RU2012809C1 - Method for construction of transport gallery on permanent open pit edge - Google Patents

Method for construction of transport gallery on permanent open pit edge Download PDF

Info

Publication number
RU2012809C1
RU2012809C1 SU4940441A RU2012809C1 RU 2012809 C1 RU2012809 C1 RU 2012809C1 SU 4940441 A SU4940441 A SU 4940441A RU 2012809 C1 RU2012809 C1 RU 2012809C1
Authority
RU
Russia
Prior art keywords
gallery
trench
construction
structures
transport
Prior art date
Application number
Other languages
Russian (ru)
Inventor
В.А. Берсенев
А.В. Фролов
Original Assignee
Берсенев Виктор Анатольевич
Фролов Александр Владимирович
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Берсенев Виктор Анатольевич, Фролов Александр Владимирович filed Critical Берсенев Виктор Анатольевич
Priority to SU4940441 priority Critical patent/RU2012809C1/en
Application granted granted Critical
Publication of RU2012809C1 publication Critical patent/RU2012809C1/en

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

FIELD: opencast mining. SUBSTANCE: provided prior to formation of trench 1 parallel to its design contour is auxiliary trench 2 for delivery of equipment and structures to construction site. Arranged from trench 2 are access ramps 3 to each horizon. Then, trench 1 is formed for gallery, gallery supports are installed and mounting equipment and structures are delivered. EFFECT: higher efficiency. 2 dwg

Description

Изобретение относится к горной промышленности и может быть использовано при открытой разработке месторождений полезных ископаемых для строительства транспортной галереи на постоянном борту карьера. The invention relates to the mining industry and can be used in the open development of mineral deposits for the construction of a transport gallery on a permanent side of the quarry.

Известен способ строительства транспортной галереи на постоянном борту карьера, включающий формирование траншеи на борту путем срезания бульдозером части пород уступа в ее проектных контурах и перемещение их на нижележащий уступ, сооружение опор под галерею, доставку монтажного оборудования и конструкций галереи на строительно-монтажные площадки на горизонтах по бермам шириной 15 м на каждом горизонте. There is a method of constructing a transport gallery on a permanent quarry, including the formation of a trench on board by cutting a portion of the ledge rocks in its design contours with a bulldozer and moving them to the underlying ledge, constructing supports for the gallery, delivering installation equipment and gallery structures to construction sites at horizons 15 m wide berm on each horizon.

Однако этот способ характеризуется необходимостью выемки значительного дополнительного объема вскрыши от разноса борта карьера для строительно-монтажных площадок и расширения берм безопасности. However, this method is characterized by the need to excavate a significant additional volume of overburden from the spacing of the pit side for construction sites and the expansion of safety berms.

Известен также способ строительства транспортной галереи на постоянном борту карьера, включающий формирование траншеи на борту путем срезания бульдозером части пород уступа в ее проектных контурах и перемещение их на нижележащий уступ, доставку монтажного оборудования и конструкций галереи к месту ее строительства по транспортной коммуникации, расположенной на основании траншеи, возведение галереи на основании траншеи с монтажных площадок, расположенных на основании траншеи. There is also known a method of building a transport gallery on a permanent quarry, including the formation of a trench on board by cutting a portion of the ledge rocks in its design contours with a bulldozer and moving them to the underlying ledge, delivery of installation equipment and gallery structures to its construction site via transport communication, located on the base trenches, erection of a gallery on the basis of the trench from mounting sites located on the basis of the trench.

Однако в этом способе имеют место большие затраты на строительство за счет выемки большого дополнительного объема вскрыши от разноса борта карьера под основание траншеи, ширина которого увеличивается на ширину транспортной коммуни- кации и полосы монтажные площадки. However, in this method, there are large construction costs due to excavation of a large additional volume of overburden from the sidewall of the quarry under the base of the trench, the width of which increases by the width of the transport communication and strip installation sites.

Цель изобретения - сокращение затрат на строительство путем уменьшения объема вскрыши. The purpose of the invention is to reduce construction costs by reducing the volume of overburden.

Поставленная цель достигается тем, что в известном способе, включающем формирование траншеи на борту путем срезания бульдозером части пород уступа в ее проектных контурах и перемещение их на нижележащий уступ, сооружение опор под галерею, доставку монтажного оборудования и конструкций галереи к месту ее строительства, возведение галереи, перед формированием траншеи дополнительно формируют параллельно ее проектному контуру траншею для доставки по ней оборудования и конструкций к месту строительства, проводят съезды из указанной траншеи на каждый горизонт, после чего начинают формировать траншею под галерею. This goal is achieved by the fact that in the known method, including the formation of trenches on board by cutting a portion of the ledge rocks in its design contours with a bulldozer and moving them to the underlying ledge, constructing supports for the gallery, delivering installation equipment and gallery structures to the place of its construction, erecting the gallery , before forming the trench, they additionally form a trench parallel to its design contour to deliver equipment and structures along it to the construction site, conduct congresses from the specified tranche it on each horizon, after which they begin to form a trench under the gallery.

На фиг. 1 представлен борт карьера во время строительства галереи. In FIG. 1 shows the side of the quarry during the construction of the gallery.

Способ заключается в следующем. Бульдозером на постоянном борту карьера параллельно проектному контуру траншеи 1 под транспортную галерею формируют траншею 2 для доставки по ней оборудования и конструкций галереи. Из траншеи 2 на каждый горизонт к месту строительства галереи проводят съезды 3. Затем на борту формируют траншею 1 под транспортную галерею путем срезания бульдозером части пород уступа в ее проектных контурах и перемещением их на нижележащий уступ. На каждом горизонте под транспортную галерею сооружают опоры 4. По траншее 2 и съездам 3 на каждый горизонт к месту строительства доставляют монтажное оборудование 5. На тракторной тележке 6 по траншее 2 к месту строительства доставляют конструкции галереи. Монтажным оборудованием 5, размещаемым на предохра- нительных бермах, в траншее 1 и на опорах 4 возводят галерею 7. The method is as follows. A bulldozer on the permanent side of the quarry parallel to the design contour of the trench 1 under the transport gallery form a trench 2 for delivery of equipment and gallery structures along it. From trench 2, exits 3 are conducted to each horizon to the gallery construction site. Then, trench 1 is formed on board to form the transport gallery by bulldozing a part of the ledge rocks in its design contours and moving them to the underlying ledge. On each horizon, supports 4 are built under the transport gallery. Mounting equipment 5 is delivered to trench 2 and ramps 3 to each construction site to the construction site. On a tractor trolley 6 along trench 2 gallery structures are delivered to the construction site. Gallery 5 is being erected by mounting equipment 5, placed on the safety berms, in the trench 1 and on the supports 4.

Этот способ позволяет сократить затраты на строительство транспортной галереи путем уменьшения объема вскрыши в карьере. (56) Мельников Н. Н. и др. Перспективы перехода на циклично-поточную технологию. Горный журнал, 1987, N 7, с. 21-24. This method allows to reduce the cost of building a transport gallery by reducing the volume of overburden in the quarry. (56) Melnikov N.N. et al. Prospects for the transition to cyclic-flow technology. Mountain Journal, 1987, N 7, p. 21-24.

Берсенев В. А. , Тетерин Ю. А. Бестранспортный способ проведения и объемы конвейерной траншеи. Асбест. Труды ВНИИпроектасбест, вып. 22, 1980, с. 41-42. Bersenev V.A., Teterin Yu.A. Transportless way of carrying out and volumes of the conveyor trench. Asbestos. Proceedings of VNIIproektasbest, vol. 22, 1980, p. 41-42.

Claims (1)

СПОСОБ СТРОИТЕЛЬСТВА ТРАНСПОРТНОЙ ГАЛЕРЕИ НА ПОСТОЯННОМ БОРТУ КАРЬЕРА, включающий формирование траншеи на борту путем срезания бульдозером части пород уступа в ее проектных контурах и перемещение их на нижележащий уступ, сооружение опор под галерею, доставку монтажного оборудования и конструкций галереи к месту ее строительства, возведение галереи, отличающийся тем, что, с целью сокращения затрат на строительство путем уменьшения объема вскрытий перед формированием траншеи, дополнительно формируют параллельно ее проектному контуру вспомогательную траншею для доставки по ней оборудования и конструкций к месту строительства, проводят съезды из указанной траншеи на каждый горизонт, после чего начинают формировать траншеи под галерею. METHOD FOR CONSTRUCTING A TRANSPORT GALLERY ON A PERMANENT CAREER BOARD, including forming a trench on board by cutting a part of the ledge rocks in its design contours and moving them to the underlying ledge, constructing supports for the gallery, delivering installation equipment and gallery structures to the place of construction, gallery erection characterized in that, in order to reduce construction costs by reducing the volume of openings before the formation of the trench, it is additionally formed parallel to its design contour spomogatelnuyu trench for the delivery of its equipment and structures to the construction site, conduct congresses of said trenches to each horizon, and then begin to form a trench under the gallery.
SU4940441 1991-05-30 1991-05-30 Method for construction of transport gallery on permanent open pit edge RU2012809C1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU4940441 RU2012809C1 (en) 1991-05-30 1991-05-30 Method for construction of transport gallery on permanent open pit edge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU4940441 RU2012809C1 (en) 1991-05-30 1991-05-30 Method for construction of transport gallery on permanent open pit edge

Publications (1)

Publication Number Publication Date
RU2012809C1 true RU2012809C1 (en) 1994-05-15

Family

ID=21576740

Family Applications (1)

Application Number Title Priority Date Filing Date
SU4940441 RU2012809C1 (en) 1991-05-30 1991-05-30 Method for construction of transport gallery on permanent open pit edge

Country Status (1)

Country Link
RU (1) RU2012809C1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2521191C1 (en) * 2013-02-12 2014-06-27 Федеральное государственное бюджетное учреждение науки Институт горного дела Уральского отделения Российской академии наук (ИГД УрО РАН) Access ramp for trucks in open-pit mine

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2521191C1 (en) * 2013-02-12 2014-06-27 Федеральное государственное бюджетное учреждение науки Институт горного дела Уральского отделения Российской академии наук (ИГД УрО РАН) Access ramp for trucks in open-pit mine

Similar Documents

Publication Publication Date Title
RU2528704C1 (en) Method of open working out of steep deposits of platform shape
RU2652234C1 (en) Method of open development of inclined deposits with the use of spoil banks
RU2012809C1 (en) Method for construction of transport gallery on permanent open pit edge
RU2632606C1 (en) Method for depreservation steeply inclined nonactive sidewalls
RU2064582C1 (en) Method for openpit mining of minerals
SU1668667A1 (en) Method for combination mining of gently sloping seams
RU2632604C1 (en) Method for forming and depreserving steep temporary nonactive walls when developing deep laying deposits
RU2425220C1 (en) Method for formation of steeply inclined transport access track
RU2114307C1 (en) Method for opencast mining of flooded mineral deposits
RU2685587C1 (en) Method for open development of steeply-dipping deposits with application of combined temporary non-working sides
CN103615008B (en) Overlength superelevation difference single span formula cableway terminal foundations the stone base of a column side cuts excavation construction engineering method open
RU2231642C1 (en) Method of barring and development of elongated in width and gradient coal fields with flat dipping and inclined beds of big thickness
Plotnikov et al. Features of new sites designing on quarry fields of the existing open pit mines of Kuzbass
RU2247241C1 (en) Method for extraction of mineral resources
RU2294433C1 (en) Method for closely located ore bodies cutting with separate pits
RU2685583C1 (en) Method for open development of steep deposits with application of multistage temporarily non-working sides
RU2013550C1 (en) Method for open-pit mining of steeply dipping mineral deposits
RU2702779C1 (en) Method for block-modular construction of structures in foundation pits and buried structure for military infrastructure facilities
RU2091583C1 (en) Method of mining of mineral upper horizons
JP2620111B2 (en) Excavation construction method for long space
RU2106494C1 (en) Method for handling overburden earth
RU2070292C1 (en) Method for stripping and development of inclined and steeply dipping deposits
SU1008450A1 (en) Method for open-pit working of gently sloping mineral deposits
RU2139429C1 (en) Method for opencast mining of flat and sloping deposits of minerals
SU1758226A1 (en) Method of excavating steep trench