RU2014124598A - METHOD FOR PREPARING WEIR CONCRETE WEIR - Google Patents

METHOD FOR PREPARING WEIR CONCRETE WEIR Download PDF

Info

Publication number
RU2014124598A
RU2014124598A RU2014124598/13A RU2014124598A RU2014124598A RU 2014124598 A RU2014124598 A RU 2014124598A RU 2014124598/13 A RU2014124598/13 A RU 2014124598/13A RU 2014124598 A RU2014124598 A RU 2014124598A RU 2014124598 A RU2014124598 A RU 2014124598A
Authority
RU
Russia
Prior art keywords
layer
stone
concrete
laying
lower walls
Prior art date
Application number
RU2014124598/13A
Other languages
Russian (ru)
Other versions
RU2593780C2 (en
Inventor
Юрий Александрович Ландау
Original Assignee
ПАО "Укргидропроект"
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ПАО "Укргидропроект" filed Critical ПАО "Укргидропроект"
Priority to RU2014124598/13A priority Critical patent/RU2593780C2/en
Publication of RU2014124598A publication Critical patent/RU2014124598A/en
Application granted granted Critical
Publication of RU2593780C2 publication Critical patent/RU2593780C2/en

Links

Landscapes

  • Revetment (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

Способ выполнения плотины, состоящей из верховой и низовой стенок, из укатанного бетона, соединенных продольными бетонными стенками с внутренними полостями между ними, заполненными камнем, с послойной укладкой и уплотнением бетона в верховую и низовую стенки и параллельно укладкой и уплотнением камня во внутренние полости, с упрочнением цементным раствором, отличающийся тем, что после укладки и уплотнения слоя бетона в верховую и низовую стенки, укладки соответствующего слоя камня во внутреннюю полость между верховой и низовой стенкой производят упрочнение цементным раствором поверхности слоя камня в пределах участков возведения продольных стенок, между которыми образуются ячейки, заполненные камнями, с дальнейшим уплотнением всей поверхности слоя катками с образованием на участках, упрочненных цементным раствором продольных стенок, соединяющих верховую и низовую стенки, а между ними - вертикальных ячеек, заполненных камнем.A method of making a dam consisting of upper and lower walls, of rolled concrete, connected by longitudinal concrete walls with internal cavities between them, filled with stone, with layer-by-layer laying and compaction of concrete in the upper and lower walls and parallel with laying and compaction of the stone in the internal cavities, with hardening with cement mortar, characterized in that after laying and compacting the concrete layer in the upper and lower walls, laying the corresponding layer of stone in the inner cavity between the upper and lower walls cement layer hardening is performed on the surface of the stone layer within the longitudinal wall erection sections, between which cells filled with stones are formed, with further compaction of the layer layer with rollers with the formation of longitudinal walls connecting the upper and lower walls in the areas hardened by cement, and between them vertical cells filled with stone.

Claims (1)

Способ выполнения плотины, состоящей из верховой и низовой стенок, из укатанного бетона, соединенных продольными бетонными стенками с внутренними полостями между ними, заполненными камнем, с послойной укладкой и уплотнением бетона в верховую и низовую стенки и параллельно укладкой и уплотнением камня во внутренние полости, с упрочнением цементным раствором, отличающийся тем, что после укладки и уплотнения слоя бетона в верховую и низовую стенки, укладки соответствующего слоя камня во внутреннюю полость между верховой и низовой стенкой производят упрочнение цементным раствором поверхности слоя камня в пределах участков возведения продольных стенок, между которыми образуются ячейки, заполненные камнями, с дальнейшим уплотнением всей поверхности слоя катками с образованием на участках, упрочненных цементным раствором продольных стенок, соединяющих верховую и низовую стенки, а между ними - вертикальных ячеек, заполненных камнем. A method of making a dam consisting of upper and lower walls, of rolled concrete, connected by longitudinal concrete walls with internal cavities between them, filled with stone, with layer-by-layer laying and compaction of concrete in the upper and lower walls and parallel with laying and compaction of the stone in the internal cavities, with hardening with cement mortar, characterized in that after laying and compacting the concrete layer in the upper and lower walls, laying the corresponding layer of stone in the inner cavity between the upper and lower walls cement layer hardening is performed on the surface of the stone layer within the longitudinal wall erection sections, between which cells filled with stones are formed, with further compaction of the layer layer with rollers with the formation of longitudinal walls connecting the upper and lower walls in the areas hardened by cement, and between them vertical cells filled with stone.
RU2014124598/13A 2014-06-17 2014-06-17 Method of making dam from rolled concrete RU2593780C2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU2014124598/13A RU2593780C2 (en) 2014-06-17 2014-06-17 Method of making dam from rolled concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2014124598/13A RU2593780C2 (en) 2014-06-17 2014-06-17 Method of making dam from rolled concrete

Publications (2)

Publication Number Publication Date
RU2014124598A true RU2014124598A (en) 2015-12-27
RU2593780C2 RU2593780C2 (en) 2016-08-10

Family

ID=55023219

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2014124598/13A RU2593780C2 (en) 2014-06-17 2014-06-17 Method of making dam from rolled concrete

Country Status (1)

Country Link
RU (1) RU2593780C2 (en)

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU43841A1 (en) * 1934-10-11 1935-07-31 Н.Н. Маслов The method of construction of concrete and reinforced concrete hydraulic structures
JPH09158158A (en) * 1995-12-05 1997-06-17 Fujita Corp Filling type concrete dam and construction method thereof
RU2495190C2 (en) * 2011-08-23 2013-10-10 Публичное акционерное общество "Укргидропроект" Gravity dam with expanded joints

Also Published As

Publication number Publication date
RU2593780C2 (en) 2016-08-10

Similar Documents

Publication Publication Date Title
MX2010008600A (en) Method of constructing an insulated shallow pier foundation building.
KR20180084411A (en) Construction method of lower pier casion footing using PCC structure
PH12019500299A1 (en) Caisson block construction method and caisson block structure
PL3249105T3 (en) Precast concrete foundation pile, method of grouting and manufacturing
MX2017011636A (en) Hard road construction method for natural groundwater recharge.
PE20140062A1 (en) DISPOSABLE FORMWORK THAT CAN BE ASSEMBLED TO BUILD MODULAR FORMWORK FOR THE MANUFACTURE OF CONCRETE FOUNDATIONS
MY176153A (en) Storage tank construction method
MD983Y (en) Process for plastering construction surfaces using the formwork
RU2014124598A (en) METHOD FOR PREPARING WEIR CONCRETE WEIR
CN204435431U (en) Basement bottom board waterproof construction
UA109731C2 (en) METHOD OF ROLLING FROM CONCRETE CONCRETE
CN106088446A (en) Fine-stone concrete blockwork and the method for auxiliary body of wall top skew brick construction thereof
RU2011108866A (en) METHOD FOR CONSTRUCTION OF THE BASE AND ITS DEVICE
NZ628259A (en) Concrete shuttering
RU2014135048A (en) Arch bridge
RU2014145407A (en) METHOD FOR PRODUCING MULTILAYER BUILDING PRODUCTS
JP1773455S (en) Foundation blocks
JP1773456S (en) Foundation blocks
JP1773262S (en) Foundation blocks
JP1773457S (en) Foundation blocks
JP1773337S (en) Foundation blocks
HUP1900090A1 (en) Method for constructing wall structure using hemp concrete bricks
CN203361188U (en) Post-cast strip temporary retaining wall structure of basement side wall
UA111943U (en) METHOD OF RESTORATION OF DRYING CHANNELS WITH THE HELP OF GABIONS
PL411308A1 (en) Method for producing precast reinforced concrete foundation slabs for the high voltage pillars, with increased mechanical properties