SU1190128A1 - Method of laying underground pipeline along water-logged and swamped sections - Google Patents

Method of laying underground pipeline along water-logged and swamped sections Download PDF

Info

Publication number
SU1190128A1
SU1190128A1 SU833638461A SU3638461A SU1190128A1 SU 1190128 A1 SU1190128 A1 SU 1190128A1 SU 833638461 A SU833638461 A SU 833638461A SU 3638461 A SU3638461 A SU 3638461A SU 1190128 A1 SU1190128 A1 SU 1190128A1
Authority
SU
USSR - Soviet Union
Prior art keywords
pipeline
pockets
ballasting
soil
swamped
Prior art date
Application number
SU833638461A
Other languages
Russian (ru)
Inventor
Валентин Сергеевич Сумароков
Игорь Петрович Новиков
Борис Лейбович Кривошеин
Олег Дмитриевич Ткаченко
Original Assignee
Государственный Научно-Исследовательский И Проектно-Конструкторский Институт "Южниигипрогаз"
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Государственный Научно-Исследовательский И Проектно-Конструкторский Институт "Южниигипрогаз" filed Critical Государственный Научно-Исследовательский И Проектно-Конструкторский Институт "Южниигипрогаз"
Priority to SU833638461A priority Critical patent/SU1190128A1/en
Application granted granted Critical
Publication of SU1190128A1 publication Critical patent/SU1190128A1/en

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

СПОСОБ ПРОКЛАДКИ ПОДЗЕМНОГО ТРУБОПРОВОДА НА ПЕРЕУВЛАЖНЕННЫХ И ЗАБОЛОЧЕННЫХ УЧАСТКАХ, заключающийс  в расположении трубопровода на уровне поверхности участков, закреплей и на нем ут желителей и карманов, заделывании трубопровода на проектные отметки ниже уровн  поверхности балластировкой карманов грунтом и засыпке заделанного трубопровода, отличающийс  тем, что, с целью упрощени  прокладки путем устранени  отрывки транщеи, балластировку карманов при заделывании трубопровода на проектные отметки дополн ют отсасыванием грунта из-под трубопровода , а в качестве грунта балластировки карманов и засыпки заделанного трубопровода используют отсосанный грунт, при этом балластировку карманов, а затем и засыпку трубопровода ведут одновременно с отсасыванием. (ЛMETHOD FOR LAYING UNDERGROUND PIPING FOR overmoistening and wetlands, comprising a pipeline arrangement at surface portions, fixed and thereon ut zheliteley and pockets embedding conduit to project a point below the surface level of ballasting the pockets with soil and backfilling embedded pipeline, characterized in that, with in order to simplify the installation by removing fragments of the trench, ballasting the pockets when the pipeline is sealed to the design marks is supplemented with suction of the soil from under the pipeline, and as soil pockets ballasting and backfilling pipeline embedded Sucked primer used, the ballasting of the pockets and then filling pipe lead simultaneously with suction. (L

Description

юYu

00 Изобретение относитс  к стронтельству и может найти применение при прокладке магистральных трубопроводов. Целью изобретени   вл етс  упрощение прокладки трубопровода путем устранени  отрывки траншеи. В соответствии со способом прокладки трубопровода на переувлажненных и заболоченных участках производ т расположение трубопровода на уровне поверхности переувлажненных или заболоченных участков , закрепл ют на трубопроводе в чере1 28 дующемс  пор дке ут желители и карманы и заделывают трубопровод на проектные отметки балластировкой карманов грунтом , а также одновременным отсасыванием грунта из-под трубопровода. При этом в качестве грунта балластировки, а в дальнейшем - засыпки трубопровода используют отсосанный грунт. Отсасывание грунта производ т , преимущественно, иглофильтрами с щелевыми отверсти ми. Иглофильтрами, в основном, разрабатывают грунт под ут желител ми и устанавливают их под углом к трубопроводу.00 The invention relates to strontium and can be used when laying main pipelines. The aim of the invention is to simplify the laying of the pipeline by removing the trench pieces. In accordance with the method of laying the pipeline on wetlands and wetlands, the pipeline is located at the surface of the overwetted or wetlands, fixed on the pipeline in alternate order, wands and pockets and sealed the pipeline to the design marks with pocket balancing with soil, as well as simultaneous suction of soil from under the pipeline. At the same time as the soil ballasting, and later - backfilling of the pipeline using sucked soil. Suction of the soil is carried out mainly by needle-filters with slotted holes. Needle filters, mainly, develop the soil under the iron and place them at an angle to the pipeline.

Claims (1)

СПОСОБ ПРОКЛАДКИ ПОДЗЕМНОГО ТРУБОПРОВОДА НА ПЕРЕУВЛАЖНЕННЫХ И ЗАБОЛОЧЕННЫХMETHOD FOR INSTALLING UNDERGROUND PIPELINE ON OVERWATERED AND WATERFORGED УЧАСТКАХ, заключающийся в расположении трубопровода на уровне поверхности участков, закреплении на нем утяжелителей и карманов, заделывании трубопровода на проектные отметки ниже уровня поверхности балластировкой карманов грунтом и засыпке заделанного трубопровода, отличающийся тем, что, с целью упрощения прокладки путем устранения отрывки траншеи, балластировку карманов при заделывании трубопровода на проектные отметки дополняют отсасыванием грунта из-под трубопровода, а в качестве грунта балластировки карманов и засыпки заделанного трубопровода используют отсосанный грунт, при этом балластировку карманов, а затем и засыпку трубопровода ведут одновременно g с отсасыванием. jSITES, consisting in the location of the pipeline at the surface level of the plots, fixing weighting materials and pockets on it, embedding the pipeline at design elevations below the surface level by ballasting the pockets with soil and filling the closed pipeline, characterized in that, in order to simplify the laying by eliminating fragments of the trench, ballasting the pockets when closing a pipeline to design elevations, it is supplemented by suctioning the soil from under the pipeline, and as soil, ballasting of pockets and filling Sucked th pipeline used primer, the ballasting of the pockets and then filling the pipeline are simultaneously g with suction. j
SU833638461A 1983-08-19 1983-08-19 Method of laying underground pipeline along water-logged and swamped sections SU1190128A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU833638461A SU1190128A1 (en) 1983-08-19 1983-08-19 Method of laying underground pipeline along water-logged and swamped sections

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU833638461A SU1190128A1 (en) 1983-08-19 1983-08-19 Method of laying underground pipeline along water-logged and swamped sections

Publications (1)

Publication Number Publication Date
SU1190128A1 true SU1190128A1 (en) 1985-11-07

Family

ID=21080397

Family Applications (1)

Application Number Title Priority Date Filing Date
SU833638461A SU1190128A1 (en) 1983-08-19 1983-08-19 Method of laying underground pipeline along water-logged and swamped sections

Country Status (1)

Country Link
SU (1) SU1190128A1 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Авторское свидетельство СССР № 796608, кл. F 16 L 1/02, 1979. Покровский г. И. Усовершенствование балластировки трубопровода, - Строительство трубопроводов, 1977, № 9, с. 20-21. *

Similar Documents

Publication Publication Date Title
ES2120041T3 (en) PROCEDURE AND TOOL FOR LAYING UNDERGROUND COLLECTING PIPES FOR LIQUIDS AND GASES.
SU1190128A1 (en) Method of laying underground pipeline along water-logged and swamped sections
RO81325B1 (en) Installation for burying coduits under water
SE8205938D0 (en) SET AND APPARATUS FOR THE CONSTRUCTION OF BENEFITS IN TARGET MARKET AND IN SUCH MARK LOCATED BENEFITS
CN210194654U (en) Deep basal pit well point dewatering construction equipment
DK1141495T3 (en) Base part for a sewer well
CA2557463A1 (en) Support system inside a casing for a well pump
SU619682A1 (en) Underground pumping unit of mine drainage
RU1778425C (en) Method of laying pipe line
JPS57130631A (en) Method and apparatus for treating underground water in underground excavation work
SU1030483A1 (en) Method for determining location of drain effluents
SU1802044A1 (en) Drainage system construction method
SU1331951A1 (en) Method of constructing enclosed horizontal drainage system
SU1783215A1 (en) Pipeline weighting device
SU1585455A1 (en) Drainage well
SU652275A1 (en) Water level lowering apparatus
SU1664964A1 (en) Method for constructing drainage system
SU779521A1 (en) Device for taking water from well
SU1545157A1 (en) Method of detecting seams under cover
SU1133339A1 (en) Drainage pipeline
RU1799412C (en) Method for withdrawal of mineralized water from underground mine working
JPS5768426A (en) Waterproofing method for foundation of bottom plate of tank
SU1010191A1 (en) Filtering coating of drain pipe
SU1180446A1 (en) Water-drawing mine installation
SU68601A1 (en) Method of draining floats