RO135120A2 - System for retention of rainwater, revitalization of drained soil, and restoration of biodiversity - Google Patents

System for retention of rainwater, revitalization of drained soil, and restoration of biodiversity Download PDF

Info

Publication number
RO135120A2
RO135120A2 RO202000855A RO202000855A RO135120A2 RO 135120 A2 RO135120 A2 RO 135120A2 RO 202000855 A RO202000855 A RO 202000855A RO 202000855 A RO202000855 A RO 202000855A RO 135120 A2 RO135120 A2 RO 135120A2
Authority
RO
Romania
Prior art keywords
area
created
ditch
rainwater
unpaved
Prior art date
Application number
RO202000855A
Other languages
Romanian (ro)
Inventor
Stefan Valo
Original Assignee
PlanetFuturum s.r.o.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PlanetFuturum s.r.o. filed Critical PlanetFuturum s.r.o.
Publication of RO135120A2 publication Critical patent/RO135120A2/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/18Making embankments, e.g. dikes, dams
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F1/00Methods, systems, or installations for draining-off sewage or storm water
    • E03F1/002Methods, systems, or installations for draining-off sewage or storm water with disposal into the ground, e.g. via dry wells
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/10Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
    • E03F5/103Naturals or landscape retention bodies, e.g. ponds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Paleontology (AREA)
  • Health & Medical Sciences (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Environmental & Geological Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Sewage (AREA)
  • Revetment (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention relates to a system for the retention of rainwater, revitalization of drained soil and restoration of biodiversity. The claimed system consists of an unpaved area (1) with rainwater (6), water seepage (61) and soil pores (62) linked to ground water (7) and where a retention berm (11) is formed with a deeply sloped artificial ditch (4) and a ditch foil (41) with soil excavated from the ditch (42), with a sloped embankment area (3), with an excavation (31), at the bottom of which an artificial dug discharge ditch (91) is carried out with loosely placed stones (32) and a permanent impermeable wall (33), behind which a compact area (2) is formed, followed by the artificially-formed waved area (8).

Description

Domeniul InvențieiField of the Invention

Invenția este legată de sistemul pentru reținerea scurgerilor de apă pluvială, revitalizarea zonei de drenaj și refacerea biodiversității destinat să revitalizeze ecosistemul și biodiversitatea în special în domeniul construcției de obiective de reținere a apei și al recultivării terenului agricol și pădurilor.The invention relates to the system for retaining rainwater runoff, revitalizing the drainage area and restoring biodiversity intended to revitalize the ecosystem and biodiversity, especially in the field of construction of water retention objectives and the recultivation of agricultural land and forests.

Stadiul Tehnicii în DomeniuState of the Art

Creșterea necontrolată a zonelor compactate și a pantelor create artificial unde porii din pământ sunt comprimați (compactați) și blocați, de exemplu pe drumuri forestiere alunecoase și nepavate, are ca rezultat un număr crescut de inundații locale cu apa care inundă sate și orașe îndepărtând prin spălare terenul fertil, uscându-l și provocând de asemenea și alunecări de teren. Până în prezent au existat diverse sisteme naturale de reținere a apei cunoscute că păstrează echilibrat regimul apei și ulterior, apa este utilizată în agricultură, industrie sau pentru generarea de energie. Un dezavantaj al acestor sisteme, totuși, este că ele nu se ocupă de reținerea apei în terenul agricol și păduri, nereușind să împiedice secetele și inundațiile care erodează pământul într-un mod eficient.Uncontrolled growth of compacted areas and artificially created slopes where earth pores are compressed (compacted) and blocked, for example on slippery and unpaved forest roads, results in an increased number of local floods with water flooding villages and towns away by washing fertile ground, drying it out and also causing landslides. Until now, there have been various natural water retention systems known to keep the water regime balanced and subsequently, water is used in agriculture, industry or for energy generation. A disadvantage of these systems, however, is that they do not deal with water retention in agricultural land and forests, failing to prevent droughts and floods that erode the soil effectively.

Altă invenție cunoscută este dezvăluită în modelul de utilitate slovac înregistrat cu Nr. 5 252 ca Sistem Tehnologic Integrat pentru Redresarea Climei unde un bloc rezervor de apă este legat la cel puțin un bloc biotehnologic de tratare a apei și/sau la cel puțin un bloc tehnologic de tratare a apei care este, pe o latură, legat la cel puțin un bloc tehnologic de infiltrare a apei legat la cel puțin un bloc tehnologic de absorbție a apei și, pe latura cealaltă, este legat la cel puțin un bloc tehnologic de drenare a apei și pe a treia latură este legat la cel puțin un bloc tehnologic rezervor de vapori de apă. Un dezavantaj al acestei invenții constă în dificultatea sa tehnică, costurile ridicate de realizare și nereușita în a revitaliza pământul compactat, și a recupera biodiversitatea. Altă invenție cunoscută este dezvăluită în modelul de utilitate slovac înregistrat cu Nr. 5 847 ca Structură Modulară a unei Bariere Antiinundații unde fiecare modul orizontal are cel puțin un modul adiacent vertical sau înclinat la care fiecare modul vertical este dotat cu o bară de legătură ancorată în modulul orizontal, la care zona de impact a modulului vertical este latura modulului vertical orientată către modulul orizontal, sauAnother known invention is disclosed in the Slovak utility model registered with No. 5 252 as an Integrated Technology System for Climate Recovery where a water reservoir block is connected to at least one biotechnological water treatment block and / or to at least one water treatment technological block which is, on the one hand, connected to the at least one technological block of water infiltration connected to at least one technological block of water absorption and, on the other side, is connected to at least one technological block of water drainage and on the third side is connected to at least one technological block water vapor tank. A disadvantage of this invention is its technical difficulty, high construction costs and failure to revitalize compacted soil, and recover biodiversity. Another known invention is disclosed in the Slovak utility model registered with No. 5 847 as Modular Structure of a Flood Barrier where each horizontal module has at least one adjacent vertical or inclined module in which each vertical module is equipped with a connecting bar anchored in the horizontal module, where the impact area of the vertical module is the side of the module vertically oriented towards the horizontal module, or

fiecare modul înclinat este dotat cu o bară de legătură ancorată în modulul orizontal unde zona de impact a modulului înclinat este latura modulului înclinat orientată în partea opusă față de modulul orizontal. Un dezavantaj al acestei invenții este dificultatea sa tehnică și complexitatea proiectării variantei de realizare și nereușita de a revitaliza pământul compactat și a recupera biodiversitatea.each inclined module is equipped with a connecting bar anchored in the horizontal module where the impact area of the inclined module is the side of the inclined module oriented in the opposite direction to the horizontal module. A disadvantage of this invention is its technical difficulty and the complexity of designing the embodiment and the failure to revitalize the compacted soil and recover biodiversity.

Altă invenție cunoscută este dezvăluită în modelul de utilitate slovac înregistrat cu Nr. 5 726 ca o Barieră Antiinundații unde un postament portabil are o etanșare gonflabilă încastrată în jurul perimetrului și dimensiunea postamentului corespunde cu dimensiunea cadrului construit în deschiderea obiectivului unde este amplasat postamentul și fixat cu ajutorul a cel puțin două știfturi retractabile utilizând etanșarea gonflabilă. Un dezavantaj al acestei invenții este că nu se reușește a fi revitalizat pământul compactat, nu poate fi utilizată la drumuri forestiere și nu se reușește a fi recuperată biodiversitatea.Another known invention is disclosed in the Slovak utility model registered with No. 5 726 as a Flood Barrier where a portable pedestal has an inflatable seal embedded around the perimeter and the size of the pedestal corresponds to the size of the frame built in the opening of the objective where the pedestal is located and fixed with at least two retractable pins using inflatable sealing. A disadvantage of this invention is that it is not possible to revitalize the compacted land, it cannot be used on forest roads and it is not possible to recover biodiversity.

Altă invenție cunoscută este dezvăluită în modelul de utilitate slovac înregistrat cu Nr. 5 855 ca o Barieră Antiinundații unde compartimente și fâșii de echilibrare sunt montate într-un balon etanș la aer și impermeabil la apă care este presurizat cu lichid sau aer la presiune mai mare dacă este atmosferică sau hidrostatică și poate fi închis utilizând un dop atașat la balonul de stabilizare și compensare cu o supapă pe partea exterioară a balonului, o sârmă de stabilizare și cleme elastice pentru a atașa o Barieră Antiinundații foarte lungă, și o bază de siguranță poate fi amplasată sub balon și atașată cu fixatoare cu Velcro și ochiuri auxiliare; baza de siguranță împiedică balonul să sufere deteriorare mecanică sau să alunece la vale într-un teren rugos și alunecos. Un dezavantaj al acestei invenții este costul său ridicat, dificultatea tehnică și complexitatea proiectării variantei de realizare și nereușita de a revitaliza pământul compactat și a recupera biodiversitatea.Another known invention is disclosed in the Slovak utility model registered with No. 5 855 as a Flood Barrier where compartments and balancing strips are mounted in an airtight and waterproof balloon that is pressurized with liquid or air at a higher pressure if it is atmospheric or hydrostatic and can be closed using a plug attached to the stabilizing and compensating balloon with a valve on the outside of the balloon, a stabilizing wire and elastic clamps to attach a very long Flood Barrier, and a safety base can be placed under the balloon and attached with Velcro fasteners and auxiliary mesh; the safety base prevents the balloon from suffering mechanical damage or sliding downhill in rough, slippery ground. A disadvantage of this invention is its high cost, technical difficulty and complexity of designing the embodiment and the failure to revitalize the compacted soil and recover biodiversity.

Altă invenție cunoscută este dezvăluită în modelul de utilitate slovac înregistrat cu Nr. 5 928 ca o Barieră Antiinundații unde baze din cauciuc și elemente structurale sunt legate între ele utilizând elemente de legătură care constau din trei panouri legate cu balamale pliate de forma modulului cu o secțiune transversală triunghiulară pe baza din cauciuc relevantă la care panoul cu o placă din metal și accesorii încastrate este amplasat pe baza din cauciuc. Un dezavantaj al acestei invenții este că nu se reușește a fi revitalizat pământul compactat, nu poate fi utilizată cu drumuri forestiere și biodiversitatea nu se reușește a fi recuperată.Another known invention is disclosed in the Slovak utility model registered with No. 5 928 as a Flood Barrier where rubber bases and structural elements are connected to each other using connecting elements consisting of three panels connected by module-shaped folded hinges with a relevant rubber-based triangular cross section to which the panel with a plate of metal and recessed accessories is placed on the rubber base. A disadvantage of this invention is that it is not possible to revitalize the compacted land, it cannot be used with forest roads and the biodiversity cannot be recovered.

Altă invenție cunoscută este dezvăluită în cererea slovacă publicată a modelului de utilitate Nr. 230 - 2011 ca Sistemul pentru Reținerea Scurgerilor de Apă Pluvială și Revitalizarea Zonei de Taluz Compactate și Procedeul său de Realizare care constă din cel puțin o zonă de taluz compactată în zona de taluz nepavată pe baza acestei invenții care poate fi rezumată după cum urmează: în cel puțin o zonă de taluz compactată, există cel puțin un șanț de captare a apei pluviale conținând apa pluvială și constând, pe o parte, din zona înclinată adiacentă la taluz și, pe partea cealaltă, zona adiacentă la taluz cu zona de captare a apei amplasată deasupra nivelului zonei de taluz compactate și fundul drenajului de infiltrație amplasat între acestea cu cel puțin o infiltrație a apei pluviale captate în apa freatică. Un dezavantaj al acestei invenții este că nu reușește să utilizeze tuburile capilare subterane și să recupereze biodiversitatea.Another known invention is disclosed in the published Slovak application of utility model no. 230 - 2011 as the System for Retaining Rainwater Drainage and Revitalizing the Compacted Slope Area and its Implementation Process consisting of at least one compacted slope area in the unpaved slope area based on this invention which can be summarized as follows: at least one compacted slope area, there is at least one rainwater catchment ditch containing rainwater and consisting, on one side, of the sloping area adjacent to the slope and, on the other side, the area adjacent to the slope with the catchment area located above the level of the compacted slope area and the bottom of the infiltration drain placed between them with at least one infiltration of rainwater trapped in the groundwater. A disadvantage of this invention is that it fails to use underground capillaries and recover biodiversity.

Altă invenție cunoscută este dezvăluită în dosarul de brevet ceh Nr. 297 401 ca o Incintă pentru Inundații unde panouri contra inundațiilor sunt montate vertical între stâlpi de stabilizare verticali, și stâlpi de stabilizare verticali și un prag de stavilă sunt încastrați în postamentul din beton armat; la care o fâșie de etanșare orizontală flexibilă cu caneluri profilate este amplasată pe muchia de fund a fiecărui panou contra inundațiilor; aceste caneluri profilate auto-agață fâșia de etanșare orizontală pe panoul contra inundațiilor la care o bară de presiune cu o fâșie de etanșare flexibilă este fixată de stâlpul de stabilizare între stâlpul de stabilizare și elementul de legătură al panourilor contra inundațiilor, și aceste panouri contra inundațiilor sunt legate de stâlpii de stabilizare cu ajutorul unor piese tip etrier ale căror brațe trec prin găurile de asamblare ale panourilor contra inundațiilor învecinate. Un dezavantaj al acestei invenții este în costurile mari de realizare, nereușita de a revitaliza pământul compactat, indisponibilitatea de a fi aplicată la drumuri forestiere și nereușita de a recupera biodiversitatea.Another known invention is disclosed in Czech Patent File No. 297 401 as a Flood Enclosure where flood panels are mounted vertically between vertical stabilization posts, and vertical stabilization posts and a dam sill are embedded in the reinforced concrete pedestal; in which a flexible horizontal sealing strip with profiled grooves is placed on the bottom edge of each flood panel; these profiled grooves self-attach the horizontal sealing strip to the flood panel at which a pressure bar with a flexible sealing strip is attached to the stabilizing post between the stabilizing post and the connecting element of the flood panels, and these flood panels they are connected to the stabilizing pillars by means of stirrup-type parts whose arms pass through the assembly holes of the panels against the neighboring floods. A disadvantage of this invention is in the high construction costs, the failure to revitalize the compacted soil, the unavailability to be applied to forest roads and the failure to recover biodiversity.

Altă invenție cunoscută este dezvăluită în modelul de utilitate slovac înregistrat cu Nr. 6 839 ca Sistemul pentru Reținerea Scurgerilor de Apă de Ploaie și Revitalizarea Zonei de Taluz Compactate care poate fi rezumată drept constând din cel puțin o zonă de taluz compactată într-o zonă de taluz nepavată pe baza acestei invenții care poate fi rezumată după cum urmează: într-o zonă de taluz nepavată, cu pori din pământ, există cel puțin o groapă adâncă taluzată cu apă de ploaie realizată de-a lungul conturului; în această groapă, este amplasat pământ taluzat săpat în care partea de fund a găurii adânci taluzate este legată cu apa freatică prin infiltrarea apei și porii din pământ; șiAnother known invention is disclosed in the Slovak utility model registered with No. 6 839 as the System for Retaining Rainwater Drainage and Revitalizing the Compacted Slope Area which may be summarized as consisting of at least one compacted slope area into an unpaved slope area based on this invention which may be summarized as follows: in an unpaved slope area, with earth pores, there is at least one deep pit trenched with rainwater made along the contour; In this pit, is placed excavated sloping earth in which the bottom of the sloping deep hole is connected with groundwater by infiltration of water and pores from the ground; and

RO 135120 Α2 >RO 135120 Α2>

4 unde cel puțin o folie pentru groapă este atașată la cel puțin o latură a gropii adânci taluzate; la care cel puțin o zonă cu taluz înclinat cu o bermă taluzată este creată întro zonă de taluz nepavată, și la partea de fund a bermei taluzate, există un șanț al bermei conținând apă de ploaie; șanțul bermei este legat cu apa freatică prin infiltrarea apei și porii din pământ; în spatele șanțului bermei, există creată o zonă de taluz compactată acolo unde este creat cel puțin un șanț de captare a apei pluviale cu apă de ploaie; șanțul de captare a apei pluviale este legat cu apa freatică prin infiltrarea apei și porii din pământ; în spatele șanțului de captare a apei pluviale, există cel puțin o zonă de val creată pe o parte; în spatele acestei zone de val, există creată cel puțin o zonă laterală de taluz, și unde în spatele cel puțin unui șanț de captare a apei pluviale conținând apă de ploaie, există o formațiune laterală a șanțului creată pe latura frontală. Un dezavantaj al acestei invenții este aplicabilitatea sa doar la zonele compactate deoarece crearea unei berme într-un taluz artificial nu va reține sau opri scurgerea apă din porii blocați din pământ. 4 where at least one pit foil is attached to at least one side of the sloping deep pit; in which at least one sloping area with a sloping berm is created in an unpaved slope area, and at the bottom of the sloping berm, there is a trench containing the rainwater; the berm ditch is connected to groundwater by infiltrating water and pores from the ground; behind the berm ditch, a compacted slope area is created where at least one rainwater catchment ditch with rainwater is created; the rainwater catchment ditch is connected to the groundwater by infiltrating water and pores from the ground; behind the rainwater catchment ditch, there is at least one wave area created on one side; Behind this wave area, there is created at least one lateral slope area, and where behind at least one rainwater catchment ditch containing rainwater, there is a lateral ditch formation created on the front side. A disadvantage of this invention is its applicability only to compacted areas because the creation of a berm in an artificial slope will not retain or stop the flow of water from the pores blocked in the ground.

Rezumatul invențieiSummary of the Invention

Deficiențele menționate mai sus sunt eliminate masiv de sistemul pentru reținerea scurgerilor de apă de ploaie, revitalizarea zonei de drenaj și recuperarea biodiversității destinat să revitalizeze ecosistemul în conformitate cu această invenție care poate fi rezumată drept constând din cel puțin o zonă nepavată cu apă de ploaie legată cu apa subterană prin infiltrarea apei și porii din pământ, în această zonă nepavată, este creată cel puțin o bermă de reținere în spatele căreia există cel puțin un șanț artificial taluzat adânc creat cu o folie pentru șanț unde este amplasat pământul excavat din șanț și în spatele său, există cel puțin o zonă cu taluz înclinat cu un debleu creat întro zonă nepavată; în partea de fund a debleului, există cel puțin o scurgere artificială săpată creată cu pietre nefixate și cel puțin un perete impermeabil amplasat permanent în spatele căruia este creată o zonă compactată cu o zonă de val artificială în spatele său.The deficiencies mentioned above are massively eliminated by the system for retaining rainwater runoff, revitalizing the drainage area and recovering biodiversity to revitalize the ecosystem in accordance with this invention which can be summarized as consisting of at least one unpaved area with bound rainwater. with groundwater by infiltrating water and pores from the ground, in this unpaved area, at least one retaining berm is created behind which there is at least one deep sloping artificial ditch created with a ditch foil where the earth excavated from the ditch is located and in behind it, there is at least one area with a sloping slope with a excavation created in an unpaved area; at the bottom of the excavation, there is at least one artificial excavation created with loose stones and at least one impermeable wall permanently placed behind which a compacted area is created with an artificial wave area behind it.

Se preferă ca, în partea de fund a debleului, să existe creat cel puțin un șanț săpat, și, în zona compactată, este creat cel puțin un șanț de captare a apei pluviale cu cel puțin o bermă șanț de accelerare; în spatele șanțului de captare a apei pluviale, există o zonă de val creată pe o latură cu formațiunea laterală a șanțului.It is preferred that at least one excavated trench be created at the bottom of the embankment, and in the compacted area at least one rainwater catchment trench with at least one acceleration trench berm be created; Behind the rainwater catchment ditch, there is a wave area created on one side with the lateral formation of the ditch.

Se preferă ca cel puțin o excavație de pământ artificială să fie creată în zona nepavată.It is preferred that at least one artificial earth excavation be created in the unpaved area.

Se preferă ca cel puțin o rigolă artificială (22) cu o zonă cu taluz înclinat artificială (3) să fie creată de-a lungul ambelor laturi ale zonei compactate (2).It is preferred that at least one artificial gutter (22) with an artificial sloping area (3) be created along both sides of the compacted area (2).

Rezumatul figurilor din deseneSummary of the figures in the drawings

Invenția va fi explicată mai în detaliu utilizând desenele unde Fig. 1 este o vedere laterală schematică a profilului zonei de taluz nepavate cu un șanț de captare a apei pluviale și trei berme de reținere; Fig. 2 este o vedere schematică de sus a zonei de taluz nepavate cu un șanț de captare a apei pluviale și formațiunea laterală a șanțului; Fig. 3 este o vedere laterală schematică a profilului zonei de taluz compactate cu un șanț de captare a apei pluviale cu bermă șanț de accelerare; Fig. 4 este o vedere laterală schematică a profilului zonei de taluz compactate cu șanțul de captare a apei pluviale și două zone de taluz înclinat cu berme de reținere și de accelerare; Fig. 5 este o vedere schematică de sus a zonei de taluz nepavate cu un șanț de captare a apei pluviale; Fig. 6 este o vedere laterală schematică a profilului zonei de taluz nepavate cu trei berme de reținere și o scurgere săpată cu un perete impermeabil; Fig. 7 este o vedere laterală schematică a zonei de taluz nepavate cu două berme de reținere și un șanț taluzat adânc și o scurgere săpată cu un perete impermeabil; Fig. 8 este o vedere laterală schematică a profilului zonei de taluz nepavate cu o zonă de taluz înclinat; Fig. 9 este o vedere laterală schematică a profilului zonei de taluz nepavate cu o excavație de pământ și o zonă de val; Fig. 10 este o vedere laterală schematică a profilului zonei de taluz nepavate cu o bermă de reținere și un debleu al taluzului cu un perete impermeabil; Fig. 11 este o vedere laterală schematică a profilului zonei de taluz nepavate cu două rigole taluzate cu o zonă de taluz înclinat; Fig. 12 este o vedere laterală schematică a profilului zonei de taluz nepavate cu o excavație de pământ în taluz cu două rigole taluzate și o zonă de val; Fig. 13 este o vedere laterală schematică a zonei de taluz nepavate cu un debleu al taluzului și un perete impermeabil și zona de val; Fig. 14 este o vedere laterală schematică a zonei de taluz nepavate cu o excavație de pământ în taluz cu două rigole taluzate și două zone de val; Fig. 15 este o vedere laterală schematică a zonei de taluz nepavate cu un debleu al taluzului înclinat și cu un perete impermeabil și zonă de val, Fig. 16 este o vedere laterală schematică a profilului zonei nepavate cu două rigole taluzate cu zonă de taluz înclinat; Fig. 17 este o vedere laterală schematică a profilului zonei nepavate cu două excavații de pământ și două zone de val; Fig. 18 este o vedere laterală schematică a profilului zonei de taluz nepavate cu două debleuri și un perete impermeabil; Fig. 19 este o vedere laterală schematică a profilului zonei nepavate cu două rigole taluzate cu zonele de taluz înclinat și cu un dig compactat; Fig. 20 este o vedere laterală schematică a profilului zonei nepavate cu două excavații de pământ și un dig compactat; și Fig. 21 este o vedere laterală schematică a zonei nepavate cu două debleuri și un dig compactat.The invention will be explained in more detail using the drawings where Figs. 1 is a schematic side view of the profile of the unpaved slope area with a rainwater catchment trench and three retaining berms; FIG. 2 is a schematic top view of the unpaved slope area with a rainwater catchment ditch and the lateral formation of the ditch; FIG. 3 is a schematic side view of the profile of the area of the slope compacted with a rainwater catchment ditch with berm acceleration ditch; FIG. 4 is a schematic side view of the profile of the slope area compacted with the rainwater catchment ditch and two sloping slope areas with retention and acceleration berms; FIG. 5 is a schematic top view of the unpaved slope area with a rainwater catchment ditch; FIG. 6 is a schematic side view of the profile of the unpaved slope area with three retaining berms and a drain dug with a waterproof wall; FIG. 7 is a schematic side view of the unpaved slope area with two retaining berms and a deep sloping ditch and a drain dug with a waterproof wall; FIG. 8 is a schematic side view of the profile of the unpaved slope area with an inclined slope area; FIG. 9 is a schematic side view of the profile of the unpaved slope area with an earth excavation and a wave area; FIG. 10 is a schematic side view of the profile of the unpaved slope area with a retaining berm and a slope of the slope with a waterproof wall; FIG. 11 is a schematic side view of the profile of the unpaved slope area with two sloping gutters with an inclined slope area; FIG. 12 is a schematic side view of the profile of the unpaved slope area with an excavation of earth in the slope with two sloping gutters and a wave area; FIG. 13 is a schematic side view of the unpaved slope area with a slope of the slope and a waterproof wall and wave area; FIG. 14 is a schematic side view of the unpaved slope area with an excavation of earth in the slope with two sloping ditches and two wave areas; FIG. Fig. 15 is a schematic side view of the unpaved slope area with a sloping slope slope and an impermeable wall and wave area, FIG. 16 is a schematic side view of the unpaved area profile with two sloping gutters with sloping slope area; FIG. 17 is a schematic side view of the profile of the unpaved area with two earth excavations and two wave areas; FIG. 18 is a schematic side view of the profile of the unpaved slope area with two excavations and a waterproof wall; FIG. 19 is a schematic side view of the profile of the unpaved area with two sloping gutters with sloping slope areas and a compacted dike; FIG. 20 is a schematic side view of the profile of the unpaved area with two earth excavations and a compacted dam; and FIG. 21 is a schematic side view of the unpaved area with two excavations and a compacted dam.

Exemple de variante de realizareExamples of embodiments

Exemplul 1Example 1

Sistemul pentru reținerea scurgerilor de apă pluvială, revitalizarea pământului și recuperarea biodiversității, în conformitate cu Fig. 1, constă din zona superioară nepavată 1 care este o zonă de drenaj cu taluz înclinat. în zona superioară nepavată 1, există create trei berme de reținere 11 și ele distrug porii 62 din pământ și rețin scurgerea apei de ploaie 6. Sub zona superioară nepavată 1, sunt creați pori noi 62 din pământ prin umplerea treptată a bermelor de reținere 11 datorită scurgerii apei de ploaie 6. Mai mult, în zona superioară nepavată 1 este creată o zonă artificială cu taluz înclinat 3 cu un debleu 31 care este pământ taluzat de 100 cm grosime săpat cu un excavator pentru a distruge porii 62 din pământ. în partea de fund a debleului 31, există un șanț săpat artificial 9 creat cu pământ taluzat săpat din debleu 31 și șanțul săpat 9. Șanțul săpat 9 este destinat pentru captarea apei de ploaie 6 din porii 62 din pământ. Șanțul săpat 9 asigură infiltrația apei de ploaie 6 la apa freatică 7 prin infiltrarea 61 apei și porii 62 din pământ. în spatele șanțului săpat 9, există creată o zonă compactată 2. în zona compactată 2, este creat un șanț 5 de captare a apei pluviale cu pământul compactat cu o benă de excavator. Șanțul 5 de captare a apei pluviale asigură infiltrația apei de ploaie 6 la apa freatică 7 prin infiltrarea 61 apei și porii 62 din pământ. în șanțul 5 de captare a apei pluviale, în conformitate cu Fig. 3, există o bermă șanț de accelerare 51 creată pentru a accelera scurgerea apei de ploaie 6 în apa freatică 7. în jurul șanțului 5 de captare a apei pluviale, în conformitate cu Fig. 2, este creată zona compactată 2 lată de nu mai puțin de 50 cm. în zona compactată 2, și în spatele unei laturi a șanțului 5 de captare a apei pluviale, există creată o zonă de val artificială 8 care este o grămadă de pământ excavată din șanțul 5 de captare a apei pluviale. în spatele laturii frontale a șanțului 5 de captare a apei pluviale, există creată o formațiune laterală 21 lată de 50 cm a șanțului. Formațiunea laterală 21 a șanțului este destinată să împiedice deversarea laterală a apei de ploaie 6 și alunecarea debleului 31. în spatele formațiunii laterale 21 a șanțului, este creată o zonă de fund nepavată 1 careThe system for retaining rainwater runoff, revitalizing the land and recovering biodiversity, according to Fig. 1, consists of the unpaved upper area 1 which is a drainage area with an inclined slope. in the unpaved upper zone 1, there are created three retaining berms 11 and they destroy the pores 62 of the earth and retain the rainwater runoff 6. Under the unpaved upper zone 1, new pores 62 of the earth are created by gradually filling the retaining berms 11 due to rainwater runoff 6. Furthermore, in the unpaved upper area 1 an artificial area with a sloping slope 3 is created with a excavation 31 which is 100 cm thick sloping earth dug with an excavator to destroy the pores 62 of the earth. At the bottom of the trench 31, there is an artificial dug trench 9 created with sloping earth dug from the trench 31 and the dug trench 9. The dug trench 9 is intended for capturing rainwater 6 from the pores 62 of the earth. The excavated ditch 9 ensures the infiltration of rainwater 6 to groundwater 7 by infiltrating 61 water and pores 62 from the ground. behind the excavated ditch 9, there is created a compacted area 2. in the compacted area 2, a ditch 5 is created for capturing rainwater with the soil compacted with an excavator dump. The rainwater catchment ditch 5 ensures the infiltration of rainwater 6 to groundwater 7 by infiltrating 61 water and pores 62 from the ground. in the rainwater catchment ditch 5, according to Figs. 3, there is an acceleration ditch berm 51 created to accelerate the runoff of rainwater 6 into groundwater 7. around the rainwater catchment ditch 5, according to FIG. 2, the compacted area 2 wide of not less than 50 cm is created. In the compacted area 2, and behind a side of the rainwater catchment ditch 5, there is created an artificial wave zone 8 which is a pile of earth excavated from the rainwater catchment ditch 5. Behind the front side of the rainwater catchment ditch 5, a 50 cm wide lateral formation 21 of the ditch is created. The lateral formation 21 of the ditch is intended to prevent the lateral discharge of rainwater 6 and the landslide 31. After the lateral formation 21 of the ditch, an unpaved bottom area 1 is created which

RO 135120 Α2 este o zonă de taluz înclinat nedrenată.RO 135120 Α2 is a non-drained sloping slope area.

Exemplul 2Example 2

Sistemul pentru reținerea scurgerilor de apă pluvială, revitalizarea zonei de drenaj și recuperarea biodiversității, în conformitate cu Fig. 4, constă din cele două zone nepavate 1 care sunt zonele de drenaj în taluz înclinat. în zona superioară nepavată 1 sunt create două berme de reținere 11. în zona de fund nepavată 1 este creată o bermă de reținere 11. Bermele de reținere 11 sunt destinate să distrugă porii 62 din pământ și să rețină scurgerea apei de ploaie 6. Sub ambele zone nepavate 1, sunt creați pori noi 62 din pământ prin umplerea treptată a bermelor de reținere 11 datorită scurgerii apei de ploaie 6. în ambele zone nepavate 1, o zonă cu taluz înclinat artificială 3 este creată cu un debleu 31 care este pământ taluzat gros de 100 cm săpat cu un excavator pentru a distruge porii 62 din pământ. în partea de fund a debleului 31, există un șanț săpat artificial 9 creat cu pământ taluzat săpat din debleu 31 și șanțul săpat 9. Șanțul săpat 9 este destinat pentru captarea apei de ploaie 6 din porii 62 din pământ. Șanțul săpat 9 asigură infiltrația apei de ploaie 6 la apa freatică 7 prin infiltrarea 61 apei și porii 62 din pământ. în spatele șanțului săpat 9, există creată o zonă compactată 2. în zona compactată 2 este creat un șanț 5 de captare a apei pluviale cu pământul compactat cu o benă de excavator. Șanțul 5 de captare a apei pluviale asigură infiltrația apei de ploaie 6 la apa freatică 7 prin infiltrarea 61 apei și porii 62 din pământ. în șanțul 5 de captare a apei pluviale, în conformitate cu Fig. 5, există o bermă șanț de accelerare 51 creată pentru a accelera scurgerea apei de ploaie 6 în apa freatică 7. Mai mult, în jurul șanțului 5 de captare a apei pluviale este creată zona compactată 2 lată de nu mai puțin de 50 cm. în zona compactată 2, și în spatele laturii șanțului 5 de captare a apei pluviale, există creată o zonă de val artificială 8 care este o grămadă de pământ excavat din șanțul săpat 9.The system for retaining rainwater runoff, revitalizing the drainage area and recovering biodiversity, according to Fig. 4, consists of the two unpaved areas 1 which are the drainage areas in the inclined slope. in the unpaved upper zone 1 two retaining berms are created 11. in the unpaved bottom zone a retaining berm 11 is created 11. The retaining berms 11 are intended to destroy the pores 62 of the earth and to retain rainwater runoff 6. Under both unpaved areas 1, new pores 62 of the earth are created by gradually filling the retaining berms 11 due to rainwater runoff 6. in both unpaved areas 1, an area with artificial sloping slope 3 is created with a excavation 31 which is thick sloping earth 100 cm dug with an excavator to destroy 62 pores in the ground. At the bottom of the trench 31, there is an artificial dug trench 9 created with sloping earth dug from the trench 31 and the dug trench 9. The dug trench 9 is intended for capturing rainwater 6 from the pores 62 of the earth. The excavated ditch 9 ensures the infiltration of rainwater 6 to groundwater 7 by infiltrating 61 water and pores 62 from the ground. behind the excavated ditch 9, there is created a compacted area 2. in the compacted area 2 is created a ditch 5 for capturing rainwater with the earth compacted with an excavator dump. The rainwater catchment ditch 5 ensures the infiltration of rainwater 6 to groundwater 7 by infiltrating 61 water and pores 62 from the ground. in the rainwater catchment ditch 5, according to Figs. 5, there is an acceleration ditch berm 51 created to accelerate the runoff of rainwater 6 into groundwater 7. Moreover, around the rainwater catchment ditch 5 is created the compacted area 2 wide of not less than 50 cm. in the compacted area 2, and behind the side of the rainwater catchment ditch 5, there is created an artificial wave zone 8 which is a pile of earth excavated from the excavated ditch 9.

Exemplul 3Example 3

Sistemul pentru reținerea scurgerilor de apă pluvială, revitalizarea zonei de drenaj și recuperarea biodiversității, în conformitate cu Fig. 6, constă din zona superioară nepavată 1 care este o zonă de drenaj cu taluz înclinat. în zona superioară nepavată 1, există create trei berme de reținere 11 pentru a distruge porii 62 din pământ și a reține scurgerea apei de ploaie 6. Sub zona superioară nepavată 1 sunt creați pori noi din pământ prin umplerea treptată a bermelor de reținere 11 datorită scurgerii apei de ploaie 6. Mai mult, o zonă cu taluz înclinat artificială 3 este creată pe zona superioară nepavată 1 cu un debleu 31 care este pământ taluzat gros de 100 cm săpat cu un excavator pentru a distruge porii 62 din pământ. în partea de fund a debleului 31, este creată scurgerea săpată 91. Scurgerea săpată 91 asigură infiltrația apei de ploaie 6 la apa freatică 7 prin infiltrarea 61 apei și porii 62 din pământ. în scurgerea săpată 91, este amplasat permanent un perete impermeabil 33, care este o secțiune din beton. Peretele impermeabil 33 este destinat să rețină presiunea pământului săpat din taluz în zona cu taluz înclinat 3. în scurgerea săpată 91, există pietre nefixate 32 așezate în diverse dimensiuni și structuri împreună cu pământul săpat din debleu 31. Pietrele 32 îmbunătățesc infiltrația apei de ploaie 6 la porii 62 din pământ și ele de asemenea asigură stabilitatea peretelui impermeabil 33. în spatele peretelui impermeabil 33, există o zonă compactată 2 care este un drum forestier nesăpat. în spatele zonei compactate 2, este creată o zonă de fund nepavată 1 care este o zonă de taluz înclinat nedrenată.The system for retaining rainwater runoff, revitalizing the drainage area and recovering biodiversity, according to Fig. 6, consists of the unpaved upper area 1 which is a drainage area with an inclined slope. in the unpaved upper zone 1, three retaining berms 11 are created to destroy the pores 62 of the earth and to retain the drainage of rainwater 6. Under the unpaved upper zone 1 new pores are created from the earth by gradually filling the retaining berms 11 due to leakage rainwater 6. Furthermore, an area with artificial sloping slope 3 is created on the unpaved upper area 1 with a excavation 31 which is 100 cm thick sloping earth dug with an excavator to destroy the pores 62 of the earth. In the bottom of the embankment 31, the excavated drain 91 is created. The excavated drain 91 ensures the infiltration of rainwater 6 to the groundwater 7 by the infiltration of water 61 and the pores 62 of the earth. In the excavated drain 91, a waterproof wall 33 is permanently placed, which is a section of concrete. The impermeable wall 33 is intended to retain the pressure of the excavated earth from the slope in the area with a sloping slope 3. in the excavated drain 91, there are loose stones 32 placed in various sizes and structures together with the excavated earth from the excavation 31. The stones 32 improve rainwater infiltration 6 at the pores 62 of the earth and they also ensure the stability of the impermeable wall 33. behind the impermeable wall 33, there is a compacted area 2 which is an unexcavated forest road. Behind the compacted zone 2, an unpaved bottom zone 1 is created which is an undrained sloping slope zone.

în zona de fund nepavată 1, există o zonă de val 8 creată cu pământul taluzat excavat de la scurgerea săpată 91.In the unpaved bottom area 1, there is a wave area 8 created with the sloping earth excavated from the excavated drain 91.

Exemplul 4Example 4

Sistemul pentru reținerea scurgerilor de apă pluvială, revitalizarea zonei de drenaj și recuperarea biodiversității, în conformitate cu Fig. 7, constă din zona superioară nepavată 1 care este o zonă de drenaj cu taluz înclinat. în zona superioară nepavată 1, există două berme de reținere 11 create pentru a distruge porii 62 din pământ și a reține scurgerea apei de ploaie 6. Sub zona superioară nepavată 1, sunt creați pori noi 62 din pământ prin umplerea treptată a bermelor de reținere 11 datorită scurgerii apei de ploaie 6. în spatele bermelor de reținere 11, un șanț taluzat adânc 4 este creat dea lungul conturului, acest șanț fiind lat de 1,2 m și adânc de 3 m. Șanțul taluzat adânc 4 asigură infiltrația apei de ploaie 6 la apele freatice 7 prin infiltrarea 61 apei și porii 62 din pământ. O folie pentru șanț 41 este atașată la o latură a șanțului taluzat adânc 4; scopul este să asigure impermeabilitatea pentru apa de ploaie 6. Ulterior, pământul excavat din șanț 42 care distruge porii 62 din pământ este amplasat în șanțul taluzat adânc 4. Mai mult, o zonă cu taluz înclinat artificială 3 este creată în zona superioară nepavată 1 cu un debleu 31 care este pământ taluzat gros de 100 cm săpat cu un excavator pentru a distruge porii 62 din pământ. în partea de fund a debleului 31 este creată scurgerea săpată 91. Scurgerea săpată 91 asigură infiltrația apei de ploaie 6 la apa freatică 7 prin infiltrarea 61 apei și porii 62 din pământ. în scurgerea săpată 91 este amplasat permanent un perete impermeabil 33, care este o secțiune din beton. Peretele impermeabil 33 este destinat să rețină presiunea pământului taluzat săpat în zona cu taluz înclinat 3. în scurgerea săpată 91, există pietre nefixate 32 așezate în diverse dimensiuni și structuri împreună cu pământ taluzat săpat din debleu 31. Pietrele 32 îmbunătățesc infiltrația apei de ploaie 6 la porii 62 din pământ și ele asigură de asemenea stabilitatea peretelui impermeabil 33. în spatele peretelui impermeabil 33, există o zonă compactată 2 care este un drum nesăpat. în spatele zonei compactate 2 este creată o zonă de fund nepavată 1 care este o zonă de taluz înclinat nedrenată. în zona de fund nepavată 1, există o zonă de val 8 creată cu pământul taluzat excavate de la scurgerea săpată 91.The system for retaining rainwater runoff, revitalizing the drainage area and recovering biodiversity, according to Fig. 7, consists of the unpaved upper area 1 which is a drainage area with an inclined slope. in the unpaved upper zone 1, there are two retaining berms 11 created to destroy the pores 62 of the earth and to retain the rainwater runoff 6. Under the unpaved upper zone 1, new pores 62 of the earth are created by gradually filling the retaining berms 11 due to the drainage of rainwater 6. behind the retaining berms 11, a deep sloping ditch 4 is created along the contour, this ditch being 1.2 m wide and 3 m deep. The deep sloping ditch 4 ensures the infiltration of rainwater 6 to groundwater 7 by infiltrating 61 water and pores 62 from the ground. A ditch foil 41 is attached to one side of the deep sloped ditch 4; the purpose is to ensure impermeability to rainwater 6. Subsequently, the earth excavated from the ditch 42 which destroys the pores 62 of the earth is placed in the deep sloping ditch 4. Moreover, an area with artificial sloping slope 3 is created in the unpaved upper area 1 with a excavation 31 which is 100 cm thick sloping earth dug with an excavator to destroy the pores 62 of the earth. In the bottom part of the deble 31 the excavated drain 91 is created. The excavated drain 91 ensures the infiltration of rainwater 6 to the groundwater 7 by the infiltration 61 of the water and the pores 62 of the earth. In the excavated drain 91 is permanently placed a waterproof wall 33, which is a section of concrete. The impermeable wall 33 is intended to retain the pressure of the excavated sloping earth in the area with a sloping slope 3. in the excavated drain 91, there are loose stones 32 placed in various sizes and structures together with excavated sloping earth from the trough 31. The stones 32 improve rainwater infiltration 6 at the pores 62 of the earth and they also ensure the stability of the impermeable wall 33. behind the impermeable wall 33, there is a compacted area 2 which is a non-excavated road. Behind the compacted area 2 an unpaved bottom area 1 is created which is an undrained sloping slope area. In the unpaved bottom area 1, there is a wave area 8 created with the sloping earth excavated from the excavated drain 91.

Exemplul 5Example 5

Sistemul pentru reținerea scurgerilor de apă pluvială, revitalizarea zonei de drenaj și recuperarea biodiversității, în conformitate cu Fig. 8, constă din zona superioară nepavată 1 care este o zonă de drenaj cu taluz înclinat. în zona superioară nepavată 1 este creată o zonă cu taluz înclinat artificială 3. în spatele peretelui impermeabil 3, există o zonă compactată 2 care este un drum nesăpat. în spatele zonei compactate 2, este creată o zonă de fund nepavată 1 care este o zonă de taluz înclinat nedrenată, în zona superioară nepavată 1, în conformitate cu Fig. 9, există creată o excavație de pământ artificială 30. în zona de fund nepavată 1, există o zonă de val 8 creată prin aceea că volumul total al excavației de pământ 30 este deplasat prin zona compactată 2. Mai mult, în conformitate cu Fig. 10, în zona superioară nepavată 1 există o bermă de reținere 11 creată pentru a distruge porii 62 din pământ și a reține scurgerea apei de ploaie 6. Sub zona superioară nepavată 1 sunt creați pori noi 62 din pământ prin umplerea treptată a bermei de reținere 11 datorită scurgerii apei de ploaie 6. Mai mult, în zona superioară nepavată 1, este creat debleul 31 care este pământ taluzat săpat gros de 100 cm și destinat să distrugă porii 62 din pământ. în spatele debleului 31 este amplasat permanent un perete impermeabil 33 care este o secțiune din beton. Peretele impermeabil 33 este destinat să rețină presiunea pământului excavat din debleu 31. Apă de ploaie 6 se infiltrează prin debleu 31 și curge în jurul pereteluiThe system for retaining rainwater runoff, revitalizing the drainage area and recovering biodiversity, according to Fig. 8, consists of the unpaved upper area 1 which is a drainage area with an inclined slope. In the unpaved upper area 1 an area with an artificial sloping slope 3 is created. Behind the impermeable wall 3, there is a compacted area 2 which is a non-excavated road. Behind the compacted area 2, an unpaved bottom area 1 is created which is an undrained sloping slope area, in the unpaved upper area 1, according to FIG. 9, there is created an artificial earth excavation 30. in the unpaved bottom area 1, there is a wave area 8 created in that the total volume of the earth excavation 30 is displaced through the compacted area 2. Moreover, according to FIG. 10, in the unpaved upper zone 1 there is a retaining berm 11 created to destroy the pores 62 of the earth and to retain the rainwater drain 6. Under the unpaved upper zone 1 new pores 62 of the earth are created by gradually filling the retaining berm 11 due to the run-off of rainwater 6. Moreover, in the unpaved upper area 1, deble 31 is created which is 100 cm thick excavated sloping earth and intended to destroy the pores 62 of the earth. behind the ditch 31 is permanently placed a waterproof wall 33 which is a section of concrete. The waterproof wall 33 is intended to retain the pressure of the earth excavated from the drain 31. Rainwater 6 seeps through the drain 31 and flows around the wall

impermeabil 33 care direcționează apa la apa subterană 7 prin infiltrarea 61 apei și porii 62 din pământ.impermeable 33 which directs water to groundwater 7 by infiltrating 61 water and pores 62 from the ground.

Exemplul 6Example 6

Sistemul pentru reținerea scurgerilor de apă pluvială, revitalizarea zonei de drenaj și recuperarea biodiversității, în conformitate cu Fig. 11, constă din cele două zone nepavate 1 care sunt zonele de drenaj în taluz înclinat. în spatele zonei superioare nepavate 1, există o rigolă taluzată artificială 22 cu o zonă cu taluz înclinat artificială 3. în spatele rigolei taluzate 22, există o zonă compactată 2 care este un drum nesăpat, în spatele zonei compactate 2, există o a doua rigolă taluzată artificială 22 cu o zonă cu taluz înclinat artificială 3. Zona cu taluz înclinat 3 distruge porii 62 din pământ și accelerează scurgerea apei de ploaie 6 prin rigola taluzată 22. în zona superioară nepavată 1, în conformitate cu figura 12, există o excavație de pământ artificială 30 care este creată prin săparea zonei cu taluz înclinat 3.0 parte din excavația de pământ 30 este deplasată prin zona compactată 2 la rigola taluzată 22. în zona de fund nepavată 1 există creată o zonă de val 8 prin care a doua parte a excavației de pământ 30 este deplasată prin zona compactată 2. Mai mult, în zona superioară nepavată 1, în conformitate cu Fig. 13, este creat debleul artificial 31 care este pământ taluzat săpat gros de 100 cm și destinat să distrugă porii 62 din pământ. în spatele debleului 31 este amplasat permanent un perete impermeabil 33, care este o secțiune din beton. Peretele impermeabil 33 este destinat să rețină presiunea pământului excavat în debleu 31. Apă de ploaie 6 se infiltrează prin debleu 31 și curge în jurul peretelui impermeabil 33 care direcționează apa la apa subterană 7 prin porii 62 din pământ.The system for retaining rainwater runoff, revitalizing the drainage area and recovering biodiversity, according to Fig. 11, consists of the two unpaved areas 1 which are the drainage areas in the inclined slope. behind the unpaved upper area 1, there is an artificial sloping gutter 22 with an artificial sloping slope area 3. behind the sloping gutter 22, there is a compacted area 2 which is a non-excavated road, behind the compacted area 2, there is a second sloping gutter artificial 22 with an area with a sloping slope artificial 3. The area with a sloping slope 3 destroys the pores 62 of the earth and accelerates the drainage of rainwater 6 through the sloping gutter 22. in the unpaved upper area 1, according to figure 12, there is an earth excavation artificial 30 which is created by digging the sloping area 3.0 part of the earth excavation 30 is moved through the compacted area 2 to the sloping gutter 22. in the unpaved bottom area 1 there is created a wave area 8 through which the second part of the excavation earth 30 is moved through the compacted area 2. Furthermore, in the unpaved upper area 1, according to FIG. 13, the artificial ditch 31 is created which is 100 cm thick excavated sloping earth and intended to destroy the pores 62 of the earth. behind the ditch 31 is permanently placed a waterproof wall 33, which is a section of concrete. The impermeable wall 33 is intended to retain the pressure of the earth excavated in the excavation 31. Rainwater 6 infiltrates through the excavation 31 and flows around the impermeable wall 33 which directs the water to the groundwater 7 through the pores 62 of the earth.

Exemplul 7Example 7

Sistemul pentru reținerea scurgerilor de apă pluvială, revitalizarea zonei de drenaj și recuperarea biodiversității, în conformitate cu Fig. 11, constă din cele două zone nepavate 1 care sunt zonele de drenaj în taluz înclinat. în spatele zonei superioare nepavate 1, există o rigolă taluzată artificială 22 cu o zonă cu taluz înclinat artificială 3. Zona cu taluz înclinat 3 distruge porii 62 din pământ și accelerează scurgerea apei de ploaie 6 prin rigola taluzată 22. în spatele rigolei taluzate 22, există o zonă compactată 2 care este un drum nesăpat. în spatele zonei compactate 2, există o a doua rigolă taluzată artificială 22 cu o zonă cu taluz înclinat artificială 3. în zona superioară nepavată 1, în conformitate cu figura 14, există o excavație de pământ artificială 30 care este creată prin săparea zonei cu taluz înclinat 3. O parte din excavația de pământ 30 este deplasată prin zona compactată 2 la ambele rigole taluzate 22. în ambele zone nepavate 1, există creată o zonă de val 8 la care a doua parte din excavația de pământ 30 este deplasată prin zona compactată 2. în zona superioară nepavată 1, în conformitate cu Fig. 15, există creat un debleu artificial 31 în așa fel încât zona superioară nepavată 1 este la un unghi de 10 grade. Debleul 31 constă din pământ taluzat săpat gros de 100 cm și destinat să distrugă porii 62 din pământ. în spatele debleului 31 este amplasat permanent un perete impermeabil 33, care este o secțiune din beton. Peretele impermeabil 33 este destinat să rețină presiunea pământului excavat în debleu 31.0 parte a debleului 31 care este lungă de 3 m este înclinată artificial la un unghi de 5 grade în sus la peretele impermeabil 33. Apă de ploaie 6 se infiltrează prin debleu 31 și curge în jurul peretelui impermeabil 33 care direcționează apa la apa subterană 7 prin porii 62 din pământ.The system for retaining rainwater runoff, revitalizing the drainage area and recovering biodiversity, according to Fig. 11, consists of the two unpaved areas 1 which are the drainage areas in the inclined slope. Behind the unpaved upper area 1, there is an artificial sloping gutter 22 with an artificial sloping slope area 3. The sloping slope area 3 destroys the pores 62 of the earth and accelerates the flow of rainwater 6 through the sloping gutter 22. behind the sloping gutter 22, there is a compacted area 2 which is a bumpy road. Behind the compacted area 2, there is a second artificial sloping channel 22 with an artificial sloping area 3. in the unpaved upper area 1, according to figure 14, there is an artificial earth excavation 30 which is created by digging the sloping area 3. A part of the earth excavation 30 is moved through the compacted area 2 at both sloping ditches 22. in both unpaved areas 1, a wave zone 8 is created at which the second part of the earth excavation 30 is moved through the compacted area 2 in the unpaved upper area 1, according to FIG. 15, there is created an artificial excavation 31 such that the unpaved upper area 1 is at an angle of 10 degrees. Deble 31 consists of 100 cm thick excavated sloping earth and intended to destroy pores 62 of the earth. behind the ditch 31 is permanently placed a waterproof wall 33, which is a section of concrete. The impermeable wall 33 is intended to retain the pressure of the earth excavated in the excavation 31.0 part of the excavation 31 which is 3 m long is artificially inclined at an angle of 5 degrees upwards to the impermeable wall 33. Rainwater 6 seeps through the excavation 31 and flows around the impermeable wall 33 which directs the water to the groundwater 7 through the pores 62 of the earth.

Exemplul 8Example 8

Sistemul pentru reținerea scurgerilor de apă pluvială, revitalizarea zonei de drenaj și recuperarea biodiversității, în conformitate cu Fig. 16, constă din cele două zone nepavate 1 care sunt zone de drenaj plate. între zonele nepavate 1 există o zonă compactată 2 care este un drum nesăpat. Pe fiecare latură a zonei compactate 2, există o rigolă artificială 22 creată cu o zonă cu taluz înclinat artificială 3. Zona cu taluz înclinat 3 distruge porii 62 din pământ și accelerează scurgerea apei de ploaie 6 prin rigola taluzată 22. în zona nepavată 1, în conformitate cu figura 17, există două excavații de pământ artificiale 30 care sunt create prin săparea zonei cu taluz înclinat 3. O parte din fiecare excavație de pământ 30 este deplasată la ambele rigole 22. în zona nepavată 1, sunt create două zone de val 8 și care constau din a doua parte din excavația de pământ 30. în zona nepavată 1, în conformitate cu Fig. 18, sunt create două debleuri artificiale 31 care sunt pământ taluzat săpat gros de 100 cm și destinat să distrugă porii 62 din pământ. De-a lungul ambelor laturi ale zonei compactate 2 sunt amplasați permanent pereții impermeabili 33, care sunt o secțiune din beton. Peretele impermeabil 33 este destinat să rețină presiunea pământului săpat în debleu 31. O parte lungă de 3 m a debleului 31 este înclinată artificial la un unghi de 5 grade în susThe system for retaining rainwater runoff, revitalizing the drainage area and recovering biodiversity, according to Fig. 16, consists of the two unpaved areas 1 which are flat drainage areas. between unpaved areas 1 there is a compacted area 2 which is an unpaved road. On each side of the compacted area 2, there is an artificial gutter 22 created with an artificial sloping slope area 3. The sloping slope area 3 destroys the pores 62 of the earth and accelerates the flow of rainwater 6 through the sloping gutter 22. in the unpaved area 1, According to Figure 17, there are two artificial earth excavations 30 which are created by digging the area with a sloping slope 3. Part of each earth excavation 30 is moved to both ditches 22. in the unpaved area 1, two wave areas are created 8 and consisting of the second part of the earth excavation 30. in the unpaved area 1, according to Figs. 18, two artificial excavations 31 are created which are 100 cm thick excavated sloping earth and intended to destroy the pores 62 of the earth. Along both sides of the compacted area 2 are permanently placed the waterproof walls 33, which are a section of concrete. The impermeable wall 33 is intended to retain the pressure of the earth dug in the excavation 31. A 3 m long part of the excavation 31 is artificially inclined at an angle of 5 degrees upwards

RO 135120 Α2 ț la peretele impermeabil 33. Apă de ploaie 6 se infiltrează prin debleu 31 și curge în jurul peretelui impermeabil 33 care direcționează apa la apa subterană 7 prin porii 62 din pământ.RO 135120 Α2 ț to the impermeable wall 33. Rainwater 6 infiltrates through the drain 31 and flows around the impermeable wall 33 which directs the water to the groundwater 7 through the pores 62 of the earth.

Exemplul 9Example 9

Sistemul pentru reținerea scurgerilor de apă pluvială, revitalizarea zonei de drenaj și recuperarea biodiversității, în conformitate cu Fig. 19, constă din cele două zone nepavate 1 care sunt zone de drenaj plate. între zonele nepavate 1 există o zonă compactată 2 care este un drum nesăpat. Sub zona compactată 2, există creată un dig compactat artificial 12. Pe fiecare latură a digului compactat 12 există creată o rigolă artificială 22 cu o zonă cu taluz înclinat artificială 3. Zona cu taluz înclinat 3 distruge porii 62 din pământ și accelerează scurgerea apei de ploaie 6 prin rigola taluzată 22. în zona nepavată 1, în conformitate cu figura 20, există două excavații de pământ artificiale 30 care sunt create prin săparea zonei cu taluz înclinat 3. O parte din excavația de pământ 30 este deplasată la rigolă 22. în zona nepavată 1, în conformitate cu Fig. 21, sunt create două debleuri artificiale 31 care sunt pământ taluzat săpat gros de 100 cm și destinat să distrugă porii 62 din pământ. Apă de ploaie 6 se infiltrează prin debleu 31 care direcționează apa la apa subterană 7 prin porii 62 din pământ.The system for retaining rainwater runoff, revitalizing the drainage area and recovering biodiversity, according to Fig. 19, consists of the two unpaved areas 1 which are flat drainage areas. between unpaved areas 1 there is a compacted area 2 which is an unpaved road. Under the compacted zone 2, an artificial compacted dam 12 is created. On each side of the compacted dam 12 there is created an artificial gutter 22 with an artificial sloping area 3. The sloping slope area 3 destroys the pores 62 of the earth and accelerates the flow of water. rain 6 through the sloping ditch 22. in the unpaved area 1, according to figure 20, there are two artificial earth excavations 30 which are created by digging the sloping slope area 3. Part of the earth excavation 30 is moved to the ditch 22. in unpaved area 1, according to FIG. 21, two artificial excavations 31 are created which are 100 cm thick excavated sloping earth and intended to destroy the pores 62 of the earth. Rainwater 6 infiltrates through the drain 31 which directs the water to the groundwater 7 through the pores 62 of the earth.

Aplicabilitatea TehnicăTechnical Applicability

Sistemul pentru reținerea scurgerilor de apă pluvială, revitalizarea zonei de drenaj și refacerea biodiversității poate fi utilizat pentru a împiedica eroziunea pământului, a crește capacitatea de reținere a apei a păturii de pământ expuse la ploaie, restrângerea semnificativă a scurgerii apei pluviale din pătura de pământ, completarea apei freatice și ca atare revitalizarea regimului hidrologic al pădurilor, pajiștilor și terenului agricol, crearea a noi resurse mici de apă, protecția zonelor împotriva secetei, incendiilor și revărsărilor, refacerea biodiversității, stabilizarea climatică și temperarea fluctuațiilor meteorologice. în plus față de saturația pământului și creșterea resurselor de apă freatică, se poate asuma că precipitațiile vor fi mai echilibrate. în domeniul zonei de protecție contra inundațiilor aplicabilitatea invenției comută importanța de la protejarea ariei supusă la inundații și revărsări la prevenirea și controlul inundațiilor, și de asemenea, în domeniul protecției contra secetei, de la măsuri de siguranță la momentul secetei la măsuri de prevenire a secetei, adică întreținerea generală a terenului agricol și forestier în bune condiții pentru a gestiona și controla în mod rezonabil precipitațiile și a asigura suficiente resurse de apă pe teren. Aplicabilitatea invenției va asigura capacitatea zonei de a recupera performanța funcțiilor sale naturale atunci când distribuie apă pluvială la rădăcinile plantelor, sursele de torenți și apa freatică. Pentru a împiedica apa pluvială să se scurgă prin rigole, drumuri și zone compactate și pentru a o face să se infiltreze în porii din pământ, o parte de 3 m lungime a debleului este înclinată artificial la un unghi de 5 la 10 grade în sus la peretele impermeabil.The system for retaining rainwater runoff, revitalizing the drainage area and restoring biodiversity can be used to prevent soil erosion, increase the water retention capacity of the soil layer exposed to rain, significantly restrict the runoff of rainwater from the soil layer, the completion of groundwater and as such the revitalization of the hydrological regime of forests, meadows and agricultural land, the creation of new small water resources, the protection of areas against drought, fires and spills, the restoration of biodiversity, climate stabilization and weather fluctuations. In addition to soil saturation and increasing groundwater resources, it can be assumed that rainfall will be more balanced. In the field of flood protection the applicability of the invention shifts the importance from flood protection and flooding to flood prevention and control, and also in the field of drought protection, from safety measures at the time of drought to drought prevention measures. , ie general maintenance of agricultural and forestry land in good condition to reasonably manage and control rainfall and ensure sufficient water resources on the land. The applicability of the invention will ensure the ability of the area to recover the performance of its natural functions when distributing rainwater to plant roots, torrent sources and groundwater. To prevent rainwater from flowing through ditches, roads and compacted areas and to cause it to infiltrate into the earth's pores, a 3 m long part of the deble is artificially inclined at an angle of 5 to 10 degrees upwards to the wall. impervious.

Lista semnelor de referințăList of reference signs

- zonă nepavată- unpaved area

- bermă de reținere- restraint

- dig compactat- compacted dam

- zonă compactată- compacted area

- formațiunea laterală a sântului- the lateral formation of the saint

- rigolă- gutter

- zonă de taluz înclinat- sloping slope area

- excavație de pământ- earth excavation

-debleu-you have to

- pietre- stones

- perete impermeabil- waterproof wall

- șanț taluzat adânc- deep sloping ditch

- folie pentru șanț- ditch foil

- pământ excavat din șanț- earth excavated from the ditch

- șanț de captare a apei pluviale- rainwater catchment ditch

- bermă de accelerare- acceleration berm

- apă de ploaie- Rain water

- infiltrarea apei- water infiltration

- porii din pământ- pores in the earth

- apa freatică- groundwater

- zona de val- valley area

- șanț săpat- dug trench

- scurgere săpată- excavated drain

Claims (4)

REVENDICĂRIdemand 1. Sistem pentru reținerea scurgerilor de apă de ploaie, revitalizarea zonei de drenaj și recuperarea biodiversității caracterizat prin aceea că el constă din cel puțin o zonă nepavată (1) cu apă de ploaie (6) legată cu apa subterană (7) prin infiltrarea (61) apei și porii (62) din pământ; în această zonă nepavată este creată cel puțin o bermă de reținere (11) în spatele căreia există cel puțin un șanț artificial taluzat adânc (4) creat cu o folie (41) pentru șanț unde este amplasat pământul (42) excavat din șanț și în spatele său, există cel puțin o zonă cu taluz înclinat (3) cu un debleu (31) creat într-o zonă nepavată (1); în partea de fund a debleului există cel puțin o scurgere artificială săpată (91) creată cu pietre nefixate (32) și cel puțin un perete impermeabil amplasat permanent (33) în spatele căruia este creată o zonă compactată (2) cu o zonă de val artificială (8) în spatele său.1. A system for retaining rainwater runoff, revitalizing the drainage area and recovering biodiversity, characterized in that it consists of at least one unpaved area (1) with rainwater (6) connected to groundwater (7) by infiltration ( 61) water and pores (62) of the earth; in this unpaved area at least one retaining berm (11) is created behind which there is at least one deep sloping artificial ditch (4) created with a ditch foil (41) where the earth (42) excavated from the ditch is located and in behind it, there is at least one area with a sloping slope (3) with a excavation (31) created in an unpaved area (1); at the bottom of the excavation there is at least one artificial drain (91) created with loose stones (32) and at least one permanently placed waterproof wall (33) behind which a compacted area (2) is created with a wave area artificial (8) behind it. 2. Sistemul pentru reținerea scurgerilor de apă de ploaie, revitalizarea zonei de drenaj și recuperarea biodiversității în conformitate cu revendicarea 1 caracterizat prin aceea că în partea de fund a debleului (31) există creat cel puțin un șanț săpat (9) și în zona compactată (2) este creat cel puțin un șanț de captare a apei pluviale (5) cu cel puțin o bermă șanț de accelerare (51); în spatele șanțului de captare a apei pluviale, există o zonă de val (8) creată pe o latură cu formațiunea laterală a șanțului (21).System for the retention of rainwater runoff, revitalization of the drainage area and recovery of biodiversity according to claim 1, characterized in that at least one excavated trench (9) is created in the bottom of the embankment (31) and in the compacted area (2) at least one rainwater catchment ditch (5) with at least one acceleration ditch berm (51) is created; behind the rainwater catchment ditch, there is a wave area (8) created on one side with the lateral formation of the ditch (21). 3. Sistemul pentru reținerea scurgerilor de apă pluvială, revitalizarea zonei de drenaj și refacerea biodiversității în conformitate cu revendicarea 1 caracterizat prin aceea că în zona nepavată (1) este creată cel puțin o excavație de pământ artificială (30).The system for retaining rainwater runoff, revitalizing the drainage area and restoring biodiversity in accordance with claim 1, characterized in that at least one artificial earth excavation is created in the unpaved area (1) (30). 4. Sistemul pentru reținerea scurgerilor de apă pluvială, revitalizarea zonei de drenaj și refacerea biodiversității în conformitate cu revendicarea 1, caracterizat prin aceea că de-a lungul ambelor laturi ale zonei compactate (2) este creată cel puțin o rigolă artificială (22) cu o zonă cu taluz înclinat artificial (3).The system for retaining rainwater runoff, revitalizing the drainage area and restoring biodiversity in accordance with claim 1, characterized in that at least one artificial gutter (22) is created along both sides of the compacted area (2) with an area with an artificially inclined slope (3).
RO202000855A 2020-01-02 2020-12-22 System for retention of rainwater, revitalization of drained soil, and restoration of biodiversity RO135120A2 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SK1-2020U SK9007Y1 (en) 2020-01-02 2020-01-02 System for retention of rainwater runoff, revitalization of drained soil and restoring biodiversity

Publications (1)

Publication Number Publication Date
RO135120A2 true RO135120A2 (en) 2021-07-30

Family

ID=72291241

Family Applications (1)

Application Number Title Priority Date Filing Date
RO202000855A RO135120A2 (en) 2020-01-02 2020-12-22 System for retention of rainwater, revitalization of drained soil, and restoration of biodiversity

Country Status (6)

Country Link
AT (1) AT523365A2 (en)
DE (1) DE102020135027A1 (en)
FR (1) FR3105978A1 (en)
PL (1) PL242650B1 (en)
RO (1) RO135120A2 (en)
SK (1) SK9007Y1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115305863A (en) * 2022-08-17 2022-11-08 西安理工大学 Slope-bank zone-water body integrated water ecological comprehensive treatment mode for small watershed

Also Published As

Publication number Publication date
AT523365A2 (en) 2021-07-15
PL436481A1 (en) 2022-05-09
SK12020U1 (en) 2020-09-03
PL242650B1 (en) 2023-04-03
DE102020135027A1 (en) 2021-07-08
FR3105978A1 (en) 2021-07-09
SK9007Y1 (en) 2021-01-27

Similar Documents

Publication Publication Date Title
CN106087953A (en) A kind of drainage and construction method preventing and treating large-scale spoil ground, mountain area mud-rock flow
US20200277747A1 (en) Express flood mitigation works using elevated and or at ground level with tunnel integrated large scale aqueduct with numerous functions, with main function to divert flood water or river water away from cities in order to fight or mitigate flood events and effect of global warming, with discharge invert levels to the sea higher than high tide levels
RO135120A2 (en) System for retention of rainwater, revitalization of drained soil, and restoration of biodiversity
CZ24865U1 (en) System for retention of meteoric water drainage and revitalization of compacted soil on a slope
CN208701703U (en) A kind of expansive soil cut slope support structure of anti-row's one
RU2763752C1 (en) Method for restoring the geophysical stability of an emergency ground dam on a weak foundation
CN112281912A (en) Protective system for abandoned river soil field on river beach in steep mountain area and construction method of protective system
Caldwell et al. Geotechnical stability considerations in the design and reclamation of tailings impoundments
CZ2020659A3 (en) Rainwater runoff containment system, revitalizing drained soil and restoring biodiversity
SK582022A3 (en) System for retention of rainwater runoff, revitalization of drained soil and restoring biodiversity
Martin-Rosales et al. Sediment yield estimation and check dams in a semiarid area (Sierra de Gádor, southern Spain)
CN103233440A (en) Slag type debris flow formation mechanism based prevention method
CZ26113U1 (en) System for retention of discharge of atmospheric water and revitalization of compacted soil on a slope
JP2022084334A (en) Drainage structure for valley terrain and culvert block
CZ28542U1 (en) System to hold outflow of precipitations and revitalization of consolidated soil on slope
CN217580027U (en) Upper reservoir arrangement structure of pumped storage power station
CN203462485U (en) Open-cut road river bottom tunnel for road construction encountering river
SK7535Y1 (en) System of rainwater retention and revitalization of soil compaction on slope
CN208309753U (en) A kind of high gradient slope water draining and accumulating system
Hasanov et al. CHANNEL THAT CAN BE USED ON SLOPE, SLIDE PRONE AND SEISMIC AREAS, SWELLING AND COLLAPSING SOILS
Santoro et al. Angkor Wat west embankment-restoration and strengthening of the backfill by means of a composite geotextile
Satyanarayana Reddy Issues Related to Erosion and Its Effects on Structures in Visakhapatnam
Rimoldi et al. Base and slope reinforcement of very tall reinforced embankments for the A1 highway in Italy
CN115075205A (en) Upper reservoir arrangement structure of pumped storage power station
CN116591101A (en) Coastal composite toughness embankment structure and construction method