RU2275300C2 - Method of unloading of the concrete mixture from the baromixers and the device the method realization - Google Patents

Method of unloading of the concrete mixture from the baromixers and the device the method realization Download PDF

Info

Publication number
RU2275300C2
RU2275300C2 RU2004113340/03A RU2004113340A RU2275300C2 RU 2275300 C2 RU2275300 C2 RU 2275300C2 RU 2004113340/03 A RU2004113340/03 A RU 2004113340/03A RU 2004113340 A RU2004113340 A RU 2004113340A RU 2275300 C2 RU2275300 C2 RU 2275300C2
Authority
RU
Russia
Prior art keywords
cavity
compressed air
unloading
pumping
concrete mixture
Prior art date
Application number
RU2004113340/03A
Other languages
Russian (ru)
Other versions
RU2004113340A (en
Inventor
Абакар Ахмедпашаевич Акаев (RU)
Абакар Ахмедпашаевич Акаев
Original Assignee
Абакар Ахмедпашаевич Акаев
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Абакар Ахмедпашаевич Акаев filed Critical Абакар Ахмедпашаевич Акаев
Priority to RU2004113340/03A priority Critical patent/RU2275300C2/en
Publication of RU2004113340A publication Critical patent/RU2004113340A/en
Application granted granted Critical
Publication of RU2275300C2 publication Critical patent/RU2275300C2/en

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Preparation Of Clay, And Manufacture Of Mixtures Containing Clay Or Cement (AREA)

Abstract

FIELD: building industry; method and devices for unloading of the concrete mixture from the baromixers.
SUBSTANCE: the invention is pertaining to the field of building industry and is intended for application in the building industry, in particular, in baromixers used for preparation of the concrete mixtures. The method of unloading of the concrete mixtures from the baromixers includes feeding in the cavity of the baromixer of the compressed air with the calculated pressure for unloading of the concrete mixture. At that for saving the power necessary for production of the compressed air and also for reduction of duration of the cycle of the concrete mixture unloading the part of the compressed air remained in the cavity of the baromixer after the unloading of the concrete mixture is let to gravity flow into the cavity of the following baromoxer, and the second part of the compressed air after equalization of the pressure in both cavities pumping into the cavity of the following baromixer is forced by the air compressor bringing the pressure in its cavity up to the calculated value. The method is realized with the help of the device including baromixers with the unloading branch-pipes, gates of injection of the compressed air, which are connected with a pneumatic drive of injection and the air compressor, the oil-moisture separator. At that for the compressed air pumping-over from the cavity of one baromixer into the cavity of another baromixer, these baromixers are supplied with the pumping-out valves and are connected with each other by the pumping-out pneumatic drive connected to the compressor. At that the pneumatic drives of the pumping-in and pumping-out are connected among themselves by pressure-relief valve. The technical result of the invention is reduction of the time duration necessary for preparation of concrete mixture and of the power input necessary for production of the compressed air.
EFFECT: the invention ensures reduction of the time duration necessary for preparation of concrete mixture and of the power input necessary for production of the compressed air.
2 cl, 1 dwg

Description

Способ выгрузки бетонной смеси из баросмесителя и устройство для его осуществления предназначены для применения в строительной технике, частности в баросмесителях, применяемых для приготовления бетонных смесей.The method of unloading concrete mixture from the bar mixer and the device for its implementation are intended for use in construction equipment, in particular in bar mixers used for the preparation of concrete mixtures.

Известна мобильная установка ПРН-500М производства ОАО Нижнетуринского машиностроительного завода «Вента» (проспект прилагается), предназначенная для приготовления и подачи жестких растворов (бетона, цемента и пр.). Установка включает в себя смонтированный на шасси бак, футерованный изнутри бронированными плитами и имеющий загрузочный люк; устройство для перемешивания приготавливаемого раствора, приводимое в действие при помощи электродвигателя и понижающего редуктора; разгрузочный патрубок. Выгрузка готовой продукции (бетонной смеси) осуществляется сжатым воздухом, подаваемым в полость бака. Недостаток данной установки заключается в том, что после выгрузки бетонной смеси (перед загрузкой следующей порции ингредиентов) сжатый воздух, закачанный в бак, стравливается в атмосферу. Таким образом, для выгрузки очередной порции готовой бетонной смеси в баке приходится повторно создавать расчетное давление (давление, величина которого достаточна для выдавливания бетонной смеси из полости баросмесителя и подачи его по бетонопроводу на необходимую высоту. Величина расчетного давления зависит от объема бетонной смеси, его консистенции, конструктивных параметров самого баросмесителя и т.д).A well-known mobile installation PRN-500M produced by OJSC Nizhny Turinsky Machine-Building Plant "Venta" (the prospectus is attached), intended for the preparation and supply of hard solutions (concrete, cement, etc.). The installation includes a tank mounted on the chassis, lined from the inside with armored plates and having a loading hatch; a device for mixing the prepared solution, driven by an electric motor and a reduction gear; discharge pipe. Unloading of finished products (concrete mix) is carried out by compressed air supplied to the tank cavity. The disadvantage of this installation is that after unloading the concrete mixture (before loading the next portion of the ingredients), the compressed air pumped into the tank is vented to the atmosphere. Thus, to unload the next portion of the finished concrete mixture in the tank, it is necessary to re-create the calculated pressure (a pressure that is sufficient to squeeze the concrete mixture from the cavity of the mixer and supply it through the concrete pipe to the required height. The value of the calculated pressure depends on the volume of the concrete mixture, its consistency , design parameters of the bar mixer itself, etc.).

Известна также установка для приготовления пенобетона аэрированием (заявка №2003127174 с приоритетом от 12.09.03). Установка включает в себя баросмеситель с крышкой, тележку, разгрузочный патрубок, привод ротора, пульт управления, контрольно-измерительную аппаратуру. В состав установки также входит система подачи сжатого воздуха через клапан закачки из пневмопровода закачки, предназначенная для аэрирования бетонной смеси. Этот же сжатый воздух используется для выгрузки пенобетона через разгрузочный патрубок и подачи его к месту потребления. Недостаток установки такой же, как в предыдущей установке.Also known installation for the preparation of foam concrete by aeration (application No. 2003127174 with priority from 09/12/03). The installation includes a bar mixer with a lid, a trolley, an unloading nozzle, a rotor drive, a control panel, and instrumentation. The installation also includes a compressed air supply system through the injection valve from the pneumatic injection pipeline, designed to aerate the concrete mixture. The same compressed air is used to unload foam concrete through the discharge pipe and supply it to the place of consumption. The disadvantage of the installation is the same as in the previous installation.

Целью данного изобретения является сокращение времени для приготовления бетонной смеси и экономия энергии, необходимой для выработки сжатого воздуха.The aim of this invention is to reduce the time for preparation of concrete mix and save energy needed to produce compressed air.

Достигается данная цель перепуском части сжатого воздуха, оставшегося в полости баросмесителя после выгрузки бетонной смеси, в полость следующего баросмесителя. После выравнивания давления в обеих полостях (становится равной половине расчетного давления) вторая часть сжатого воздуха, оставшегося в полости баросмесителя, перекачивается в полость следующего (принимающего) баросмесителя принудительно, при помощи компрессора, тем самым доводя давление в его полости до расчетного значения. Таким образом, весь объем сжатого воздуха из первого баросмесителя перекачивается в следующий. При этом давление в первом баросмесителе становится равным атмосферному, а давление в следующем баросмесителе становится равным расчетному.This goal is achieved by transferring part of the compressed air remaining in the cavity of the mixer after unloading the concrete mixture into the cavity of the next mixer. After equalizing the pressure in both cavities (it becomes equal to half of the design pressure), the second part of the compressed air remaining in the cavity of the mixer is pumped into the cavity of the next (receiving) mixer using the compressor, thereby bringing the pressure in its cavity to the calculated value. Thus, the entire volume of compressed air from the first mixer is pumped into the next. In this case, the pressure in the first bar mixer becomes equal to atmospheric, and the pressure in the next bar mixer becomes equal to the calculated one.

На чертеже приведено устройство для выгрузки бетонной смеси из баросмесителя, которое имеет баросмесители 1, 2, 3, соединенные с компрессором 4 пневмопроводами для закачки и выкачки сжатого воздуха 5 и 6. Баросмесители снабжены электромагнитными клапанами закачки 7, 8, 9 и выкачки 10, 11, 12 сжатого воздуха. Пневмопровод выкачки снабжен масловлагоотделителем 13 и воздухозаборным клапаном 14. Между пневмопроводами закачки и выкачки сжатого воздуха установлен перепускной клапан 15. Разгрузочные патрубки 16 баросмесителей объединены в бетонопровод 17. Стрелками обозначены направления движения сжатого воздуха и выхода бетонной смеси.The drawing shows a device for unloading concrete mixture from a bar mixer, which has bar mixers 1, 2, 3 connected to a compressor 4 by pneumatic pipelines for injection and pumping of compressed air 5 and 6. Bar mixers are equipped with electromagnetic valves for pumping 7, 8, 9 and pumping 10, 11 12 compressed air. The pumping air line is equipped with an oil separator 13 and an air intake valve 14. A bypass valve 15 is installed between the air lines for pumping and pumping out the compressed air 15. The discharge nozzles 16 of the mixer are combined into a concrete pipe 17. The arrows indicate the directions of movement of the compressed air and the exit of the concrete mixture.

Устройство для выгрузки бетонной смеси из баросмесителя работает следующим образом.A device for unloading concrete from a bar mixer works as follows.

В баросмеситель 1 по пневмопроводу закачки 5 через открытый клапан закачки 7 подается сжатый воздух для выгрузки готовой бетонной смеси. При этом все остальные клапаны находятся в закрытом положении. После выгрузки бетонной смеси через разгрузочный патрубок 16 в бетонопровод 17, клапан закачки 7 и клапан разгрузочного патрубка (не указан) закрываются. Одновременно открываются клапан выкачки 10, клапан закачки 8 и перепускной клапан 15. Сжатый воздух, оставшийся в полости баросмесителя 1, по пневмопроводу выкачки 6 через открытые клапаны 10, 15 и 8 самотеком поступает в полость баросмесителя 2. После выравнивания давления в полостях баросмесителей 1 и 2 закрывается перепускной клапан 15, и оставшийся в полости 1 сжатый воздух, давление которого равно половине расчетного давления, по пневмопроводу выкачки 6 поступает в компрессор 4. Сжатый воздух из полости баросмесителя выкачивается (высасывается), доводя давление в нем до величины атмосферного давления, одновременно доводя давление сжатого воздуха в полости баросмесителя 2 до расчетного значения. Таким образом, весь остаточный сжатый воздух, ранее выпускаемый в атмосферу, в два этапа полностью перекачивается в следующий баросмеситель. Тем самым, «бросовый» сжатый воздух выполняет полезную работу. Также происходит перекачка остаточного сжатого воздуха из баросмесителя 2 в баросмеситель 3, а из баросмесителя 3 в баросмеситель 1. Очевидно, что экономится значительное количество энергии для выработки сжатого воздуха и сокращается цикл непрерывного получения бетонной смеси. Для справки: для достижения в полости баросмесителя объемом в 2 м3 давления сжатого воздуха в 16 атмосфер необходимо затратить 15-20 минут.Compressed air is supplied to the mixer 1 through an injection pneumatic pipeline 5 through an open injection valve 7 to unload the finished concrete mixture. In this case, all other valves are in the closed position. After unloading the concrete mixture through the discharge pipe 16 into the concrete pipe 17, the injection valve 7 and the discharge pipe valve (not specified) are closed. At the same time, the pumping valve 10, the injection valve 8 and the bypass valve 15 open. Compressed air remaining in the cavity of the mixer 1, through the pneumatic pumping pipe 6 through open valves 10, 15 and 8 by gravity enters the cavity of the mixer 2. After equalizing the pressure in the cavities of the mixer 1 and 2, the bypass valve 15 is closed, and the compressed air remaining in the cavity 1, the pressure of which is equal to half the design pressure, enters the compressor 4 through the pneumatic pumping line 6. The compressed air is pumped out of the cavity of the mixer (sucked out ) Adjusting the pressure therein to atmospheric pressure, simultaneously bringing the compressed air pressure in the cavity 2 to barosmesitelya calculated value. Thus, all residual compressed air previously discharged into the atmosphere is completely pumped into the next bar mixer in two stages. Thus, the "waste" compressed air performs useful work. Residual compressed air is also pumped from the mixer 2 to the mixer 3, and from the mixer 3 to the mixer 1. It is obvious that a significant amount of energy is saved for the production of compressed air and the cycle of continuous production of concrete mix is shortened. For reference: to achieve a pressure of 16 atmospheres in a cavity of a mixer bar with a volume of 2 m 3, it is necessary to spend 15-20 minutes.

Claims (2)

1. Способ выгрузки бетонной смеси из баросмесителей, включающий подачу в полость баросмесителя сжатого воздуха с расчетным давлением для выгрузки бетонной смеси, отличающийся тем, что для экономии энергии, необходимой для выработки сжатого воздуха, а также сокращения цикла выгрузки бетонной смеси, часть воздуха, оставшегося в полости баросмесителя после выгрузки бетонной смеси, перепускают в полость следующего баросмесителя самотеком, а вторую часть сжатого воздуха после выравнивания давления в обеих полостях перекачивают в полость следующего баросмесителя принудительно компрессором, доводя давление в его полости до расчетного значения. 1. A method of unloading concrete mixture from bar mixers, comprising supplying compressed air to the cavity of the mixer bar with a design pressure for unloading concrete mixture, characterized in that in order to save energy needed to produce compressed air, as well as to reduce the cycle of unloading concrete mixture, some of the air remaining in the cavity of the mixer after unloading the concrete mixture, it is passed by gravity into the cavity of the next mixer, and the second part of the compressed air after equalizing the pressure in both cavities is pumped into the cavity the driving mixer is forced by the compressor, bringing the pressure in its cavity to the calculated value. 2. Устройство для выгрузки бетонной смеси из баросмесителей, включающее баросмесители с выгрузочными патрубками, клапанами закачки сжатого воздуха, соединенными с пневмоприводом закачки и компрессором, масловлагоотделитель, воздухозаборный клапан, отличающееся тем, что для перекачки сжатого воздуха из полости одного баросмесителя в полость другого баросмесителя баросмесители выполнены с клапанами выкачки и соединены друг с другом пневмопроводом выкачки, соединенным с компрессором, причем пневмопроводы закачки и выкачки соединены между собой перепускным клапаном.2. A device for unloading concrete mixes from bar mixers, including bar mixers with discharge nozzles, compressed air injection valves, connected to a pneumatic pump and compressor, an oil separator, an air intake valve, characterized in that for pumping compressed air from the cavity of one mixer to the cavity of another mixer bar made with pumping valves and connected to each other by a pumping pneumatic conduit connected to the compressor, wherein the injection and pumping pneumatic conduits are connected m between itself bypass valve.
RU2004113340/03A 2004-04-29 2004-04-29 Method of unloading of the concrete mixture from the baromixers and the device the method realization RU2275300C2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU2004113340/03A RU2275300C2 (en) 2004-04-29 2004-04-29 Method of unloading of the concrete mixture from the baromixers and the device the method realization

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2004113340/03A RU2275300C2 (en) 2004-04-29 2004-04-29 Method of unloading of the concrete mixture from the baromixers and the device the method realization

Publications (2)

Publication Number Publication Date
RU2004113340A RU2004113340A (en) 2005-10-27
RU2275300C2 true RU2275300C2 (en) 2006-04-27

Family

ID=35863570

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2004113340/03A RU2275300C2 (en) 2004-04-29 2004-04-29 Method of unloading of the concrete mixture from the baromixers and the device the method realization

Country Status (1)

Country Link
RU (1) RU2275300C2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
MD3509C2 (en) * 2005-12-16 2008-09-30 Евсей ШАМИС Device for preparing activated building mixes on base of mineral binders

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
MD3509C2 (en) * 2005-12-16 2008-09-30 Евсей ШАМИС Device for preparing activated building mixes on base of mineral binders

Also Published As

Publication number Publication date
RU2004113340A (en) 2005-10-27

Similar Documents

Publication Publication Date Title
US4185923A (en) Method and apparatus for producing insulating material
US7766537B2 (en) Lightweight foamed concrete mixer
CN101786295A (en) Trucd mixer
US20050195681A1 (en) Lightweight concrete mixer
CN201043349Y (en) Double-piston type spraying machine
CN110748330A (en) Frequency conversion integrated motor driven electric sand mixing sledge
CN110435011A (en) Concrete moves production equipment
RU2275300C2 (en) Method of unloading of the concrete mixture from the baromixers and the device the method realization
CN203499260U (en) Movable dry and wet dual-purpose automatic mixing and guniting integrated machine
CN201989235U (en) Non-steamed aerated block forming equipment
US3889850A (en) Texture and acoustic spraying equipment
CN112248229A (en) Concrete mixer
CN101462309A (en) Direct type concrete additive agent adding machine
CN203112576U (en) High-efficient micropore aeration reactor for sewage treatment
CN214973446U (en) Building glue stirring device
CN108640306A (en) A kind of uniformly mixed sewage disposal aerator
RU107503U1 (en) ROTARY-PULSATION COMPLEX FOR FOAM CONCRETE PRODUCTION
CN113263628A (en) Full-automatic foam concrete construction system of on-vehicle intelligence
CN208812295U (en) A kind of silt spray equipment for tunnel maintenance
KR100386683B1 (en) A method and an apparatus for pumping
RU2540693C1 (en) Method to produce foam concrete mix using mechanically activated binder
RU38673U1 (en) UNIVERSAL CONCRETE MIXER-SPRAYER
CN220741609U (en) Curing device for autoclaved aerated concrete plate
CN203765803U (en) Batching and stirring vehicle-mounted pump
CN115256642B (en) Building agitated vessel

Legal Events

Date Code Title Description
MM4A The patent is invalid due to non-payment of fees

Effective date: 20080430