NL2004212A - Floating marine structure with suction piles and platform resting on a barge clamped between suction piles and platform. - Google Patents

Floating marine structure with suction piles and platform resting on a barge clamped between suction piles and platform. Download PDF

Info

Publication number
NL2004212A
NL2004212A NL2004212A NL2004212A NL2004212A NL 2004212 A NL2004212 A NL 2004212A NL 2004212 A NL2004212 A NL 2004212A NL 2004212 A NL2004212 A NL 2004212A NL 2004212 A NL2004212 A NL 2004212A
Authority
NL
Netherlands
Prior art keywords
platform
suction
float
water
support legs
Prior art date
Application number
NL2004212A
Other languages
Dutch (nl)
Other versions
NL2004212C2 (en
Inventor
Mark Riemers
Original Assignee
Suction Pile Technology B V
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suction Pile Technology B V filed Critical Suction Pile Technology B V
Priority to NL2004212A priority Critical patent/NL2004212C2/en
Priority to EP10153118A priority patent/EP2216447A1/en
Publication of NL2004212A publication Critical patent/NL2004212A/en
Application granted granted Critical
Publication of NL2004212C2 publication Critical patent/NL2004212C2/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/02Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto
    • E02B17/021Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto with relative movement between supporting construction and platform
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0039Methods for placing the offshore structure
    • E02B2017/0047Methods for placing the offshore structure using a barge
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0056Platforms with supporting legs
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0056Platforms with supporting legs
    • E02B2017/0073Details of sea bottom engaging footing
    • E02B2017/0078Suction piles, suction cans

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Description

Title: Floating marine structure with suction piles and platform resting on a barge clamped between suction piles and platform.
The invention concerns a marine structure, a method of installing a marine structure and a suction pile. Particularly, the invention concerns application to a so called "marginal field" i.e. an offshore field for which the predicted economical exploitation is limited to less then 10 years.
Suction piles and their way of installing are a.o. known from GB-B-2300661 and EP-B-0011894, which disclosures are enclosed in here by reference. Briefly, a suction pile is a thin walled steel cylinder, closed at at least one longitudinal end, that is located on the subsea bottom with the opposite end and penetrates the subsea bottom with the aid of a suction created within the cylinder. The creation of the suction can be with the aid of a suction source, such as a pump, being on, or close to or at a distance (e.g. above the water surface, e.g. at a vessel) from the suction pile. The applied level of the suction can be e.g. at least substantially constant, smoothly increase or decrease or else pulsate, for which there are convenient means; for an e.g. pulsating level a possibly in the suction pile integrated pressure accumulator that is intermittently connected to the inner space of the cylinder. After use, the suction pile can easily be removed by creating an overpressure within the cylinder, e.g. by pumping in (sea) water.
A self installing platform applying suction piles which provide buoyancy is known from e.g. W099/51821 (SIP1) or EP-A-1 101 872 (SIP2) of the present inventor.
In stead of installing a suction pile into the under water bottom by generating a fluid pressure difference between the inside and outside of the suction pile, it is also feasible that the suction pile at least partly penetrates the under water bottom by a weight resting on it, e.g. the platform and/or a ballast body .
Therefor according to the invention it is proposed to make the marine structure self floating and self foundating or self installing by providing it with buoyancy and one or more suction piles. So the hoisting device and the plant for installing the foundation, e.g. hammering device, can be eliminated. Preferably the structure has buoyancy of its own, e.g. obtained by the with the structure integrated appliance that is designed to, once the structure is installed, ballast the structure. Buoyancy can also be obtained from the suction pile, which for that can be provided with a floater. Said own buoyancy is preferably such that it is substantially contributing to the required buoyancy to make the structure self floating. It is preferable, if the buoyancy can be at least substantially decreased for installation purposes. By e.g. filling the one or more floating bodies with ballast, like water. Therefor it is convenient, to provide the structure with means for adding and possibly removing of ballast, such as between the closed and open position switcheable shutter valves in a water supplying respectively water venting opening to a ballast tank.
Since the structure is self floating and is provided with one or more suction piles, removal after use is made easier. On the one hand in that by pressing out the suction pile, the anchoring of the structure to the underwater bottom can be removed. On the other hand in that the structure can independently rise to the water surface by the (possibly regained) buoyancy.
In this respect the marine structure typically will be rather large, e.g. a production platform with equipment. Due to its own weight, such marine structure is designed to be applied with a foundation of pile bodies to be pressed in the bottom. The marine structure preferably has, apart from the suction piles, no floating bodies, apart from parasitic floating bodies such as air filled spaces that are normally present, such as frame tubes. The marine structure according to the present invention will typically weigh not more than about 5, 000, 000 kilo, although structures with a much higher weight of e.g. 10,000,000 kilo or more are also feasible.
For the purpose of transporting to the final destination it is preferred that the marine structure is loaded onto a barge or other separate floating and/or sailing body with buoyancy of its own. "Barge" preferably means at least a vessel known as such with one or more floating spaces at least substantially hermetically delimited from the environment. Preferably the barge has no equipment of its own for propelling and/or directional control.
Preferably the marine structure is loaded onto the barge such that the suction piles penetrate the body of water into which the barge floats or are completely submerged while preferably the platform of the marine structure is at a distance above said body of water. More preferably, one or more of the following features are applied: the marine structure is loaded onto the barge in the upright orientation or the orientation equal to the operating position of the marine structure, which is typically the vertical orientation; the suction piles are completely below the water level of the body of water in which the barge floats and are preferably completely below the bottom level of the barge onto which the marine structure is loaded; the barge is present straight above at least a part of a suction pile and preferably at least a part of all suction piles; the barge with the marine structure loaded onto it is connected to a propulsion vessel, e.g. a towing boat, e.g. by virtue of a towing cable, and is preferably propulsed by said vessel; the barge with the marine structure loaded onto it advances through the body of water into which the barge floats, preferably with a speed between 4 and 6 nautical miles per hour; from each suction pile a supporting leg extends upward; the platform has a rectangular shape in top view; at each corner of the platform and possibly also at more locations along the side of the platform a supporting leg and/or suction pile is present; the platform is connected to the supporting legs by connection means that allow the platform to move along the supporting legs; the supporting legs have a length of at least 20 metres (e.g. 20 metre for a water depth of 5 metre and 100 metre for a water depth of 60 metre) ; each suction pile has a diameter of at least 5 metres and a height of at least 5 metres and a wall thickness of at least 1 centimetre; the longitudinal axis of the suction pile and the relevant supporting leg are substantially in line; from the circumference, seen in top view, of each suction pile one or more mutually spaced straight frame members extend upward, inclined towards the relevant supporting leg and connected to it at a distance above the suction pile, to provide a bracing; said bracings are absent at the side of the supporting leg facing the barge; the vertical distance between the top of the suction pile and the barge measures 1 or 2 or 3 metre to a maximum; the barge is clamped or sandwiched between the platform and the top of the suction piles; the barge bears onto the top of the suction piles .
It is feasible that the barge has insufficient buoyancy of its own to keep the marine structure floating, considering the prevailing safety requirements. In such a case the one or more suction piles provide the additionally required buoyancy.
Thus a cost and time and energy and environmental saving is possible, and also the work is safer. Besides, additional dynamic stability is gained of the in the body of water floating and advancing assembly provided by the barge and the marine structure loaded onto it, compared to the embodiments disclosed in the state of the art, e.g. EP-A-1 101 872 (SIP2). Also the draft of the floating assembly is limited.
By providing that the barge is clamped or sandwiched between the platform and the top of the suction piles or bears onto the to of the suction piles (e.g. through the aid of spacers located between the bottom of the barge and the top of the suction piles) , an extremely stable and reliable assembly is obtained.
To provide the additional buoyancy, the suction pile is preferably provided with compressed air or integral floating means, preferably present inside the suction pile. The floating means can at least substantially comprise a space in open communication with the surrounding water at its under side, such as the pressure space of the suction pile.
The invention is further illustrated by way of a non-limiting, presently preferred embodiment providing the best way of carrying out the invention and shown in the drawings.
Fig. 1 shows a side view of a marine structure prior to installation;
Fig. 2 shows a front view of the structure of fig. 1;
Fig. 3 shows a view according to fig. 1, after installation;
Fig. 4 shows a top view of the structure of fig. 1;
Fig. 5 shows a top view of the structure of fig. 3;
Fig. 6 shows a top view of a suction pile;
Fig. 7 shows a side view of the suction pile of fig. 6; and
Fig. 8 shows a side view of the suction pile of fig. 6 from another angle.
Fig. 1-5 show a marine structure 1 consisting of a platform 2, rectangular in top view, each corner of which having a supporting leg 3 at the lower side of which a suction pile 4 is connected. The supporting legs 3 are mutually connected by braces 10, however braces 10 are not always required. Each supporting leg 3 is connected to the suction pile 4 such that the longitudinal axis of both are in line.
In this example the suction piles 4 are at such low level beneath the water level 6, that the space between the supporting legs 3 is completely available to a barge 5, providing a floating transport means. The buoyancy provided by the barge can therewith be optimised. This is also beneficial for the stability during transport across the water 6.
The barge 5 partly covers each suction pile 4 and is present at a small distance straight above part of each suction pile 4 .
During transport over water, the supporting legs 3 are retracted such that they maximally extend above the water level 6. The marine structure is at least partly supported by the barge 5 and the platform 2 is preferably close to the water surface 6. Therefor, the platform 2 preferably rests directly onto the barge 5, possibly through supports 7. The barge provides all required buoyancy, or the barge and the suction piles 4 together provide the required buoyancy.
During installation, the supporting legs 3 and the platform 2 are mutually shifted in longitudinal direction of the supporting legs 3, such that the lower side of the supporting legs 3 move away from the platform 2. One can proceed in at least the two following manners: 1. While the structure 1 still rests onto the barge 5 floating in the water, one lowers the suction piles 4 onto the under water bottom 8 together with the supporting legs 3. After the suction piles 4 have penetrated the under water bottom 8, preferably to their final depth, the platform 2 is lifted from the barge 5 and to its operating position while the barge 5 is removed by sailing it from below the platform 2. Lifting of the platform 2 is carried out by lifting means operating between the supporting legs 3 and the platform 2. During lifting, the platform 2 shifts along the stationary supporting legs 3.
2. One lifts the structure 1 from the barge 5, preferably by increasing the buoyancy of the suction piles 4, whereafter one disengages the barge 5 from the structure 1 and removes it by sailing it away from below the platform. Subsequently one lowers the suction piles 4 together with the lower side of the supporting legs 3 onto the under water bottom 8, while one shifts the platform 2 along the supporting legs 3 to remain at least substantially at the same level above the water surface. After the suction piles 4 are penetrated into the under water bottom 8, preferably to their final depth, the platform 2 is lifted to its final level, shifting along the supporting legs 3.
To be able to mutually shift the supporting legs 3 and the platform 2, convenient means can be present, such as strands and strand jacks or cables 9 and driven winches which are connected to the platform 2 and the supporting legs 3.
Fig. 6-8 show that the supporting leg 3 is concentric or coaxially with the suction pile 4. From the radial circumference of the suction pile two straight braces extend upward, inclined towards the leg 3.
The invention is not limited to the above described and in the drawings illustrated embodiments. E.g. the marine structure can have less than four, e.g. two or three, or more than four, e.g. five or six, suction piles 4 . The number of supporting legs 3 is preferably equal to the number of suction piles 4, but this is not absolutely necessary. E.g. three suction piles are at the corners of a structure 1 that is triangular in top view. It is not required that the suction piles and supporting legs are at the corners of the structure 1. The platform 2 can be constructed and/or shaped differently. The suction pile can be eccentrically connected to the relevant supporting leg 3, e.g. the supporting leg 3 is connected to the suction pile 4 at or near the circumferential edge of the suction pile 4 in which case it is feasible that the barge is present above the almost complete suction pile 4.
It is possible to assemble the marine structure from separate sub assemblies in the harbour or offshore, e.g. at the operating site. E.g. a first sub assembly comprises the suction piles 4 and possibly the lower part of the legs 3 and their mutual connecting braces 10. A second sub assembly comprises the platform 2 and the supporting legs 3 or upper part of it. The first sub frame is lowered onto the water bottom such that the suction piles thereof penetrate the bottom. Then the second sub assembly is located above the first sub assembly and the first and second sub assemblies are coupled, during which operations the second sub assembly is supported by the barge 5. Then the supporting legs 3 are lifted by shifting them along the platform 2, taking the suction piles 4 with them. Now the condition shown in fig. 1-3 is obtained such that the complete marine structure is now supported by the barge 5 and can be towed to the final location.
Alternatively, in a different production variant, the suction piles 4 and lower part of the supporting legs 3 can be installed offshore at the final location after which the platform 2, supported onto the barge 5, and top section of the legs 3, connected to the platform 2, move in between the pre installed lower part of the legs 3. Then the top section of the legs 3 are lowered onto the pre installed lower part of the legs 3 and connected with them. Then the platform 2 is lifted (while shifting along the legs 3) to the top level and the barge 5 is removed from below the platform 2 and from between the legs 3.
In another production variant, the platform is constructed with clamps, the number of which equals the number of supporting legs. First the platform is located on a barge floating in the water. Then an upright supporting leg mounted to a suction pile is mated with a corresponding clamp and the clamp is closed.
After all clamps are loaded with a relevant supporting leg mounted to a relevant suction pile, the condition shown in fig. 1-3 is obtained and the marine structure is ready to be towed to its final location.
In again another production variant, the supporting legs are pivotably mounted, such that they can pivot from a substantially vertical position to a substantially horizontal position. In the latter position, the suction piles at their lower ends can completely extend above the water while the platform rests on a barge, such that in this position the stability during towing is assured. At the final location, the supporting legs are pivoted to their upright position such that the suction piles can be lowered to penetrate the water bottom.

Claims (2)

1. Een offshore constructie (1) die drijft in het water (6), welke constructie bestaat uit een platform (2) boven het water en met ten minste drie zich uiteen bevindende omhoog stekende steunpoten (3) die zich vanaf het platform (2) neerwaarts uitstrekken naar het water, aan de onderzijde waarvan een zuigpaal (4) is bevestigd, welke steunpoten (3) zijn gemonteerd aan het platform (2) door montagemiddelen zodat de steunpoten (3) kunnen schuiven ten opzichte van het platform (2) in lengterichting van de steunpoten (3) zodat de onderzijde van de steunpoten (3) weg kan worden bewogen van het platform (2), welke offshore constructie geladen is op een afzonderlijk drijflichaam of drijver (5) zodat het platform zich over de drijver (5) uitstrekt en erop rust en de steunpoten (3) strekken zich naast de drijver uit zodat de drijver aanwezig is tussen de steunpoten, waarbij de drijver (5) en de offshore constructie (1) samen voorzien in het benodigde drijfvermogen om het samenstel onafhankelijk drijvend in het water te houden, terwijl de drijvende offshore constructie een rechtop staande oriëntatie heeft gelijk aan de rechtop staande positie na installatie op de zeebodem zodat de offshore constructie op de zeebodem kan worden geïnstalleerd zonder het wijzigen van de oriëntatie van de offshore constructie door eerst de drijver van onder het platform (2) te verwijderen en dan de zuigpalen op de zeebodem te laten zakken door het neerwaarts schuiven van de steunpoten (3) .An offshore structure (1) floating in the water (6), which structure consists of a platform (2) above the water and with at least three spaced-up support legs (3) extending from the platform (2) ) extend downwards to the water, on the underside of which a suction pile (4) is attached, which support legs (3) are mounted on the platform (2) by mounting means so that the support legs (3) can slide relative to the platform (2) in the longitudinal direction of the support legs (3) so that the underside of the support legs (3) can be moved away from the platform (2), which offshore structure is loaded on a separate floating body or float (5) so that the platform extends over the float ( 5) extends and rests on it and the support legs (3) extend alongside the float so that the float is present between the support legs, the float (5) and the offshore structure (1) together providing the required buoyancy around the assembly independently floating in the water, while the floating offshore structure has an upright orientation equal to the upright position after installation on the seabed so that the offshore structure can be installed on the seabed without changing the orientation of the offshore structure by first remove the float from under the platform (2) and then lower the suction piles to the seabed by sliding down the support legs (3). 2. Een offshore constructie volgens conclusie 1, waarbij - de bovenkant van de zuigpalen (4) zich bevindt op een niveau beneden de onderzijde van de drijver (5) zodat de zuigpalen (4) zich volledig beneden de waterspiegel bevinden en de steunpoten (3) door de waterspiegel steken zodat zij zich gedeeltelijk boven en gedeeltelijk in het water uitstrekken; - elke zuigpaal (4) ten minste gedeeltelijk overlapt met de drijver (5), gezien in bovenaanzicht; - het platform (2) zich bovenop de drijver (5) uitstrekt; en - de drijver (5) is geklemd tussen de onderzijde van het platform (2) en de bovenzijde van de zuigpalen (4).An offshore construction according to claim 1, wherein - the top of the suction piles (4) is at a level below the bottom of the float (5) so that the suction piles (4) are completely below the water level and the support legs (3) ) protrude through the water surface so that they extend partly above and partly into the water; - each suction pile (4) at least partially overlaps with the float (5), viewed in top view; - the platform (2) extends on top of the float (5); and - the float (5) is clamped between the bottom of the platform (2) and the top of the suction piles (4).
NL2004212A 2009-02-09 2010-02-08 Floating marine structure with suction piles and platform resting on a barge clamped between suction piles and platform. NL2004212C2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
NL2004212A NL2004212C2 (en) 2009-02-09 2010-02-08 Floating marine structure with suction piles and platform resting on a barge clamped between suction piles and platform.
EP10153118A EP2216447A1 (en) 2009-02-09 2010-02-09 Floating marine structure with suction piles and platform resting on a barge clamped between suction piles and platform.

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
NL2002508 2009-02-09
NL2002508 2009-02-09
NL2004212 2010-02-08
NL2004212A NL2004212C2 (en) 2009-02-09 2010-02-08 Floating marine structure with suction piles and platform resting on a barge clamped between suction piles and platform.

Publications (2)

Publication Number Publication Date
NL2004212A true NL2004212A (en) 2010-08-10
NL2004212C2 NL2004212C2 (en) 2011-01-20

Family

ID=42136150

Family Applications (1)

Application Number Title Priority Date Filing Date
NL2004212A NL2004212C2 (en) 2009-02-09 2010-02-08 Floating marine structure with suction piles and platform resting on a barge clamped between suction piles and platform.

Country Status (2)

Country Link
EP (1) EP2216447A1 (en)
NL (1) NL2004212C2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107288114A (en) * 2016-03-31 2017-10-24 周俊麟 A kind of small ocean platform jack up spud leg
CN112376565A (en) * 2020-11-05 2021-02-19 中交第一航务工程局有限公司 Offshore wind power vertical pile guide frame fixing construction method and offshore wind power vertical pile guide frame dismantling construction method

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL2004443C2 (en) * 2010-03-22 2011-09-23 Suction Pile Technology B V Movable platform, assembly of a movable platform and a barge, method of installation, method of exploitation, method of re-use.
NL2012008B1 (en) 2012-12-21 2016-07-08 Suction Pile Tech B V Offshore installation method, e.g. by floatover, and system.
KR101672595B1 (en) 2014-11-18 2016-11-04 현대건설주식회사 Suction bucket foundation for decreasing resistance of seawater and adjusting verticality, installing and lifting method
CN212099278U (en) * 2020-03-25 2020-12-08 上海惠生海洋工程有限公司 Shallow water is from mounting platform
CN113026740A (en) * 2021-02-02 2021-06-25 中铁大桥局集团第五工程有限公司 Method for quickly butting frame body and suction pile of suction pile type tooling platform
CN113700029B (en) * 2021-09-22 2022-10-28 中交第一航务工程局有限公司 Floating transportation method for suction pile jacket

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3138932A (en) * 1961-04-14 1964-06-30 Richfield Oil Corp Locating an offshore drilling platform
US3727414A (en) * 1971-06-28 1973-04-17 Bowden Drilling Services Ltd Off shore drilling platform construction
EP0011894B1 (en) 1978-12-04 1984-07-04 Shell Internationale Researchmaatschappij B.V. A method for installing a tubular element in the bottom of a body of water and apparatus for carrying out this method
IT1184238B (en) * 1985-06-19 1987-10-22 Saipem Spa PROCEDURE FOR THE INSTALLATION OF THE MONOBLOCK SUPERSTRUCTURE OF AN OFFSHORE PLATFORM AND EQUIPMENT FOR ITS PRACTICE
FR2604413A1 (en) * 1986-09-26 1988-04-01 Technip Geoproduction Method for moving an offshore drilling and production platform from one site to another
NL9400101A (en) 1994-01-21 1995-09-01 Hogervorst Johannes R Method and device for installing a hollow suction pole in the bottom of a water.
EP1068403B2 (en) 1998-04-02 2018-10-10 SPT Equipment bv Marine structure
US6481932B1 (en) 1999-11-18 2002-11-19 Suction Pile Technology B.V. Marine structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107288114A (en) * 2016-03-31 2017-10-24 周俊麟 A kind of small ocean platform jack up spud leg
CN112376565A (en) * 2020-11-05 2021-02-19 中交第一航务工程局有限公司 Offshore wind power vertical pile guide frame fixing construction method and offshore wind power vertical pile guide frame dismantling construction method

Also Published As

Publication number Publication date
NL2004212C2 (en) 2011-01-20
EP2216447A1 (en) 2010-08-11

Similar Documents

Publication Publication Date Title
NL2004212C2 (en) Floating marine structure with suction piles and platform resting on a barge clamped between suction piles and platform.
EP1101872B1 (en) Marine structure
US6488446B1 (en) Marine structure
JP6835594B2 (en) Floating structure and installation method of floating structure
CN107542101B (en) Construction method of offshore four-buoy-buoyancy tank combined foundation structure
US9758941B2 (en) Offshore tower for drilling and/or production
EP2171159B1 (en) Device and method for marine tower structure
KR20110030628A (en) Support structure for use in the offshore wind farm industry
CN107630461B (en) Combined offshore four-buoy buoyancy tank foundation structure and construction method thereof
CN102762447A (en) Universal floating and launching system and operating method
NO346090B1 (en) Single column semi-submersible platform for fixed anchoring in deep water
US20120201608A1 (en) Foundation for offshore wind turbine and method and means for its transportation and installation in deepwaters
NO20092241L (en) Subsoil foundations, as well as methods for installing the foundation
RU2727496C1 (en) Port facility and method of mooring in port facility
NL2005370C2 (en) Floating marine structure with suction piles and vessel.
CN115704209A (en) Shallow water area offshore platform installation method
GB2578294A (en) Method of installing a wind turbine in a body of water
CN214219658U (en) Floating type guide frame for wind power pile construction
KR20120053984A (en) System and method for submerging a hydraulic turbine engine
KR102645338B1 (en) Subsea space platform elevating system
DK2860314T3 (en) Gravity fundering
AU2021202442B2 (en) Gravity-Based Structure For Off-Shore Structures
EP3196362B1 (en) Jack-up vessel and method for positioning the vessel on an underwater bottom
NL1011740C1 (en) Marine structure for embedding into sea bottom or floating transportation used for marine application
JP2002047664A (en) Conveying device and method for jacket structure

Legal Events

Date Code Title Description
MM Lapsed because of non-payment of the annual fee

Effective date: 20160301