RU2004803C1 - Method for opencast mining of mineral deposits - Google Patents

Method for opencast mining of mineral deposits

Info

Publication number
RU2004803C1
RU2004803C1 SU4885660A RU2004803C1 RU 2004803 C1 RU2004803 C1 RU 2004803C1 SU 4885660 A SU4885660 A SU 4885660A RU 2004803 C1 RU2004803 C1 RU 2004803C1
Authority
RU
Russia
Prior art keywords
mining
worked out
block
mineral deposits
adjacent
Prior art date
Application number
Other languages
Russian (ru)
Inventor
Виктор Болеславович Рутковский
Original Assignee
Виктор Болеславович Рутковский
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Виктор Болеславович Рутковский filed Critical Виктор Болеславович Рутковский
Priority to SU4885660 priority Critical patent/RU2004803C1/en
Application granted granted Critical
Publication of RU2004803C1 publication Critical patent/RU2004803C1/en

Links

Landscapes

  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

Изобретение относитс  к горной промышленности , в частности к использованию при разработке всех типов месторождений открытым способом. Цель изобретени  - повышение интенсивности отработки при обеспечении ритмичности работ. Отработку карьерных полей ведут смежными блоками. Последующий блок включает в отработку после достижени  в предыдущем среднего показател  текущего коэффициента вскрышки, после чего отрабатывают их одновременно. После отработки смежного блока его выработанное пространство используетс  под внутренние отвалы последующих. 1 ил.The invention relates to the mining industry, in particular to use in open pit mining of all types of deposits. The purpose of the invention is to increase the intensity of mining while ensuring the rhythm of work. Quarry field mining is carried out by adjacent blocks. The subsequent block is put into operation after reaching the current average overburden ratio in the previous average, after which they are worked out simultaneously. After working off an adjacent block, its worked out space is used for internal dumps of subsequent ones. 1 ill.

Description

Изобретение относитс  к горной промышленности , в частности к использованию при разработке всех типов месторождений открытым способом.The invention relates to the mining industry, in particular to use in open pit mining of all types of deposits.

Известен способ открытой разработки крутопадающих пластов, при котором отработку ведут на полную глубину карьера по транспортной системе поперчными заход- ками с общим направлением развити  фронта работ по простиранию пластов и организацией внутренних отвалов,  русы которых располагают на одинаковых высотных отметках с одновременно отрабатываемыми породными уступами 1.There is a known method for open-cast mining of steeply falling strata, in which mining is carried out to the full depth of the quarry through transverse crossings with the general direction of development of the front of work on strike of strata and the organization of internal dumps, the beds of which are located at the same elevations with simultaneously worked out rock ledges 1.

Недостатками известного способа  вл ютс  большие капитальные затраты при проведении первоначальной разрезной траншеи на полную глубину карьера, что св зано с высоким текущим коэффициентом вскрыши, небольшим фронтом вскрышных и добычных работ, формирующегос  попе- речными заходками, что отдал ет сроки освоени  производственной мощности и удлин ет сроки строительства карьера, а также трудности с сохранением одинаковых высотных отметок  русов внутренних отвалов с одновременно отрабатываемыми породными уступами.The disadvantages of this method are the high capital costs during the initial cutting trench to the full depth of the quarry, which is associated with a high current stripping ratio, a small front of stripping and mining operations, which is formed by transverse cuts, which delays the development of production capacity and lengthens the terms of the construction of the quarry, as well as difficulties with maintaining the same elevations of the internal dumps with simultaneously practiced rock ledges.

Наиболее близким к предлагаемому по технической сущности  вл етс  способ открытой разработки крутопадающих пластов , при котором карьерное поле раздел ют на блоки, которые отрабатывают поочередно продольными заходками с направлением подвигани  фронта работ вкрест простирани  пласта, а породы вскрыши располагают в выработанном пространстве смежного блока, причем отработку начинают с наиболее угленасыщенного участка с вывозом породы на внешние отва- лы 2f.Closest to the proposed technical essence is a method of open development of steeply falling formations, in which the quarry field is divided into blocks that are worked out alternately by longitudinal approaches with the direction of movement of the work front across the strike of the formation, and overburden rocks are located in the worked-out space of the adjacent block, and mining start from the most coal-saturated area with the removal of the rock to the external dumps 2f.

Недостатки этого способа заключаютс  в неравномерности режима горных работ, т.е. отработке каждого блока текущий коэффициент вскрыши посто нно достигает сео- его максимального значени , а также в трудности с наращиванием производственной мощности карьера.The disadvantages of this method are the unevenness of the mining regime, i.e. for each block, the current stripping ratio is constantly reaching its maximum value, as well as in difficulties with increasing the production capacity of the quarry.

00

55

00

55

00

55

00

Цель изобретени  состоит в повышении эффективности отработки месторождени .An object of the invention is to increase the efficiency of field development.

На чертеже представлена принципиальна  схема осуществлени  предлагаемого способа.The drawing shows a schematic diagram of the implementation of the proposed method.

Поставленна  цель достигаетс  тем, что отработка карьерных полей производитс  по новой технологии смежными блоками, когда каждый последующий блок включаетс  в работу после достижени  в предыдущем среднего показател  текущего коэффициента вскрыши.The goal is achieved in that mining of quarries is carried out by adjacent blocks in accordance with the new technology, when each subsequent block is put into operation after reaching the current average overburden ratio in the previous average.

Предлагаемый способ открытой разработки месторождений полезных ископаемых реализован следующим образом. Карьерное поле раздел ют на блоки. Отработку начинают с наиболее угленасыщенного блока и при достижении в нем среднего показател  текущего коэффициента вскрыши включают в работу очередной блок с вывозом породы на внешние отвалы. После отработки смежного блока его выработанное пространство используетс  под внутренние отвалы последующих. Отработку блоков ведут продольными заходкамм с направлением подвигани  фронта работ вкрест простирани  пласта. Так продолжаетс  до полной отработки полезного ископаемого с последующим возведением в выработанном пространстве внутренних от- валор.The proposed method of open development of mineral deposits is implemented as follows. The quarry field is divided into blocks. Development begins with the most coal-saturated block and when it reaches the average indicator of the current stripping ratio, the next block is put into operation with the removal of the rock to external dumps. After working off an adjacent block, its worked out space is used for internal dumps of subsequent ones. Block mining is carried out by longitudinal approaches with the direction of the front movement across the strike of the formation. This continues until the complete mining of the mineral with the subsequent construction of the internal waste in the worked out space.

В сравнении с известными способами предлагаемый обеспечивает ритмичную работу предпри ти  и позвол ет наращивать производственную мощность за счет параллельной работы смежных блоков, что ведет к увеличению прибыли и сокращает срок отработки карьера.In comparison with the known methods, the proposed one provides the rhythmic operation of the enterprise and allows one to increase production capacity due to the parallel operation of adjacent blocks, which leads to an increase in profit and shortens the pit mining life.

(56) Барабанов В.Ф,, Томаков П.И., Дерга- чев И.И. Разработка крутых и наклонных пластов открытым способом с размещением пустых пород в выработанном пространстве -Уголь, 1959, № 12.С.6-8.(56) Drums V.F., Tomakov P.I., Dergachev I.I. The development of steep and inclined formations in an open way with the placement of waste rock in a worked-out space - Ugol, 1959, No. 12. P. 6-8.

Авторское свидетельство СССР № 337516, кл. Е21 С 41/00, 1961.USSR copyright certificate No. 337516, cl. E21 C 41/00, 1961.

Claims (1)

Формула изобретени The claims СПОСОБ ОТКРЫТОЙ РАЗРАБОТКИ МЕСТОРОЖДЕНИЙ ПОЛЕЗНЫХ ИСКОПАЕМЫХ , включающий отработку карьера смежными блоками, отличающийс  тем, что, с целью повышени  интенсивностиMETHOD FOR OPEN DEVELOPMENT OF MINERAL DEPOSITS FIELDS, including quarrying of adjacent blocks, characterized in that, in order to increase the intensity процесса отработки при обеспечении рит- 55 мичности работ, по достижении в отрабатываемом блоке текущего коэффициента вскрыши, равного его среднему показателю , начинают отрабатывать смежный блок, после чего ведут их одновременную отработку .the mining process, while ensuring the rhythm of work, when the current stripping ratio is reached in the processing block equal to its average value, the adjacent block is started to be worked out, and then they are worked out simultaneously. }} «,,„.,.s . .„.,  “,,„.,. S. . „., Z 2::ix zi 2 PtX; sZ 2 :: ix zi 2 PtX; s sjssar;sjssar; .у. лу fxxv. , . . . . Jb ,VС.y. lu fxxv. ,. . . . Jb, VС XX J-/-e-p-0-(|-D-I OOOC I WJ - / - e-p-0- (| -D-I OOOC I W
SU4885660 1990-10-02 1990-10-02 Method for opencast mining of mineral deposits RU2004803C1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU4885660 RU2004803C1 (en) 1990-10-02 1990-10-02 Method for opencast mining of mineral deposits

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU4885660 RU2004803C1 (en) 1990-10-02 1990-10-02 Method for opencast mining of mineral deposits

Publications (1)

Publication Number Publication Date
RU2004803C1 true RU2004803C1 (en) 1993-12-15

Family

ID=21547033

Family Applications (1)

Application Number Title Priority Date Filing Date
SU4885660 RU2004803C1 (en) 1990-10-02 1990-10-02 Method for opencast mining of mineral deposits

Country Status (1)

Country Link
RU (1) RU2004803C1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2005124104A1 (en) * 2004-06-21 2005-12-29 Bhp Billiton Innovation Pty Ltd Method, apparatus and computer program for scheduling the extraction of a resource and for determining the net present value of an extraction schedule
AU2005254579B2 (en) * 2004-06-21 2010-03-11 Bhp Billiton Innovation Pty Ltd Method, apparatus and computer program for scheduling the extraction of a resource and for determining the net present value of an extraction schedule
US7853439B2 (en) 2005-04-11 2010-12-14 Bhp Billiton Innovation Pty Ltd. Mining optimisation
CN101006249B (en) * 2004-06-21 2013-05-22 Bhp比利顿创新公司 Method and apparatus for scheduling the extraction of a resource and for determining the net present value of an extraction schedule

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2005124104A1 (en) * 2004-06-21 2005-12-29 Bhp Billiton Innovation Pty Ltd Method, apparatus and computer program for scheduling the extraction of a resource and for determining the net present value of an extraction schedule
AU2005254579B2 (en) * 2004-06-21 2010-03-11 Bhp Billiton Innovation Pty Ltd Method, apparatus and computer program for scheduling the extraction of a resource and for determining the net present value of an extraction schedule
US8082167B2 (en) 2004-06-21 2011-12-20 Bhp Billiton Innovation Pty Ltd. Method, apparatus and computer program for scheduling the extraction of a resource and for determining the net present value of an extraction schedule
CN101006249B (en) * 2004-06-21 2013-05-22 Bhp比利顿创新公司 Method and apparatus for scheduling the extraction of a resource and for determining the net present value of an extraction schedule
US7853439B2 (en) 2005-04-11 2010-12-14 Bhp Billiton Innovation Pty Ltd. Mining optimisation

Similar Documents

Publication Publication Date Title
RU2004803C1 (en) Method for opencast mining of mineral deposits
SU1668667A1 (en) Method for combination mining of gently sloping seams
SU1756567A1 (en) Method for mineral opencast mining
SU1083662A1 (en) Method of mining steep-slope ore-bodies
RU2762170C1 (en) Method for developing thin and low-powered steel-falling ore bodies
RU1828921C (en) Method for working pillars in room-and-pillar mining system
SU1665038A1 (en) Method of driving narrow-face workings with separate coal and rock extraction
RU2187647C1 (en) Method of softening of surface layer of opencast benches in seasonal ground freezing
SU1076579A1 (en) Method of producing natural stone blocks
SU1129355A1 (en) Method of mining thick inclined mineral deposits
SU1652562A1 (en) Method for roof control in outburst-risky seams
RU2012805C1 (en) Method for driving of development working in mineral bed at large depth
RU1770571C (en) Method for making raise mine working
SU878937A1 (en) Ore mining method
SU1188326A1 (en) Method of mining bedded deposits
SU1694897A1 (en) Method of complete pillar drawing
RU2068094C1 (en) Method for sloping of benches
SU1314065A1 (en) Method of mining ore bodies
RU1810545C (en) Method for mining mineral beds at large depth
SU1157234A1 (en) Method of opening-up and working mining levels of elongated open pits
SU1020583A1 (en) Method of working steep ore deposits
RU2012807C1 (en) Method for removal of hard rock overburden
SU756009A1 (en) Method of open-pit mining
RU2036308C1 (en) Method for combination mining of mineral deposit
RU2091583C1 (en) Method of mining of mineral upper horizons