RU2644659C2 - Method of construction and protection of the pipeline from rockfall on slopes in mountainous areas - Google Patents

Method of construction and protection of the pipeline from rockfall on slopes in mountainous areas Download PDF

Info

Publication number
RU2644659C2
RU2644659C2 RU2015148732A RU2015148732A RU2644659C2 RU 2644659 C2 RU2644659 C2 RU 2644659C2 RU 2015148732 A RU2015148732 A RU 2015148732A RU 2015148732 A RU2015148732 A RU 2015148732A RU 2644659 C2 RU2644659 C2 RU 2644659C2
Authority
RU
Russia
Prior art keywords
pipeline
construction
slopes
rock
route
Prior art date
Application number
RU2015148732A
Other languages
Russian (ru)
Other versions
RU2015148732A (en
Inventor
Вадим Андреевич Иванов
Олег Евгеньевич Аксютин
Игорь Григорьевич Волынец
Геннадий Витальевич Котишевский
Арнольд Анатольевич Дауров
Аслан Фуадович Закураев
Original Assignee
Вадим Андреевич Иванов
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Вадим Андреевич Иванов filed Critical Вадим Андреевич Иванов
Priority to RU2015148732A priority Critical patent/RU2644659C2/en
Publication of RU2015148732A publication Critical patent/RU2015148732A/en
Application granted granted Critical
Publication of RU2644659C2 publication Critical patent/RU2644659C2/en

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

FIELD: construction; mining.
SUBSTANCE: invention relates to methods of constructing a pipeline in a mountainous area in cramped conditions. Method of construction and protection of the main pipeline laid on slopes in mountainous areas from damage comprises geodesic breakdown of the route on the slopes. Rock on the mountain slopes is "softly" loosed by undermining. Construction site is cleared with a bulldozer and technological corridor is levelled by using a milling unit to form an even bed for the pipeline. Pipeline is consistently extended with the help of a front-gantry pipelayer with a caterpillar tracks. Separate sections of the pipeline with factory isolation are placed in the "belly" area of the pipelayer, delivered and descended to the bed of the route. Then, the sections of the extended pipeline are welded into a string, waterproofing of external welded joints of the pipeline is performed, a ballast protection device in the form of an elastic arch is installed on the pipeline by using local rock.
EFFECT: technical result is reduced width of the technological corridor.
1 cl, 8 dwg

Description

Изобретение относится к области строительства, а именно к прокладке трубопровода и его защите от камнепада в горных условиях.The invention relates to the field of construction, namely to laying a pipeline and protecting it from rockfall in mountain conditions.

Известен способ строительства трубопровода в горных условиях, который во многих случаях требует устройства полок на откосах горы либо проходки горного массива методом микротоннелирования. При существующих методах строительства трубопроводов на полках и откосах гор необходим монтаж подпорной стенки или специального укрытия, которые, как защитные устройства, в случае обрушения горной породы (камнепад) являются малоэффективными. Устройство полок, на которых в дальнейшем сооружается трубопровод и работают грузоподъемные механизмы, осуществляется методом взрыва шнуровыми зарядами (удаление части горных пород с откоса). Это способствует предварительному созданию горизонтального технологического коридора для трубопровода. После проведения взрывных работ, с помощью экскаватора выравнивают поверхность технологического коридора. Следующим этапом, для обеспечения качественной «постели» под трубопроводом, завозится и разравнивается «мягкий» грунт - песок (Мазур И.И. Нефтегазовое строительство. – М.: Из-во Омега, 2005).A known method of constructing a pipeline in mountain conditions, which in many cases requires the installation of shelves on the slopes of the mountain or the penetration of the massif by microtunnelling. With existing methods for constructing pipelines on shelves and slopes of mountains, it is necessary to install a retaining wall or a special shelter, which, as protective devices, in the event of a rock collapse (rockfall) are ineffective. The shelves, on which the pipeline is subsequently constructed and load-lifting mechanisms work, are carried out by the method of explosion with cord charges (removal of part of the rocks from the slope). This contributes to the preliminary creation of a horizontal technological corridor for the pipeline. After blasting, using the excavator to level the surface of the technological corridor. The next step, to ensure a high-quality “bed” under the pipeline, is imported and leveled “soft” soil - sand (Mazur II Oil and gas construction. - M .: Izme Omega, 2005).

Размеры технологического коридора выполняются с таким условием, чтобы была достаточная ширина для размещения самого строящегося трубопровода, грузоподъемной техники (трубоукладчики), вспомогательных механизмов (трубовозы очистные, изолировочные машины, устройства водоотвода с верхней части горы и др.). Все это приводит к значительным размерам полосы отвода по ширине (150-200 м) и затратам на подготовку трассы под трубопровод, прокладываемый на полках на откосах гор.The dimensions of the technological corridor are fulfilled in such a way that there is sufficient width to accommodate the pipeline under construction, lifting equipment (pipe layers), auxiliary mechanisms (cleaning pipe trucks, insulating machines, drainage devices from the top of the mountain, etc.). All this leads to significant dimensions of the right-of-way strip in width (150-200 m) and the cost of preparing the route for the pipeline laid on shelves on the slopes of the mountains.

Недостатками известного способа являются:The disadvantages of this method are:

большой объем взрывотехнических работ, который возникает из-за большой ширины устраиваемой полки;a large volume of blasting operations, which occurs due to the large width of the shelves being arranged;

необходимость создания широкого до 150-200 м технологического коридора (полки) для размещения на нем самого трубопровода и строительной техники (трубоукладчики, трубовозы, вспомогательная техника и др.);the need to create a wide technological corridor (shelf) up to 150-200 m to accommodate the pipeline itself and construction equipment (pipe layers, pipe carriers, auxiliary equipment, etc.);

колоссальные затраты на разработку горной породы (полученной методом взрыва) экскаваторами под площадку застройки, так как возникает необходимость переброски скальной породы от упорной стенки в откос горы;huge costs for the development of rock (obtained by the method of explosion) by excavators under the construction site, since there is a need to transfer rock from the thrust wall to the slope of the mountain;

доставка большого количества «мягкого грунта» (песок) для устройства постели под трубопровод, так как экскаватором невозможно сделать ровную поверхность площадки для укладки трубопровода;delivery of a large amount of “soft soil” (sand) for bedding under the pipeline, since it is impossible to excavate a flat surface of the site for laying the pipeline;

практически отсутствие защитных устройств трубопровода от эрозионных разрушений в случае камнепада, осыпей, селей и трещинообразований в площадке, возникающих от взрыва скальной породы.almost no protective devices of the pipeline from erosion in the case of rockfall, talus, mudflows and fractures in the site arising from the explosion of rock.

Задачей изобретения является разработка нового способа, строительства трассы со значительным сокращением материально-технических затрат за счет уменьшения работы экскаваторов, исключения необходимости в подвозке песка, использования фронтально-козлового трубоукладчика, работающего на любых продольных и поперечных уклонах, позволяющего снизить в 2 раза ширину технологического коридора, исключения из технологической цепочки использования традиционных трубоукладчиков, защиты построенного трубопровода от камнепада, осыпей, селей с помощью предотвращающего продольное и поперечное перемещение трубопровода балластозащитного устройства, использования для балластировки трубопровода местной горной породы.The objective of the invention is the development of a new method, the construction of the route with a significant reduction in material and technical costs by reducing the work of excavators, eliminating the need for sand transportation, using a front-gantry pipe layer working on any longitudinal and transverse slopes, which reduces the width of the technological corridor by 2 times , exceptions from the technological chain of using traditional pipe layers, protecting the constructed pipeline from rockfall, talus, mudflows from with help to prevent the longitudinal and transverse movement of the pipeline ballast protection device, use for ballasting the pipeline of local rocks.

При осуществлении заявляемого технического решения поставленная задача решается за счет достижения технического результата, который заключается в сокращении ширины технологического коридора, повышении надежности и эффективности строительства и защиты от камнепада магистрального трубопровода на откосах в горной местности.When implementing the claimed technical solution, the task is solved by achieving a technical result, which consists in reducing the width of the technological corridor, increasing the reliability and efficiency of construction and protecting the main pipeline from rockfalls on slopes in mountainous areas.

Технический результат достигается тем, что в способе строительства и защиты от камнепада магистрального трубопровода, проложенного на откосах в горной местности, предусматривают следующие операции: геодезическую разбивку трассы на косогорах, осуществление «мягкого» рыхления скальной породы методом подрыва зарядами на откосах горы, которое исключает образование трещин в скальной породе основания площадки; произведение черновой расчистки строительной площадки бульдозером со сбросом излишков породы в откос горы; выравнивание при помощи фрезерной установки площадки технологического коридора с образованием идеально ровной постели под трубопровод; последовательное наращивание строящегося трубопровода с помощью фронтально-козлового трубоукладчика на гусеничном ходу, который обеспечивает доставку и спуск на постель трассы отдельных секций или плетей трубопровода с заводской изоляцией, размещенных в «подбрюшной» области; осуществление сварки секций нарощенного трубопровода в нитку; спуск плети трубопровода на постель трассы; сварка нарощенного трубопровода; гидроизоляцию наружных сварных стыков трубопровода; установку на трубопровод балластозащитных устройств в виде упругой арки с использованием местной горной породы.The technical result is achieved by the fact that in the method of construction and protection against rockfall of the main pipeline laid on slopes in the mountains, the following operations are provided: geodetic breakdown of the track on slopes, the implementation of "soft" loosening of rock by blasting charges on the slopes of the mountain, which eliminates the formation of cracks in the rock of the base of the site; a rough clearing of the construction site with a bulldozer with dumping of excess rock into the slope of the mountain; alignment with the help of a milling installation of the technological corridor site with the formation of a perfectly flat bed under the pipeline; consecutive extension of the pipeline under construction with the help of the front-gantry pipe-laying machine on a caterpillar track, which ensures the delivery and descent to the bed of the route of individual sections or lashes of the pipeline with factory insulation, located in the "abdominal" region; welding sections of the extended pipeline into a thread; descent of the whip of the pipeline onto the bed of the route; welding extension pipe; waterproofing of external welded joints of the pipeline; installation of ballast protection devices in the form of an elastic arch on the pipeline using local rock.

Сопоставительный анализ с традиционной технологией показывает, что заявленный способ строительства использует прогрессивные методы, технику и технологию, реализуется с помощью фронтально-козлового трубоукладчика и комбинированного бутово-балластозащитного покрытия. Этот способ позволяет сократить в 2-3 раза время строительства и защитить действующий трубопровод от повреждений балластозащитным устройством при камнепаде, осыпях, селях.A comparative analysis with traditional technology shows that the claimed method of construction uses advanced methods, techniques and technology, is implemented using a front-gantry pipe-laying machine and a combined rubble-and-ballast coating. This method allows to reduce the construction time by 2-3 times and protect the existing pipeline from damage by a ballast protection device during rockfall, talus, mudflows.

Сравнение заявленного решения с традиционным способом строительства трубопроводов показывает известность операций способа, однако неизвестно, что за счет заявляемой совокупности и последовательности действий можно сократить в 2-4 раза ширину технологического коридора, а при использовании «мягкого» рыхления скального грунта методом подрыва снизить объем разработки горных пород в 3-4 раза и исключить в теле площадки трещинообразований; при произведении бульдозером черновой расчистки технологического коридора; выравнивании при помощи фрезерной установки площадки технологического коридора и постели под трубопровод; осуществление строительства трубопровода фронтально-козловым трубоукладчиком, свободно перемещающимся над строящимся трубопроводом, совмещающим операции доставки секций длиной до 50 м для наращивания трубопровода и производящим сварочно-монтажные операции; проведении комбинированной балластировки и защиты действующего трубопровода от повреждения камнепадом можно соорудить трассу под трубопровод.Comparison of the claimed solution with the traditional method of construction of pipelines shows the popularity of the operations of the method, however, it is not known that due to the claimed combination and sequence of actions, the width of the technological corridor can be reduced by 2-4 times, and when using “soft” loosening of rocky soil by blasting, reduce mining rocks 3-4 times and exclude crack formation in the body of the site; when a bulldozer performs rough cleaning of a technological corridor; alignment with the help of a milling installation of the site of the technological corridor and bed under the pipeline; construction of the pipeline by a front-gantry pipe-laying machine, freely moving over the pipeline under construction, combining delivery operations of sections up to 50 m in length for building up the pipeline and performing welding and installation operations; By carrying out combined ballasting and protecting the existing pipeline from rockfall damage, it is possible to build a route for the pipeline.

Причинно-следственная связь между существенными признаками изобретения и заявляемым и техническим результатом следующая: уменьшается объем взрывотехнических работ в 3-4 раза, так как для технологической площадки под трубопровод достаточна ширина 15-20 м; соответственно уменьшается объем удаляемой бульдозером скальной породы со строящейся трассы трубопровода в откос; практически исключается необходимость в подвозе песка за счет выравнивания фрезерованием поверхности площадки, использование фронтально-козлового трубоукладчика позволяет снизить в 2-4 раза ширину технологического коридора, исключить из технологической цепочки использование 5-7 традиционных трубоукладчиков и трубовозов, защита и балластировка построенного трубопровода от камнепада, осыпей, селей с помощью балластозащитного устройства (например, матрацы Рено) с использованием в них местной горной породы (бутовый камень) исключает доставку камня из карьеров.The causal relationship between the essential features of the invention and the claimed and technical result is as follows: the volume of blasting operations is reduced by 3-4 times, since a width of 15-20 m is sufficient for the technological site for the pipeline; accordingly, the volume of rock removed by the bulldozer from the pipeline route under construction to the slope decreases; virtually eliminating the need for sand transportation due to leveling by milling of the surface of the site, the use of a front-gantry pipe layer allows reducing the width of the technological corridor by 2-4 times, eliminating the use of 5-7 traditional pipe layers and pipe carriers from the technological chain, protecting and ballasting the constructed pipeline from rockfall, screes, mudflows with a ballast protection device (for example, Renault mattresses) using local rock in them (rubble stone) eliminates a mortar of stone from quarries.

На фиг. 1 показано: геодезическая разбивка территории под площадку трассы будущего трубопровода на горном откосе.In FIG. 1 shows: geodetic breakdown of the territory under the site of the route of the future pipeline on a mountain slope.

На фиг. 2 показано: «мягкое» рыхление скального грунта на откосе горного участка методом подрыва под расчищаемую (устраиваемую) методом взрыва площадку.In FIG. 2 shows: “soft” loosening of rocky soil on the slope of a mountain section by blasting under a cleared (arranged) by the explosion method.

На фиг. 3 показано: черновая расчистка полки (технологического коридора) бульдозером.In FIG. 3 shows: rough clearing of the shelf (technological corridor) with a bulldozer.

На фиг. 4 показано: фрезерование полки под постель трубопровода и строительную площадку с установкой упорной стенки.In FIG. 4 shows: milling a shelf for a bed of a pipeline and a construction site with the installation of a thrust wall.

На фиг. 5 показано: транспортировка и монтаж трубных секций фронтально-козловым трубоукладчиком на гусеничном ходу при наращивании трубопровода.In FIG. Figure 5 shows: transportation and installation of pipe sections by a front-gantry pipe-laying machine on a caterpillar track when building the pipeline.

На фиг. 6 показано: сварка трубопровода в плеть (линию).In FIG. 6 shows: welding of the pipeline in a whip (line).

На фиг. 7 показано: гидроизоляция сварных стыков.In FIG. 7 shows: waterproofing of welded joints.

На фиг. 8 показано: укладка балластирующих и защитных от камнепадов, осыпей и селей устройств.In FIG. 8 shows: laying ballasting and protective devices against rockfalls, screes and mudflows.

Заявляемую последовательность действий при прокладке трубопровода в горных условиях условно можно разделить на строительную и защитную составляющие.The claimed sequence of actions when laying a pipeline in mountain conditions can conditionally be divided into building and protective components.

Строительная составляющая включает использование стандартных методов и средств, в частности бульдозера, фрезерной машины и двухмодульного фронтально-козлового трубоукладчика.The construction component includes the use of standard methods and tools, in particular a bulldozer, a milling machine and a two-module front-gantry pipe-laying machine.

Защитная составляющая включает использование для защиты от камнепада сооруженного балластозащитного устройства, в качестве которого возможно применение комбинированного бутово-балластозащитного покрытия с использованием для балластировки трубопровода местной горной породы, например матрацев Рено, заполненным бутовым камнем.The protective component includes the use of a built-in ballast protection device for protection against rockfall, which can be combined with a rubble-ballast protection coating using local rock for ballasting, for example, Renault mattresses filled with rubble stone.

Сущность изобретения заключается в том, что трубопровод сооружается с помощью фронтально-козлового трубоукладчика (RU 2485384 С1) методом последовательного натаскивания новых секций трубопровода над уже смонтированным отрезком с осуществлением следующих основных операций способа.The essence of the invention lies in the fact that the pipeline is constructed using the front-gantry pipe-laying machine (RU 2485384 C1) by the method of successively dragging new sections of the pipeline over the already mounted section with the following basic operations of the method.

Выполняют разбивку оси трассы, по которой пройдет трубопровод (Фиг. 1). Производят «мягкое» рыхление скального грунта методом подрыва (Фиг. 2). Производят бульдозером черновую расчистку технологического коридора (Фиг. 3). Осуществляют планировку технологического коридора для будущей трассы трубопровода методом фрезерования горной породы (Фиг. 4). Осуществляют транспортировку трубных секций или плетей фронтально-козловым трубоукладчиком, размещенных в его «подбрюшной» части (Фиг. 5). Производят сварку наращиваемого трубопровода (Фиг. 6). Производят изоляцию сварных стыков трубопровода (Фиг. 7). Производят балластировку и защиту от камнепада построенного трубопровода (Фиг. 8).Perform a breakdown of the axis of the route along which the pipeline will pass (Fig. 1). Produce "soft" loosening of rocky soil by blasting (Fig. 2). Produce a bulldozer rough cleaning of the technological corridor (Fig. 3). Planning of the technological corridor for the future pipeline route by the method of milling rock (Fig. 4). Carry out the transportation of pipe sections or lashes by the front-gantry pipe-layer placed in its "abdominal" part (Fig. 5). Weld a stackable pipeline (Fig. 6). Insulate the welded joints of the pipeline (Fig. 7). Ballast and protect against rockfall of the constructed pipeline (Fig. 8).

Пример осуществления способа. Специалист 2 осуществляет геодезическую разбивку территории 3 под площадку трассы будущего трубопровода на горном откосе 1 (участке). Размещают посредством шурфования заряды для подрыва и удаления части грунта на откосе горного участка 1 (фиг. 2). Производят «мягкое» рыхление 5 скального грунта методом подрыва для образования горизонтальной полки 7 шириной В, равной 15-20 м (фиг. 2), для чего под расчищаемую (устраиваемую) площадку устанавливают 4 взрывчатых заряда. Устанавливают ограничительные столбики 6, служащие одновременно реперами. Производят черновую расчистку технологического коридора бульдозером 8 на горизонтальной полке 7 (фиг. 3). Выравнивают строительную площадку и дорожки под трубопровод для выравнивания полученной горизонтальной полки 7 методом фрезерования при помощи бульдозера 10 с фрезерным основанием и устанавливают упорную стенку 9, предотвращающую перемещение скального грунта с верхнего откоса (Фиг. 4).An example implementation of the method. Specialist 2 carries out geodetic breakdown of territory 3 under the site of the route of the future pipeline on the slope 1 (section). Place by means of punching charges to undermine and remove part of the soil on the slope of the mountain section 1 (Fig. 2). “Soft” loosening of 5 rocky soil is carried out by blasting to form a horizontal shelf 7 of width B equal to 15-20 m (Fig. 2), for which 4 explosive charges are placed under the cleared (arranged) site. Establish limiting columns 6, serving simultaneously as benchmarks. A rough clearing of the technological corridor is carried out with a bulldozer 8 on a horizontal shelf 7 (Fig. 3). The construction site and the tracks under the pipeline are leveled to level the obtained horizontal flange 7 using the milling method using a bulldozer 10 with a milling base and a thrust wall 9 is installed to prevent the rock from moving from the upper slope (Fig. 4).

Производят фронтально-козловым трубоукладчиком 11 укладку первых 12 и последующих 13 секций (плетей) трубопровода (фиг. 5). Производят холостой ход фронтально-козлового трубоукладчика 11 за новыми секциями. Поднимают с помощью лебедок в «подбрюшную» часть фронтально-козлового трубоукладчика 11 новые секции трубопровода с заводской изоляцией до положения выше диаметра строящегося трубопровода, который осуществляет рабочий ход над уложенной частью трубопровода и опускает в конце построенной части трубопровода доставленные секции на постель для наращивания трубопровода. Таким образом, перемещаясь над первыми секциями 12 и 13 построенной нитки трубопровода, фронтально-козловой трубоукладчик 11 с новыми секциями методом «натаскивания» наращивает линейную часть строящегося трубопровода (фиг. 6). Производят стыковочную сварку секций трубопровода в линию (фиг. 6). Производят изоляцию 15 сваренных стыков 14 трубопровода (фиг. 7). Производят монтаж балластировочно-защитных устройств (фиг. 8) путем укладки в виде упругой арки 16 над сваренным в нитку 17 трубопроводом. В качестве балластировочно-защитных устройств используют, например, матрацы Рено, заполненные бутовым камнем, полученным при проведении «мягкого» рыхления грунта.Produce the front-gantry pipe layer 11 laying the first 12 and subsequent 13 sections (lashes) of the pipeline (Fig. 5). Front-gantry pipe-laying device 11 is idled for new sections. With the help of winches, they lift new sections of the pipeline with factory insulation to the “abdominal” part of the front-gantry pipe layer 11 to a position above the diameter of the pipeline under construction, which carries out a stroke over the laid part of the pipeline and lowers the delivered sections to the bed at the end of the constructed part of the pipeline to build the pipeline. Thus, moving over the first sections 12 and 13 of the constructed pipeline string, the front-gantry pipe layer 11 with new sections by the “drag” method increases the linear part of the pipeline under construction (Fig. 6). Dock welding sections of the pipeline in a line (Fig. 6). Isolation 15 of the welded joints 14 of the pipeline (Fig. 7). Ballast-protective devices are installed (Fig. 8) by laying in the form of an elastic arch 16 over a pipe welded into a thread 17. As ballasting protective devices, for example, Renault mattresses are used, filled with rubble stone obtained by carrying out “soft” loosening of the soil.

Claims (1)

Способ строительства и защиты от камнепада магистрального трубопровода, проложенного на откосах в горной местности, предусматривающий следующие операции: геодезическую разбивку трассы на косогорах, осуществление «мягкого» рыхления скальной породы методом подрыва на откосах горы, произведение черновой расчистки строительной площадки бульдозером; выравнивание при помощи фрезерной установки площадки технологического коридора с образованием ровной постели под трубопровод; последовательное наращивание строящегося трубопровода с помощью фронтально-козлового трубоукладчика на гусеничном ходу, который обеспечивает доставку и спуск на постель трассы отдельных секций трубопровода, размещенных в «подбрюшной» области, осуществление сварки секций нарощенного трубопровода в нитку, гидроизоляцию наружных сварных стыков трубопровода, установку на сваренный в нитку трубопровод балластозащитных устройств в виде упругой арки с использованием местной горной породы.A method of construction and protection from rockfall of a main pipeline laid on slopes in mountainous areas, which includes the following operations: geodetic breakdown of the track on slopes, the implementation of "soft" loosening of rock by blasting on the slopes of the mountain, and roughing out the construction site with a bulldozer; alignment with the help of a milling installation of the technological corridor site with the formation of an even bed under the pipeline; consecutive extension of the pipeline under construction using the front-gantry pipe-laying machine on a caterpillar track, which ensures delivery and descent to the bed of the route of individual sections of the pipeline located in the "abdominal" area, welding sections of the extended pipeline in the thread, waterproofing the external welded joints of the pipeline, installation on the welded into the string is a pipeline of ballast protection devices in the form of an elastic arch using local rock.
RU2015148732A 2015-11-12 2015-11-12 Method of construction and protection of the pipeline from rockfall on slopes in mountainous areas RU2644659C2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU2015148732A RU2644659C2 (en) 2015-11-12 2015-11-12 Method of construction and protection of the pipeline from rockfall on slopes in mountainous areas

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2015148732A RU2644659C2 (en) 2015-11-12 2015-11-12 Method of construction and protection of the pipeline from rockfall on slopes in mountainous areas

Publications (2)

Publication Number Publication Date
RU2015148732A RU2015148732A (en) 2017-05-15
RU2644659C2 true RU2644659C2 (en) 2018-02-13

Family

ID=58715375

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2015148732A RU2644659C2 (en) 2015-11-12 2015-11-12 Method of construction and protection of the pipeline from rockfall on slopes in mountainous areas

Country Status (1)

Country Link
RU (1) RU2644659C2 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2194903C2 (en) * 2000-10-19 2002-12-20 АО "НГС-оргпроектэкономика" Method of erection of main pipe line on slope of mountainous terrain
US6969215B2 (en) * 2004-03-11 2005-11-29 Duncan Kenneth R Method and apparatus for laying pipe on an incline
RU2485384C2 (en) * 2011-09-01 2013-06-20 Вадим Андреевич Иванов Front gantry pipe-laying machine

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2194903C2 (en) * 2000-10-19 2002-12-20 АО "НГС-оргпроектэкономика" Method of erection of main pipe line on slope of mountainous terrain
US6969215B2 (en) * 2004-03-11 2005-11-29 Duncan Kenneth R Method and apparatus for laying pipe on an incline
RU2485384C2 (en) * 2011-09-01 2013-06-20 Вадим Андреевич Иванов Front gantry pipe-laying machine

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
Бородавкин П.П., Глоба В.М. "Сооружение трубопроводов в горах" М.: "Недра", 1978, 144 с., с.3-4,45-46. *
Газета "Сибирский газовик" N 13-14 (1228-1229) от 3 апреля 2015 г., с.4-5, Свидетельство о регистрации ПИ N17-0505 от 21.10.2002. *

Also Published As

Publication number Publication date
RU2015148732A (en) 2017-05-15

Similar Documents

Publication Publication Date Title
AU2015281641B2 (en) Method for removing hydraulic support for solid filling coal mining
CN106641440B (en) A kind of transverse crossing railway line underground piping jacking construction method
CN104832181B (en) Dovetail type section constructing tunnel technique
CN102748040B (en) Main structure for metro long-span station and pillar arching construction method thereof
CN103821558A (en) Coal mine gob filling mining system and gob-side entry retaining filling process
CN108843333A (en) Collapsible Loess District tunneling double-arched tunnel passes through the construction method of existing railway
CN106121659B (en) The narrow-bore tunnel excavation method of major urban arterial highway upper-soft lower-hard ground is worn under one kind
CN108049417A (en) A kind of high-locality landslide body reinforces method of disposal
RU2425218C1 (en) Underground development method of series of thin steep deposits
CN104895121A (en) Transverse partition method for reducing ground surface settlement and building structure deformation of underground structure construction
CN104196036B (en) Based on foundation pit supporting construction and the supporting method of old outer wall of basement structure
RU2644659C2 (en) Method of construction and protection of the pipeline from rockfall on slopes in mountainous areas
CN110273708B (en) Roadway support structure body control drainage method
Joass et al. Risk management and remediation of the north wall slip, West Angelas Mine, Western Australia
CN105587321A (en) Collapse column bypassing extraction process
RU2449124C1 (en) Method to increase stability of ceiling in downward slicing development of deposit with backfilling
RU2563895C1 (en) Method of open and underground mining of series of semi-steep coal layers
RU2651833C1 (en) Method of open-underground development of coal bed, lying in the form of brachysyncline
CN214787406U (en) I-steel self-filling roadside support facility
CN109356622A (en) A kind of structure and implementation method handling tunnel roof fall
RU2733759C1 (en) Open-underground method of development of stratified deposits of minerals
RU2490467C2 (en) Method to tunnel horizontal or inclined underground mine and tunnelling machine for method realisation
CN105350543A (en) Single-channel excavation method for deep foundation pit
CN106567381A (en) Large u-shaped steel sheet pile construction technology
RU2568447C1 (en) Development of thick inflammable steeply inclined coal beds

Legal Events

Date Code Title Description
HZ9A Changing address for correspondence with an applicant
MM4A The patent is invalid due to non-payment of fees

Effective date: 20191113