NO346091B1 - Device for mounting floating wind turbines - Google Patents
Device for mounting floating wind turbines Download PDFInfo
- Publication number
- NO346091B1 NO346091B1 NO20200157A NO20200157A NO346091B1 NO 346091 B1 NO346091 B1 NO 346091B1 NO 20200157 A NO20200157 A NO 20200157A NO 20200157 A NO20200157 A NO 20200157A NO 346091 B1 NO346091 B1 NO 346091B1
- Authority
- NO
- Norway
- Prior art keywords
- jack
- elements
- wire
- column
- winch
- Prior art date
Links
- 238000007667 floating Methods 0.000 title claims description 14
- 238000009434 installation Methods 0.000 description 5
- 238000005516 engineering process Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 238000004873 anchoring Methods 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 238000010248 power generation Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 230000001360 synchronised effect Effects 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/18—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
- B66C23/185—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use erecting wind turbines
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/18—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
- B66C23/20—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes with supporting couples provided by walls of buildings or like structures
- B66C23/207—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes with supporting couples provided by walls of buildings or like structures with supporting couples provided by wind turbines
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/62—Constructional features or details
- B66C23/64—Jibs
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/34—Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
- E04H12/342—Arrangements for stacking tower sections on top of each other
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D13/00—Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
- F03D13/20—Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
- F03D13/25—Arrangements for mounting or supporting wind motors; Masts or towers for wind motors specially adapted for offshore installation
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B35/00—Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
- B63B35/44—Floating buildings, stores, drilling platforms, or workshops, e.g. carrying water-oil separating devices
- B63B2035/4433—Floating structures carrying electric power plants
- B63B2035/446—Floating structures carrying electric power plants for converting wind energy into electric energy
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
- E02B2017/0091—Offshore structures for wind turbines
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D13/00—Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
- F03D13/10—Assembly of wind motors; Arrangements for erecting wind motors
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F05—INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
- F05B—INDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
- F05B2230/00—Manufacture
- F05B2230/60—Assembly methods
- F05B2230/61—Assembly methods using auxiliary equipment for lifting or holding
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/72—Wind turbines with rotation axis in wind direction
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/727—Offshore wind turbines
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/728—Onshore wind turbines
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P70/00—Climate change mitigation technologies in the production process for final industrial or consumer products
- Y02P70/50—Manufacturing or production processes characterised by the final manufactured product
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Sustainable Development (AREA)
- Sustainable Energy (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- General Engineering & Computer Science (AREA)
- Wind Motors (AREA)
- Jib Cranes (AREA)
Description
MONTASJEANORDNING OG METODE FOR MONTERING AV FLYTENDE VINDTURBINER ASSEMBLY DEVICE AND METHOD FOR ASSEMBLY OF FLOATING WIND TURBINES
Denne oppfinnelsen vedrører en anordning for å kunne montere vindturbiner uten bruk av eksterne heisekraner fundamentert i bakkenivå. Nærmere bestemt dreier det seg om en anordning der en tårnstruktur til selve vindturbinen benyttes til en bærende struktur for montasjeanordningen. This invention relates to a device for being able to mount wind turbines without the use of external cranes based at ground level. More specifically, it concerns a device where a tower structure for the wind turbine itself is used as a supporting structure for the assembly device.
Bakgrunn for oppfinnelsen Background for the invention
En moderne vindturbin består i hovedsak av en sylindrisk tårnstruktur hvor det på toppen av tårnstrukturen er montert en propell som via aksling og opplagring kobles til en generator. I tillegg til generator er det anbrakt nødvendig hjelpeutstyr som transformator og styre – og kontrollanlegg. A modern wind turbine mainly consists of a cylindrical tower structure where a propeller is mounted on top of the tower structure and is connected to a generator via shafting and storage. In addition to the generator, the necessary auxiliary equipment such as a transformer and steering - and control system has been installed.
Toppstrukturen (nacellen) er opplagret mot en sylindrisk tårnstruktur med lager, slik at nacellen kan roteres om en vertikalakse til tårnstrukturen og tilpasses varierende vindretninger. The top structure (the nacelle) is supported against a cylindrical tower structure with bearings, so that the nacelle can be rotated about a vertical axis to the tower structure and adapted to varying wind directions.
Vindturbinene har utviklet seg fra små landbaserte vindturbiner på 200-300 kW til dagens store turbiner på ca.10 MW. Hovedstrukturen på oppbyggingen er den samme, det er i all hovedsak bare foretatt en skalering av dimensjoner og arrangement. The wind turbines have developed from small land-based wind turbines of 200-300 kW to today's large turbines of approx. 10 MW. The main structure of the build-up is the same, there has essentially only been a scaling of dimensions and arrangement.
Nå er det under planlegging og utvikling store flytende vindturbiner opp mot 15 – 20 MW installert effekt. Large floating wind turbines with an installed power of up to 15-20 MW are now being planned and developed.
På dagens vindturbiner bygges nacellen i en samlet konstruksjon som heises opp på toppen av tårnstrukturen når denne er montert opp i full høyde. Vindturbiner på ca. 10 MW har gjerne en tårnhøyde på ca.200m og en nacellevekt på 300 – 400 tonn. Når 300 – 400 tonn skal heises ca.200 m opp kreves store og kostbare heiseinnretninger. For flytende vindturbiner er utfordringen i tillegg at det må benyttes flytende fundament for heiseinnretningen som igjen påvirkes av bølgebevegelser. Tidsintervallene for akseptable bølgeforhold blir svært korte noe som medfører at montasje av flytende vindturbiner er teknisk krevende og kostbart. On today's wind turbines, the nacelle is built in an integrated construction that is lifted up on top of the tower structure when it has been assembled to its full height. Wind turbines of approx. 10 MW usually has a tower height of approx. 200m and a nacelle weight of 300 - 400 tonnes. When 300 - 400 tonnes are to be lifted approx. 200 m up, large and expensive lifting devices are required. For floating wind turbines, the additional challenge is that a floating foundation must be used for the lifting device, which in turn is affected by wave movements. The time intervals for acceptable wave conditions are very short, which means that the installation of floating wind turbines is technically demanding and expensive.
Patentdokumentet US2018282134 beskriver en kran for montering av en flerhet søyleelementer for en flytende vindturbin omfattende en nacelle og propellblader. Kranen festes til én side av et søyleelementene, i det hver av søyleelementene omfatter et utvendig feste for kranen. Kranen forflyttes trinnvis oppover ved hjelp av hydrauliske sylindre. Én ulempe med denne løsningen, er at søyleelementene påføres et bøyemoment i det kranen kun er montert på én side. Alternativt kan det brukes to kraner, én på hver side av søyleelementene. En ulempe med dette, er at det kreves en synkron betjening av de to kranene, noe som kompliserer monteringen. I tillegg må hvert av søyleelementene ha dobbelt sett med fester for kranen. The patent document US2018282134 describes a crane for mounting a plurality of column elements for a floating wind turbine comprising a nacelle and propeller blades. The crane is attached to one side of one of the column elements, in that each of the column elements comprises an external attachment for the crane. The crane is moved upwards in steps using hydraulic cylinders. One disadvantage of this solution is that the column elements are subjected to a bending moment when the crane is only mounted on one side. Alternatively, two cranes can be used, one on each side of the column elements. A disadvantage of this is that synchronous operation of the two cranes is required, which complicates the installation. In addition, each of the column elements must have a double set of fasteners for the crane.
Oppfinnelsen har til formål å avhjelpe eller å redusere i det minste én av ulempene ved kjent teknikk, eller i det minste å skaffe til veie et nyttig alternativ til kjent teknikk. The purpose of the invention is to remedy or to reduce at least one of the disadvantages of known technology, or at least to provide a useful alternative to known technology.
Formålet oppnås ved trekkene som er angitt i nedenstående beskrivelse og i de etterfølgende patentkravene. The purpose is achieved by the features indicated in the description below and in the subsequent patent claims.
Generell beskrivelse av oppfinnelsen General description of the invention
Det er tilveiebrakt en montasjeanordning som gjør det mulig å montere en vindturbin med en sylindrisk stålstruktur, en nacelle og en propell ved hjelp av en montasjeanordning som klatrer og benytter selve tårnstrukturen som del av en bærende struktur. Med tårnstruktur kan det heri forstås en søyle. A mounting device is provided which makes it possible to mount a wind turbine with a cylindrical steel structure, a nacelle and a propeller by means of a mounting device which climbs and uses the tower structure itself as part of a supporting structure. A tower structure can here be understood as a pillar.
For å oppnå dette benyttes to sylindriske langstrakte jekkeelement som vekselvis festes til tårnstrukturen. Tårnstrukturen settes sammen av langstrakte søyleelementer som stables oppå hverandre i passende lengder. To achieve this, two cylindrical elongated jack elements are used which are alternately attached to the tower structure. The tower structure is assembled from elongated column elements that are stacked on top of each other in suitable lengths.
Jekkeelementene festes til flensforbindelser mellom hvert sylindrisk søyleelement og forskyves en seksjon oppover. På toppen av det ene jekkeelementet er det anbrakt en kranbom med hydrauliske sylindere slik at kranbommen kan hente opp søyleelementer og plassere disse sentrisk over tidligere oppsatte søyleelementer. Forskyvning av jekkeelementene utføres med wire og vinsjer som står på en arbeidsplattform festet til det nederste søyleelementet. The jack elements are attached to flange connections between each cylindrical column element and are offset one section upwards. A crane boom with hydraulic cylinders is placed on top of one jacking element so that the crane boom can pick up column elements and place them centrally over previously installed column elements. Displacement of the jacking elements is carried out with wire and winches that stand on a work platform attached to the bottom column element.
Montering av nacellen utføres ved at selve nacellen er delt opp i flere moduler slik at vekten av hver modul er akseptabel i forhold til kranbommen på jekkeelementet. For mindre vindturbiner monteres nacellen i én modul. Kranbommen på toppen av jekkeelementet svinger inn nacellemodulene i posisjon. Oppheising skjer med wire og vinsjer. Selve propellbladene heises også opp med kranbommen og wire og festes til navet. Assembly of the nacelle is carried out by dividing the nacelle into several modules so that the weight of each module is acceptable in relation to the crane boom on the jacking element. For smaller wind turbines, the nacelle is mounted in one module. The crane boom on top of the jack element swings the nacelle modules into position. Hoisting is done with wire and winches. The propeller blades themselves are also hoisted up with the crane boom and wire and attached to the hub.
Når monteringen av vindturbinen er fullført heises jekkeelementene ned og demonteres. When the assembly of the wind turbine is completed, the jacking elements are lifted down and dismantled.
Oppfinnelsen skal nå forklares nærmere med henvisning til figurer som anskueliggjør et foretrukket utførelseseksempel. The invention will now be explained in more detail with reference to figures which illustrate a preferred embodiment.
Fig.1 viser en flytende vindturbin med en søyle og et flytefundament med forankring; Fig.1 shows a floating wind turbine with a column and a floating foundation with anchoring;
Fig.2 viser et flytende fundament og et fartøy med vindturbinkomponenter; Fig.2 shows a floating foundation and a vessel with wind turbine components;
Fig.3 viser montert et første søyleelement og et jekkeelement med en kranbom; Fig.3 shows mounted a first column element and a jack element with a crane boom;
Fig.4 viser detalj A fra fig 3; Fig. 4 shows detail A from Fig. 3;
Fig.5 viser detalj B fra fig 3; Fig. 5 shows detail B from Fig. 3;
Fig.6 viser montering av søylen fra fartøyet; Fig.6 shows assembly of the column from the vessel;
Fig.7 viser detalj B fra fig 6; Fig. 7 shows detail B from Fig. 6;
Fig.8 viser et sylindrisk søyleelement; Fig.8 shows a cylindrical column element;
Fig.9 viser detalj B fra fig 8; Fig.9 shows detail B from Fig.8;
Fig.10 viser detalj av et låseelement; Fig.10 shows detail of a locking element;
Fig.11 viser et andre jekkeelement 13; Fig.11 shows a second jack element 13;
Fig.12 viser et første jekkeelement 12 med en kranbom; Fig.12 shows a first jack element 12 with a crane boom;
Fig.13 viser montering av nacelleelementer og propellblader; Fig.13 shows the installation of nacelle elements and propeller blades;
Fig.14 viser en topp av det sylindriske søyleelement med låseklakker; og Fig.14 shows a top of the cylindrical column element with locking lugs; and
Fig.15 viser snitt A- A fra fig 14. Fig. 15 shows section A-A from fig. 14.
På figurene angir henvisningstallet 1 en vertikal sylindrisk søyle satt sammen av sylindriske søyleelement 11. Søylen 1 er montert vertikalt til et flytefundament 5 med forankringer 10. Over en havoverflate 4 er det anordnet en arbeidsplattform 9 til bruk ved installasjon. På toppen av søylen 1 er det montert en nacelle 3 som inneholder tekniske installasjoner som generator og kontrollanlegg. En propell 200 roterer når vinden blåser, og gir kraft til strømproduksjon. In the figures, the reference number 1 denotes a vertical cylindrical column composed of cylindrical column elements 11. The column 1 is mounted vertically to a floating foundation 5 with anchorages 10. Above a sea surface 4, a working platform 9 is arranged for use during installation. A nacelle 3 is mounted on top of the pillar 1, which contains technical installations such as a generator and control system. A propeller 200 rotates when the wind blows, providing power for power generation.
Når vindturbinen skal monteres er flytefundamentet 5 forankret og posisjonert på planlagt sted. Deretter ankommer et fartøy 7 med alle komponentene som skal til for å montere vindturbinen. En kran 8 benyttes til å håndtere de enkelte vindturbinelementene fra fartøyet 7 til riktig monteringsposisjon. When the wind turbine is to be installed, the floating foundation 5 is anchored and positioned in the planned location. A vessel 7 then arrives with all the components needed to mount the wind turbine. A crane 8 is used to handle the individual wind turbine elements from the vessel 7 to the correct mounting position.
Første trinn i monteringen er montering av et første vertikalt søyleelement 11 til flytefundamentet 5. Monteringen utføres med kranen 8. Når denne monteringen er utført monteres et første jekkeelement 12 og et andre jekkeelement 13 bestående av halvsirkelelementer og skrudd sammen med flensforbindelser 16 og 17. The first step in the assembly is the assembly of a first vertical column element 11 to the floating foundation 5. The assembly is carried out with the crane 8. When this assembly has been carried out, a first jack element 12 and a second jack element 13 consisting of semi-circular elements and screwed together with flange connections 16 and 17 are mounted.
Det første jekkeelement 12 er forsynt med en kranbom 14 opplagret i bolteforbindelsen 20 og betjent av hydrauliske sylindere 15. Kranbommen 14 er videre forsynt med wireruller 18 for en wire 21 som er forbundet til en vinsj 22 plassert på en arbeidsplattform 9. The first jacking element 12 is provided with a crane boom 14 stored in the bolt connection 20 and operated by hydraulic cylinders 15. The crane boom 14 is also provided with wire rollers 18 for a wire 21 which is connected to a winch 22 placed on a work platform 9.
Jekkeelementene 12 og 13 festes til flensforbindelser 24 mellom søyleelementene 11 med klakker 25 som går i inngrep 27 mot flensen 24. The jack elements 12 and 13 are attached to flange connections 24 between the column elements 11 with lugs 25 that engage 27 against the flange 24.
Ett søyleelement 11 heises nå på plass vertikalt ved hjelp av kranbommen 14 og wiren 21 koblet til vinsjen 22 plassert på arbeidsplattformen 9. One column element 11 is now lifted into place vertically by means of the crane boom 14 and the wire 21 connected to the winch 22 placed on the work platform 9.
Søyleelementet 11 forbindes til nedenfor søyleelement 11 med flens 24 og skrueforbindelse. Column element 11 is connected to below column element 11 with flange 24 and screw connection.
Klakkeforbindelsen 27 på det første jekkeelement 12 frigjøres og det første jekkeelementet 12 heises opp ved hjelp av en første vinsj 50 og en første wire 30 over wireruller 55 festet til det andre jekkeelementet 13 videre til feste 31 på det første jekkeelementet 12. The lug connection 27 on the first jacking element 12 is released and the first jacking element 12 is raised by means of a first winch 50 and a first wire 30 over wire rollers 55 attached to the second jacking element 13 further to attachment 31 on the first jacking element 12.
Det første jekkeelement 12 festes nå til toppen av oppheist søyleelement 11 med klakker 25 i inngrep mot flensen 24. The first jack element 12 is now attached to the top of the raised column element 11 with lugs 25 in engagement with the flange 24.
Det andre jekkeelement 13 heises deretter opp ved hjelp av en andre vinsj 35 og en andre wire 30 over wireruller 41 og festet til det første jekkeelement 12 i punkt 36. Det andre jekkeelementet 13 festes nå til flensforbindelsen 24 mellom oppheist og nedenfor søyleelementer 11 med klakker 25. The second jacking element 13 is then hoisted up using a second winch 35 and a second wire 30 over wire rollers 41 and attached to the first jacking element 12 at point 36. The second jacking element 13 is now attached to the flange connection 24 between the hoisted and below column elements 11 with lugs 25.
Det første jekkeelement 12 med kranbommen 14 er nå stabilt festet til søylen 1 og i posisjon for oppheising av neste søyleelement 11. Prosessen gjentas til et ønsket antall søyleelementer 11 er plassert. The first jack element 12 with the crane boom 14 is now stably attached to the column 1 and in position for lifting the next column element 11. The process is repeated until a desired number of column elements 11 have been placed.
Etter at ønsket antall søyleelementer 11 er plassert heises nacelleelementer 45, 46 og 47 på plass ved hjelp av wiren 21 og vinsjen 22. After the desired number of column elements 11 have been placed, the nacelle elements 45, 46 and 47 are lifted into place using the wire 21 and the winch 22.
Navet 48 for propellbladene 2 heises også på plass ved hjelp av kranbommen 14 og wire 21, deretter heises propellbladene 2 på plass ved bruk av heiseverktøyet 49. The hub 48 for the propeller blades 2 is also lifted into place using the crane boom 14 and wire 21, then the propeller blades 2 are lifted into place using the lifting tool 49.
Når montasjen er fullført heises jekkeelementene 12 og 13 ned og demonteres. When assembly is complete, the jack elements 12 and 13 are lifted down and dismantled.
Claims (3)
Priority Applications (4)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
NO20200157A NO346091B1 (en) | 2020-02-07 | 2020-02-07 | Device for mounting floating wind turbines |
EP21750481.0A EP4100354A4 (en) | 2020-02-07 | 2021-02-08 | Crane system for assembling a wind turbine and a method for using the crane system |
PCT/NO2021/050038 WO2021158123A1 (en) | 2020-02-07 | 2021-02-08 | Crane system for assembling a wind turbine and a method for using the crane system |
NO20210161A NO346750B1 (en) | 2020-02-07 | 2021-02-08 | Crane system for mounting a wind turbine and method of using the crane system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
NO20200157A NO346091B1 (en) | 2020-02-07 | 2020-02-07 | Device for mounting floating wind turbines |
Publications (2)
Publication Number | Publication Date |
---|---|
NO20200157A1 NO20200157A1 (en) | 2021-08-09 |
NO346091B1 true NO346091B1 (en) | 2022-02-07 |
Family
ID=77199375
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
NO20200157A NO346091B1 (en) | 2020-02-07 | 2020-02-07 | Device for mounting floating wind turbines |
NO20210161A NO346750B1 (en) | 2020-02-07 | 2021-02-08 | Crane system for mounting a wind turbine and method of using the crane system |
Family Applications After (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
NO20210161A NO346750B1 (en) | 2020-02-07 | 2021-02-08 | Crane system for mounting a wind turbine and method of using the crane system |
Country Status (3)
Country | Link |
---|---|
EP (1) | EP4100354A4 (en) |
NO (2) | NO346091B1 (en) |
WO (1) | WO2021158123A1 (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2014082176A1 (en) * | 2012-11-27 | 2014-06-05 | Marmen Inc. | Lifting system for wind turbine towers and method for erecting a wind turbine tower |
CA3049516A1 (en) * | 2017-01-16 | 2018-07-19 | Mammoet Holding B.V. | Method for onshore or offshore erecting an upstanding construction |
US20180282134A1 (en) * | 2015-10-01 | 2018-10-04 | Lagerwey Wind B.V. | Hoisting system for installing a wind turbine |
NL2021913B1 (en) * | 2018-11-01 | 2020-05-14 | Mammoet Holding B V | Method for onshore or offshore erecting an upstanding construction |
Family Cites Families (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1228040B (en) * | 1961-09-19 | 1966-11-03 | Markus Schmidt Tychsen Derrick | Crane whose column is built up from a plurality of mast elements |
US6868646B1 (en) * | 2002-12-13 | 2005-03-22 | Valmont Industries, Inc. | Method and means for erecting a wind energy tower |
DE202005009236U1 (en) * | 2005-05-09 | 2006-09-21 | Liebherr-Werk Biberach Gmbh | Rotating tower crane, in tower sections, has a traverse and support shoe with hydraulic piston/cylinder units to raise a section for the insertion of a new section to increase the crane height |
ATE517254T1 (en) * | 2006-05-20 | 2011-08-15 | W2E Wind To Energy Gmbh | DEVICE FOR BUILDING A WIND TURBINE TOWER COMPOSED OF INDIVIDUAL TOWER SEGMENTS |
US8601748B2 (en) * | 2009-09-09 | 2013-12-10 | National Oilwell Varco, L.P. | Method and apparatus for wind turbine erection |
DE102011102316A1 (en) * | 2011-05-25 | 2012-11-29 | Philipp Wagner | Multi-stage process for the erection and maintenance of wind turbines |
US9238923B2 (en) * | 2012-12-21 | 2016-01-19 | Acciona Windpower, S.A. | Wind turbine assembly system |
AU2015212355B2 (en) * | 2014-01-31 | 2019-05-16 | Gregory John Neighbours | A concrete tower and related formwork and related method of construction |
NL2012614B1 (en) * | 2014-04-14 | 2016-05-09 | Kig Heerenveen Bv | Mast system for building a mast. |
EP3163069B1 (en) * | 2015-10-30 | 2020-10-21 | Nordex Energy Spain, S.A. | Wind turbine assembly system and associated method |
DK3406896T3 (en) * | 2017-03-30 | 2020-08-10 | Sling Supply International Sa | WIND TURBLE INSTALLATION AND DISASSEMBLY SYSTEM |
WO2019216866A1 (en) * | 2018-06-22 | 2019-11-14 | Landau Mykhailo | Method of installing tall and super-tall towers |
-
2020
- 2020-02-07 NO NO20200157A patent/NO346091B1/en unknown
-
2021
- 2021-02-08 EP EP21750481.0A patent/EP4100354A4/en active Pending
- 2021-02-08 WO PCT/NO2021/050038 patent/WO2021158123A1/en active Search and Examination
- 2021-02-08 NO NO20210161A patent/NO346750B1/en unknown
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2014082176A1 (en) * | 2012-11-27 | 2014-06-05 | Marmen Inc. | Lifting system for wind turbine towers and method for erecting a wind turbine tower |
US20180282134A1 (en) * | 2015-10-01 | 2018-10-04 | Lagerwey Wind B.V. | Hoisting system for installing a wind turbine |
CA3049516A1 (en) * | 2017-01-16 | 2018-07-19 | Mammoet Holding B.V. | Method for onshore or offshore erecting an upstanding construction |
NL2021913B1 (en) * | 2018-11-01 | 2020-05-14 | Mammoet Holding B V | Method for onshore or offshore erecting an upstanding construction |
Also Published As
Publication number | Publication date |
---|---|
NO20210161A1 (en) | 2021-08-09 |
EP4100354A4 (en) | 2024-03-06 |
NO346750B1 (en) | 2022-12-12 |
WO2021158123A1 (en) | 2021-08-12 |
NO20200157A1 (en) | 2021-08-09 |
EP4100354A1 (en) | 2022-12-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108349713B (en) | Hoisting system for mounting a wind turbine | |
DK2454427T3 (en) | Telescopic tower arrangement and method | |
DK2956400T3 (en) | Apparatus and method for installing a wind turbine rotor blade | |
JP5736133B2 (en) | Floating structure work system, work boat, and floating structure work method | |
US10294626B2 (en) | Method of installation of an offshore wind turbine tower, with pile-based foundations, and equipment for implementing said method | |
US7238009B2 (en) | Offshore windmill electric generators | |
EP3623645B1 (en) | Support structure for a wind turbine mast and method for realizing a bolt connection between connecting flanges of a wind turbine mast and a support structure for a wind turbine mast | |
US20230365383A1 (en) | Apparatus for installation and dissaembly of wind turbine and construction method | |
EP1101935B1 (en) | Method and vessel for installation of off-shore windmills | |
EP1499778B1 (en) | Method and vessel for manipulating an offshore construction | |
US20120027523A1 (en) | Device and method for assembling a structure at sea | |
EP2256079B1 (en) | Device for assembling a large structure at sea | |
EP3483342B1 (en) | Device and method for arranging a secondary construction on an offshore primary construction | |
US10815687B2 (en) | Wind turbine assembly system and associated method | |
WO2011102738A2 (en) | A method and vessel for offshore transport and installation of windmill assemblies | |
NO800069L (en) | DEVICE FOR AND PROCEDURE FOR RECOVERING ITEMS IN THE SEA. | |
CN112392667A (en) | Method for modifying a wind turbine foundation and wind turbine foundation | |
NO346091B1 (en) | Device for mounting floating wind turbines | |
US20220341397A1 (en) | Method of offshore mounting a wind turbine | |
NO782219L (en) | PROCEDURE AND DEVICE FOR LOCATING A SUPPORT STRUCTURE ON A PLATFORM | |
NO20201356A1 (en) | Device and method for use when installing land-based and floating wind turbines | |
US20190264655A1 (en) | Conversion of moveable offshore drilling platforms to a wind turbine installation unit | |
NO326537B1 (en) | Procedure for lifting and mounting heavy units to a wind turbine | |
NO327521B1 (en) | Process for the construction of wind turbines for high production of electrical energy and installation / replacement of heavy machine parts | |
NO331394B1 (en) | Procedure with associated devices for maintenance, repair and replacement of larger or machine components for wind turbines at sea |