RU2718099C1 - Dismantling method of decommissioning gas or oil pipeline - Google Patents
Dismantling method of decommissioning gas or oil pipeline Download PDFInfo
- Publication number
- RU2718099C1 RU2718099C1 RU2019123559A RU2019123559A RU2718099C1 RU 2718099 C1 RU2718099 C1 RU 2718099C1 RU 2019123559 A RU2019123559 A RU 2019123559A RU 2019123559 A RU2019123559 A RU 2019123559A RU 2718099 C1 RU2718099 C1 RU 2718099C1
- Authority
- RU
- Russia
- Prior art keywords
- pipe
- gas
- pipeline
- oil
- plugs
- Prior art date
Links
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/024—Laying or reclaiming pipes on land, e.g. above the ground
- F16L1/028—Laying or reclaiming pipes on land, e.g. above the ground in the ground
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L55/00—Devices or appurtenances for use in, or in connection with, pipes or pipe systems
- F16L55/10—Means for stopping flow from or in pipes or hoses
- F16L55/1003—Means for stopping flow from or in pipes or hoses by introduction of paste, powder, particles, or the like
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Processing Of Solid Wastes (AREA)
Abstract
Description
Изобретение относится к трубопроводному транспорту, а именно, к технологиям проведения демонтажных работ выведенного из эксплуатации (изношенного) газо-, нефтепровода в местах прохождения технологических эстакад газо-, нефтепроводов.The invention relates to pipeline transport, and in particular, to technologies for the dismantling of decommissioned (worn out) gas and oil pipelines at the places of passage of technological flyovers of gas and oil pipelines.
Газо-, нефтепровод, подлежащий выводу из эксплуатации, должен быть подготовлен к демонтажу. Подготовка заключается в освобождении газо-, нефтепровода от нефти, очистке полости трубы от грязи и парафиносмолистых отложений. Газо-, нефтепроводы, выведенные из эксплуатации и переведенные в безопасное состояние, не требуют проведения подготовительных работ, так как они должны быть отключены от соседних участков, опорожнены и очищены от нефтяных углеводородов. Как правило, в процессе очистки нефтепровода, не удается полностью освободить трубопровод от остатков нефти и асфальтосмолистых отложений, что в процессе демонтажа труб приводит к истечению нефти, которая оказывает негативное воздействие на состояние компонентов природной среды. В таких случаях проводят рекультивацию грунта, загрязненного нефтепродуктами, в особенности в болотистой и заводненной местности, которая является трудоемким и дорогостоящим процессом. Ликвидация разливов нефти является актуальной проблемой. Поэтому одной из важнейших задач является предотвращение разливов нефти при демонтаже газо-, нефтепроводов.The gas and oil pipeline to be decommissioned must be prepared for dismantling. Preparation consists in freeing the gas and oil pipelines from oil, cleaning the pipe cavity from dirt and paraffin-tar deposits. Gas and oil pipelines decommissioned and put into a safe condition do not require preparatory work, as they must be disconnected from neighboring sections, emptied and cleaned of petroleum hydrocarbons. As a rule, in the process of cleaning an oil pipeline, it is not possible to completely free the pipeline from oil residues and asphalt-tar deposits, which during pipe dismantling leads to the outflow of oil, which has a negative impact on the state of the components of the natural environment. In such cases, soil contaminated with oil products is recultivated, especially in marshy and waterlogged areas, which is a laborious and expensive process. Oil spill response is an urgent problem. Therefore, one of the most important tasks is to prevent oil spills during the dismantling of gas and oil pipelines.
Известен демонтаж линейной части магистральных трубопроводов как комплекс технических мероприятий, направленных на извлечение трубопровода из грунта, резку на части и транспортировку труб к месту складирования (ОСТ153-39.4-027-2002). Способ демонтажа выведенного из эксплуатации газо-, нефтепровода включает снятие поверхностного горизонта почвы (дерна), вскрытие грунта до верхней образующей трубы, резку трубы и ее транспортировку. Проводят разметку демонтируемой трубы на участки длиной, определяемой разрешенной грузоподъемной массой газо-, нефтепровода для ее транспортировки. В размеченных местах просверливают технологические отверстия, через которые подают во внутреннюю полость нефтепровода пенокарбамид (пеноизол) для создания «пробок». Проводят резку трубопровода по центрам образованных пробок. При использовании изобретения обеспечивается надежная герметизация внутренней полости газо-, нефтепровода и абсорбция остаточных нефтяных углеводородов пеноизолом.Known dismantling the linear part of the main pipelines as a set of technical measures aimed at removing the pipeline from the soil, cutting into parts and transporting pipes to the storage location (OST153-39.4-027-2002). The method of dismantling a decommissioned gas and oil pipeline involves removing the surface horizon of the soil (turf), opening the soil to the upper generatrix of the pipe, cutting the pipe and transporting it. Mark the dismantled pipe into sections with a length determined by the permitted load-carrying mass of the gas and oil pipelines for its transportation. Technological holes are drilled in marked places through which penocarbamide (penoizol) is fed into the internal cavity of the oil pipeline to create “plugs”. The pipe is cut along the centers of the formed traffic jams. When using the invention provides reliable sealing of the internal cavity of the gas and oil pipelines and the absorption of residual petroleum hydrocarbons with penoizol.
Известен способ вскрытия траншеи и подъема подземного трубопровода при капитальном ремонте магистральных трубопроводов или при демонтаже выведенных из эксплуатации недействующих трубопроводов (патент RU2389930, МПК F16L1/028, опубл. 20.05.2010 г.). Способ вскрытия траншеи и подъема подземного трубопровода при демонтаже и капитальном ремонте включает рыхление и удаление растительного и минерального грунта засыпки, подъем трубопровода и укладку его на поверхность грунта по оси траншеи, причем рыхление и удаление растительного и минерального грунта засыпки производят синхронно перемещением многорядной троллейной подвески и подъемом трубопровода рыхлителями, присоединенными к тягачам.There is a method of opening a trench and lifting an underground pipeline during the overhaul of main pipelines or during the dismantling of decommissioned inactive pipelines (patent RU2389930, IPC F16L1 / 028, published on 05/20/2010). The method of opening the trench and lifting the underground pipeline during dismantling and overhaul includes loosening and removing vegetable and mineral soil backfill, raising the pipeline and laying it on the soil surface along the axis of the trench, moreover, loosening and removing vegetable and mineral soil backfill is carried out simultaneously by moving the multi-row trolley suspension and lifting the pipeline with rippers attached to the tractors.
Известен способ демонтажа выведенного из эксплуатации нефтепровода (патент RU2585158, МПК F16L1/028, опубл. 27.05.2016 г.), который включает вскрытие грунта до верхней образующей трубы, разметку демонтируемой трубы на участки длиной, определяемой разрешенной грузоподъемной массой газо-, нефтепровода для ее транспортировки. В ходе демонтажа просверливают технологические отверстия, через которые отводят избыточное давление в трубопроводе и подают во внутреннюю полость нефтепровода пенополиуретан для создания «пробок». Проводят резку трубопровода по центрам образованных пробок и транспортировку труб. Принято за прототип.A known method of dismantling a decommissioned oil pipeline (patent RU2585158, IPC F16L1 / 028, published on 05.27.2016), which includes opening the soil to the upper generatrix pipe, marking the dismantled pipe into sections with a length determined by the permissible lifting weight of the gas and oil pipelines its transportation. During dismantling, technological holes are drilled through which excess pressure is removed in the pipeline and polyurethane foam is fed into the internal cavity of the pipeline to create “plugs”. Pipes are cut along the centers of formed plugs and pipes are transported. Taken as a prototype.
Известные способы демонтажа выведенных из строя газо-, нефтепроводов с использованием устройств для герметизации внутренней полости трубопровода являются малоэффективными и трудозатратными. Кроме того, пенополиуретан по ГОСТ 30244 отнесен к группе Г4 - сильногорючий, по ГОСТ 30402 - В3 - легковоспламеняемый; по ГОСТ 12.1.044 - Д3 - с высокой дымообразующей способностью и Т4 - чрезвычайно токсичный при горении.Known methods for dismantling disabled gas, oil pipelines using devices for sealing the internal cavity of the pipeline are ineffective and labor-intensive. In addition, polyurethane foam in accordance with GOST 30244 is assigned to group G4 - highly combustible, in accordance with GOST 30402 - B3 - highly flammable; according to GOST 12.1.044 - D3 - with high smoke generating ability and T4 - extremely toxic when burning.
Технической проблемой, решаемой изобретением, является упрощение процесса демонтажа выведенного из эксплуатации (изношенного) газо-, нефтепровода с сохранением растительности поверхностного горизонта почвы путем предотвращения разлива нефтепродуктов, оставшихся в трубе, обеспечением пожаро- и взрывобезопасности.The technical problem solved by the invention is to simplify the process of dismantling a decommissioned (worn out) gas and oil pipeline while preserving the vegetation of the surface soil horizon by preventing the spill of oil products remaining in the pipe, ensuring fire and explosion safety.
Технический результат - предотвращение разлива нефтепродуктов, оставшихся в трубе газо-, нефтепровода, за счет надежной герметизации внутренней полости опорожненной трубы в заданных участках.The technical result is the prevention of the spill of oil products remaining in the pipe of the gas and oil pipelines due to reliable sealing of the inner cavity of the emptied pipe in predetermined areas.
Проблема решается, а технический результат достигается способом демонтажа выведенного из эксплуатации газо- или нефтепровода, включающим вскрытие грунта до верхней образующей трубы, резку трубы и ее транспортировку, при этом проводят разметку демонтируемой трубы на участки длиной, определяемой разрешенной грузоподъемной массой газо- или нефтепровода для ее транспортировки, в размеченных местах просверливают технологические отверстия, через которые отводят избыточное давление в трубопроводе, после чего подают во внутреннюю полость трубы компонент для создания герметизирующих «пробок» во всех размеченных местах и проводят резку трубы по центру образованных пробок. В отличие от прототипа в качестве компонента для создания герметизирующих «пробок» используют заливочный пеноизол с плотностью от 18 до 60 кг/м³ карбамидных пенопластов, при этом пеноизол подают во внутреннюю полость трубы во всех размеченных местах через трубку, расположенную вертикально в трубе на глубину 0,25-0,75 от ее диаметра.The problem is solved, and the technical result is achieved by the method of dismantling the decommissioned gas or oil pipeline, including opening the soil to the upper forming pipe, cutting the pipe and transporting it, while marking the dismantled pipe into sections with a length determined by the permitted lifting weight of the gas or oil pipeline for its transportation, technological holes are drilled in marked places, through which excess pressure is removed in the pipeline, after which it is fed into the internal cavity component tubes to create sealing "plugs" in all marked places and conduct pipe cutting in the center of the formed plugs. In contrast to the prototype, as a component for creating sealing "plugs", pouring penoizol with a density of 18 to 60 kg / m³ of urea foams is used, while the penoizol is fed into the internal cavity of the pipe in all marked places through a pipe located vertically in the pipe to a depth of 0 , 25-0.75 of its diameter.
Выбор компонента для создания герметизирующих «пробок» обусловлен следующим. Пеноизолы с плотностью до 18 кг/м³ применять нецелесообразно, так как пределы прочности при сжатии, при изгибе и растяжении становятся ниже 0.4, 0.2, 0.1 кг/см³ соответственно и возрастает паропроницаемость (В.П. Герасименя, К.З. Гумаргалиева, С.В. Захаров, И.Г. Калинина, Л. А. Соболев // Пластические массы, 2015, №1-2, с. 59). С плотностью выше 60 кг/м³ применение экономически становится нецелесообразным.The choice of component to create a sealing "plugs" due to the following. Penoizols with a density of up to 18 kg / m³ are impractical to use, since the compressive strength, bending and stretching become lower than 0.4, 0.2, 0.1 kg / cm³, respectively, and the vapor permeability increases (V.P. Gerasimenya, K.Z. Gumargalieva, С .V. Zakharov, I.G. Kalinina, L.A. Sobolev // Plastics, 2015, No. 1-2, p. 59). With a density above 60 kg / m³, the application becomes economically inexpedient.
Кроме того, экспериментально установлено, что подача пеноизола через трубку, находящуюся вертикально в трубопроводе на глубину 0,25-0,75 диаметра трубы, обеспечивает равномерное распределение пеноизола, так как отверждение его происходит снизу вверх и трубка обеспечивает подачу пеноизола в нижнюю точку трубы, что исключает образование сквозных пустот в пробке на всю её длину.In addition, it was experimentally established that the supply of penoizol through a tube located vertically in the pipeline to a depth of 0.25-0.75 of the pipe diameter ensures uniform distribution of penoizol, since it hardens from bottom to top and the tube provides penoizol to the bottom of the pipe, which eliminates the formation of through voids in the cork for its entire length.
Сущность поясняется рисунками, где показан заявляемый способ:The essence is illustrated by drawings, which show the inventive method:
Фиг 1 - показано схематично просверливание технологических отверстий;Fig 1 - schematically shows the drilling of technological holes;
Фиг.2 - показано прикручивание к приваренному патрубку шарового крана;Figure 2 - shows the screwing to the welded nozzle of the ball valve;
Фиг.3 - показана подача в полость трубы под давлением пеноизола из механической установки.Figure 3 - shows the flow into the cavity of the pipe under the pressure of penoizol from a mechanical installation.
На чертежах обозначено:In the drawings indicated:
1 - верхняя образующая труба газо- или нефтепровода,1 - upper forming pipe of a gas or oil pipeline,
2 - сверло,2 - drill
3 - технологическое отверстие,3 - technological hole,
4 - патрубок,4 - pipe
5 - шаровой кран,5 - ball valve,
6 - трубка для подачи пеноизола,6 - tube for supplying penoizol,
7 - рукав для подачи пеноизола,7 - sleeve for supplying penoizol,
8 - установка для подачи пеноизола,8 - installation for the supply of penoizol,
9 - пеноизольная пробка.9 - foam insulation plug.
Способ осуществляют следующим образом.The method is as follows.
Демонтируемую трубу 1 размечают на участки определенной длины, по которым будут проводить резку трубы. Масса одного участка трубы не должна превышать разрешенную грузоподъемную массу транспортировщика.The dismantled
Длину одного участка трубы вычисляют по формуле: The length of one pipe section is calculated by the formula:
L= (m-3):[ π·(d-s) ·s·ρ·10-6],L = (m-3): [π · (ds) · s · ρ · 10 -6 ],
где L – длина участка трубы (м),where L is the length of the pipe section (m),
m – грузоподъемность механизма (кг),m - load capacity of the mechanism (kg),
3 – масса пробки (кг),3 - cork mass (kg),
π=3,14 (постоянная величина),π = 3.14 (constant value),
d - наружный диаметр трубы (см),d is the outer diameter of the pipe (cm),
s – толщина стенки (см),s is the wall thickness (cm),
ρ - плотность материала труб, г/см3.ρ is the density of the pipe material, g / cm 3 .
После разметки участков трубы в размеченных местах высверливают на верхней образующей трубе 1 отверстие 3 диаметром 1.0-1.5 см для определения уровня остатка нефтепродуктов в трубопроводе металлическим щупом и для отвода избыточного давления (фиг.1). Рабочее давление в нефтепроводе в месте производства работ не должно превышать 2,5 МПа. В случае обнаружения избыточного давления в трубопроводе, создающего угрозу безопасности ведения сварочных работ, принимаются соответствующие меры по отводу избыточного давления. К отверстиям 3 приваривается патрубок 4 - металлический цилиндр диаметром от 100 до 150 мм с внутренней резьбой. К приваренному патрубку 4 прикручивается шаровой кран 5 (фиг.2). К шаровому крану прикручивается рукав 7, по которому осуществляется подача в полость трубы под давлением пеноизола из специальной механической установки 8 (фиг.3).After marking the pipe sections in the marked places, a
Герметизация внутренней полости трубопроводов пеноизолом должна осуществляться в соответствии со следующей технологией.Sealing the internal cavity of the pipelines with penoizol should be carried out in accordance with the following technology.
Во внутреннюю полость газонефтепровода под давлением подают пеноизол. Длина заливаемого участка внутренней полости трубопровода должна быть не менее одного метра. Для контроля заполнения газо-, нефтепровода пеноизолом используется ультразвуковой толщиномер MG2-XT (Panametrics, США). Количество пеноизола для образования одной герметизирующей пробки (1 метр) в полости трубопровода рассчитывается по формуле:Penoizol is fed into the internal cavity of the gas pipeline under pressure. The length of the filled section of the internal cavity of the pipeline should be at least one meter. To control the filling of the gas and oil pipelines with penoizol, the MG2-XT ultrasonic thickness gauge (Panametrics, USA) is used. The amount of penoizol for the formation of one sealing plug (1 meter) in the cavity of the pipeline is calculated by the formula:
M=1,4·3,14·ρ·r2,M = 1.4 · 3.14 · ρ · r 2 ,
где М - количество пеноизола, необходимого для изготовления одной пробки, кг;where M is the amount of penoizol required for the manufacture of one tube, kg;
- 1,4-коэффициент массопотери пеноизола, кг;- 1.4-coefficient of mass loss of penoizol, kg;
π=3,14 (постоянная величина),π = 3.14 (constant value),
d - диаметр трубы (м),d is the diameter of the pipe (m),
ρ - плотность пеноизола, кг/м 3.ρ is the density of penoizol, kg / m 3 .
Пример конкретного выполнения способа демонтажа выведенного из эксплуатации газонефтепровода.An example of a specific implementation of the method of dismantling a decommissioned gas pipeline.
Пример расчета необходимого количества пробок пеноизола и пеноизола для их изготовления для трубы диаметром 219 мм и длиной 2 км. 1. Рассчитывается количество исходного сырья-пеноизола для изготовления 1 пробки длиной 1 метр по формуле: M=1,4·3,14·ρ·r2 =1,4·40·0,03765 =2,1084≈2,1 кг.An example of calculating the required number of penoizol and penoizol plugs for their manufacture for a pipe with a diameter of 219 mm and a length of 2 km. 1. The amount of the initial penoizole feedstock is calculated for the manufacture of 1
2. Вес 1 метра этой трубы по таблице сортамента составляет 41,63 кг, а грузоподъемность механизма составляет 10 т, поэтому длина участка трубы, которую может поднять транспортировщик составляет 10000:(41,63+2,1)=228,7 м. Количество таких участков по длине трубопровода будет равно2. The weight of 1 meter of this pipe according to the assortment table is 41.63 kg, and the carrying capacity of the mechanism is 10 tons, so the length of the pipe section that the transporter can lift is 10000: (41.63 + 2.1) = 228.7 m. The number of such sections along the length of the pipeline will be equal
2000:228,7=8,75 шт. ≈9 шт.2000: 228.7 = 8.75 pcs. ≈ 9 pcs
3. Для 9 участков необходимо 10 пробок пеноизола, для изготовления которых необходимо10·2,1084=21,084 кг сырья.3. For 9 sites, 10 plugs of penoizole are needed, for the manufacture of which 10 · 10.1084 = 21.084 kg of raw materials are needed.
Образуют герметизирующие пробки во всех размеченных местах газонефтепровода. После образования герметизирующих пробок производят резку трубы. Резку трубы проводят по центру образованной пробки (т.е половина ее длины). После проведения резки края газонефтепровода полностью загерметизированы, трубы транспортируются к месту складирования.Form sealing caps in all marked areas of the gas pipeline. After the formation of sealing plugs, the pipe is cut. Pipe cutting is carried out in the center of the formed cork (i.e. half its length). After cutting, the edges of the gas pipeline are completely sealed, the pipes are transported to the storage location.
Подготовка трубопровода к демонтажу заключается в обеспечении условий, исключающих разлив нефтепродуктов и парафиносмолистых отложений из полости трубопровода, и увеличение жесткости трубы для исключения образования изломов.The preparation of the pipeline for dismantling is to ensure conditions that exclude the spill of oil products and paraffin-tar deposits from the cavity of the pipeline, and increase the rigidity of the pipe to prevent fractures.
Способ демонтажа выведенного из эксплуатации газо-, нефтепровода включает в себя следующие технологические операции:The method of dismantling a decommissioned gas and oil pipeline includes the following technological operations:
- уточнение положения нефтепровода и подземных коммуникаций, пересекающих нефтепровод, установка вешек;- clarification of the position of the pipeline and underground utilities crossing the pipeline, installation of milestones;
- снятие поверхностного горизонта почвы (дерна) на глубину не менее 60 мм;- removal of the surface soil horizon (turf) to a depth of not less than 60 mm;
- снятие плодородного слоя почвы и перемещение его во временный отвал;- removing the fertile soil layer and moving it to a temporary dump;
- разработку траншеи до верхней и нижней образующей нефтепровода;- development of trenches to the upper and lower generatrix of the pipeline;
- разметку трубопровода на участки заданной длины, по которым будут проводить резку трубы;- marking the pipeline into sections of a given length along which the pipe will be cut;
- просверловка технологических отверстий в нефтепроводе, для проведения газоанализа воздушной среды и подачи во внутреннюю полость трубы пеноизола, замер концентрации ГВС в полости трубопровода;- drilling of technological holes in the oil pipeline, for gas analysis of the air and supplying the foam pipe to the internal cavity, measuring the concentration of hot water in the pipeline cavity;
- подсоединение специализированной механической установки для подачи пеноизола для образования пробки и подача пеноизола во внутреннюю полость нефтепровода под давлением в соответствии со схемой;- connecting a specialized mechanical installation for supplying penoizol to form a plug and feeding penoizol into the internal cavity of the oil pipeline under pressure in accordance with the scheme;
- резка трубопровода по центрам образованных пробок; - cutting the pipeline in the centers of the formed traffic jams;
- извлечение труб из траншеи и транспортировка их к месту складирования;- removing pipes from the trench and transporting them to the storage location;
- засыпка траншеи;- backfilling of the trench;
- укладка снятого поверхностного горизонта почвы (дерна);- laying of the removed surface soil horizon (turf);
- рекультивация.- reclamation.
Перед тем как производить резку трубопровода на части перед транспортировкой, необходимо провести следующие действия, которые направлены на герметизацию тех участков трубопровода, где будет производиться ее резка, с целью предотвращения разлива остатков нефтепродукта при транспортировке труб после их резки:Before cutting the pipeline into parts before transportation, it is necessary to carry out the following actions, which are aimed at sealing those sections of the pipeline where it will be cut, in order to prevent spillage of oil residues during transportation of pipes after they are cut:
1. Демонтируемую трубу размечают на участки заданной длины, по которым будут проводить резку трубы. Количество участков и его длина, на которые будет делиться трубопровод, рассчитывается, принимая во внимание условие, что масса одного участка не должна превышать разрешенную грузоподъемную массу для ее транспортировки спецтехникой до подготовленной площадки.1. The dismantled pipe is marked into sections of a given length along which the pipe will be cut. The number of sections and its length into which the pipeline will be divided is calculated taking into account the condition that the mass of one section should not exceed the permissible load-lifting mass for its transportation by special equipment to the prepared site.
2. Герметизация внутренней полости трубопроводов пеноизолом должна осуществляться в соответствии со следующим. Длина запененного участка внутренней полости газо-, нефтепровода должна быть не менее 0,8÷1,2 метра в зависимости от диаметра трубопровода. Для контроля заполнения газо-, нефтепровода пеноизолом используется ультразвуковой толщиномер MG2-XT (Panametrics, США). Образуют герметизирующие пробки из пеноизола во всех размеченных местах газо-, нефтепровода в соответствии со схемой. После образования герметизирующих пробок производят резку трубы по центрам образованных пробок. После проведения резки края газо-, нефтепровода полностью загерметизированы, остатки нефтепродукта в полости трубы транспортируются к месту складирования.2. Sealing of the internal cavity of pipelines with penoizol should be carried out in accordance with the following. The length of the foamed section of the internal cavity of the gas and oil pipeline should be at least 0.8 ÷ 1.2 meters, depending on the diameter of the pipeline. To control the filling of the gas and oil pipelines with penoizol, the MG2-XT ultrasonic thickness gauge (Panametrics, USA) is used. Form sealing caps of penoizol in all marked places of the gas and oil pipelines in accordance with the scheme. After the formation of sealing plugs, the pipe is cut along the centers of the formed plugs. After cutting, the edges of the gas and oil pipelines are completely sealed, the residual oil in the pipe cavity is transported to the storage location.
Для предотвращения разлива нефтепродукта из выведенного из эксплуатации газо-, нефтепровода для трубы длиной 3 км требуется всего 44,7 кг пеноизола, что на 17,9 кг меньше, чем при применении пенополиуретана. Демонтаж выведенного из эксплуатации газо-, нефтепровода заявленным способом позволяет предотвратить разлив остатков нефтепродукта при транспортировке труб, после их резки, что снижает риск загрязнения окружающей среды. К тому же необходимо отметить, что пеноизол будет абсорбировать нефть с высокой эффективностью, так как нефтепоглощающая способность его составляет 40-60 г нефти/г пеноизола (Веприкова Е.В., Терещенко Е.А., Чеснокова Н.В., Щипко М.Л., Кузнецова Б.Н. J. SiberianFed. Univer. Chemistry. 2010. 3 (3). 285-304., Степанова Е.В., Чаплина Т.О. Мониторинг. Наука и технологии. 2017. № 1(30). 62-68. Таким образом, демонтаж выведенного из эксплуатации газо-, нефтепровода заявленным способом является более простым и эффективным в сравнении с существующими способами. Исключается необходимость проведения рекультивации земель, загрязненных нефтепродуктами, т.е. обеспечивается сохранение экологически чистых земель, снижение антропогенного загрязнения окружающей среды от разливов нефти и нефтепродуктов.To prevent oil spills from decommissioned gas and oil pipelines, a pipe length of 3 km requires only 44.7 kg of penoizol, which is 17.9 kg less than when using polyurethane foam. The dismantling of the decommissioned gas and oil pipelines by the claimed method allows to prevent spillage of oil product residues during transportation of pipes after their cutting, which reduces the risk of environmental pollution. In addition, it should be noted that penoizol will absorb oil with high efficiency, since its oil absorption capacity is 40-60 g of oil / g of penoizol (Veprikova E.V., Tereshchenko EA, Chesnokova N.V., Schipko M .L., Kuznetsova B.N. J. Siberian Fed. Univer. Chemistry. 2010.3 (3). 285-304., Stepanova E.V., Chaplina T.O. Monitoring. Science and Technology. 2017. No. 1 (30). 62-68. Thus, the dismantling of decommissioned gas and oil pipelines by the claimed method is simpler and more effective in comparison with existing methods. conduct land reclamation, contaminated by petroleum products, provided that the preservation of environmentally friendly land, reduction of anthropogenic pollution from oil spills.
Из 4-х параметров горючести пеноизола (карбамидный пенопласт) 2 соответствуют показателям для группы горючести Г1 (ГОСТ 30244-94). К ним относятся: параметр «продолжительность самостоятельного горения» - он составил ноль секунд и параметр «степень повреждения по длине» - от 42 до 57% при нормативе для группы горючести Г1 не более 65%. Параметр «степень повреждения по массе» находится при всех испытаниях от 22% до 36% при нормативе для группы горючести Г2 не более 50%. Карбамидный пенопласт изготавливается из смол, относящихся к группе термореактивных, в которых обратная реакция не происходит и материал не может снова перейти в жидкую форму, т.е. во время пожара он не дает расплава, а только теряет в массе, выделяя при этом воду, углекислый газ и азот, не опасные для человека. Материал стоек к действию микроорганизмов и грызунов.Of the 4 parameters of the combustibility of penoizol (urea foam), 2 correspond to the indicators for the combustibility group G1 (GOST 30244-94). These include: the parameter "duration of independent burning" - it amounted to zero seconds and the parameter "degree of damage along the length" - from 42 to 57% when the standard for the combustibility group G1 is not more than 65%. The parameter "degree of damage by weight" is found in all tests from 22% to 36% with a standard for the flammability group G2 not more than 50%. Urea foam is made from resins belonging to the group of thermosets in which the reverse reaction does not occur and the material cannot again go into liquid form, i.e. during a fire, it does not melt, but only loses mass, releasing water, carbon dioxide and nitrogen, which are not dangerous to humans. The material is resistant to the action of microorganisms and rodents.
Таким образом, изобретение обеспечивает предотвращение разлива нефтепродуктов, оставшихся в трубе газо-, нефтепровода, за счет надежной герметизации внутренней полости опорожненной трубы в заданных участках.Thus, the invention provides the prevention of spillage of oil products remaining in the pipe of the gas and oil pipelines due to reliable sealing of the inner cavity of the emptied pipe in predetermined areas.
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
RU2019123559A RU2718099C1 (en) | 2019-07-26 | 2019-07-26 | Dismantling method of decommissioning gas or oil pipeline |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
RU2019123559A RU2718099C1 (en) | 2019-07-26 | 2019-07-26 | Dismantling method of decommissioning gas or oil pipeline |
Publications (1)
Publication Number | Publication Date |
---|---|
RU2718099C1 true RU2718099C1 (en) | 2020-03-30 |
Family
ID=70156485
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
RU2019123559A RU2718099C1 (en) | 2019-07-26 | 2019-07-26 | Dismantling method of decommissioning gas or oil pipeline |
Country Status (1)
Country | Link |
---|---|
RU (1) | RU2718099C1 (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3310615A (en) * | 1964-04-30 | 1967-03-21 | Richard B Bender | Method for plugging pipe |
DE102007016749A1 (en) * | 2007-04-07 | 2008-10-09 | Stadtwerke Karlsruhe Gmbh | Gas mains connection lines separating method for external pressure gauge, involves forming foaming plug by foam applied in connection lines through hole, and hole by plug, separating connection lines, and welding end cap to ends of lines |
US20130220436A1 (en) * | 2012-02-29 | 2013-08-29 | Chevron U.S.A. Inc. | Apparatus, system and methods for sealing and severing a subsea pipeline |
RU2585158C1 (en) * | 2015-04-16 | 2016-05-27 | Общество с ограниченной ответственностью "Трейд Металл" | Method of dismantling decommissioned oil pipeline |
RU2017146316A (en) * | 2017-12-27 | 2019-06-27 | Общество с ограниченной ответственностью "Трейд Металл" | The method of dismantling the pipeline for decommissioning or in order to repair it |
-
2019
- 2019-07-26 RU RU2019123559A patent/RU2718099C1/en active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3310615A (en) * | 1964-04-30 | 1967-03-21 | Richard B Bender | Method for plugging pipe |
DE102007016749A1 (en) * | 2007-04-07 | 2008-10-09 | Stadtwerke Karlsruhe Gmbh | Gas mains connection lines separating method for external pressure gauge, involves forming foaming plug by foam applied in connection lines through hole, and hole by plug, separating connection lines, and welding end cap to ends of lines |
US20130220436A1 (en) * | 2012-02-29 | 2013-08-29 | Chevron U.S.A. Inc. | Apparatus, system and methods for sealing and severing a subsea pipeline |
RU2585158C1 (en) * | 2015-04-16 | 2016-05-27 | Общество с ограниченной ответственностью "Трейд Металл" | Method of dismantling decommissioned oil pipeline |
RU2017146316A (en) * | 2017-12-27 | 2019-06-27 | Общество с ограниченной ответственностью "Трейд Металл" | The method of dismantling the pipeline for decommissioning or in order to repair it |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5120160A (en) | Method and apparatus for confining and reclaiming hydrocarbon contaminated land sites | |
US5733067A (en) | Method and system for bioremediation of contaminated soil using inoculated support spheres | |
CN101608551B (en) | Closed origin and arrival construction method of shield machine | |
US5416257A (en) | Open frozen barrier flow control and remediation of hazardous soil | |
US6254524B1 (en) | Method for in situ remediation of waste through multi-point injection | |
CN105862932A (en) | Structure for protecting municipal pipeline | |
CN104027911B (en) | A kind of fire extinguishing method for coal gangue hill | |
US8336637B2 (en) | Fire extinguishing system for hydrocarbon storage tanks | |
CN113107527B (en) | Multi-level supporting process and monitoring method for roadway with large rock burst | |
RU2718099C1 (en) | Dismantling method of decommissioning gas or oil pipeline | |
CN103643669A (en) | Equipment and method for reconnoitering and field sampling in soft soil region | |
RU2585158C1 (en) | Method of dismantling decommissioned oil pipeline | |
Kurbangaleeva | Improvement of Emergency Oil Spill Management Technology | |
US20210222835A1 (en) | System and method for secondary containment of products conveyed by pipeline transport | |
CN108824509A (en) | A kind of tank foundation correcting and then reinforcing structure and its construction technology | |
US4120168A (en) | Apparatus for laying a pipeline in a body of water | |
RU2701652C1 (en) | Method of dismantling a pipeline for decommissioning or for repair purposes | |
Tolmač et al. | Oil products and pumping stations | |
RU2728614C1 (en) | Fire-fighting string installation | |
RU178916U1 (en) | DRILLING RIG SUPPORT USED FOR STRENGTHENING EARTH STRUCTURE | |
CN105178323A (en) | Grouting disposal method for long-distance large-caliber retired pipeline | |
Cripps et al. | Disposal of oil-based cuttings | |
RU62424U1 (en) | BALANCE BAR (OPTIONS) | |
Onov | Application of a New Method of Collecting Oil and Petroleum Products to Improve the Quality of Spill Response | |
Liu | Study on the Oil Pipeline Design of R Oil Field |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
RH4A | Copy of patent granted that was duplicated for the russian federation |
Effective date: 20200901 |