SE511488C2 - Procedure for the manufacture of a wall part for a housing body - Google Patents
Procedure for the manufacture of a wall part for a housing bodyInfo
- Publication number
- SE511488C2 SE511488C2 SE9800603A SE9800603A SE511488C2 SE 511488 C2 SE511488 C2 SE 511488C2 SE 9800603 A SE9800603 A SE 9800603A SE 9800603 A SE9800603 A SE 9800603A SE 511488 C2 SE511488 C2 SE 511488C2
- Authority
- SE
- Sweden
- Prior art keywords
- layer
- mixture
- cement
- layers
- surface portion
- Prior art date
Links
- 238000000034 method Methods 0.000 title claims abstract description 16
- 238000004519 manufacturing process Methods 0.000 title claims abstract description 12
- 239000004568 cement Substances 0.000 claims abstract description 78
- 239000000203 mixture Substances 0.000 claims abstract description 78
- 238000009413 insulation Methods 0.000 claims abstract description 24
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 17
- 239000002002 slurry Substances 0.000 claims abstract description 16
- 239000011230 binding agent Substances 0.000 claims abstract 6
- 241000196324 Embryophyta Species 0.000 claims description 20
- 239000010902 straw Substances 0.000 claims description 15
- 238000005507 spraying Methods 0.000 claims description 14
- 239000004576 sand Substances 0.000 claims description 10
- 230000002787 reinforcement Effects 0.000 claims description 6
- 230000015572 biosynthetic process Effects 0.000 claims description 4
- 239000004033 plastic Substances 0.000 claims description 4
- 229920006328 Styrofoam Polymers 0.000 claims description 3
- 241000209140 Triticum Species 0.000 claims description 3
- 235000021307 Triticum Nutrition 0.000 claims description 3
- 235000021028 berry Nutrition 0.000 claims description 3
- 238000002791 soaking Methods 0.000 claims description 3
- 239000008261 styrofoam Substances 0.000 claims description 3
- 238000002203 pretreatment Methods 0.000 claims description 2
- 239000000945 filler Substances 0.000 claims 4
- 238000001035 drying Methods 0.000 claims 1
- 239000011368 organic material Substances 0.000 claims 1
- 238000005192 partition Methods 0.000 claims 1
- 239000000758 substrate Substances 0.000 claims 1
- 239000000463 material Substances 0.000 abstract description 5
- 239000000835 fiber Substances 0.000 abstract 2
- 235000013311 vegetables Nutrition 0.000 abstract 2
- 238000005253 cladding Methods 0.000 description 5
- 239000002184 metal Substances 0.000 description 3
- 239000007921 spray Substances 0.000 description 3
- 238000009835 boiling Methods 0.000 description 2
- 238000010276 construction Methods 0.000 description 2
- 230000003247 decreasing effect Effects 0.000 description 2
- 239000002023 wood Substances 0.000 description 2
- ZCSHACFHMFHFKK-UHFFFAOYSA-N 2-methyl-1,3,5-trinitrobenzene;2,4,6-trinitro-1,3,5-triazinane Chemical compound [O-][N+](=O)C1NC([N+]([O-])=O)NC([N+]([O-])=O)N1.CC1=C([N+]([O-])=O)C=C([N+]([O-])=O)C=C1[N+]([O-])=O ZCSHACFHMFHFKK-UHFFFAOYSA-N 0.000 description 1
- 206010011469 Crying Diseases 0.000 description 1
- 206010020751 Hypersensitivity Diseases 0.000 description 1
- 206010061217 Infestation Diseases 0.000 description 1
- 241000256602 Isoptera Species 0.000 description 1
- 230000007815 allergy Effects 0.000 description 1
- 235000013339 cereals Nutrition 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 230000001419 dependent effect Effects 0.000 description 1
- 229910010272 inorganic material Inorganic materials 0.000 description 1
- 239000011147 inorganic material Substances 0.000 description 1
- 239000012774 insulation material Substances 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 238000005086 pumping Methods 0.000 description 1
- 235000000346 sugar Nutrition 0.000 description 1
- 150000008163 sugars Chemical class 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C2/00—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
- E04C2/02—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials
- E04C2/04—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of concrete or other stone-like material; of asbestos cement; of cement and other mineral fibres
- E04C2/044—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of concrete or other stone-like material; of asbestos cement; of cement and other mineral fibres of concrete
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/07—Reinforcing elements of material other than metal, e.g. of glass, of plastics, or not exclusively made of metal
- E04C5/073—Discrete reinforcing elements, e.g. fibres
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Building Environments (AREA)
- Curing Cements, Concrete, And Artificial Stone (AREA)
- Laminated Bodies (AREA)
- Panels For Use In Building Construction (AREA)
Abstract
Description
10 7. 1 1 4 8 8 komst av allergier etc. Vete är ett av de sädesslag som odlas mest i världen, men halmsortemas antal är stort, it.ex. Sydafrika finns minst 30 olika sorter. 10 7. 1 1 4 8 8 occurrence of allergies, etc. Wheat is one of the most widely grown grains in the world, but the number of straw varieties is large, it.ex. South Africa has at least 30 different varieties.
Länder såsom Syd Afrika m.fl. är det ett skriande behov av bostäder, och bostäderna skall vara billiga att tillverka och därtill skall produktionstakten vara hög.Countries such as South Africa m. Fl. there is a crying need for housing, and housing must be cheap to manufacture and in addition the production rate must be high.
Därtill kommer traditioner hur ett hus yttre fasad är anordnad.In addition, there are traditions of how a house's exterior facade is arranged.
Beskrivning av uppfinningen Syftet med föreliggande uppfinning är att åstadkomma förfarande, enligt ingressen till patentkraven 1 Problemlösningen uppnås enligt den kännetecknande delen enligt patentkraven 1 Ett förfarande enligt uppfinning vid tillverkning av tunn armerad skiva, skiva för be- klädnad av väggar och tak kännetecknas av att skivan byggs upp av tre lager cementkomposition med ett första lager som innehåller cementkomposition A, ett andra lager som innehåller cementkomposition B med armering av växtfi- ber, därtill ett tredje lager som innehåller cementkomposition C. Varje lager av cementkompositionen A, B, och C appliceras genom sprutning. Det första lagret ges en tjocklek inom intervallen 1- 3 mm. Vid det första lagrets yta ap- pliceras ett andra lager cementkomposition B, även det appliceras genom sprutning. Det andra lagret sprutas i ett antal skikt och varje skikt har särskil- jande cementkomposition B, B1 etc. Det särskiljande i cementkompositionen Bl, B2, B3...Bn utmärkas av; att det första skiktets cementkomposition B1 innehåller högre andel cement än det andra skiktets cementkomposition (B2); efterföljande skikts cementkomposition B3..Bn innehåller lägre andel cement än föregående skikts cementkomposition B2 osv. På det andra lagrets yta anordnas, genom sprutning, en tredje cementkomposition C. \fid sprutning av slurry nyttjas ”betongpump” som ger möjlighet att reglera mängd slurry per tidsenhet.Description of the invention The object of the present invention is to provide a procedure, according to the preamble to claims 1 The problem solution is achieved according to the characterizing part according to claims 1 A method according to the invention in the manufacture of thin reinforced board, board for cladding of walls and ceilings is characterized by the fact that the board is built up of three layers cement composition with a first layer containing cement composition A, a second layer containing cement composition B with plant reinforcement fi- ber, in addition a third layer containing cement composition C. Each layer of cement compositions A, B, and C are applied by spraying. The first the bearing is given a thickness in the intervals 1-3 mm. At the surface of the first layer ap- a second layer of cement composition B is applied, also it is applied through spraying. The second layer is sprayed in a number of layers and each layer has different cement composition B, B1 etc. The distinctive feature of the cement composition Bl, B2, B3 ... Bn is marked by; that the cement composition B1 of the first layer contains a higher proportion of cement than the cement composition (B2) of the second layer; subsequent cement composition B3..Bn contains a lower proportion of cement than the previous layer cement composition B2, etc. On the surface of the second layer arranged, by spraying, a third cement composition C. \ fi d spraying of slurry is used "concrete pump" which provides the opportunity to regulate quantity slurry per unit of time.
Wd sprutning av skikten i andra lagret skall cementkompositionen bringas mot ytan med så stor hastighet, -kraft- , att merparten av luttblåsor pressas ut ur ce- mentkompositionen. Genom att pressa ut luften så kommer skiktet att få ökad hållfasthet. Växtfiber, exempelvis halm, medverkar till att arrnera skivan, ski- van kan utsättas för högre belastning än skiva utan arrnering. Därtill medver- l0 3 511 488 kar växtfibem till att skivan blir skruv - och spikbar, utan att man behöver nyttja olika typer av plastpluggar etc.When spraying the layers in the second layer, the cement composition must be brought to the surface with such speed, -power-, that most of the lye blisters are forced out of the ment composition. By squeezing out the air, the layer will increase strength. Plant fi ber, for example straw, helps to arrange the disc, ski- The van can be subjected to a higher load than a disc without locking. In addition, l0 3 511 488 kar plant fi bem so that the disc becomes screwed - and nailable, without the need use different types of plastic plugs etc.
Förfarande enligt uppfinningen vid tillverkning av väggelement innefattande annerad väggbeklädnad där armering utgöres av växtfiber kännetecknas av att ram- verk kläs med isolerings skivor. l isoleringens yta fräses längdsgående spår för strimla, av oorganiskt material med företrädesvis en tjocklek av 4 mm.Method according to the invention in the manufacture of wall elements comprising other wall cladding where reinforcement consists of plant fi should be characterized by works are covered with insulation boards. Longitudinal grooves are milled in the surface of the insulation for shredding, of inorganic material, preferably 4 mm thick.
Strimlans bredd anpassas till isoleringens tjocklek, strimlans bredd är alltid mindre än isoleringens tjocklek. Strimlan skjuter upp ca 1- 3 mm ovanför iso- leringsskivans yta.The width of the strip is adapted to the thickness of the insulation, the width of the strip is always less than the thickness of the insulation. The strip protrudes about 1-3 mm above the iso- the surface of the clay disc.
På isoleringsskivans yta och de uppskjutande strimlomas ändparti sprutas ett första lager cementkomposition A till en tjocklek ~1-3 mm. Totalt anbringas tre lager cementkomposition A, B, C på lsoleringsskivan. Pà det första lagrets yta, cementkomposition A, sprutas ett andra lager cementkomposition med ett antal skikt. Det andra lagret innehållande växtfiber, dessa växtfibrer utgör skivans armering. Skiktens sammansättning förändras, genom att minska andelen cement i kompositionen. Anledning till denna förändring är att få en skiva som dels har en stor hårdhet dels minimera risken för sprickor. \fid sprutning av det andra lagret är det viktigt att slurryn sprutas under högt tryck mot skivan, allt för att pressa ur luftblåsor. Luftblåsor minskar skivans håll- fasthet. Tjockleken på det andra skiktet inom företrädesvis ~5- 8 mm.A first is sprayed on the surface of the insulation board and the end portion of the projecting strips layer cement composition A to a thickness ~ 1-3 mm. A total of three layers are applied cement composition A, B, C on the insulation board. On the surface of the first layer, cement composition A, a second layer of cement composition is sprayed with one number of layers. The second layer containing plants, these plants make up the reinforcement of the disc. The composition of the layers changes, by decreasing the proportion of cement in the composition. The reason for this change is to get one disc that has a high hardness and minimizes the risk of cracks. \ fi d spraying the second layer, it is important that the slurry is sprayed under high pressure against the disc, all to squeeze out air bubbles. Air bubbles reduce the hold of the disc. firmness. The thickness of the second layer is preferably ~ 5-8 mm.
På andra lagrets yta sprutas ett tredje lager (16) av cementkomposition C med en tjocklek av ~5 mm Ramverket tillverkas företrädesvis av rullformade tunna metallprofiler, av förzinkad stälplät t.ex. i tjocklekar 0,4 till 2,5 mm som formats till U-, L-, Z- form. Ram- verket hopsättas genom nitning, bultförband etter någon annan likvärdig me- tod. Alternativt ramverk är en spikad konstruktion med träribbor.On the surface of the second layer, a third layer (16) of cement composition C is sprayed with a thickness of ~ 5 mm The framework is preferably made of roll-shaped thin metal profiles, of galvanized stälplät e.g. in thicknesses 0.4 to 2.5 mm formed into U-, L-, Z-shape. Frame- the work is assembled by riveting, bolted joints by any other equivalent means. tod. An alternative framework is a nailed construction with wooden slats.
Utanpå ramverket fästes isoleringsskivor av typ expanderad plast, typ frigolit, ett rela- tivt billigt isoleringsmaterial som motstår fukt etc. l isoleringsskivans spår an- ordnas strimlor av tunna oorganiska skivmaterial, typ cementbaserade tunna skivor i tjockleken 4 mm som sågats upp i strimlor.On the outside of the framework, insulating sheets of the expanded plastic type, Styrofoam type, a rela- cheap insulation material that resists moisture, etc. In the grooves of the insulation board strips of thin inorganic sheet material, such as cement-based barrels, are arranged slices 4 mm thick that have been sawn into strips.
Uppfinningen anvisar även ett förfarande vid tillverkning cementkomposition innehål- lande växtfiber, att nyttjas vid tillverkning av väggskiva som kännetecknas av lO 511 488 H att ett första lager cementkomposition A, innehåller företrädesvis; 1 del ce- ment och 1 del sand slammad i vatten. Ett andra lager, med ett antal applice- rade skikt uppvisar cementkomposition B1, B2.....Bn. Cementkomposition, B1, B2.....Bn, innehåller förbehandlad växtfiber, företrädesvis vetehalm, kros- sad och klippt i längder om ~0,5 - 2 cm, dessa växtfibrer tjänstgör som ski- vans armering. innehållet i andra lagrets första skikt, cementkomposition B1, förevisa företrädesvis; 2 delar växtfiber, halm, 2 delar sand, 2 delar cement och vatten till en koncent- ration anpassad för applicering genom sprutning. Därefter appliceras ett and- ra skikt som uppvisa ett innehåll med lägre koncentration cement än i det första skiktet. Varje tillkommande skikt, cementkomposition, innehåller lägre koncentration av cement än cementkompositionen i föregående skikt. Antalet skikt som sprutas i andra lagret är företrädesvis inom intervallen 2 -6 stycken.The invention also discloses a process for manufacturing cement composition containing plant fi ber, to be used in the manufacture of wallboard characterized by lO 511 488 H that a first layer of cement composition A, preferably contains; 1 del ce- ment and 1 part sand slurried in water. A second layer, with a number of applications laminated layers show cement composition B1, B2 ..... Bn. Cement composition, B1, B2 ..... Bn, contains pre-treated plant fi berries, preferably wheat straw, crushed sown and cut to lengths of ~ 0.5 - 2 cm, these plants serve as skis. vans reinforcement. the contents of the first layer of the second layer, cement composition B1, preferably exhibit; 2 parts plant fi ber, straw, 2 parts sand, 2 parts cement and water to a ration adapted for application by spraying. Then a breath is applied. layers which have a content with a lower concentration of cement than in it first layer. Each additional layer, cement composition, contains lower concentration of cement than the cement composition in the previous layer. The number layers sprayed in the second layer are preferably in the range of 2-6 pieces.
Det yttre, ett tredje lager, cementkomposition C, uppvisar ett innehåll med företrä- desvis 6 delar sand, 1 del cement och vatten till koncentration anpassad för pumpning, slurry, och applicering genom sprutning.The outer, third layer, cement composition C, has a content with preferred also 6 parts sand, 1 part cement and water to concentration adapted for pumping, slurry, and spray application.
Förbehandling av växtfiber t.ex. halm, sker genom att den klippta och krossade fibern blötläggs i varmt vatten, inte kokande, upp till 18 timmar allt beroende på halmkvalitet. \fid blötläggningen så ”rengörs”, lakas, strået yta från de vaxar- tade skiktet samt vissa sockerarter, samt att fibem blir formbar. Efter blöt- läggningen skall växtfibern ha sådan konsistens att den med lätthet kan blan- das till en pump- och sprut applicerbar slurry.Pre-treatment of plant fi asks e.g. straw, is made by the cut and crushed fi bern soak in warm water, not boiling, up to 18 hours depending on straw quality. \ fi d the soaking so 'cleaned', leached, the straw surface from the wax- the layer as well as certain sugars, and that att bem becomes malleable. After soaking the plant must be of such a consistency that it can be easily mixed das to a pump and spray applicable slurry.
BESKRIVNING TILL FIGURBLAD Uppfinningen beskrivs nedan i form av utföringsexempel i anslutning till bifogade fi- gurblad.DESCRIPTION OF FIGURE SHEET The invention is described below in the form of exemplary embodiments in connection with the appended fi- gurblad.
FIG. 1 visar framsida av ett hus F IG. 2 visar en sidovy av hus F IG. 3 visar en väggmodul, inklusive ramverk F IG. 4 visar ett snitt A-A ur figur 3 FlG. 5 visar en förstoring av del i FIG. 4.FIG. 1 shows the front of a house F IG. 2 shows a side view of house F IG. 3 shows a wall module, including framework F IG. 4 shows a section A-A of clock 3 FlG. 5 shows an enlargement of a part in FIG. 4.
FIG. 6 visar ett snitt i byggskiva, de olika lagren av cementkomposition lO 511 488 FlG. 7 visar detalj i figur 5 byggskíva inklusive tvärställda strimlor l figur 1, 2 visas väggparti 1, 2 i ett småhus, väggpartier 1, 2 som med fördel tillverkas i industriell skala och därefter monteras pá en grundplatta 3. l figur 3, 4 visas väggelement 4 innehållande ramverk 5 med reglar 6 och vid ramver- kets 5 utsida 7 anordnad isolering 8. Reglar 6 kan vara av metallprofil eller trä- virke, med fördel nyttjas reglar 6 av metall i fuktigt klimat eller där risk föreligger för angrepp av termiter. isolering 8, har funktionen att vara isolerande och ett underlag för montering av yttre väggskiva 9. Exempel på isolering 8 är expanderad plast, typ frigolit, där tjockle- ken på isoleringen 8 anpassas till klimatet etc, en tunnare skiva för hus i Syd Afrika medan tjockare isolering 8 för byggnader i Sverige. isolering 8 spikas, skruvas fast eller på annat sätt anordnas vid ramverk 5, tillsam- mans utgör ramverk 5 och isolering 8 ett väggelement 4. l isolering 8 ytparti 10 anordnas företrädesvis vinkelrätt mot ytan 10 lángdsgående spårbildning 11. I spårbildningen 11 anordnas strimlor 12 av t.ex. tunna ce- mentskivor tjocklek ~4 mm. Strimloma 12 sticker upp någon eller några mm, ~1- 3, ovanför isoleringens 8 yta 10 Vid isoleringens yta 10 anordnas yttre väggbeklädnad, väggelement 13. Väggbekläd- nad 13 innefattar strimlor 12 och väggskiva 9, strimloma 12 är fast anordnade vid väggskiva 9 l fig. 5, uppvisas förstoring av väggskiva 9 med strimlor 12 och isolering 8. väggskiva 9 är uppbyggd av tre lager 14, 15, 16 cementkomposition A, B, C.FIG. 6 shows a section in the building board, the different layers of cement composition lO 511 488 FlG. 7 shows detail in 5 gur 5 construction board including transverse strips Layers 1, 2 show wall sections 1, 2 in a detached house, wall sections 1, 2 which are advantageously manufactured on an industrial scale and then mounted on a base plate 3. Figures 3, 4 show wall elements 4 containing frame 5 with studs 6 and at frame The outer surface of the chain 5 is arranged 8. The bars 6 can be of metal profile or wood. wood, it is advantageous to use bars 6 of metal in humid climates or where there is a risk for termite infestation. insulation 8, has the function of being insulating and a base for mounting the exterior wall panel 9. An example of insulation 8 is expanded plastic, type styrofoam, where the thickness the insulation 8 is adapted to the climate etc, a thinner board for houses in the South Africa while thicker insulation 8 for buildings in Sweden. insulation 8 is nailed, screwed on or otherwise arranged at framework 5, together man forms a framework 5 and insulation 8 a wall element 4. In insulation 8 surface portion 10 is preferably arranged perpendicular to the surface 10 longitudinally groove formation 11. In the groove formation 11 strips 12 of e.g. thin ce- ment boards thick ~ 4 mm. Strips 12 protrude some or a few mm, ~ 1- 3, above the surface 10 of the insulation 8 At the surface 10 of the insulation, outer wall cladding, wall elements 13 are arranged. 13 comprises strips 12 and wall plate 9, the strips 12 being fixedly arranged at wall panel 9 l fi g. 5, enlargement of wall panel 9 with strips 12 and insulation 8 wall panel is shown 9 is made up of three layers 14, 15, 16 cement composition A, B, C.
I fig. 6 uppvisas separat strimlor 12 och väggskiva 9. Genom att anordna strimlor 12 vid skiva 9 så uppnås en styvare väggbeklädnad 13, kan ta upp större belastning än en enkel väggskiva 9 Det första lagret 14 cementkomposition A innehåller företrädesvis; 1 del cement, 1 del sand slammad i vatten till slurry som applicerat vid ytparti 10 genom sprutning, till en tjocklek inom företrädesvis intervallen ~1- 3 mm. Det första lagret (14) verkar som primer för kommande lager av cementkomposition.I fi g. 6, strips 12 and wall panel 9 are shown separately. By arranging strips 12 at board 9 a stiffer wall cladding 13 is achieved, can take up greater load than a simple wall panel 9 The first layer 14 cement composition A preferably contains; 1 part cement, 1 part sand slurried in water to slurry as applied to surface portion 10 by spraying, to a thickness in preferably the ranges ~ 1-3 mm. The first layer (14) acts as a primer for future layers of cement composition.
Det andra lagret 15 cementkomposition B är applicerat i ett antal skikt 15.1, 15.2, .3...15.n, företrädesvis två till sex skikt, där cementkomposition B innehåller lO 511 488 armering av växtfiber, företrädesvis halm klippta och krossade i längder om 0,5 till 2 cm längd. Cementkomposition B innehåller företrädesvis 2 delar halm, 2 delar sand, 2 delar cement och vatten anordnad som slurry för applicering ge- nom sprutning. l andra lagrets 15 första skikt 15.1 bringas en cementkomposition B, vid första lagrets 14 yta 17, därefter bringas ett andra skiktet 15.2 med cementkomposition B1 med reduceras mängden, andelen, cement, i varje därpå anordnat skikt .3....15.n av cementkomposition B2, B3....Bn minskas successivt andelen cement. Tjockleken av andra lagret 15 företrädesvis inom intervallen ~5- 8 mm.The second layer 15 cement composition B is applied in a number of layers 15.1, 15.2, .3 ... 15.n, preferably two to six layers, where cement composition B contains lO 511 488 reinforcement of plant fi ber, preferably straw cut and crushed in lengths of 0.5 to 2 cm in length. Cement composition B preferably contains 2 parts of straw, 2 parts sand, 2 parts cement and water arranged as a slurry for application nom spraying. In the first layer 15.1 of the second layer 15, a cement composition B is applied, at the first layer 14 surface 17, then a second layer 15.2 with cement composition B1 is applied with reduces the amount, proportion, cement, in each layer applied thereto .3 .... 15.n of cement composition B2, B3 .... Bn gradually reduces the proportion cement. The thickness of the second layer 15 is preferably in the range ~ 5-8 mm.
Wd beredning av cementkomposition B blötläggas den klippta i bitar och krossade växtfibem, halmen ivarmt vatten, ej kokande, upp till ca 18 timmar. Blötlägg- ningstiden är helt beroende av halmkvalitet, i Sydafrika finns uppskattningsvis olika sorters halm. Halmen skall blötläggas under så lång tid att den i slurry ingående halmen ej fastnar i sprutanordningens munstycke. \fid applicenng av cementkomposition B skall den bringas mot ytan med så stor has- tighet -kraft- att merparten av luftblåsor i slurry pressas ut. Hållfastheten i lagret minskas om mängden luftblåsor ökar.Wd preparation of cement composition B soaked it cut into pieces and crushed plant fi bem, straw in warm water, not boiling, up to about 18 hours. Soak- The processing time is completely dependent on straw quality, in South Africa it is estimated different kinds of straw. The straw should be soaked for such a long time that it slurries the incoming straw does not get stuck in the nozzle of the sprayer. When applying cement composition B, it must be brought to the surface with such a high power -for- that most of the air bubbles in the slurry are squeezed out. The strength of the bearing decreased if the amount of air bubbles increases.
Det tredje lagret 17 cementkomposition C, företrädesvis 6 delar sand, 1 del cement och vatten omrörd till slurry för sprutapplicering, bringas till andra lagrets 15 yta 18. Tjocklek för det tredje lagret upp till ~5 mm.The third layer 17 cement composition C, preferably 6 parts sand, 1 part cement and water stirred into a slurry for spray application, is brought to the surface of the second layer 18. Thickness of the third layer up to ~ 5 mm.
Vid tillverkning av väggelement 1, så anordnas reglar 6 i fixtur, och bringas ihop ge- nom tex. bultförband, eller med något annat fästelement till ett ramverk 5.In the manufacture of wall elements 1, bars 6 are arranged in xt xture, and are brought together nom tex. bolted joint, or with another fastener to a framework 5.
Därefter fästes isoleringsskiva 8 på utsida ramverket 5. \f|d isoleringens 8 ytparti fräses längdsgående spår 11, i spåren anordnas stnmlor 12 av exempelvis tunna oementskivor.Thereafter, the insulation board 8 is attached to the outside of the framework 5. The surface portion of the insulation 8 longitudinal grooves 11 are milled, stems 12 of, for example, are arranged in the grooves thin oement slices.
Ett första lager 14 av cementkomposition A appliceras på ytan 10, appliceringen sker genom sprutning av slurryn A under högt tryck. Detta första lager 14 skall funge- ra som primer för nästa lager 15 av cementkomposition B.A first layer 14 of cement composition A is applied to the surface 10, the application takes place by spraying the slurry A under high pressure. This first layer 14 shall function ra as a primer for the next layer 15 of cement composition B.
Den nu tillverkade väggelementen 4 anordnat med ett första lager 14 av cementkom- position A monteras på husgrunden 3. Efter det att alla väggelementen 4 är monterade så utförs först sprutning av cementkomposition B, och därefter oe- mentkomposition C på väggelementets 4 yttre yta. * 511488 Givetvis begränsas ej uppfinningen till att applicera lager 14, 15, 16 av cementkom- position A, B, C på väggelement 4 utan förfarandet kan med fördel nyttjas vid att tillverka skivor. Fig. 7 uppvisar en enkel väggskiva skiva. \fid tillverkning av ski- vor nyttjas med fördel formar, med botten och kanter. lnnan sprutning av första lager 14 cementkomposition A på formens botten behandlas bottenytan med något medel för att undvika vidhäftning mellan lagret 14 och bottenplattan. Och lager 14, 15, 16 sprutas i formen. Skivan kan nyttjas på samma sätt som en gipsskiva, som vägg och tak beklädnads materialThe now manufactured wall elements 4 arranged with a first layer 14 of cement position A is mounted on the house foundation 3. After all the wall elements 4 are mounted, first spraying of cement composition B is carried out, and then oe- ment composition C on the outer surface of the wall element 4. * 511488 Of course, the invention is not limited to applying layers 14, 15, 16 of cement position A, B, C on wall element 4 without the method can be used to advantage in that make discs. Fig. 7 shows a simple wall panel board. Manufacture of skis spring is advantageously used molds, with bottom and edges. lnnan spraying of the first layer 14 cement composition A on the bottom of the mold is treated with the bottom surface some means to avoid adhesion between the bearing 14 and the base plate. And bearings 14, 15, 16 are sprayed into the mold. The disc can be used in the same way as one plasterboard, as wall and ceiling cladding material
Claims (8)
Priority Applications (4)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| SE9800603A SE511488C2 (en) | 1998-02-25 | 1998-02-25 | Procedure for the manufacture of a wall part for a housing body |
| AU93722/98A AU9372298A (en) | 1998-02-25 | 1998-10-01 | Method for the manufacture of a wall section for a main body of a house and the wall section itself |
| PCT/SE1998/001774 WO1999043908A1 (en) | 1998-02-25 | 1998-10-01 | Method for the manufacture of a wall section for a main body of a house and the wall section itself |
| ZA989252A ZA989252B (en) | 1998-02-25 | 1998-10-09 | Wall portion for a building |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| SE9800603A SE511488C2 (en) | 1998-02-25 | 1998-02-25 | Procedure for the manufacture of a wall part for a housing body |
Publications (3)
| Publication Number | Publication Date |
|---|---|
| SE9800603D0 SE9800603D0 (en) | 1998-02-25 |
| SE9800603L SE9800603L (en) | 1999-08-26 |
| SE511488C2 true SE511488C2 (en) | 1999-10-04 |
Family
ID=20410330
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| SE9800603A SE511488C2 (en) | 1998-02-25 | 1998-02-25 | Procedure for the manufacture of a wall part for a housing body |
Country Status (4)
| Country | Link |
|---|---|
| AU (1) | AU9372298A (en) |
| SE (1) | SE511488C2 (en) |
| WO (1) | WO1999043908A1 (en) |
| ZA (1) | ZA989252B (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN200957623Y (en) * | 2006-09-29 | 2007-10-10 | 杭州大庄地板有限公司 | High-density flattening plate |
Family Cites Families (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US2850890A (en) * | 1951-06-04 | 1958-09-09 | Rubenstein David | Precast element and reinforced facing layer bonded thereto |
| GB1150600A (en) * | 1967-02-01 | 1969-04-30 | Peter John Mullis | Improvements in or relating to Building Materials |
| AT303333B (en) * | 1970-04-17 | 1972-11-27 | Elten Tech Ontwickel Bv | Lightweight panel |
| FR2214309A5 (en) * | 1972-12-15 | 1974-08-09 | Sommer Charles | |
| DE2312261A1 (en) * | 1973-03-12 | 1974-09-19 | Broeker Friedrich Wilhelm Dipl | Extracting setting retardants from fibrous materials - designated for compounding with hydraulic cement to produce structural materials |
| US3974024A (en) * | 1973-03-23 | 1976-08-10 | Onoda Cement Company, Ltd. | Process for producing board of cement-like material reinforced by glass fiber |
| DE9000238U1 (en) * | 1990-01-11 | 1990-04-19 | Kakuk, Stefan, 68794 Oberhausen-Rheinhausen | Kit of lightweight components for walls, columns, ceilings and other components |
-
1998
- 1998-02-25 SE SE9800603A patent/SE511488C2/en not_active IP Right Cessation
- 1998-10-01 WO PCT/SE1998/001774 patent/WO1999043908A1/en not_active Ceased
- 1998-10-01 AU AU93722/98A patent/AU9372298A/en not_active Abandoned
- 1998-10-09 ZA ZA989252A patent/ZA989252B/en unknown
Also Published As
| Publication number | Publication date |
|---|---|
| AU9372298A (en) | 1999-09-15 |
| WO1999043908A1 (en) | 1999-09-02 |
| SE9800603L (en) | 1999-08-26 |
| SE9800603D0 (en) | 1998-02-25 |
| ZA989252B (en) | 1999-05-21 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US7861476B2 (en) | Cementitious exterior sheathing product with rigid support member | |
| DE3685581T2 (en) | MODULAR CONSTRUCTION CONSTRUCTION AND METHOD FOR ASSEMBLING SUCH BUILDINGS. | |
| US7575701B2 (en) | Method of fabricating shake panels | |
| AU2002248752B2 (en) | Two-piece siding plank, methods of making and installing | |
| AU2021203093A1 (en) | Permeable elastomeric membrane adhered to fire-rated structural osb panels | |
| US20120192517A1 (en) | Cementitious exterior sheathing product having improved interlaminar bond strength | |
| US20160375663A1 (en) | Thermal insulation wallboard and method for producing the same | |
| WO2009056117A1 (en) | Composite cellulose element | |
| CN102731903A (en) | Composite material of imitated glass reinforced plastic, its manufacture method and its application | |
| US5288775A (en) | Moldable building material composites | |
| CN102021966A (en) | Plant fibers and formaldehyde-free artificial board composited building wall panel | |
| EP2726680B1 (en) | Façade construction for thermally insulating and cladding external walls of buildings, and method for producing such a façade construction | |
| CN100371281C (en) | Straw fiber cement composite material | |
| SE511488C2 (en) | Procedure for the manufacture of a wall part for a housing body | |
| US20240336530A1 (en) | Building material made of industrial tailings/waste | |
| WO2007025272A3 (en) | Biocidal premixtures | |
| CN108396935A (en) | A kind of hollow glass steel floor and preparation method thereof | |
| EP4471221B1 (en) | Prefabricated element for covering building envelopes and procedure for obtaining it | |
| JP3071150B2 (en) | Building exterior wall construction method | |
| EP0466685B1 (en) | Lining for buildings and method for its manufacture | |
| Rufin | Rice Hull Ceiling Board | |
| WO1984002941A1 (en) | Cover panels with upper decorative surface intended to prevent fire propagation | |
| WO2024242711A1 (en) | Polymer construction studs and sheathing | |
| AU2016101410A4 (en) | Wall Construction for Framed Building | |
| DK9700250U3 (en) | Element for wall, facade or roof insulation |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| NUG | Patent has lapsed |
Ref document number: 9800603-4 Format of ref document f/p: F |