CN115704209A - Shallow water area offshore platform installation method - Google Patents

Shallow water area offshore platform installation method Download PDF

Info

Publication number
CN115704209A
CN115704209A CN202110945970.9A CN202110945970A CN115704209A CN 115704209 A CN115704209 A CN 115704209A CN 202110945970 A CN202110945970 A CN 202110945970A CN 115704209 A CN115704209 A CN 115704209A
Authority
CN
China
Prior art keywords
hull
offshore platform
ship body
pile leg
crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110945970.9A
Other languages
Chinese (zh)
Inventor
张晓春
殷庆国
姜晓波
翁博
董月洲
章昀昊
邢洪涛
李海伟
丁丽芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Petrochina Co Ltd
Original Assignee
Petrochina Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Petrochina Co Ltd filed Critical Petrochina Co Ltd
Priority to CN202110945970.9A priority Critical patent/CN115704209A/en
Publication of CN115704209A publication Critical patent/CN115704209A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The invention discloses a shallow water offshore platform installation method, which comprises the steps of selecting a bottom-mounted self-elevating engineering ship and a transportation barge to carry an offshore platform to a designated installation sea area, and using a crane to carry out module hoisting or integral hoisting on the offshore platform in a bottom-mounted and pile inserting mode. Large floating crane equipment with expensive rent and short resources is not required to be used, the working amount of deep excavation and dredging of a channel and an operation area can be avoided or reduced, and the construction operation cost and the operation period are obviously reduced; on the other hand, the crane has strong wind and wave resistance, meets the working requirements of the crane to the greatest extent, ensures the hoisting and mounting precision, can reduce the influence of weather and sea conditions on the mounting work, improves the working efficiency, and can greatly improve the safety performance of the mounting work process.

Description

一种浅水域海上平台安装方法A method for installing an offshore platform in shallow water

技术领域technical field

本发明涉及海上平台安装技术领域,尤其是一种浅水域海上平台安装方法。The invention relates to the technical field of offshore platform installation, in particular to a method for installing an offshore platform in shallow water.

背景技术Background technique

随着海洋石油工业迅猛发展,海上平台正向大型化、集约化方向发展,海上平台的整体重量也随之增加。这类大型海上平台采用模块化吊装或整体安装,模块化吊装方法受到海洋外部环境、浮吊载重量及施工海域的水深条件等限制,致使平台的建造工期长,经济效益差,而采用浮吊吊装或驳船浮托方法进行整体安装,通常需要用大型的作业船舶和设备,特别是在滩浅海地区由于水深浅,大型施工设备无法进入到安装海域,这时还需要进行航道及安装作业区域深挖疏浚,既增加了安装作业成本,又延长了平台建设工期。With the rapid development of the offshore oil industry, offshore platforms are becoming larger and more intensive, and the overall weight of offshore platforms is also increasing. This type of large-scale offshore platform adopts modular hoisting or overall installation. The modular hoisting method is limited by the external environment of the ocean, the load capacity of the floating crane, and the water depth conditions in the construction sea area, resulting in a long construction period for the platform and poor economic benefits. The hoisting or barge float-over method for overall installation usually requires large-scale operating ships and equipment, especially in shallow sea areas where large-scale construction equipment cannot enter the installation sea area due to the shallow water depth. Digging and dredging not only increases the cost of installation operations, but also prolongs the construction period of the platform.

发明内容Contents of the invention

本发明所要解决的技术问题是,提供一种浅水域海上平台安装方法,实现了抵抗风浪能力强,降低天气和海况对安装工作的影响,可缩短海上平台安装作业周期。The technical problem to be solved by the present invention is to provide a method for installing an offshore platform in shallow waters, which has a strong ability to resist wind and waves, reduces the influence of weather and sea conditions on the installation work, and can shorten the installation cycle of the offshore platform.

为了解决上述技术问题,本发明采用的技术方案是:一种浅水域海上平台安装方法,包括以下步骤:In order to solve the above technical problems, the technical solution adopted by the present invention is: a method for installing an offshore platform in shallow water, comprising the following steps:

1)首先预备一艘集坐底和自升功能于一体的坐底自升式工程船,包括:上船体、起重机、下船体、外桩腿和内桩腿,起重机安装在上船体上,外桩腿安装在上船体上,通过齿条式升降装置控制外桩腿升降,下船体通过外桩腿连接到上船体,内桩腿安装在下船体上,通过插销式升降装置控制内桩腿升降,下船体设置有压载水系统;1) First prepare a sitting-bottom self-elevating engineering ship that integrates the functions of sitting on the bottom and jacking up, including: upper hull, crane, lower hull, outer legs and inner legs. The crane is installed on the upper hull, and the outer The legs are installed on the upper hull, and the outer leg is controlled by the rack-type lifting device. The lower hull is connected to the upper hull through the outer leg. The inner leg is installed on the lower hull, and the inner leg is controlled by the pin-type lifting device. The lower hull is provided with a ballast water system;

2)根据安装海域水深情况,选择坐底自升式工程船和运输驳船运载海上平台到指定的安装海域;2) According to the water depth of the installation sea area, select the bottom jack-up engineering ship and transport barge to carry the offshore platform to the designated installation sea area;

3)坐底自升式工程船到达指定位置后,利用齿条式升降装置将外桩腿向下伸出,带动下船体向下移动,直至下船体坐底在海床上,保持外桩腿继续向下运动,依靠海床对下船体的支撑力和下船体的浮力,将上船体顶离水面一定高度,令风浪涌穿过;3) After the self-elevating engineering ship sits on the bottom and reaches the designated position, use the rack type lifting device to extend the outer legs downward, and drive the lower hull to move downward until the lower hull sits on the seabed, keeping the outer legs to continue Moving downward, relying on the support force of the seabed to the lower hull and the buoyancy of the lower hull, the upper hull is lifted to a certain height from the water surface, so that the wind and waves can pass through;

4)利用插销式升降装置将内桩腿向下伸出插入到海床中,此时,内桩腿既能抵抗水平力的滑移,又能承担部分因上船体起重机吊装作业时产生的倾覆力矩,还能依靠其与泥层的摩擦力承受部分船体自重;压载水系统向下船体注水,使其满足海上平台安装时对船体的稳性要求;4) Use the pin-type lifting device to extend the inner leg downwards and insert it into the seabed. At this time, the inner leg can not only resist the sliding of the horizontal force, but also bear part of the overturning caused by the hoisting operation of the upper hull crane It can also rely on its friction with the mud layer to bear part of the hull's own weight; the ballast water system injects water into the hull to meet the stability requirements of the hull when the offshore platform is installed;

5)坐底自升式工程船与运输驳船就位后,用起重机进行海上平台分模块吊装或整体吊装;5) After the self-elevating engineering ship and the transport barge are in place, use the crane to lift the offshore platform in modules or as a whole;

6)吊装作业完成后,压载水系统排空下船体,利用插销式升降装置将内桩腿向上回收,依靠海床对下船体的支撑力和下船体的浮力从海床中拔出内桩腿,再利用齿条式升降装置将外桩腿向上回收,将上船体下降至水面,继续回收外桩腿,依靠上船体的浮力将下船体收至上船体下方。6) After the hoisting operation is completed, the ballast water system empties the lower hull, and the inner pile legs are recovered upwards by using the plug-type lifting device, and the inner pile is pulled out from the seabed by relying on the support force of the seabed to the lower hull and the buoyancy of the lower hull Legs, and then use the rack type lifting device to recover the outer legs upwards, lower the upper hull to the water surface, continue to recover the outer legs, and rely on the buoyancy of the upper hull to receive the lower hull below the upper hull.

所述内桩腿、外桩腿设置在靠近上船体纵横两个方向的边线,以减小吊装作业时的倾覆力矩。The inner legs and the outer legs are arranged close to the vertical and horizontal sides of the upper hull, so as to reduce the overturning moment during the hoisting operation.

所述内桩腿、外桩腿长度根据作业区域水深进行调整。The lengths of the inner legs and outer legs are adjusted according to the water depth in the working area.

所述坐底自升式工程船调遣或拖航时,内桩腿、外装腿收缩,下船体收起至上船体下方。When the self-elevating engineering ship on the bottom is dispatched or towed, the inner legs and outer legs are retracted, and the lower hull is retracted to the bottom of the upper hull.

所述下船体能调节吸排水量,使得下船体获得不同的浮力,用以改变坐底对海床的压力,用压载水系统平衡起重机吊装作业时产生的倾覆力矩。The lower hull can adjust the suction and displacement, so that the lower hull can obtain different buoyancy, which is used to change the pressure of the bottom on the seabed, and use the ballast water system to balance the overturning moment generated when the crane is hoisting.

本发明的有益效果是:代替传统吊装安装法和浮托安装法,以实现海上平台在浅水域的安装,从而不需要动用租金昂贵且资源紧张的大型浮吊,也可以避免或减少航道及作业区域深挖疏浚的作业量,达到显著降低海上平台安装费用和作业周期的目的。The beneficial effects of the present invention are: to replace the traditional hoisting installation method and float-over installation method to realize the installation of offshore platforms in shallow waters, so that there is no need to use large-scale floating cranes with expensive rent and resource constraints, and it is also possible to avoid or reduce navigation channels and operations. The workload of regional deep excavation and dredging achieves the purpose of significantly reducing the installation cost and operation cycle of offshore platforms.

附图说明Description of drawings

图1是本发明中坐底自升式工程船结构示意图。Fig. 1 is a structural schematic diagram of a self-elevating engineering vessel sitting on the bottom in the present invention.

图2是本发明中坐底自升式工程船坐底状态示意图。Fig. 2 is a schematic diagram of the state of the self-elevating engineering ship sitting on the bottom in the present invention.

图3是本发明中坐底自升式工程船坐底后插桩状态示意图。Fig. 3 is a schematic diagram of the state of pile insertion after the self-elevating engineering ship sitting on the bottom sits on the bottom in the present invention.

图4是本发明中坐底自升式工程船及运输驳船就位示意图。Fig. 4 is a schematic view showing the position of the self-elevating engineering ship and the transport barge in the present invention.

图5是本发明中海上平台安装示意图。Fig. 5 is a schematic diagram of installation of an offshore platform in the present invention.

其中:1.上船体,2.起重机,3.下船体,4.外桩腿,5.内桩腿,6.齿条式升降装置,7.插销式升降装置,8.海床,9.水面,10.海上平台,11.平台下部基础,12.运输驳船。Among them: 1. Upper hull, 2. Crane, 3. Lower hull, 4. Outer legs, 5. Inner legs, 6. Rack type lifting device, 7. Pin type lifting device, 8. Seabed, 9. Water surface, 10. Offshore platform, 11. Platform lower foundation, 12. Transport barge.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述;显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例,基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings in the embodiments of the present invention; obviously, the described embodiments are only part of the embodiments of the present invention, not all embodiments, based on The embodiments of the present invention and all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

在本发明的描述中,需要说明的是,术语“上”、“下”、“内”、“外”、“顶/底端”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In the description of the present invention, it should be noted that the orientations or positional relationships indicated by the terms "upper", "lower", "inner", "outer", "top/bottom" etc. are based on the orientations shown in the drawings Or positional relationship is only for the convenience of describing the present invention and simplifying the description, but does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be construed as limiting the present invention.

在本发明的描述中,需要说明的是,除非另有明确的规定和限定,术语“安装”、“设置有”、“套设/接”、“连接”等,应做广义理解,例如“连接”,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本发明中的具体含义。In the description of the present invention, it should be noted that, unless otherwise specified and limited, the terms "installed", "set with", "sleeved/connected", "connected", etc. should be understood in a broad sense, such as " Connection" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediary, and it can be an internal connection between two components. connectivity. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present invention in specific situations.

如图1-5所示,本发明的浅水域海上平台安装方法,包括如下步骤:As shown in Figures 1-5, the offshore platform installation method in shallow waters of the present invention includes the following steps:

1)首先预备一艘集坐底和自升功能于一体的坐底自升式工程船,包括:上船体1、起重机2、下船体3、外桩腿4和内桩腿5。起重机2安装在上船体1上。外桩腿4安装在上船体1上,通过齿条式升降装置6控制外桩腿4升降。下船体3通过外桩腿4连接到上船体1。内桩腿5安装在下船体3上,通过插销式升降装置7控制内桩腿5升降。下船体3设置有压载水系统,如图1所示。1) First prepare a bottom-seat self-elevating engineering ship integrating bottom-seat and self-elevate functions, including: upper hull 1, crane 2, lower hull 3, outer legs 4 and inner legs 5. The crane 2 is installed on the upper hull 1 . The outer leg 4 is installed on the upper hull 1, and the outer leg 4 is controlled by a rack type lifting device 6 to lift. The lower hull 3 is connected to the upper hull 1 by outer legs 4 . The inner pile leg 5 is installed on the lower hull 3, and the inner pile leg 5 is controlled by a bolt type lifting device 7 to lift. The lower hull 3 is provided with a ballast water system, as shown in FIG. 1 .

2)根据安装海域水深情况等选择运输驳船12运载海上平台10到指定的安装海域。2) Select the transport barge 12 to carry the offshore platform 10 to the designated installation sea area according to the water depth of the installation sea area.

3)坐底自升式工程船到达指定位置后,利用齿条式升降装置6将外桩腿4向下伸出,带动下船体3向下移动,直至下船体3坐底在海床8上。保持外桩腿4继续向下运动,依靠海床8对下船体3的支撑力和下船体3的浮力,将上船体1被顶离水面9一定高度,令风浪涌穿过,如图2所示。3) After the self-elevating engineering ship sitting on the bottom reaches the designated position, the outer pile leg 4 is extended downward by the rack type lifting device 6, and the lower hull 3 is driven to move downward until the lower hull 3 sits on the bottom of the seabed 8 . Keep the outer pile legs 4 to continue to move downward, rely on the support force of the seabed 8 to the lower hull 3 and the buoyancy of the lower hull 3, push the upper hull 1 to a certain height from the water surface 9, and let the wind and waves pass through, as shown in Figure 2 shown.

4)利用插销式升降装置7将内桩腿5向下伸出插入到海床8中,此时,内桩腿5既能抵抗水平力的滑移,又承担部分因起重机2吊重产生的倾覆力矩,还依靠其与泥层的摩擦力承受部分整船自重,如图3所示。4) Utilize the bolt-type lifting device 7 to extend the inner leg 5 downwards and insert it into the seabed 8. At this time, the inner leg 5 can not only resist the sliding of the horizontal force, but also bear part of the load generated by the crane 2. The overturning moment also relies on its friction with the mud layer to bear part of the ship's own weight, as shown in Figure 3.

压载水系统向下船体3注水,使其满足海上平台10安装时对船体的稳性要求。The ballast water system injects water into the lower hull 3 to meet the stability requirements of the hull when the offshore platform 10 is installed.

5)坐底自升式工程船与运输驳船12就位后,如图4所示,用起重机2进行海上平台10整体吊装在平台下部基础11上,如图5所示,通过焊接、浇注水泥或螺栓固定的方式进行连接紧固。5) After the bottom jack-up engineering ship and transport barge 12 are in place, as shown in Figure 4, the offshore platform 10 is hoisted as a whole on the lower foundation 11 of the platform with the crane 2, as shown in Figure 5, by welding and pouring cement Or fasten the connection with bolts.

6)吊装作业完成后,压载水系统排空下船体3,利用插销式升降装置7将内桩腿5向上回收,依靠海床8对下船体3的支撑力和下船体3的浮力从海床8中拔出内桩腿5,再利用齿条式升降装置6将外桩腿4向上回收,将上船体1下降至水面9,继续回收外桩腿4,依靠上船体1的浮力将下船体3收至上船体1下方。6) After the hoisting operation is completed, the ballast water system empties the lower hull 3, and the inner pile legs 5 are recovered upwards by using the pin-type lifting device 7, and the lower hull 3 is lifted from the sea by the support force of the seabed 8 and the buoyancy of the lower hull 3. Pull out the inner leg 5 in the bed 8, and then use the rack type lifting device 6 to recover the outer leg 4 upwards, lower the upper hull 1 to the water surface 9, continue to reclaim the outer leg 4, rely on the buoyancy of the upper hull 1 to move the lower The hull 3 is received below the upper hull 1 .

进一步的,下船体3具有良好的刚度,可以局部坐入海床8泥面,适应海床8泥面的微斜坡和局部凹凸不平。Further, the lower hull 3 has good rigidity, can partially sit on the mud surface of the seabed 8, and adapts to the slight slope and local unevenness of the mud surface of the seabed 8.

进一步的,内桩腿5、外桩腿4尽量设置在靠近上船体1纵横两个方向的边线,以减小吊装作业时的倾覆力矩。Further, the inner legs 5 and the outer legs 4 are arranged as close to the vertical and horizontal sides of the upper hull 1 as possible, so as to reduce the overturning moment during the hoisting operation.

进一步的,内桩腿5、外桩腿4长度可根据作业区域水深进行适度调整。Further, the lengths of the inner legs 5 and the outer legs 4 can be appropriately adjusted according to the water depth of the working area.

进一步的,坐底自升式工程船调遣或拖航时,内桩腿5、外桩腿4收缩,下船体3收起至上船体1下方。Furthermore, when the jack-up construction ship is dispatched or towed, the inner legs 5 and outer legs 4 are retracted, and the lower hull 3 is retracted below the upper hull 1 .

进一步的,下船体3能通过压载水系统调节吸排水量,使得下船体3获得不同的浮力,用以改变坐底对海床8的压力,用压载水系统,平衡起重机3吊装作业时产生的倾覆力矩。Further, the lower hull 3 can adjust the suction and displacement through the ballast water system, so that the lower hull 3 can obtain different buoyancy to change the pressure on the seabed 8 when sitting on the bottom, and use the ballast water system to balance the hoisting operation of the crane 3. overturning moment.

本发明由于采用了坐底及插桩的方式,一方面适用于极浅水海域,无需动用租金昂贵且资源紧张的大型浮吊设备,也可以避免或减少航道及作业区域深挖疏浚的作业量,显著降低施工作业费用及作业周期;另一方面具有较强的抵抗风浪能力,最大程度上满足起重机工作要求,保证起吊和安装精度,可降低天气和海况对安装工作的影响,提高作业效率,同时能大大提高安装作业过程的安全性能。Because the present invention adopts the method of sitting on the bottom and inserting piles, on the one hand, it is suitable for extremely shallow waters, and it does not need to use large-scale floating cranes that are expensive in rent and resource-intensive, and can also avoid or reduce the workload of deep digging and dredging in waterways and operating areas. Significantly reduce the construction operation cost and operation cycle; on the other hand, it has a strong ability to resist wind and waves, which can meet the working requirements of the crane to the greatest extent, ensure the lifting and installation accuracy, reduce the influence of weather and sea conditions on the installation work, and improve the operation efficiency. Can greatly improve the safety performance of the installation process.

综上所述,本发明的内容并不局限在上述的实施例中,相同领域内的有识之士可以在本发明的技术指导思想之内可以轻易提出其他的实施例,但这种实施例都包括在本发明的范围之内。In summary, the content of the present invention is not limited to the above-mentioned embodiments, people of insight in the same field can easily propose other embodiments within the technical guidance of the present invention, but this embodiment All are included within the scope of the present invention.

Claims (5)

1. A shallow water offshore platform installation method is characterized by comprising the following steps:
1) Firstly, a bottom-sitting self-elevating engineering ship integrating the functions of bottom-sitting and self-elevating is prepared, which comprises: the water ballast device comprises an upper ship body, a crane, a lower ship body, an outer pile leg and an inner pile leg, wherein the crane is installed on the upper ship body, the outer pile leg is installed on the upper ship body and is controlled to lift through a rack type lifting device, the lower ship body is connected to the upper ship body through the outer pile leg, the inner pile leg is installed on the lower ship body and is controlled to lift through a bolt type lifting device, and a water ballast system is arranged on the lower ship body;
2) According to the water depth condition of an installation sea area, selecting a bottom-sitting self-elevating engineering ship and a transportation barge to carry the offshore platform to the appointed installation sea area;
3) After the bottom-sitting self-elevating engineering ship reaches a designated position, the outer pile leg is extended downwards by using the rack type lifting device to drive the lower ship body to move downwards until the lower ship body sits on the seabed, the outer pile leg is kept to move downwards continuously, and the upper ship body is jacked to a certain height above the water surface by virtue of the supporting force of the seabed on the lower ship body and the buoyancy of the lower ship body, so that wind waves pass through;
4) The inner pile leg extends downwards to be inserted into the seabed by using the bolt type lifting device, and at the moment, the inner pile leg can resist the sliding of horizontal force, can bear part of overturning moment generated during the hoisting operation of a crane on the hull, and can bear part of the dead weight of the hull by means of the friction force between the inner pile leg and a mud layer; the ballast water system injects water to the lower ship body, so that the stability requirement of the ship body when the offshore platform is installed is met;
5) After the bottom-sitting self-elevating engineering ship and the transportation barge are in place, a crane is used for hoisting the offshore platform in modules or integrally;
6) After the hoisting operation is completed, the ballast water system empties the lower hull, the inner pile leg is upwards recovered by the bolt type lifting device, the inner pile leg is pulled out from the seabed by depending on the supporting force of the seabed on the lower hull and the buoyancy of the lower hull, the outer pile leg is upwards recovered by the rack type lifting device, the upper hull is lowered to the water surface, the outer pile leg is continuously recovered, and the lower hull is retracted to the lower part of the upper hull by depending on the buoyancy of the upper hull.
2. The method for installing a shallow offshore platform as claimed in claim 1, wherein the inner and outer legs are disposed close to the vertical and horizontal sides of the upper hull to reduce the overturning moment during the hoisting operation.
3. The method of installing a shallow offshore platform as claimed in claim 1 wherein the lengths of the inner and outer legs are adjusted according to the depth of water in the area of operation.
4. The method of installing a shallow offshore platform as claimed in claim 1 wherein the inner legs and outer legs are retracted and the lower hull is stowed beneath the upper hull during deployment or towing of the submersible jack-up vessel.
5. The shallow water offshore platform installation method of claim 1, wherein the lower hull is capable of adjusting the suction and discharge amount of water so that the lower hull obtains different buoyancy for changing the pressure of the bottom to the seabed and balancing the overturning moment generated during the hoisting operation of the crane with a ballast water system.
CN202110945970.9A 2021-08-17 2021-08-17 Shallow water area offshore platform installation method Pending CN115704209A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110945970.9A CN115704209A (en) 2021-08-17 2021-08-17 Shallow water area offshore platform installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110945970.9A CN115704209A (en) 2021-08-17 2021-08-17 Shallow water area offshore platform installation method

Publications (1)

Publication Number Publication Date
CN115704209A true CN115704209A (en) 2023-02-17

Family

ID=85181324

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110945970.9A Pending CN115704209A (en) 2021-08-17 2021-08-17 Shallow water area offshore platform installation method

Country Status (1)

Country Link
CN (1) CN115704209A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116791555A (en) * 2023-08-29 2023-09-22 西南石油大学 A kind of drilling platform spud shoe structure
CN118854915A (en) * 2024-09-29 2024-10-29 中海油能源发展股份有限公司采油服务分公司 A method and device for pulling piles from bottom of self-elevating platform

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120139931A (en) * 2011-06-20 2012-12-28 대우조선해양 주식회사 Method and system of attaching and detaching spud can to the jack-up platform
CN103924567A (en) * 2014-05-06 2014-07-16 太重(天津)滨海重型机械有限公司 Self-elevating drilling platform
CN107284612A (en) * 2017-07-20 2017-10-24 上海振华重工(集团)股份有限公司 Sit bottom jack up wind-powered electricity generation pile driving barge
CN107804437A (en) * 2017-07-20 2018-03-16 上海振华重工(集团)股份有限公司 Sit bottom jack up wind-powered electricity generation pile driving barge
CN207792620U (en) * 2017-12-06 2018-08-31 中船黄埔文冲船舶有限公司 A kind of jack up hoistable platform
CN207919524U (en) * 2018-02-01 2018-09-28 烟台中集来福士海洋工程有限公司 Self-elevating ocean platform
CN110712721A (en) * 2019-10-23 2020-01-21 中国船舶科学研究中心(中国船舶重工集团公司第七0二研究所) Offshore wind farm fan installation operation engineering ship and operation method thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120139931A (en) * 2011-06-20 2012-12-28 대우조선해양 주식회사 Method and system of attaching and detaching spud can to the jack-up platform
CN103924567A (en) * 2014-05-06 2014-07-16 太重(天津)滨海重型机械有限公司 Self-elevating drilling platform
CN107284612A (en) * 2017-07-20 2017-10-24 上海振华重工(集团)股份有限公司 Sit bottom jack up wind-powered electricity generation pile driving barge
CN107804437A (en) * 2017-07-20 2018-03-16 上海振华重工(集团)股份有限公司 Sit bottom jack up wind-powered electricity generation pile driving barge
CN207792620U (en) * 2017-12-06 2018-08-31 中船黄埔文冲船舶有限公司 A kind of jack up hoistable platform
CN207919524U (en) * 2018-02-01 2018-09-28 烟台中集来福士海洋工程有限公司 Self-elevating ocean platform
CN110712721A (en) * 2019-10-23 2020-01-21 中国船舶科学研究中心(中国船舶重工集团公司第七0二研究所) Offshore wind farm fan installation operation engineering ship and operation method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116791555A (en) * 2023-08-29 2023-09-22 西南石油大学 A kind of drilling platform spud shoe structure
CN116791555B (en) * 2023-08-29 2023-11-17 西南石油大学 A kind of drilling platform spud shoe structure
CN118854915A (en) * 2024-09-29 2024-10-29 中海油能源发展股份有限公司采油服务分公司 A method and device for pulling piles from bottom of self-elevating platform

Similar Documents

Publication Publication Date Title
EP2643210B1 (en) Floating marine structure
CN201695381U (en) Three-cylindrical foundation one-legged mooring platform
CN108454790B (en) Bottom-sitting self-elevating wind power piling ship
CN101837929B (en) Operation method for lifting fan for barge in shoal area
CN102080370A (en) Foundation construction platform for intertidal zone or offshore zone
CN201056685Y (en) Combined simple shaft mouth processing platform
CN205044921U (en) Multi -functional marine construction is from peaceful platform
CN103924567A (en) Self-elevating drilling platform
GB2202494A (en) Deep water support assembly for a jack-up platform structure
CN110761286A (en) A negative pressure cylinder type pile first method jacket piling positioning guide device and working method
CN115704209A (en) Shallow water area offshore platform installation method
CN112726548B (en) Construction method for split jacket foundation of deep-open sea converter station
CN102409650A (en) Installation method of shallow water ocean jacket platform
CN102923261A (en) A bottom-mounted offshore wind turbine installation barge
CN115637724A (en) Low-cost method for installing guide pipe frame of suction bucket
CN112814015B (en) Combined structure system of multi-pile foundation and floating fan and single-ship installation method
CN102206938A (en) Novel method for installing upper part block of offshore platform
CN111962543A (en) Rapid connection and separation process of pile stabilizing platform and mother ship
CN117127571A (en) Self-elevating offshore booster station platform and installation method thereof
CN202966598U (en) A new type of bottom-mounted offshore wind turbine installation barge
CN217870596U (en) Tensioning type fan foundation anchored on foundation seabed
CN213328975U (en) Semi-submersible pile inserting type ocean hoisting construction platform
CN212506365U (en) High pile cap foundation installation system suitable for ultra-shallow water area
CN212316977U (en) Mounting platform is used in construction of deep water socketed type jacket foundation
CN202208909U (en) Movable-baseplate self-lifting platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20230217