeyi Subscription
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU843813931A SU1234587A1 (en) | 1984-11-22 | 1984-11-22 | Method of completing wells with loosely cemented collector rock |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU843813931A SU1234587A1 (en) | 1984-11-22 | 1984-11-22 | Method of completing wells with loosely cemented collector rock |
Publications (1)
Publication Number | Publication Date |
---|---|
SU1234587A1 true SU1234587A1 (en) | 1986-05-30 |
Family
ID=21147281
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
SU843813931A SU1234587A1 (en) | 1984-11-22 | 1984-11-22 | Method of completing wells with loosely cemented collector rock |
Country Status (1)
Country | Link |
---|---|
SU (1) | SU1234587A1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO1990005832A1 (en) * | 1988-11-22 | 1990-05-31 | Tatarsky Gosudarstvenny Nauchno-Issledovatelsky I Proektny Institut Neftyanoi Promyshlennosti | Method of casing the production seam in a well |
-
1984
- 1984-11-22 SU SU843813931A patent/SU1234587A1/en active
Non-Patent Citations (1)
Title |
---|
Ашрафь н М.О. и др. СИ. сер. Бурение, М.: ВНИИОЭНГ, с . 48. Авторское свидетельство СССР № 899870, кл. Е 21 В 43/08, 1979. * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO1990005832A1 (en) * | 1988-11-22 | 1990-05-31 | Tatarsky Gosudarstvenny Nauchno-Issledovatelsky I Proektny Institut Neftyanoi Promyshlennosti | Method of casing the production seam in a well |
US5031699A (en) * | 1988-11-22 | 1991-07-16 | Artynov Vadim V | Method of casing off a producing formation in a well |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4890675A (en) | Horizontal drilling through casing window | |
WO2020113870A1 (en) | Method for cooperatively draining roof separation water and mining coal-measure gas | |
RU2421586C1 (en) | Procedure for construction of horizontal well in devonian strata | |
CN110397428A (en) | A kind of gas displacing coal-bed method for increasing of straight well and U-shaped butt shaft unitized production coal bed gas | |
CN108756884A (en) | Coal mine tight roof full face ground shifts to an earlier date outburst elimination method | |
CN105201458A (en) | Well completion method for glass fiber reinforced plastic sieve tube of coal bed gas horizontal well | |
CN105909225A (en) | Fully mechanized caving face inter-frame oriented hydraulic fracturing top-coal weakening method | |
CA2025996C (en) | Borehole mining process for recovery of petroleum from unconsolidated heavy oil formations | |
RU2612060C9 (en) | Method of development of carbonate shaly oil deposits | |
SU1234587A1 (en) | Method of completing wells with loosely cemented collector rock | |
CN103089193A (en) | Tail pipe completion method by plugging expandable casing on top of screen pipe | |
US4368920A (en) | Method of thermal-mine working of oil reservoir | |
CN106801589A (en) | High temperature resistant big orifice hydraulic booster expanding suspension instrument and method | |
CN115822530A (en) | Long horizontal section under-pressure drill rod transmission well-flushing and perforation integrated tool and method | |
RU2167273C1 (en) | Method of casing liner installation in well | |
CN205135416U (en) | Inflation formula tail pipe drilling operation device | |
CN113356824A (en) | Integral development method for adjacent coal seam horizontal well in multi-coal seam development area | |
CN105971504A (en) | Drilling structure, method and device for uncertain stratum of target reservoir | |
RU2513376C1 (en) | Method of thermal production for shale oil | |
CN205172462U (en) | Fluid pressure type rigidity sleeve pipe centralizer | |
RU2385408C1 (en) | Method of development of oil or gas deposit | |
SU1610049A1 (en) | Method of methane drainage from coal seam | |
RU2140521C1 (en) | Method of well completion | |
SU1434133A1 (en) | Method of degassing coal-bearing stratum thickness | |
SU470584A1 (en) | Well boring method |