SE508833C2 - Method for extracting a vertical rock compartment with an elliptical or oval cross section and a rock compartment made by the method - Google Patents

Method for extracting a vertical rock compartment with an elliptical or oval cross section and a rock compartment made by the method

Info

Publication number
SE508833C2
SE508833C2 SE9704572A SE9704572A SE508833C2 SE 508833 C2 SE508833 C2 SE 508833C2 SE 9704572 A SE9704572 A SE 9704572A SE 9704572 A SE9704572 A SE 9704572A SE 508833 C2 SE508833 C2 SE 508833C2
Authority
SE
Sweden
Prior art keywords
rock
roof
rock chamber
chamber
section
Prior art date
Application number
SE9704572A
Other languages
Swedish (sv)
Other versions
SE9704572D0 (en
SE9704572L (en
Inventor
Per-Anders Daerga
Karl Ivar Sagefors
Original Assignee
Daerga Anders
Karl Ivar Sagefors
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daerga Anders, Karl Ivar Sagefors filed Critical Daerga Anders
Priority to SE9704572A priority Critical patent/SE508833C2/en
Publication of SE9704572D0 publication Critical patent/SE9704572D0/en
Publication of SE9704572L publication Critical patent/SE9704572L/en
Publication of SE508833C2 publication Critical patent/SE508833C2/en
Priority to PCT/SE1998/002232 priority patent/WO1999030003A1/en
Priority to AU18955/99A priority patent/AU1895599A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D13/00Large underground chambers; Methods or apparatus for making them

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Foundations (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention refers to a method for excavating a vertical rock cavern having an elliptical or oval cross section, whereby access from ground level to the cavern takes place via a ramp or through a vertical shaft, and that the cavern is intended for the storage of bulk products, e.g. gas and/or fluids. Vertical rock caverns combine a good environment for storage with favourable rock stability in the surrounding rock, which is a pre-requisite for being able to construct caverns with large spans. However, the work of excavating a vertical rock cavern has not been carried through in a sufficiently efficient manner as the work has, among other things, taken place on far too many levels. The procedure according to the invention is distinguished in that a roof section (2) and a bottom section (3) are developed on at least two levels, and that the volume existing between them is bench drilled, blasted and removed.

Description

15 20 25 30 35 508 833 ; antal arbetscykler och en koncentration av arbetet till företrädesvis endast bergrummets tak- resp. bottenparti. Med särdragen enligt uppfinningen uppnås fördelen att utlastning samtidigt kan utföras på två nivåer i botten av bergrummen vilket möjliggör att den väsentliga bergvolym som erhålles från pallbrytningen mycket snabbt kan utlastas från det upptagna bergrummet. I botten av bergrummet erhålles en unik uppsamlingsplats vilken ger utrymmet för uppsarnling av eventuella partiklar som utfalls från det medium som lagras i bergrummet. De vertikala schakten mellan den övre och nedre lastnivån i bergrummet bottenparti uppvisar härvid en trattformad utformning varvid utfällda partiklar från det lagrade mediet leds vidare ned till den permanenta bottennivån. För att underlätta avrinning och för att möjliggöra rengöring av bergrummets bottenparti är det tänkvärt att belägga vissa väggpartier med betong och anordna ett spolningssystem i bergrummets bottentunnlar. 15 20 25 30 35 508 833; number of work cycles and a concentration of the work to preferably only the roof space's roof resp. bottom part. With the features according to the invention, the advantage is achieved that unloading can be carried out simultaneously on two levels in the bottom of the rock chambers, which enables the significant rock volume obtained from the pallet mining to be unloaded very quickly from the occupied rock chamber. At the bottom of the rock chamber, a unique collection point is obtained which provides the space for collecting any particles that precipitate from the medium stored in the rock chamber. The vertical shafts between the upper and lower load level in the rock space bottom portion here have a funnel-shaped design, whereby precipitated particles from the stored medium are led further down to the permanent bottom level. In order to facilitate drainage and to enable cleaning of the bottom part of the rock space, it is conceivable to coat certain wall sections with concrete and arrange a flushing system in the bottom tunnels of the rock room.

Vid spolning transporteras lämpligen slam och avfall till en för ändamålet anordnad uppsamlingsplats .During rinsing, sludge and waste are suitably transported to a collection point arranged for the purpose.

Förfarandet enligt uppfinningen utnyttjar den modernaste tekniken inom underjordisk gruvbrytning, speciellt vad gäller borrning och sprängning och kombinerar detta med genomtänkta planlösningar. Beträffande takpartiet innebär detta en enkel tillredning, en rationell borrning och sprängning av den stora underliggande rumsvolymen.The method according to the invention utilizes the most modern technology in underground mining, especially with regard to drilling and blasting, and combines this with well-thought-out floor plans. Regarding the roof section, this means a simple preparation, a rational drilling and blasting of the large underlying room volume.

Det medger vidare en permanent bevakning av takstabiliteten och möjliggör en effektiv ventilation under både anläggriings- och driftskedet. I bottenpartiet innebär detta ett förgrenat arrangemang av orter i minst två nivåer som förenar en effektiv utlastning av berget under anläggningsskedet med ett skyddat tillträde och flexibla planlösningar för installation, inspektion och service under driftskedet.It also allows permanent monitoring of the roof stability and enables efficient ventilation during both the construction and operation phases. In the bottom part, this means a branched arrangement of sites in at least two levels that combine an efficient unloading of the rock during the construction phase with a protected access and plan visible floor plans for installation, inspection and service during the operational phase.

Bergrum med elliptisk eller oval tvärsektion erbjuder i jämförelse med bergrum med cirkulär tvärsektion en väsentligt större lagringsvolym vid samma rumsbredd, vilket är av stor betydelse vid lagring av bulkprodukter.Rock rooms with an elliptical or oval cross-section offer, in comparison with rock rooms with a circular cross-section, a significantly larger storage volume at the same room width, which is of great importance when storing bulk products.

Syftet med föreliggande uppfinning förverkligas medelst ett förfarande och ett bergrum som erhållit de i efterföljande patentkrav angivna kännetecknen. Föredragna delmoment resp. utformningar definieras i de osjälvständiga patentkraven.The object of the present invention is realized by means of a method and a rock chamber which have obtained the features stated in the appended claims. Preferred parts resp. designs are defined in the dependent claims.

På ritningarna visar: Figl ett vertikalt längsgående snitt i rumsmitt genom takparti och bottenparti hos bergrummet enligt föreliggande uppfinning; Fig 2 ett horisontellt snitt genom takpartiet hos bergrummet enligt uppfinningen; Fig 3 ett vertikalt tvärgående snitt i rumsmitt genom takpartiet och bottenpartiet hos bergrummet enligt uppfinningen; Pig 4 ett vertikalt längsgående snitt genom rumsmitt av ett takparti av bergrummet enligt uppfinningen då tillredningsarbetet är avslutat; Pig 5 ett horisontell snitt genom takpartiet enligt Fig 4, varvid vertikala tvärgående delsnitt av sagda takparti likaså visas i Pig 5; \\SKEA\SYS\USERS\LEG\dok\arkiv\P33461SEDOC 10 15 20 25 30 35 Fig 6 Fig 7 Fig 8 Fig 9 Fig 10 Fig 11 Fig 12 Fig 13 Fig 14 Fig 15 Fig 16 Pig 17 Fig 18 Fig 19 Fig 20 Fig 21 Fig 22 Fig 23 Fig 24 Fig 25 Fgw Fgfi 508 833 ett vertikalt snitt genom takpartiet visande borrning av takpelare; ett horisontellt snitt genom takpartiet enligt Fig 6; ett vertikalt längsgående snitt i rurnsmitt genom bergrummets bottenparti med två lastnivâer och temporär bergsrygg; ett horisontellt snitt genom båda lastnivàerna enligt Fig 8; ett vertikalt tvärgående snitt genom rumsmitt av bergrummet enligt Fig 8; ett vertikalt längsgående snitt i rumsmitt genom bergrummet med pallborrning av vertikala lânghål; ett vertikalt tvärgående snitt i rumsmitt genom bergrummet med pallborrning av vertikala lânghâl; ett vertikalt längsgående snitt i rumsmitt genom bergrummet med markerade sprängningssekvenser; ett horisontellt snitt genom bergrummet enligt Fig 13 med numrerade sprängningssekvenser; I ett vertikalt tvärgående snitt i rumsmitt genom bergrummet med markerade sprängningssekvenser; ett vertikalt längsgående snitt i rumsmitt genom bergrummet schematiskt visande borrning av den temporära bergsryggen; ett vertikalt tvärgående snitt i rumsmitt genom bergrummet schematiskt visande borrning av den temporära bergsryggen; ett vertikalt längsgående snitt i rumsmitt genom bergrummet vid avslutat bergarbete; ett horisontellt snitt genom bergrummets takparti vid avslutat bergarbete; ett horisontellt snitt genom bergrummets bottenparti vid avslutat bergarbete; ett vertikalt tvärgående snitt i rurnsmitt genom bergrummet vid avslutat bergarbete; ett vertikalt längsgående snitt i rumsmitt genom bergrummets takparti med bultförstärkning schematiskt visad; ett horisontellt snitt genom bergrummets takparti och schematiskt visande bultförstärkning i ett antal delsnitt genom takpartiet; ett vertikalt tvärgående snitt i rumsmitt genom takpartiet schematiskt visande bultförstärkiiing; ett vertikalt längsgående snitt i rumsmitt genom bergrummets takparti med ventilationshål mellan bergrummet och flerfunktionsorterna; ett horisontellt snitt genom bergrummets takparti och schematiskt visande ventilationshâlen i ett antal delsnitt genom takpartiet; ett vertikalt tvärgående snitt i rumsmitt genom takpartiet visande schematiskt ventilationshâlen; \\SKEA\SYS\USERS\LEG\dok\arkiv\P3346lSEDOC 10 15 20 25 30 35 ' 508 833 " % Pig 28- Pig 31 olika snitt genom bergrummet enligt uppfinningen då en hydraulisk bur är anordnad runt bergnnnmet.In the drawings: Fig. Shows a vertical longitudinal section in the center of the room through the roof portion and bottom portion of the rock space according to the present invention; Fig. 2 is a horizontal section through the roof portion of the rock chamber according to the invention; Fig. 3 is a vertical transverse section in the center of the room through the roof portion and the bottom portion of the rock space according to the invention; Fig. 4 is a vertical longitudinal section through the center of a room of a roof portion of the rock chamber according to the invention when the preparation work is completed; Fig. 5 is a horizontal section through the roof portion according to Fig. 4, wherein vertical transverse partial sections of said roof portion are also shown in Fig. 5; \\ SKEA \ SYS \ USERS \ LEG \ dok \ arkiv \ P33461SEDOC 10 15 20 25 30 35 Fig 6 Fig 7 Fig 8 Fig 9 Fig 10 Fig 11 Fig 12 Fig 13 Fig 14 Fig 15 Fig 16 Fig 16 Fig 18 Fig 19 Fig 19 Fig Fig. 21 Fig. 22 Fig. 23 Fig. 24 Fig. 25 Fgw Fg fi 508 833 a vertical section through the roof portion showing drilling of roof pillars; a horizontal section through the roof portion according to Fig. 6; a vertical longitudinal section in the center of the pipe through the bottom part of the rock chamber with two load levels and temporary ridge; a horizontal section through both load levels according to Fig. 8; a vertical transverse section through the center of the rock space according to Fig. 8; a vertical longitudinal section in the center of the room through the rock space with pallet drilling of vertical long holes; a vertical transverse section in the center of the room through the rock chamber with pallet drilling of vertical longitudinal holes; a vertical longitudinal section in the center of the room through the rock chamber with marked blasting sequences; a horizontal section through the rock space according to Fig. 13 with numbered blasting sequences; In a vertical transverse section in the center of the room through the rock chamber with marked blasting sequences; a vertical longitudinal section in the center of the room through the rock space schematically showing drilling of the temporary ridge; a vertical transverse section in the center of the room through the rock space schematically showing drilling of the temporary ridge; a vertical longitudinal section in the center of the room through the rock chamber at the end of rock work; a horizontal section through the roof portion of the rock chamber at the end of rock work; a horizontal section through the bottom part of the rock chamber at the end of rock work; a vertical transverse section in the center of the pipe through the rock chamber at the end of rock work; a vertical longitudinal section in the center of the room through the roof portion of the rock chamber with bolt reinforcement schematically shown; a horizontal section through the roof portion of the rock chamber and schematically showing bolt reinforcement in a number of partial sections through the roof portion; a vertical transverse section in the center of the room through the roof portion schematically showing bolt reinforcement; a vertical longitudinal section in the center of the room through the roof portion of the rock chamber with ventilation holes between the rock chamber and the fl functional locations; a horizontal section through the roof portion of the rock chamber and schematically showing the ventilation holes in a number of partial sections through the roof portion; a vertical transverse section in the center of the room through the roof portion schematically showing the ventilation holes; \\ SKEA \ SYS \ USERS \ LEG \ dok \ arkiv \ P3346lSEDOC 10 15 20 25 30 35 '508 833 "% Pig 28- Pig 31 different sections through the rock space according to the invention when a hydraulic cage is arranged around the rock body.

I Pig 1-3 enligt Uttagningsförfarandet börjar med tillredningsarbete av åtminstone en men i detta fall två flerfunktionsorter 1, takparti 2 och ett bottenparti 3 i nu nämnd ordning. Plerfunktions- orterna 1 utgör plattform för kabelbultning av takpartiet 2 och inhyser ventilationsutrustning visas en översikt av bergrummet uppfinningen. under byggnadsskedet. I driftskedet används de för inspektion av takpartiets 2 stabilitet och för evakuering/tillförsel av luft när bergrummet fylls/töms.In Pig 1-3 according to the Selection Procedure, work begins on the preparation of at least one but in this case two fl functional locations 1, roof portion 2 and a bottom portion 3 in the order now mentioned. The multi-function locations 1 constitute a platform for cable bolting of the roof portion 2 and house ventilation equipment. An overview of the rock chamber invention is shown. during the construction phase. In the operational phase, they are used for inspection of the stability of the roof section 2 and for evacuation / supply of air when the rock chamber is filled / emptied.

Takpartiet 2 är arbetsplats för pallbrytningen som volymmässigt är den största operationen. Därifrån sker den vertikala långhålsborrningen ned till bottenpartiet 3, laddningen av borrhålen och sprängningen av pallberget.The roof section 2 is the workplace for pallet breaking, which is the largest operation in terms of volume. From there, the vertical long-hole drilling takes place down to the bottom part 3, the loading of the boreholes and the blasting of the pallet rock.

Bottenpartiet 3 används för utlastningen av det lossprängda berget under byggnadsskedet och för inpumpning/utpumpning av de produkter som skall lagras i driftskedet, samt för uppsamling av sedementerade avlagringar från produkterna.The bottom part 3 is used for the unloading of the blasted rock during the construction phase and for pumping / pumping out the products to be stored in the operational phase, as well as for collecting sedimentary deposits from the products.

Tillträde till bergrummet från markytan åstadkoms genom en ramp eller genom ett vertikalt schakt. Valet mellan dessa bestäms i första hand av förläggningsdjupet för bergrummet. Nonnalt är en ramp det mest fördelaktiga altemativet ur tids- och kostnadssynpunkt vid relativt ytnära förläggningsdjup (ned till ca 300 m), medan schaktalternativet är att föredra vid förläggningsdjup därunder. Valet mellan dessa alternativ avgör transportsättet av bergmassorna upp till markytan. Som en följd av uttagnings- förfarandet enligt uppfmningen behövs tillträde till bergrummet endast på två platser; takpartiet 2 respektive bottenpartiet 3. De två områdena är de huvudsakliga arbetsplatserna.Access to the rock chamber from the ground surface is achieved through a ramp or through a vertical shaft. The choice between these is primarily determined by the depth of installation of the rock chamber. Nonetheless, a ramp is the most advantageous alternative from a time and cost point of view at relatively close installation depths (down to about 300 m), while the shaft alternative is preferable at installation depths below. The choice between these alternatives determines the mode of transport of the rock masses up to the ground surface. As a result of the selection procedure according to the invention, access to the rock chamber is needed only in two places; the roof section 2 and the bottom section 3, respectively. The two areas are the main workplaces.

Takpartiet 2 nås fran rampen/schaktet viagtvå horisontella orter 4, se Pig 1 och 2, vilka ansluter till bergrummets kortsidor i höjd med takpartiets 2 anfangsnivå.The roof section 2 is reached from the ramp / shaft via two horizontal locations 4, see Pig 1 and 2, which connect to the short sides of the rock chamber at the height of the roof level 2's initial level.

Takpartiet 2 är även förbundet med flerfunktionsorterna 1 ovanför takpartiet 2, varvid såsom ovan påpekats sagda flerfunktionsorter 1 bland annat används för takförstärkning, ventilation och stabilitetsövervakning.The roof section 2 is also connected to the multifunction locations 1 above the roof section 2, whereby, as pointed out above, the fl functional locations 1 are used, among other things, for roof reinforcement, ventilation and stability monitoring.

All utlastning sker från bergrummets bottenparti 3, i två nivåer Sa och 3b. Den övre nivån 3b existerar bara under byggnadsskedet. Den har därför en temporär utformning med en väsentligen kilformad bergsrygg 5, se Pig 1 och 3, centralt i bergrummets längdriktning. Bergsryggen 5 sträcker sig från bergrummets ena kortsida till den andra kortsidan. Bergsryggen 5 omgärdas av lastdiken 6, se Pig 3, som går längs bergrummets långsidor.All unloading takes place from the bottom part 3 of the rock chamber, in two levels Sa and 3b. The upper level 3b exists only during the construction phase. It therefore has a temporary design with a substantially wedge-shaped ridge 5, see Pig 1 and 3, centrally in the longitudinal direction of the rock chamber. The ridge 5 extends from one short side of the rock space to the other short side. The ridge 5 is surrounded by the cargo trench 6, see Pig 3, which runs along the long sides of the rock chamber.

Båda nivåerna 3a och 3b har lastorter 7a resp. 7b och kommunikationsorter 8a resp. 8b. Den undre nivåns 3a lastorter 7a är förskjuta i bergrummets längdriktning i förhållande till den övre nivåns 3b lastorter 7b. Kommunikationsorterna 8a och 8b löper \\SKEA\SYS\USERS\LEG\dok\arkiv\P3346lSEDOC 10 15 20 25 30 35 508 833 centralt i bergrummets längdriktning och avgrenar sig i lastorterna 7a resp. 7b, vilka mynnar i lastdikena 6 och bildar där lastgluggar.Both levels 3a and 3b have loading bays 7a resp. 7b and communication locations 8a resp. 8b. The loading sites 7a of the lower level 3a are displaced in the longitudinal direction of the rock space in relation to the loading sites 7b of the upper level 3b. The communication locations 8a and 8b run \\ SKEA \ SYS \ USERS \ LEG \ doc \ archive \ P3346lSEDOC 10 15 20 25 30 35 508 833 centrally in the longitudinal direction of the rock space and branch off into the loading locations 7a resp. 7b, which open into the loading ditches 6 and form loading hatches there.

Den temporära bergsryggen 5 har två funktioner. För det första styr den rasflödet ut mot rumsperiferin där lastgluggarna finns. För det andra ger den skydd för personal och maskiner under utlastning av sprängmassorna. När utlastningen är klar sprängs den temporära bergsryggen 5 bort i etapper. Detta kommer att beskrivas mer i detalj nedan.The temporary ridge 5 has two functions. First, it directs the fate towards the room periphery where the load windows are located. Secondly, it provides protection for personnel and machines during unloading of the explosives. When the unloading is complete, the temporary ridge 5 is blasted away in stages. This will be described in more detail below.

Med hänvisning till Fig 4-5 kommer takpartiets 2 tillredning nu att beskrivas.With reference to Figs 4-5, the preparation of the roof portion 2 will now be described.

Från respektive kortsida av bergrummet drivs två periferiorter 9 fram till bergrummets korta mittaxel där motsvarande periferiort från andra kortsidan möter. Periferiorternas 9 takforrn anpassas till anfangets välvning. Vidare drivs från respektive kortsida en takort 10 som följer takbågens välvning längs bergrummets långa mittaxel. Eftersom orterna samtidigt drivs från båda kortsidorna fås totalt sex (4+2) drivningsfronter.From each short side of the rock chamber, two peripheral species 9 are driven up to the short central axis of the rock chamber, where the corresponding periphery from the other short side meets. The roof formwork of the 9 peripherals is adapted to the arch of the start. Furthermore, a roof card 10 is driven from the respective short side, which follows the arch of the roof arch along the long central axis of the rock space. Since the locations are operated simultaneously from both short sides, a total of six (4 + 2) drive fronts are obtained.

När samtliga orter har mött sin motpart vid bergrummets korta mittaxel sprängs slitsar 11 vinkelrätt från den centrala takorten 10 till respektive periferiort 9. Slitsarna 11 följer den korta mittaxeln. Nu är takpartiet 2 frilagt utefter bergrummets väggperiferi och längs takbågens långa mittlinje och fyra avlånga takpelare 12 stöttar upp takpartiet 2, vilket ännu inte är någon färdig takkonstruktion. Dessa takpelare 12 skall sedan sprängas bort etappvis tills hela takpartiet 2, med hjälp av takförstärkning, är självbärande genom valvverkan.When all locations have met their counterpart at the rock chamber's short central axis, slots 11 burst perpendicularly from the central roof card 10 to the respective peripheral center 9. The slots 11 follow the short central axis. Now the roof portion 2 is exposed along the wall periphery of the rock chamber and along the long center line of the roof arch and four elongated roof pillars 12 support the roof portion 2, which is not yet a finished roof construction. These roof columns 12 must then be blasted away in stages until the entire roof section 2, by means of roof reinforcement, is self-supporting by the action of the arch.

Takpelarna 12 borras upp från slitsama 11 och från bergrummets kortsidor i en kontinuerlig arbetsoperation med väsentligen horisontella långa borrhål 13, se Fig 6 och 7.The roof columns 12 are drilled up from the slots 11 and from the short sides of the rock space in a continuous working operation with substantially horizontal long boreholes 13, see Figs. 6 and 7.

Takpelarna 12 strossas sedan i lämpliga salvor mot periferiorterna 9 respektive mot takorten 10 och lastas ut från dessa orter. När takpelarna 12 är borta kan den kvarstående berg- klacken 14 eventuellt sänkas och avjämnas för att underlätta pallborrningen som därefter kan starta.The roof pillars 12 are then sprinkled in suitable ointments against the peripheries 9 and against the roof boards 10, respectively, and unloaded from these locations. When the roof pillars 12 are gone, the remaining rock heel 14 can possibly be lowered and leveled to facilitate pallet drilling, which can then start.

Med speciell hänvisning till Fig 8-10 kommer tillredningen av bottenpartiet 3 nu att beskrivas. Sagda tillredning börjar på samma sätt som för takpartiet 2. Från berg- rummets båda kortsidor drivs på båda nivåerna 3a och 3b kommunikationsorter 8a resp. 8b längs bergrummets långa mittaxel till rumsmitt inuti den blivande temporära bergryggen 5.With special reference to Figs. 8-10, the preparation of the bottom portion 3 will now be described. Said preparation begins in the same way as for the roof section 2. From both short sides of the rock chamber, communication locations 8a and 3b, respectively, are operated at both levels. 8b along the long central axis of the rock space to the center of the room inside the future temporary ridge 5.

Från respektive kommunikationsort 8a och 8b drivs därefter åt båda sidorna lastorter 7a och 7b fram till rummets teoretiska vägglinje. På den övre lastnivån 3b förbinds lastortemas 7b frontgavlar så att man får ett kontinuerligt lastdike 6 längs bergrummets långa väggsidor på ömse sidor om den temporära bergryggen 5. Från lastdiket 6 sprängs slutligen vertikala öppningar 14 ned till den undre lastnivåns 3a lastorter 7a. Därmed är bottenpartiet 3 färdigt.From the respective communication locations 8a and 8b, loading locations 7a and 7b are then driven on both sides to the theoretical wall line of the room. At the upper load level 3b, the front gables of the loading bays 7b are connected so as to have a continuous loading ditch 6 along the long wall sides of the rock space on either side of the temporary ridge 5. From the loading ditch 6, vertical openings 14 are finally blasted down to the loading bays 7a of the lower loading level 3a. Thus, the bottom part 3 is finished.

Den övervägande delen av bergrummets volym pallborras med vertikala långa hål 15 från takpartiet 2 och ned till den övre lastnivån 3b hos bottenpartiet 3 till den temporära bergryggen 5 och till tunneltakets lastdiken 6, se Fig 11-12. Borrningsarbetet utförs i en sammanhängande operation. Den vare sig påverkar eller pâverkas av andra aktiviteter.The predominant part of the rock space volume is pallet drilled with vertical long holes 15 from the roof portion 2 and down to the upper load level 3b of the bottom portion 3 to the temporary ridge 5 and to the tunnel roof trench 6, see Fig. 11-12. The drilling work is performed in a continuous operation. It neither affects nor is affected by other activities.

\\SKEA\SYS\USERS\LEG\dok\arkiv\P3346lSEDOC 10 15 20 25 30 'ß 508 835 L 6 Eftersom hela bergrumsvolymen mellan takpartiet 2 och bottenpartiet 3 pallborras med långa hål är valet av borrutrustning av stor betydelse. Borrningstekniken har under senare år avsevärt förbättrats. För den aktuella pallborrningen användes företrädesvis vattendrivna ITH-maskiner (In-The-Hole). I jämförelse med luftdrivna ITH-maskiner uppnår man 2.5 till 3 gånger högre borrsjunkning och en mindre hålavvikelse. I jämförelse med vattendrivna topphammarmaskiner uppnås avsevärt lägre borrstångskostnader, högre borreffekt och en betydligt mindre reduktion av effekten med ökande hållängd.\\ SKEA \ SYS \ USERS \ LEG \ dok \ arkiv \ P3346lSEDOC 10 15 20 25 30 'ß 508 835 L 6 Since the entire rock chamber volume between the roof section 2 and the bottom section 3 is pallet drilled with long holes, the choice of drilling equipment is of great importance. Drilling technology has significantly improved in recent years. For the current pallet drilling, water-powered ITH (In-The-Hole) machines are preferably used. In comparison with air-powered ITH machines, a 2.5 to 3 times higher drilling subsidence and a smaller hole deviation are achieved. In comparison with water-powered top hammer machines, considerably lower drill rod costs are achieved, higher drilling power and a significantly smaller reduction of the power with increasing holding length.

Rumsgeometrin och borrningsplanen gör det möjligt att spränga stora salvor. Ny initieringsteknik gör det också möjligt att genomföra sprängningen på ett skonsamt sätt och med bra styckefall. I Fig 13-15 visas schematiskt sprängningssekvensen för pallen. Såsom speciellt framgår av Fig 14 börjar sprängningsarbetet med att två så kallade öppningsschakt 16 tas upp på ömse sidor om den ännu ej bildade temporära bergryggen 14. Öppnings- schakten 16 vidgas etappvis in mot rummets mitt tills de förenas i en genomgående slits.The room geometry and drilling plan make it possible to blow up large volleys. New initiation technology also makes it possible to carry out the blasting in a gentle way and with a good fall. Figs. 13-15 schematically show the blasting sequence of the pallet. As can be seen in particular from Fig. 14, the blasting work begins with two so-called opening shafts 16 being taken up on either side of the temporary ridge 14 not yet formed. The opening shafts 16 widen in stages towards the middle of the room until they are joined in a continuous slot.

Pallsprängningen fortsätter därefter över hela rumsbredden, med pallfronterna retirerande mot respektive bergrumsgavel. I Fig 14 visas ett exempel på sprängningsfrekvenser la, lb; 2a, 2b; 3a, 3b; 4a, 4b; 5a, 5b.The pallet blasting then continues across the entire width of the room, with the pallet fronts retreating towards the respective rock chamber end. Fig. 14 shows an example of burst frequencies 1a, 1b; 2a, 2b; 3a, 3b; 4a, 4b; 5a, 5b.

Salvstorleken kan anpassas efter rådande bergförhållanden. Elektroniska s k mikrosprängkapslar med programmerbara intervalltider möjliggör precisionssprängning av stora salvor. Dokumenterade fördelar är bättre tidsprecision, bättre fragmentering, mindre markvibrationer och jämnare bergkonturer.The ointment size can be adapted to prevailing rock conditions. Electronic so-called micro-detonators with programmable interval times enable precision detonation of large ointments. Documented advantages are better time precision, better fragmentation, less ground vibrations and smoother rock contours.

Utlastningen av det lossprängda berget sker i princip som i en skivrasgruva. Den sker i två nivåer med företrädesvis eldrivna LHD-maskiner (Load-Haul-Dump) enligt principen lasta-och-bär. Den kompakta rumsorienteringen eliminerar behovet av truckar.The unloading of the blasted rock takes place in principle as in a disc landslide mine. It takes place in two levels with preferably electric LHD machines (Load-Haul-Dump) according to the load-and-carry principle. The compact room orientation eliminates the need for trucks.

Under pallsprängningen, när hög kapacitet erfordras, används båda lastnivåerna 3a och 3b vilket ger mycket stora tidsbesparingar. Arrangemanget medger en mycket hög utlastníngs- kapacitet till följd av de många lastorterna 7a, 7b, se exempelvis Fig 13. Arbetssäkerheten är god eftersom all personal arbetar i skydd inuti den temporära bergryggen 5.During pallet blasting, when high capacity is required, both load levels 3a and 3b are used, which gives very large time savings. The arrangement allows a very high unloading capacity due to the many loading sites 7a, 7b, see for example Fig. 13. Work safety is good because all personnel work in protection inside the temporary ridge 5.

Efter det att pallsprängrtingen enligt Fig 13-15 är avslutad och det lossprängda berget utlastat sker borrning av den temporära bergryggen 5. Sagda borrning sker från den övre kommunikationsorten 8b, varvid borrhålskonfigurationen 17 för den temporära bergryggen 5 schematiskt visas i Pig 16-17. Utlastningen av den sprängda bergryggen 5 sker delvis med lasta- och- bär principen från nivån 3b och delvis genom att sprängmassorna styrs ned till lastorterna 7a för den undre lastnivån 3a, varifrån sprängmassorna lastas ut.After the pallet blasting according to Figs. 13-15 has been completed and the blasted rock unloaded, drilling of the temporary ridge 5 takes place. Said drilling takes place from the upper communication location 8b, the borehole configuration 17 for the temporary ridge 5 being schematically shown in Figs. 16-17. The unloading of the blasted ridge 5 takes place partly with the loading and carrying principle from level 3b and partly by the blasting masses being guided down to the loading sites 7a for the lower load level 3a, from where the blasting masses are unloaded.

Själva bergarbetet med bergrummet enligt föreliggande uppfinning är därmed avslutat och i Fig 18-21 visas olika sektioner av det vertikala elliptiska bergrummet vid avslutat bergarbete.The actual rock work with the rock space according to the present invention is thus completed and in Figs. 18-21 different sections of the vertical elliptical rock space are shown at the completion of rock work.

\\SKEA\SYS\USERS\LEG\dok\arkiv\P33461SE.DOC 10 15 20 25 30 'ß ; 508 855 Enligt utföringsexemplet finns ovanför bergrummets takparti 2 två flerfunktions- orter 1, vilka används för flera ändamål. Under byggnadsskedet används flerfunktions- orterna för att stabilisera takpartiet 2 med kabelbultar och som frånluftsuttag för ventilationen. Under driftskedet används den för övervakning av takstabiliteten och för evakuering/tillförsel av luft vid bergrummets fyllning/tömning.\\ SKEA \ SYS \ USERS \ LEG \ dok \ arkiv \ P33461SE.DOC 10 15 20 25 30 'ß; 508 855 According to the exemplary embodiment, above the roof portion 2 of the rock chamber there are two fl functional locations 1, which are used for fl your purposes. During the construction phase, the functional areas are used to stabilize the roof section 2 with cable bolts and as an exhaust air outlet for ventilation. During the operating phase, it is used for monitoring the roof stability and for evacuating / supplying air during the filling / emptying of the rock chamber.

I Fig 22-24 visas ett exempel på bultförstärkning av takpartiet 2 och anfanget.Figs. 22-24 show an example of bolt reinforcement of the roof portion 2 and the start.

Systematisk eller selektiv takförstärkning med exempelvis kabelbultar 18 utföres från flerfunktionsorterna 1. Speciellt vid stora spännvidder, dvs över 50 m, kan systematisk takförstärkning vara nödvändig. Genom att flerfunktionsorterna 1 är skilda från varandra utefter större delen av bergrummets längd kan kabelbultarna 18 fördelas över en större takyta än som annars vore möjligt. Kabelbultarna 18 anbringas innan takpartiet 2 friläggs.Systematic or selective roof reinforcement with, for example, cable bolts 18 is carried out from the functional locations 1. Especially at large spans, ie over 50 m, systematic roof reinforcement may be necessary. Because the functional locations 1 are separated from each other along most of the length of the rock chamber, the cable bolts 18 can be distributed over a larger roof surface than would otherwise be possible. The cable bolts 18 are fitted before the roof portion 2 is exposed.

Efter friläggningen är gjord kan eventuell injektering av bulthålen utföras. Det är viktigt att kabelförstärkningen görs innan friläggriing av takpartiet 2 påbörjas. Då uppnås bästa effekt på takstabiliseringen. i Ett ventilationsarrangemang för bergrummet enligt uppfinningen visas schematiskt i Fig 25-27. Språnggaser och andra luftföroreningar ventileras med sugande fläktar (ej visade) placerade i borrhål 19 mellan takpartiet 2 och flerfunktionsorterna 1. Från flerfunktionsorterna 1 går frånluften i ett slutet ledningssystem upp till markytan där rening sker. Alternativt kan en luftreningsanläggning placeras i anslutning till flerfunktionsorterna 1, varvid rening sker där.After the exposure is done, any injection of the bolt holes can be performed. It is important that the cable reinforcement is made before the exposure of the roof section 2 begins. This achieves the best effect on roof stabilization. A ventilation arrangement for the rock chamber according to the invention is shown schematically in Figs. 25-27. Flue gases and other air pollutants are ventilated with suction fl spouts (not shown) placed in boreholes 19 between the roof section 2 and fl operating locations 1. From fl operating locations 1, the exhaust air goes in a closed pipe system up to the ground surface where cleaning takes place. Alternatively, an air purification plant can be placed adjacent to the fl functional locations 1, whereby purification takes place there.

Ventilations-/borrhâlen 19 borras från flerfunktionsorterna 1 och vinklas åt sidorna så att ventilering kan ske både under takpartiets 2 tillredning och den efterföljande pallsprängningen. Borrhålens 19 diameter bestäms av fläktarnas utrymmesbehov och erforderlig luftomsättning.The ventilation / drill hole 19 is drilled from the fl functional locations 1 and angled to the sides so that ventilation can take place both during the preparation of the roof section 2 and the subsequent pallet blasting. The diameter of the boreholes 19 is determined by the space requirements of the kt hubs and the required air circulation.

Om bergrummet enligt uppfinningen skall användas i tillämpningar som kräver inklädnad måste takpartiet 2 och bergrummets väggsidor dräneras för att undvika att vattentrycket i bergsprickorna byggs upp. I Fig 28-31 visas ett arrangemang med en ridá 20 av borrhál från flerfunktionsorterna 1 ned till orter 21 på bergrummets anfangsnivå och vidare ner till motsvarande orter 22 i höjd med bottenpartiet 3. Borridån 20 omgärdar bergrummet ett tiotal meter utanför detsamma. Genom detta arrangemang erhålles en hydraulisk bur som nollställer grundvattentrycket i berget mellan bergrummet och borrhålsridån 20.If the rock chamber according to the invention is to be used in applications that require cladding, the roof portion 2 and the wall sides of the rock chamber must be drained to avoid that the water pressure in the rock cracks builds up. Fig. 28-31 shows an arrangement with a curtain 20 of boreholes from the functional locations 1 down to locations 21 at the initial level of the rock space and further down to corresponding locations 22 at the height of the bottom portion 3. The drill curtain 20 surrounds the rock space about ten meters outside the same. By this arrangement a hydraulic cage is obtained which resets the groundwater pressure in the rock between the rock space and the borehole curtain 20.

När bergrummet fylls respektive töms behöver den innestâende luften evakueras respektive återföras. Detta gäller oavsett om bergrummet är oinklätt eller klätt. Till det ändamålet kan man med fördel använda de redan befintliga borrade ventilationshålen 18.When the rock chamber is filled or emptied, the air that remains needs to be evacuated or returned. This applies regardless of whether the rock chamber is unclad or clad. For this purpose, the already existing drilled ventilation holes 18 can be used to advantage.

\\SKEA\SYS\USERS\LEG\dol<\arkiv\P3 3461 SEDOC\\ SKEA \ SYS \ USERS \ LEG \ dol <\ archive \ P3 3461 SEDOC

Claims (10)

10 15 20 25 30 35 508 833 « PATENTKRAV10 15 20 25 30 35 508 833 «PATENT REQUIREMENTS 1. Förfarande för uttagning av ett väsentligen vertikalt bergrum med elliptisk eller oval tvärsektion, varvid tillträde från markytan till bergrummet sker via en ramp eller genom ett väsentligen vertikalt schakt, och att bergrummet är avsett att lagra bullcprodukter, exempelvis gas och/eller fluidum, k ä n n e t e c k n a t av att åtminstone en så kallad flerfunktions-ort (1) drives, att ett takparti (2), vilket är beläget nedanför flerfunktionsorten (1), tillredes genom att periferiorter (9) drivs som definierar bergrummet dels i sidled dels i höjdled, att åtminstone en mellan periferiorterna belägen takort (10) drives som definierar takets välvníng mellan periferiortema (9), varvid genom sagda drivning bildade talcpelare (12) avlägsnas genom borrning/sprängning, att ett bottenparti (3) tillredes genom drivning av kommunikationsorter (8a, 8b), på åtminstone två nivåer (3a, 3b), längs bergrummets långa mittaxel, att från sagda kommunikationsorter (Sa, 8b) drives lastorter (7a, 7b), på åtminstone sagda två nivåer (3a, 3b), fram till bergrummets teoretiska vägglinje, att bergrumsvolymen mellan takpartiet (2) och bottenpartiet (3) pallborras, spränges och utlastas via åtminstone den undre nivån (3a) hos bottenpartiet (3). _A method for extracting a substantially vertical rock chamber with an elliptical or oval cross-section, wherein access from the ground surface to the rock chamber takes place via a ramp or through a substantially vertical shaft, and that the rock chamber is intended to store bull products, for example gas and / or fl uidum, k characterized in that at least one so-called fl function (1) is operated, that a roof portion (2), which is located below the orten function (1), is prepared by operating peripherals (9) defining the rock space partly laterally and laterally, that at least one roof card (10) located between the peripheries is defined which defines the curvature of the roof between the periphery centers (9), wherein said column pillars (12) formed by said drive are removed by drilling / blasting, 8b), on at least two levels (3a, 3b), along the long central axis of the rock space, that from said communication locations (Sa, 8b) load locations (7a, 7b) are operated, at at least instone said two levels (3a, 3b), up to the theoretical wall line of the rock chamber, that the rock chamber volume between the roof portion (2) and the bottom portion (3) is pallet drilled, blasted and unloaded via at least the lower level (3a) of the bottom portion (3). _ 2. Förfarande enligt krav 1, k ä n n e t e c k n a t av att borrningen av takpelarna (12) sker medelst väsentligen horisontella borrhål (13).Method according to claim 1, characterized in that the drilling of the roof columns (12) takes place by means of substantially horizontal boreholes (13). 3. Förfarande enligt krav 1 eller 2, k ä n n e t e c k n a t av att lastorternas (7b) yttre ändar, på den övre lastnivån (3b), förbindes så att ett kontinuerligt lastdike (6) erhålles längs bergrummets långa väggsidor, och att från lastdiket (6) sprängs vertikala öppningar (14) ned till den undre lastnivåns (3a) lastorter (7a).Method according to claim 1 or 2, characterized in that the outer ends of the loading places (7b), at the upper load level (3b), are connected so that a continuous loading ditch (6) is obtained along the long wall sides of the rock chamber, and that from the loading ditch (6 ) vertical openings (14) are blasted down to the loading sites (7a) of the lower load level (3a). 4. Förfarande enligt något av kraven 1-3, k å n n e t e c k n a t av att vid pall- borrning och sprängning av bergrumsvolymen mellan takpartiet (2) och bottenpartiet (3) kvarlämnas en temporär bergrygg (5) som har en utsträckning längs bergrummets långa axel.Method according to one of Claims 1 to 3, characterized in that during pallet drilling and blasting of the rock chamber volume between the roof portion (2) and the bottom portion (3), a temporary rock ridge (5) is left which extends along the long axis of the rock chamber. 5. Förfarande enligt något av kraven 1-4, k ä n n e t e c k n a t av att två fler- funktionsorter (1) drives ovanför takpartiet (2), vilka förenas med varandra i området vertikalt ovanför bergrummets kortsidor.Method according to one of Claims 1 to 4, characterized in that two functional locations (1) are operated above the roof portion (2), which are joined to one another in the area vertically above the short sides of the rock chamber. 6. Förfarande enligt krav 5, k ä n n e t e c k n a t av att förstärkning av takpartiet (2) sker från flerfunktionsorterna (1).Method according to claim 5, characterized in that reinforcement of the roof portion (2) takes place from the fl functional locations (1). 7. Förfarande enligt krav 6, k ä n n e t e c k n a t av att förstärkningen utföres i form av systematisk eller selektiv förstärkning medelst kabelbultar.Method according to claim 6, characterized in that the reinforcement is carried out in the form of systematic or selective reinforcement by means of cable bolts. 8. Förfarande enligt krav 5, k ä n n e t e c k n a t av att ventilationshål (19) borras från flerfunktionsorterna (1) till takpartiet (2).Method according to claim 5, characterized in that ventilation holes (19) are drilled from the fl functional locations (1) to the roof portion (2). 9. Bergrum med vertikal utsträckning och med elliptiskt eller ovalt tvärsnitt, varvid bergrummet innefattar ett takparti (2), ett bottenparti (3) samt ett mellanliggande lagringsutrymme för bulkprodukter, exempelvis gas och/eller fluidum, k ä n n e t e c k n a t av att åtminstone en flerfunktionsort (l) är anordnad ovanför takpartiet (2), och att botten- \\SKEA\SYS\USERS\LEG\dok\arkiv\P3346lSEDOC ? 508 833 9 partiet (3) innefattar 'en utefter bergrummets långa axel förlöpande kornmunikationsort (8a, 8b), från vilken lastorter (7a, 7b) utgår radiellt.Vertical rock chamber with an elliptical or oval cross-section, the rock chamber comprising a roof portion (2), a bottom portion (3) and an intermediate storage space for bulk products, for example gas and / or fluid, characterized in that at least one ort site of operation ( l) is arranged above the roof portion (2), and that the bottom \\ SKEA \ SYS \ USERS \ LEG \ doc \ archive \ P3346lSEDOC? The portion (3) comprises a grain communication location (8a, 8b) extending along the long axis of the rock space, from which loading locations (7a, 7b) emanate radially. 10. Bergrum enligt krav 9, k ä n n e t e c k n a t av att takförstärkning (18) och ventilationshål (19) är anordnad mellan flerfunktionsorten (1) och takkonstruktionen (2). \\SKEA\SYS\USERS\LEG\dok\arkiv\P3346ISEDOCRock chamber according to claim 9, characterized in that the roof reinforcement (18) and ventilation holes (19) are arranged between the functional location (1) and the roof structure (2). \\ SKEA \ SYS \ USERS \ LEG \ doc \ archive \ P3346ISEDOC
SE9704572A 1997-12-08 1997-12-08 Method for extracting a vertical rock compartment with an elliptical or oval cross section and a rock compartment made by the method SE508833C2 (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
SE9704572A SE508833C2 (en) 1997-12-08 1997-12-08 Method for extracting a vertical rock compartment with an elliptical or oval cross section and a rock compartment made by the method
PCT/SE1998/002232 WO1999030003A1 (en) 1997-12-08 1998-12-07 Method for excavating a vertical rock cavern having an elliptical or oval cross section and a rock cavern made by the method
AU18955/99A AU1895599A (en) 1997-12-08 1998-12-07 Method for excavating a vertical rock cavern having an elliptical or oval cross section and a rock cavern made by the method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SE9704572A SE508833C2 (en) 1997-12-08 1997-12-08 Method for extracting a vertical rock compartment with an elliptical or oval cross section and a rock compartment made by the method

Publications (3)

Publication Number Publication Date
SE9704572D0 SE9704572D0 (en) 1997-12-08
SE9704572L SE9704572L (en) 1998-11-09
SE508833C2 true SE508833C2 (en) 1998-11-09

Family

ID=20409307

Family Applications (1)

Application Number Title Priority Date Filing Date
SE9704572A SE508833C2 (en) 1997-12-08 1997-12-08 Method for extracting a vertical rock compartment with an elliptical or oval cross section and a rock compartment made by the method

Country Status (3)

Country Link
AU (1) AU1895599A (en)
SE (1) SE508833C2 (en)
WO (1) WO1999030003A1 (en)

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SE504669C2 (en) * 1994-03-27 1997-03-24 Karl Ivar Sagefors Procedure for the removal of rock cavities

Also Published As

Publication number Publication date
SE9704572D0 (en) 1997-12-08
WO1999030003A1 (en) 1999-06-17
SE9704572L (en) 1998-11-09
AU1895599A (en) 1999-06-28

Similar Documents

Publication Publication Date Title
CN103924977A (en) Center-pillared full-face shaft drilling machine
ES2902703T3 (en) underground mining
CN102587916A (en) Method for filling and mining after ore caving
CN113530558B (en) Double-drop shaft-inclined drift combined layered construction method for high-large chamber
CN208236413U (en) A kind of shaft construction device
US4708523A (en) Rock cavity
CN112746847B (en) Mining method for gently-inclined medium-thickness ore body
CN109000525A (en) A kind of shield driving upper-soft lower-hard ground presplit blasting construction method
SE452044B (en) VIEW BY EXPLOSION OF SIGNIFICANTLY EXTENSIVE MOUNTAINS
FI80756C (en) Procedure for the construction of storage spaces in rock for liquid products
CN203742602U (en) Central stand column full-section vertical shaft drilling machine
SE508833C2 (en) Method for extracting a vertical rock compartment with an elliptical or oval cross section and a rock compartment made by the method
SE434969B (en) PROCEDURE FOR BLASTING THE BERG SPACE
PL175804B1 (en) Method of driving chambers in rock mass
ES2389677T3 (en) Screw excavation equipment for the construction of screens
JP2007138702A (en) Excavation construction method for forward advance of working cylinder and retraction of all cross sections in tunnel
Zou et al. Introduction to underground excavation by drilling and blasting
RU2395691C2 (en) Method for strengthening of hydraulic stowage massif surfaces
RU2187646C2 (en) Method of opencast mining of beded mineral deposits
RU2490393C1 (en) Hydraulic accumulating power station with underground location of lower pool and combined method of lower pool tunnelling
RU2155867C2 (en) Method of downward working of kimberlite pipe by powered mining complex and design of flexible guard roofing
CN108443506A (en) Coalcutter rotating shaft sealing structure
RU2536514C1 (en) Chamber method of mining heavy, valuable, comminuted ore deposits
RU2316460C1 (en) Method for underground liquid domestic waste and rainwater storage
RU2272138C1 (en) Method for block bottom preparation

Legal Events

Date Code Title Description
NUG Patent has lapsed

Ref document number: 9704572-8

Format of ref document f/p: F