RU2211288C2 - Procedure controlling list and sinking of solid mass structure - Google Patents

Procedure controlling list and sinking of solid mass structure Download PDF

Info

Publication number
RU2211288C2
RU2211288C2 RU2001120216A RU2001120216A RU2211288C2 RU 2211288 C2 RU2211288 C2 RU 2211288C2 RU 2001120216 A RU2001120216 A RU 2001120216A RU 2001120216 A RU2001120216 A RU 2001120216A RU 2211288 C2 RU2211288 C2 RU 2211288C2
Authority
RU
Russia
Prior art keywords
foundation
hydraulic jacks
plate
nozzle
jack
Prior art date
Application number
RU2001120216A
Other languages
Russian (ru)
Other versions
RU2001120216A (en
Inventor
К.К. Нежданов
В.А. Туманов
А.К. Нежданов
А.С. Маскаев
Original Assignee
Пензенская государственная архитектурно-строительная академия
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Пензенская государственная архитектурно-строительная академия filed Critical Пензенская государственная архитектурно-строительная академия
Priority to RU2001120216A priority Critical patent/RU2211288C2/en
Publication of RU2001120216A publication Critical patent/RU2001120216A/en
Application granted granted Critical
Publication of RU2211288C2 publication Critical patent/RU2211288C2/en

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)
  • Foundations (AREA)

Abstract

FIELD: construction industry, control over spatial position of structures and constructions listing as result of nonuniform settlement of ground foundations. SUBSTANCE: procedure controlling list and sinking of solid mass structure includes making of through nozzles in solid foundation plate, installation of double-action hydraulic jacks which force loose material into bed under foundation during single cycle by one stroke of hydraulic jacks and return to initial position. Working cycles are continued till bearing capability of foundation exceeds vertical compression effort created by mass of whole structure and foundation of structure begins squeezing out of ground upwards. Characteristic feature of invention consists in making of central and side nozzles expanding downwards and arranged in symmetry around central nozzle in solid foundation plate of structure. Steel anchor ring comprising two semi-rings is inserted into each nozzle, jack beam is placed above nozzle and is tied to anchor ring by anchor bolts. Double-action hydraulic jacks are positioned between foundation beam and each nozzle and their pistons are linked to jack beam. Hydraulic jack is pulled to jack beam by back stroke, nozzles are filled with loose material up to bearing plate of hydraulic jack which outline follows profile of section of inlet of nozzle. Family of double-action hydraulic jacks located in zone of maximal settling of plate of solid mass structure consolidates ground base gradually diminishing list of solid mass structure by synchronous operation. As list of structure diminishes additional families of double-action hydraulic jacks are put in action enlarging consolidation zone of ground base under foot of plate over area. Cycles are repeated till list of solid mass structure is completely corrected while all hydraulic jacks operate over entire area of foot of plate. EFFECT: potential to diminish list of structure with simultaneous provision for operation safety. 3 dwg

Description

Изобретение относится к области строительства, а в частности к управлению пространственным положением строительных сооружений и конструкций, получивших крен в результате неравномерной осадки грунтового основания. The invention relates to the field of construction, and in particular to the management of the spatial position of building structures and structures that received a roll as a result of uneven settlement of the soil base.

Наиболее близким к изобретению является cпособ управления креном и осадкой массивного сооружения, включающий выполнение в массивной плите фундамента сооружения сквозных сопел, установку гидродомкратов двойного действия, которые за один цикл вдавливают сыпучий материал в основание под фундаментом на ход поршня гидродомкрата, а затем возвращаются в исходное положение, причем циклы процесса продолжаются до тех пор, пока несущая способность основания не превысит вертикальное сжимающее усилие, создаваемое массой всего сооружения, и фундамент сооружения не начнет выдавливаться вверх из грунта (см. DE 4129995 А1, E 02 D 35/00, 27/34, 11.03.1993). Closest to the invention is a method of controlling the roll and draft of a massive structure, including performing through nozzles in a massive foundation plate of the structure, installing double-acting hydraulic jacks that in one cycle press the bulk material into the base under the foundation on the stroke of the hydraulic jack piston, and then return to their original position moreover, the process cycles continue until the bearing capacity of the base exceeds the vertical compressive force created by the mass of the entire structure, and the foundation The building component will not start to squeeze up from the ground (see DE 4129995 A1, E 02 D 35/00, 27/34, 03/11/1993).

Недостатком данного способа является то, что он трудоемок и мало эффективен при упрочнении грунтового основания под массивным сооружением. The disadvantage of this method is that it is time-consuming and ineffective in hardening the soil base under a massive structure.

Задачей настоящего изобретения является обеспечение возможности управления креном массивного высотного сооружения. An object of the present invention is to enable roll control of a massive high-rise structure.

Поставленная задача решается за счет того, что в способе управления креном и осадкой массивного сооружения, включающем выполнение в массивной плите фундамента сооружения сквозных сопел, установку гидродомкратов двойного действия, которые за один цикл вдавливают сыпучий материал в основание под фундаментом на ход поршня гидродомкрата, а затем возвращаются в исходное положение, причем циклы процесса продолжаются до тех пор, пока несущая способность основания не превысит вертикальное сжимающее усилие, создаваемое массой всего сооружения, и фундамент сооружения не начнет выдавливаться вверх из грунта, согласно изобретению в массивной плите фундамента сооружения выполняют расширяющиеся книзу центральное и боковые, размещенные симметрично от центрального, сопла, вкладывают в каждое сопло стальное анкерное кольцо, состоящее из двух полуколец, устанавливают над соплом домкратную балку и соединяют ее с анкерным кольцом анкерными болтами, а гидродомкраты двойного действия размещают между фундаментной балкой и каждым соплом и соединяют их поршни с домкратной балкой, обратным ходом подтягивают гидродомкрат к домкратной балке, заполняют сопла сыпучим материалом до опорной плиты гидродомкрата, повторяющей своим контуром профиль сечения входа сопел, группой гидродомкратов двойного действия, находящихся в зоне максимальной осадки плиты массивного сооружения, упрочняют грунтовое основание, постепенно уменьшают крен массивного сооружения, действуя синхронно группой гидродомкратов, по мере уменьшения крена сооружения подключают следующие дополнительные группы гидродомкратов двойного действия, увеличивая зону упрочнения грунтового основания под подошвой плиты по площади, и циклы продолжают до полной ликвидации крена массивного сооружения и до включения в работу всех гидродомкратов по всей площади подошвы плиты. The problem is solved due to the fact that in the method of controlling the roll and draft of a massive structure, including performing through nozzles in a massive foundation plate of a building, installing double-acting hydraulic jacks that press the bulk material into the base under the foundation for one stroke of the hydraulic jack piston in one cycle, and then return to their original position, and the process cycles continue until the bearing capacity of the base exceeds the vertical compressive force created by the mass of the entire structure I, and the foundation of the structure will not begin to be squeezed up from the ground, according to the invention, in the massive base plate of the structure, the central and side expanding downward, symmetrically placed from the central, nozzles are made, a steel anchor ring consisting of two half rings is inserted into each nozzle, a jack is installed over the nozzle beam and connect it to the anchor ring with anchor bolts, and double-acting hydraulic jacks are placed between the foundation beam and each nozzle and their pistons are connected to the jack beam, reverse with a stroke, pull the hydraulic jack to the jack beam, fill the nozzles with bulk material to the hydraulic jack support plate, repeating with its contour the profile of the nozzle inlet section, a group of double-acting hydraulic jacks located in the zone of maximum settlement of the massive structure plate, strengthen the soil base, gradually reduce the heel of the massive structure, acting synchronously with a group of hydraulic jacks, as the roll of the structure decreases, the following additional groups of double-acting hydraulic jacks are connected, increasing the area of hardening of the soil base under the base of the slab over the area, and the cycles continue until the roll of the massive structure is completely eliminated and all hydraulic jacks are included in the work over the entire area of the base of the slab.

Технический результат изобретения заключается в том, что процесс устранения крена массивного сооружения механизирован и даже автоматизирован. Ликвидация крена сооружения выполняется одним оператором с одного пульта. В процессе устранения крена оператор получает непрерывную информацию от контролирующей группы, определяющей приборами величину крена и скорость его устранения. Оператор, используя геодезические данные о изменении крена сооружения, включает ту или иную группу гидродомкратов, минимизируя величину крена массивного сооружения. Гарантирована безопасность работ, так как в момент вдавливания сыпучего материала под плиты сооружения рабочие в опасной зоне отсутствуют. Постепенное повышение прочности грунтового основания также повышает безопасность работ. Способ управления креном и осадкой массивного сооружения позволяет не только устранить имеющийся крен, но и создать безопасный крен в противоположную сторону. Изменение и выправление крена сооружения может быть выполнено многократно. The technical result of the invention lies in the fact that the process of eliminating the roll of a massive structure is mechanized and even automated. Liquidation of the building roll is carried out by one operator from one remote control. In the process of eliminating the roll, the operator receives continuous information from the monitoring group, which determines the amount of the roll and the speed of its removal with the instruments. The operator, using geodetic data on the change in the heel of the structure, includes one or another group of hydraulic jacks, minimizing the heel of the massive structure. Work safety is guaranteed, since at the moment of pushing bulk material under the slabs of the structure, there are no workers in the danger zone. A gradual increase in the strength of the soil base also increases the safety of work. The way to control the roll and draft of a massive structure allows not only to eliminate the existing roll, but also to create a safe roll in the opposite direction. Changing and straightening the heel of the structure can be performed repeatedly.

Изобретение поясняется чертежами, где на фиг.1 показано массивное сооружение, получившее крен при неравномерной осадке грунтового основания; на фиг.2 - фундаментная плита в плане; на фиг.3 - узел установки гидродомкратов двойного действия. The invention is illustrated by drawings, where figure 1 shows a massive structure that received a roll with uneven settlement of the soil base; figure 2 - foundation plate in plan; figure 3 - site installation of hydraulic jacks double action.

Способ осуществляют следующим образом. The method is as follows.

Массивное сооружение имеет железобетонную или иную фундаментную плиту 1, воспринимающую массу сооружения и распределяющую вертикальное давление по всей подошве плиты 1. В плите 1 бурят сквозные сопла 2, расширяющиеся книзу. Верхнюю часть каждого сопла выполняют цилиндрической, нижнюю - конической. В зоне сопряжения цилиндрической и конической частей выполняют кольцевой буртик. Над соплом 2 установливают домкратную крестообразную балку 3, опирающуюся через полые трубчатые колонны 4 на фундаментную плиту 1. Консоли домкратной балки 3 соединяют тягами 5 с анкерным кольцом 6. Каждую из тяг 5 пропускают сквозь консоль домкратной балки 3, полую трубчатую колонну 4, через плиту 1 в специальной штрабе в ней и через анкерное кольцо 6. Анкерное кольцо 6 выполняют для удобства монтажа из двух полуколец, соединенных друг с другом болтовым соединением. Диаметр цилиндрической части сопла 2 выполняют равным 1. . . 1,2 м, что позволяет опуститься в сопло монтажнику для подвески анкерного кольца 6 к тягам 5. The massive structure has a reinforced concrete or other foundation plate 1, which receives the mass of the structure and distributes the vertical pressure along the entire bottom of the plate 1. In the plate 1, through nozzles 2 are drilled, expanding downward. The upper part of each nozzle is cylindrical, and the lower is conical. In the mating zone of the cylindrical and conical parts, an annular bead is made. A jack cross beam 3 is mounted above the nozzle 2 and supported through the hollow tubular columns 4 on the foundation plate 1. The console of the jack beam 3 is connected by rods 5 to the anchor ring 6. Each of the rods 5 is passed through the console of the jack beam 3, the hollow tubular column 4, through the plate 1 in a special stub in it and through the anchor ring 6. The anchor ring 6 is made for ease of installation of two half rings connected to each other by a bolt connection. The diameter of the cylindrical part of the nozzle 2 is equal to 1.. . 1.2 m, which allows the installer to lower into the nozzle to suspend the anchor ring 6 to the rods 5.

Последовательность монтажа:
- механизировано в плите 1 бурят сопла 2;
- устанавливают колонны 4 и крестообразную фундаментную балку 3;
- на временные опоры (не показано) в сопло 2 опускают два полукольца и соединяют друг с другом в единое анкерное кольцо 6;
- сверху в отверстия в консолях домкратной балки опускают тяги 5;
- на нижние концы тяг, прошедшие сквозь кольцо 6, навинчивают крепежные гайки 7;
- временные опоры кольца (не показано) демонтируют;
- сопло заполняют щебнем или другим сыпучим материалом;
- устанавливают на щебень гидродомкрат 8 двойного действия и соединяют его поршень 9 анкерными болтами 10 с центром домкратной балки 3;
- в такой же последовательности монтируют оборудование в остальных соплах;
- объединяют гидродомкраты в группы и каждую из групп соединяют маслопроводом со своей насосной станцией;
- систему управления гидродомкратами выводят на единый пульт;
- в соответствии с программой управления креном массивного сооружения, например, Пизанской башни, оператор с пульта управления включает группу гидродомкратов, находящихся в зоне максимальной осадки плиты массивного сооружения, и каждый из гидродомкратов группы вдавливает порцию щебня под одну или другую часть массивной плиты 1, упрочняя этим грунтовое основание этой зоны под плитой;
- после вдавливания под плиту 1 очередной порции щебня оператор включает обратный ход гидродомкрата и подтягивает его к домкратной балке 3, освобождая место для очередной порции щебня, полость заполняется щебнем, и очередная порция щебня вдавливается под плиту;
- по мере упрочнения грунтового основания под плитой в работу включают дополнительные гидродомкраты и зона упрочнения грунтового основания увеличивается по площади;
- циклы продолжают до тех пор, пока прочность грунтового основания под плитой в зоне ее максимальной осадки увеличится до такой величины, что при вдавливании очередной порции щебня произойдет перераспределение напряжений контактного взаимодействия плиты с грунтовым основанием и этот наиболее осевший край плиты начнет выжиматься вверх;
- контролируя крен башни, продолжают вдавливать очередные порции щебня со стороны максимальной осадки плиты, постепенно включая новые гидродомкраты и предотвращая осадку башни со стороны минимальной осадки плиты;
- циклы продолжают до полной ликвидации крена башни и до включения в работу всех гидродомкратов по всей площади фундаментной плиты;
- контролируя осадку и крен башни, продолжают вдавливать порции щебня всеми гидродомкратами, упрочняя грунтовое основание по всей площади фундаментной плиты;
- циклы продолжают до тех пор, пока осадка массивного сооружения не начнет уменьшаться и оно не начнет выдавливаться из грунта;
- для привлечения потока туристов принудительно дают массивному сооружению обратный уклон от первоначального несколько меньшей величины, чем был ранее;
- выключают группу гидродомкратов со стороны бывшей минимальной осадки фундаментной плиты и, не допуская ее осадку, включают гидродомкраты со стороны бывшей максимальной осадки;
- циклы продолжают до установки проектного крена массивного сооружения в противоположную сторону от первоначального и на 5...10% меньше первоначального;
- продолжают контролировать крен массивного сооружения и в случае его возрастания производят корректировку крена описанным выше способом.
Installation sequence:
- mechanized in the plate 1 drill nozzle 2;
- install columns 4 and a cross-shaped foundation beam 3;
- on temporary supports (not shown), two half rings are lowered into the nozzle 2 and connected to each other in a single anchor ring 6;
- thrust 5 is lowered into the holes in the consoles of the jack beam from above;
- on the lower ends of the rods that have passed through the ring 6, fasten the mounting nuts 7;
- temporary support rings (not shown) are dismantled;
- the nozzle is filled with crushed stone or other bulk material;
- install a double-acting hydraulic jack 8 on the rubble and connect its piston 9 with anchor bolts 10 with the center of the jack beam 3;
- in the same sequence mount the equipment in the remaining nozzles;
- group the hydraulic jacks in groups and each of the groups is connected by an oil line to its pumping station;
- the hydraulic jack control system is displayed on a single remote control;
- in accordance with the roll management program of a massive structure, for example, the Leaning Tower of Pisa, the operator from the control panel includes a group of hydraulic jacks located in the zone of maximum draft of the massive structure slab, and each of the hydraulic jacks of the group presses a portion of crushed stone under one or the other part of massive plate 1, strengthening this is the soil base of this zone under the stove;
- after pressing a next portion of crushed stone under the plate 1, the operator switches on the hydraulic jack return stroke and pulls it to the jack beam 3, freeing up space for the next portion of crushed stone, the cavity is filled with crushed stone, and the next portion of crushed stone is pressed under the plate;
- as hardening of the soil base under the slab, additional hydraulic jacks are included in the work and the zone of hardening of the soil base increases in area;
- the cycles continue until the strength of the soil base under the slab in the zone of its maximum settlement increases to such a value that upon pressing another portion of crushed stone there will be a redistribution of contact interaction stresses between the slab and the ground base and this most settled edge of the slab will begin to be squeezed up;
- controlling the tower roll, continue to squeeze the next portions of crushed stone from the side of the maximum slope of the slab, gradually turning on new hydraulic jacks and preventing the tower from settling from the side of the smallest sloping of the slab;
- The cycles continue until the tower roll is completely eliminated and until all hydraulic jacks are included in the operation over the entire area of the foundation plate;
- controlling the draft and roll of the tower, they continue to squeeze portions of crushed stone with all hydraulic jacks, strengthening the soil base over the entire area of the base plate;
- cycles continue until the sediment of a massive structure begins to decrease and it begins to be squeezed out of the ground;
- in order to attract the flow of tourists, they are forced to give the massive structure a reverse deviation from the original slightly smaller value than it was before;
- turn off the group of hydraulic jacks from the side of the former minimum draft of the foundation plate and, preventing its settlement, turn on the hydraulic jacks from the side of the former maximum draft;
- the cycles continue until the installation of the design roll of the massive structure in the opposite direction from the original and 5 ... 10% less than the original;
- continue to control the roll of a massive structure and, if it grows, adjust the roll as described above.

Пример конкретной реализации. An example of a specific implementation.

Пусть необходимо управлять креном и осадкой Пизанской башни. Известно, что Пизанская башня построена более 900 лет тому назад. Высота башни 56 м. Уже в начале строительства башня начала неравномерно осаживаться и в настоящее время ее отклонение от вертикали достигает огромной величины - 4,5 м, то есть башня имеет крен от вертикали, равный α=4,6o. Такой же крен и у фундаментной плиты. Принимая диаметр башни d=16 м, площадь фундаментной плиты составит

Figure 00000002

Длина периметра стен π•d = π•16 = 50,3 м. Принимая толщину стен равной 1 м, объемная масса стен составит 2,4 т/м3. Объем стен равен V=50,3•1•56=2815 м3. Масса стен m≈2815•2,4= 6755,7 т. Массу всей башни принимают в 2 раза большей m≈6755,7•2= 13511,4 т. Управление креном осадкой башни производят двадцатью девятью пятисоттонными гидродомкратами двойного действия. Ориентировочное число домкратов
Figure 00000003

Домкраты распределяют по площади фундаментной плиты в соответствии с нагрузками на плиту, то есть в основном по контуру плиты (фиг.2). В первую группу объединяют 9 гидродомкратов со стороны максимальной осадки плиты. Во вторую центральную группу объединяют 5 гидродомкратов, находящихся справа от центрального. В третью группу - 5 гидродомкратов, находящихся слева от центрального. В четвертую группу - 9 гидродомкратов, находящихся в зоне минимальной осадки плиты.Let it be necessary to control the roll and draft of the Leaning Tower of Pisa. It is known that the Leaning Tower of Pisa was built over 900 years ago. The height of the tower is 56 m. Already at the beginning of construction, the tower began to unevenly settle and at present its deviation from the vertical reaches a huge value - 4.5 m, that is, the tower has a roll from the vertical equal to α = 4.6 o . The same foundation roll. Taking the diameter of the tower d = 16 m, the area of the foundation slab will be
Figure 00000002

The length of the perimeter of the walls is π • d = π • 16 = 50.3 m. Assuming the wall thickness is 1 m, the bulk density of the walls will be 2.4 t / m 3 . The volume of the walls is V = 50.3 • 1 • 56 = 2815 m 3 . The mass of the walls is m≈2815 • 2.4 = 6755.7 tons. The mass of the entire tower is taken to be 2 times larger m≈6755.7 • 2 = 13511.4 tons. Twenty-nine five-hundred double-acting hydraulic jacks control the heel of the tower draft. Estimated number of jacks
Figure 00000003

The jacks are distributed over the area of the foundation plate in accordance with the loads on the plate, that is, mainly along the contour of the plate (figure 2). The first group includes 9 hydraulic jacks on the side of the maximum draft of the plate. The second central group combines 5 hydraulic jacks located to the right of the central one. In the third group - 5 hydraulic jacks located to the left of the central one. In the fourth group - 9 hydraulic jacks located in the zone of minimum draft of the plate.

Последовательность подготовительных работ по управлению креном и осадкой массивного сооружения
При выполнении работ постоянно осуществляют контроль за креном сооружения и осадкой реперов, установленных по контуру сооружения. Бурение скважин и установка гидродомкратов начинается со стороны максимальной осадки поочередно. После оснащения первого сопла всеми элементами сопло засыпают щебнем и производят первоначальное обжатие щебня для исключения возникновения дополнительного крена сооружения во время производства работ. После окончания монтажа гидродомкратов первой группы производят дополнительное обжатие щебня домкратами этой группы для повышения безопасности работ. Производят бурение и оснащение сопел второй и третьей центральных групп гидродомкратов. Домкраты в соплах включают в работу последовательно во второй и третьих группах симметрично относительно центра. После оснащения очередного сопла и засыпки его щебнем для повышения безопасности работ производят предварительное обжатие щебня домкратом.
The sequence of preparatory work for the management of the roll and draft of a massive structure
When performing work, they constantly monitor the roll of the structure and the draft of benchmarks installed along the contour of the structure. Drilling of wells and installation of hydraulic jacks starts from the side of maximum draft in turn. After equipping the first nozzle with all the elements, the nozzle is covered with rubble and the initial compression of the rubble is performed to exclude the occurrence of an additional roll of the structure during work. After the installation of hydraulic jacks of the first group is completed, additional crushed stone is compressed with jacks of this group to increase the safety of work. Drill and equip the nozzles of the second and third central groups of hydraulic jacks. Jacks in nozzles are included in the work sequentially in the second and third groups symmetrically with respect to the center. After equipping the next nozzle and filling it with crushed stone, a preliminary compression of the crushed stone with a jack is carried out to increase the safety of work.

После окончания работы всех домкратов второй и третьей группы производят дополнительное обжатие щебня домкратами центральных групп. В последнюю очередь бурят и оснащают сопла четвертой группы. After the work of all the jacks of the second and third groups is completed, additional crushed stone is compressed by jacks of the central groups. Lastly, the fourth group nozzles are drilled and equipped.

Таким образом, предварительные работы завершены и в назначенный день после сбора туристов производят выравнивание крена башни. Thus, the preliminary work is completed and on the appointed day after the gathering of tourists align the tower roll.

Упрочнение грунтового основания и уменьшение крена башни до нуля
Упрочнение грунтового основания производят в первую очередь со стороны максимальной осадки фундаментной плиты сооружения, то есть домкратами первой группы.
Hardening the soil base and reducing the tower roll to zero
Hardening of the soil base is carried out primarily from the side of maximum settlement of the foundation slab of the structure, that is, jacks of the first group.

Во время работы домкратов первой группы возможно не только некоторое выправление крена башни, но и возникновение крена вправо или влево. Устранение крена вправо достигается включением в работу второй правой группы домкратов, влево - третьей левой группы домкратов. Одновременное включение в работу левой (третьей) и правой (второй) групп домкратов позволяет упрочнить грунтовое основание слева и справа. Во время упрочнения грунтового основания со стороны максимальной осадки плиты может возникнуть дополнительная осадка части плиты, где осадки минимальны (четвертая группа домкратов). Такие осадки допустимы, так как они способствуют устранению крена всего сооружения. Пo мере уменьшения крена сооружения до нуля включают четвертую группу домкратов, не допуская осадки фундаментной плиты сооружения по отношению к первоначальной. Следовательно, выправление крена сооружения происходит из-за поворота фундаментной плиты 1 вокруг оси χ, проведенной по грани плиты со стороны минимальных осадок (фиг.2). During the operation of the jacks of the first group, not only some straightening of the tower roll is possible, but also the occurrence of the roll to the right or left. The right roll is achieved by turning on the second right group of jacks, to the left - the third left group of jacks. The simultaneous inclusion in the work of the left (third) and right (second) groups of jacks allows you to strengthen the soil base on the left and right. During hardening of the soil base from the side of maximum slab upset, additional subsidence of the part of the slab where precipitation is minimal (the fourth group of jacks) may occur. Such precipitation is permissible, since they contribute to the elimination of the heel of the entire structure. As the heel of the structure decreases to zero, the fourth group of jacks is included, preventing the foundation plate of the structure from settling in relation to the initial one. Therefore, the alignment of the building roll occurs due to the rotation of the base plate 1 around the χ axis, drawn along the edge of the plate from the side of minimal precipitation (figure 2).

После уменьшения крена сооружения до нуля включают в работу гидродомкраты четвертой группы и упрочняют грунтовое основание в зоне минимальных осадок. Упрочнение грунта производится до появления минимального крена в сторону бывшего максимального крена, что свидетельствует о полном восстановлении прочности грунтового основания по всей площади фундаментной плиты. After reducing the heel of the structure to zero, hydraulic jacks of the fourth group are put into operation and the soil base is strengthened in the zone of minimal precipitation. Hardening of the soil is carried out until the minimum roll towards the former maximum roll, which indicates a complete restoration of the strength of the soil base over the entire area of the base plate.

Создание искусственного крена сооружения в обратную сторону
Обратный крен сооружения можно создать для привлечения туристов. Для устойчивости и надежной эксплуатации сооружения обратный крен должен быть меньше первоначального. Отклонение башни от вертикали должно быть 3...3,5 м, что меньше существующего (4,5 м), и составляет 3..3,6o, что меньше существующего 4,6o.
Creating an artificial roll of the structure in the opposite direction
You can create a roll back of the structure to attract tourists. For stability and reliable operation of the structure, the backward roll should be less than the initial one. The deviation of the tower from the vertical should be 3 ... 3.5 m, which is less than the existing (4.5 m), and is 3..3.6 o , which is less than the existing 4.6 o .

Для создания обратного крена сооружения включают первую и центральную группы домкратов. Центральная группа домкратов выдавливает под фундаментную плиту порцию щебня по объему в два раза меньше, чем первая группа. Четвертую группу домкратов включают в работу только в том случае, если осадка этой зоны увеличивается. To create a backward roll, the structures include the first and central groups of jacks. The central group of jacks squeezes a portion of crushed stone under the foundation plate in volume two times less than the first group. The fourth group of jacks is included in the work only if the draft of this zone increases.

Таким образом, после завершения работ несущая способность основания будет полностью восстановлена и для привлечения туристов будет создан искусственный крен сооружения в противоположную сторону. Thus, after completion of the work, the bearing capacity of the foundation will be fully restored and an artificial roll of the structure in the opposite direction will be created to attract tourists.

Высота башни увеличивается примерно на 1,2...1,3 м. The height of the tower increases by about 1.2 ... 1.3 m.

При необходимости башня может быть выдавлена из грунта дополнительно. If necessary, the tower can be squeezed out of the ground additionally.

Экономический эффект от разработанного способа - исключение обрушения исторического памятника или дорогостоящего массивного сооружения. The economic effect of the developed method is the exclusion of the collapse of a historical monument or an expensive massive structure.

Claims (1)

Способ управления креном и осадкой массивного сооружения, включающий выполнение в массивной плите фундамента сооружения сквозных сопел, установку гидродомкратов двойного действия, которые за один цикл вдавливают сыпучий материал в основание под фундаментом на ход поршня гидродомкрата, а затем возвращаются в исходное положение, причем циклы процесса продолжаются до тех пор, пока несущая способность основания не превысит вертикальное сжимающее усилие, создаваемое массой всего сооружения, и фундамент сооружения не начнет выдавливаться вверх из грунта, отличающийся тем, что в массивной плите фундамента сооружения выполняют расширяющиеся книзу центральное и боковые, размещенные симметрично от центрального сопла, вкладывают в каждое сопло стальное анкерное кольцо, состоящее из двух полуколец, устанавливают над соплом домкратную балку и соединяют ее с анкерным кольцом анкерными болтами, а гидродомкраты двойного действия размещают между фундаментной балкой и каждым соплом и соединяют их поршни с домкратной балкой, обратным ходом подтягивают гидродомкрат к домкратной балке, заполняют сопла сыпучим материалом до опорной плиты гидродомкрата, повторяющей своим контуром профиль сечения входа сопел, группой гидродомкратов двойного действия, находящихся в зоне максимальной осадки плиты массивного сооружения, упрочняют грунтовое основание, постепенно уменьшают крен массивного сооружения, действуя синхронно группой гидродомкратов, по мере уменьшения крена сооружения подключают следующие дополнительные группы гидродомкратов двойного действия, увеличивая зону упрочнения грунтового основания под подошвой плиты по площади и циклы продолжают до полной ликвидации крена массивного сооружения и до включения в работу всех гидродомкратов по всей площади подошвы плиты. A method of controlling the roll and draft of a massive structure, including performing through nozzles in a massive foundation plate of the structure, installing double-acting hydraulic jacks that press the bulk material into the base under the foundation for the hydraulic jack piston during one cycle, and then return to their original position, and the process cycles continue until the bearing capacity of the base exceeds the vertical compressive force created by the mass of the entire structure, and the foundation of the structure begins to extrude upward from the ground, characterized in that in the massive slab of the foundation of the building, central and lateral expanding downward, symmetrically placed from the central nozzle, are inserted into each nozzle, a steel anchor ring consisting of two half rings, a jack beam is installed over the nozzle and connected to the anchor ring with anchor bolts, and double-acting hydraulic jacks are placed between the foundation beam and each nozzle and their pistons are connected to the jack beam, and the hydraulic jack is pulled back to the jack b Then, fill the nozzles with bulk material to the base plate of the hydraulic jack, repeating with its contour the profile of the nozzle inlet section, a group of double-acting hydraulic jacks located in the zone of maximum settlement of the massive structure plate, strengthen the soil base, gradually reduce the roll of the massive structure, acting simultaneously with the group of hydraulic jacks, as reducing the roll of the structure connect the following additional groups of double-acting hydraulic jacks, increasing the hardening zone of the soil base under the sole of the first plate in terms of area and cycles continue until the complete elimination of the heel of the massive structure and before the inclusion of all hydraulic jacks over the entire area of the bottom of the plate.
RU2001120216A 2001-07-18 2001-07-18 Procedure controlling list and sinking of solid mass structure RU2211288C2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU2001120216A RU2211288C2 (en) 2001-07-18 2001-07-18 Procedure controlling list and sinking of solid mass structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2001120216A RU2211288C2 (en) 2001-07-18 2001-07-18 Procedure controlling list and sinking of solid mass structure

Publications (2)

Publication Number Publication Date
RU2001120216A RU2001120216A (en) 2003-06-20
RU2211288C2 true RU2211288C2 (en) 2003-08-27

Family

ID=29245661

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2001120216A RU2211288C2 (en) 2001-07-18 2001-07-18 Procedure controlling list and sinking of solid mass structure

Country Status (1)

Country Link
RU (1) RU2211288C2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2603783C1 (en) * 2015-08-27 2016-11-27 Игорь Яковлевич Харченко Method of leveling buildings and structures
RU2691800C2 (en) * 2017-06-14 2019-06-18 федеральное государственное бюджетное образовательное учреждение высшего образования "Самарский государственный технический университет" Method for control of spatial position of foundation
CN111622282A (en) * 2020-06-19 2020-09-04 山东建固特种专业工程有限公司 Multifunctional jet drilling tool, forced landing and inclination correcting equipment capable of realizing precise directional disturbance and forced landing and inclination correcting method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2603783C1 (en) * 2015-08-27 2016-11-27 Игорь Яковлевич Харченко Method of leveling buildings and structures
RU2691800C2 (en) * 2017-06-14 2019-06-18 федеральное государственное бюджетное образовательное учреждение высшего образования "Самарский государственный технический университет" Method for control of spatial position of foundation
CN111622282A (en) * 2020-06-19 2020-09-04 山东建固特种专业工程有限公司 Multifunctional jet drilling tool, forced landing and inclination correcting equipment capable of realizing precise directional disturbance and forced landing and inclination correcting method
CN111622282B (en) * 2020-06-19 2021-05-18 山东建固特种专业工程有限公司 Multifunctional jet drilling tool, forced landing and inclination correcting equipment capable of realizing precise directional disturbance and forced landing and inclination correcting method

Similar Documents

Publication Publication Date Title
CN102864795B (en) Light steel factory post foundation suitable for sedimentation of filled-in ground and construction method
EP0170503B1 (en) Ground treatment
RU2382146C1 (en) Method for straightening of slant in building erected on pile foundation
US5797704A (en) Pier foundation and method of installation
CN102704705A (en) Building long-stroke redescending-free multi-point synchronous jacking method
CN100513695C (en) Repair and reinforcement system of existing structure using reaction force of pressurizing means and method thereof
CN105133575A (en) Suspended formwork supporting device for casting lining on surface of underground continuous wall and construction method
CN1131912C (en) Variable supporting-plate club-footed embedded pile and its forming method
RU2211288C2 (en) Procedure controlling list and sinking of solid mass structure
JP3126896B2 (en) Restoration method for uneven settlement structures
CN109024612B (en) Large-span foundation pit supporting structure
CN220117272U (en) Interior step precast concrete embankment retaining wall
CN111734166A (en) Detachable conversion device and reverse dismantling construction method using same
CN201433398Y (en) External support system for supporting open caisson structure
CN216713138U (en) Building reinforcement is rectified and is traded and prop device
EP0413422B1 (en) Foundation construction method
CN202809636U (en) Light steel plant column foundation adapted to filling subgrade settlement
CN110792282B (en) Transformation method of frame column without support underpinning
CN213358613U (en) Pulling device for steel pipe slope protection pile
RU2236508C2 (en) Connection unit for two-leg eccentrically loaded column with foundation and method for restoring design level of foundation and building frame
RU2319812C2 (en) Method for foundation movement control with the use of jet engines
JP3523223B2 (en) Demolition equipment for high-rise buildings
DE715314C (en) Foundation for buildings
RU2333322C1 (en) Method for elevating and levelling buldings
RU2244783C1 (en) Method for connection of eccentrically loaded column with stepped foundation