Summary of the invention
Object of the present invention is just to provide a kind of slip casting method of disposal growing distance, the retired pipeline of heavy caliber; in view of the foregoing defects the prior art has; grouting material is injected in retired pipeline; a kind of joint disposal method of safety, environmental protection, low cost is provided; avoid the generation of bad accident, protection of the environment, ensure the safety of retired pipeline.
Technical solution of the present invention is: a kind of slip casting method of disposal growing distance, the retired pipeline of heavy caliber, that retired pipeline is divided into pipeline to be cut and grouting pipe, pipeline to be cut and grouting pipe interval are arranged, ground is shifted out in pipeline excision to be cut, grouting material is injected by after grouting pipe shutoff, reside in underground, its construction sequence is as following:
A, determine setting, build pioneer road;
B, excavation operating pit;
The process of retired pipeline before C, slip casting;
D, slip casting preparation and slip casting;
Detect after E, slip casting;
F, local re-injection process.
Compared with prior art remarkable result of the present invention is: retired duct segments is cut by the present invention, segmenting slip casting, the internal memory sewage of retired pipeline and oil gas is made all to replace out, pipeline excision to be cut between two sections of grouting pipes is weighed up ground, and resides in underground by after the retired pipeline slip casting of long distance.Can construction cost be reduced on the one hand, also ensure that the safety of the retired pipeline residing in underground simultaneously, avoid the generation of bad accident.The present invention is reasonable in design, construction is simple, input is less, can ensure retired pipe safety ground, reside in underground muchly, protect environment, have significant social benefit.
Detailed description of the invention
Below in conjunction with accompanying drawing in detail the present invention is described in detail, not limits the scope of the invention, the improvement that all uses mentality of designing of the present invention draws all belongs to protection category of the present invention.See Fig. 1 and Fig. 2, a kind of slip casting method of disposal growing distance, the retired pipeline of heavy caliber, that retired pipeline is divided into pipeline to be cut and grouting pipe, pipeline to be cut and grouting pipe interval are arranged, ground is shifted out in pipeline excision to be cut, inject grouting material by after grouting pipe shutoff, reside in underground, its construction sequence is as following:
A, determine setting, build pioneer road;
B, excavation operating pit;
The process of retired pipeline before C, slip casting;
D, slip casting prepare;
E, slip casting;
Detect after F, slip casting;
G, local re-injection process.
Determine setting, build pioneer road and comprise surveying setting-out and pipeline purging of removing obstacles, surveying setting-out is according to retired piping plan, profile, coordinate, locate with GPS, after determining retired pipeline location, spread albarium and rule, release conduit axis and operation band sideline; Pipeline purging of removing obstacles is farmland to construction area in operation band sideline, trees, orchard, ground and underground obstacle etc., confirms to remove area and quantity, and registers.Unit in charge of construction should actively contact and coordinate with local relevant department, jointly carries out reconnaissance trip.Pioneer road should be smooth, has enough bearing strengths, can ensure the driving safety of construction machinery equipment.
Excavation operating pit is depth displacement according to retired pipeline, selects that retired pipeline low spot is slip casting point, high point a little digs pit operation for discharging water, and slip casting point and the pipeline distance between discharging water a little are set in
800between m-1700m, inject the mobility of grouting material and the power of grouting equipment and slip casting point and distance between discharging water a little is directly proportional.According to injecting the performance determination slip casting point of grouting material and grouting equipment and discharging water a little, first extremely stop apart from during retired pipeline end face 0.4-0.6m with mechanical equivalent of light excavation, found out the particular location of retired pipeline again by hand excavation, the anticorrosive coating peeling of retired pipeline is exposed retired pipeline body.
Before slip casting, the process of retired pipeline comprises boring, installs shutoff air bag, pipeline to be cut draws water, Pipe Cutting, grouting pipe sealing head, above-mentioned operation is carried out successively.
Boring is included in slip casting point and bores injected hole and bore a dewatering orifice discharging water
,retired pipeline, after anticorrosive coating peeling exposes body, and can discharge water and a little get out two injected holes and two dewatering orifices respectively at the slip casting point of retired pipeline, and the distance between two injected holes and two dewatering orifices is set between 6m-8m; Reserve the body of 0.8m-1.2m in the inner side of two injected holes and two dewatering orifices, all the other bodys between two injected holes and two dewatering orifices are pipeline to be cut, and the pipeline between two adjacent injected holes and dewatering orifice is grouting pipe; During boring, weld slip casting pipe nipple 3 and connect slip casting gate 2 and drilling machine successively at injected hole place, discharging water in the welding of dewatering orifice place, also connection outlet gate 5 and drilling machine are the boring of retired pipeline to tee piece 6 successively; After boring, on dewatering orifice and injected hole, indwelling discharges water tee piece 6 and outlet gate 5 and slip casting pipe nipple 3 and slip casting gate 2 respectively, to discharge water and slip casting uses for follow-up.Special messenger will be had after retired pipeline tapping to carry out the detection of combustible medium at any time.
It is place shutoff air bag 9 in pipeline outside two injected holes and two dewatering orifices and inflate for shutoff air bag 9 that pipeline to be cut draws water; Then self priming pump 10 is put into respectively from dewatering orifice and injected hole, use self priming pump 10 to pump by the to be cut ducted sewage of shutoff air bag 9 shutoff.
Pipe Cutting is taken out from dewatering orifice and injected hole by self priming pump 10, uses pipe cutting machine excise and shift out ground to the pipeline to be cut after drawing water.
Grouting pipe sealing head puts into from the injected hole of grouting pipe the polyurethane that positioner is housed to push away water polo 4, in the injected hole of grouting pipe and the outside body of dewatering orifice, build butter wall 8 by laying bricks or stones, and body outside butter wall 8 welds end socket 7.
Slip casting prepares to comprise setting and pushes away water polo acceptance point, and select the transport of agitator position and grouting material, taken out by the shutoff air bag 9 in grouting pipe, in front, dewatering orifice, the setting of 50m place pushes away water polo signal receiver 11; Grouting material is injected from injected hole by grouting pump 1, make grouting material promotion polyurethane push away water polo 4 to move to dewatering orifice, sewage remaining in grouting pipe is passed from injected hole to dewatering orifice and on the tee piece 6 that discharges water of dewatering orifice indwelling connecting hose, sewage is put unified process after storing to storage tank.Grouting material agitator is preferably selected near grouting pipe centre position, adopts modified MH-09R automatic batching system wholly computer controlled batching, can the match ratio of accurate controlled grouting material, the stability of guarantee slurry.The grouting material transport vehicle loading time is 5-6min, and discharge time is 5-6min, and carrying capacity is 8m3/ train number, calculate the haulage vehicle needing to drop into, situ configuration steel grouting material deposit pond, ensures the ample supply of grouting material during slip casting, improves the work efficiency of mortar depositing construction.Along with the continuous injection of grouting material, residue sewage is all pushed into dewatering orifice place and is released from dewatering orifice.Because injected hole is lower than dewatering orifice, be conducive to the raising that grouting material fills degree of filling, push away the promotion of water polo 4 at polyurethane under, sewage can be discharged completely, up hill and dale from pipeline; If the water polo signal receiver 11 that pushes away of front, dewatering orifice 50m receives polyurethane and pushes away water polo 4, downshift process to be done to grouting pump 1,1 grade is reduced to step by step from top grade, once there are slurries in the gutter of grouting pump 1, first grouting pump 1 is closed, then the gutter be connected with the tee piece 6 that discharges water is closed, again to grouting pipe pressure release after the initial set of 24 hours post-grouting material.
Detecting after slip casting is carry out after slip casting completes 48h, can start the detection of slip casting result, detect one by one to grouting pipe in the complete final set of grouting material after starting to produce intensity; The test point place that grouting pipe is selected gets out detect aperture, and service precision is the height of the retired tube cavity of vernier caliper measurement of 0.02mm, calculates the packing density of grouting material; If solid filler >=95%, packing density reaches requirement; If solid filler < 95%, local re-injection process need be carried out.
During the re-injection process of local, the end socket of grouting pipe two ends welding need be removed, in detect aperture, place refills grouting material, grouting material is poured into pipe ends by detect aperture, from pipe ends draining, till cannot injecting grouting material, through process of the present invention, retired pipeline can reside in underground safely, muchly.